Offshore batch installation method for deep and far sea floating type fans

By setting up a offshore installation platform near the Shenyuan Sea Wind Farm and using the main lift and auxiliary lift to assemble and install the floating fan in sections, the problem of inconvenience in land construction of the Shenyuan Sea Wind Farm is solved, and efficient and safe machining installation is achieved. , reduces costs and risks.

CN118934475APending Publication Date: 2024-11-12POWERCHINA ZHONGNAN ENG
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411031797.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing technology is difficult to effectively solve the inconvenience of deep-sea floating fans on land construction, resulting in low construction efficiency, high cost and high risk, especially in harsh sea conditions, it is difficult to achieve efficient and safe ocean installation.

Method used

The offshore installation platform is adopted, and the basic floating body segment structure and fan components are transported to the offshore installation platform for assembly and installation through the main and auxiliary lifts. It is divided into multiple timely interruptible sub-processes, including transportation, assembly and floating off-water drainage. , reduce the requirements for offshore window periods and improve construction efficiency and safety.

Benefits of technology

It significantly improves the construction, transportation and installation efficiency of deep-sea floating fans, reduces construction costs and risks, is suitable for sea areas with water depths exceeding 60m, and adapts to the needs of large-capacity fans, reducing dependence on land infrastructure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118934475A_ABST
    Figure CN118934475A_ABST
Patent Text Reader

Abstract

The invention discloses a deep and far sea floating type fan offshore batch installation method which comprises the steps that a floating type fan offshore installation platform is arranged on the sea surface near a deep and far sea wind power plant, and berthing equipment, a main crane and an auxiliary crane are arranged on the offshore installation platform; the foundation floating body segmented structure of the floating type draught fan is transported to an offshore installation platform; foundation floating body segmented structures of the single floating type draught fan are transferred to a deck one by one, and offshore assembly of the foundation floating bodies of the floating type draught fan and binding and fixing of the formed foundation floating bodies of the floating type draught fan are completed; the draught fan composition components are transported to an offshore installation platform through a transport ship, and the draught fan composition components are sequentially assembled to a foundation floating body to form a floating type draught fan; the floating type draught fans float away from the offshore installation platform, and batch assembly of the floating type draught fans can be conducted by repeating the operation. The construction, transportation and installation efficiency of the floating type draught fan can be greatly improved, and the method can be extensively applied to operation and maintenance of large offshore components of the floating type draught fan.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to batch installation of deep-sea floating wind power equipment, in particular to a method for offshore batch installation of deep-sea floating wind turbines. Background Art

[0002] With the transformation of the global energy structure and the increasing demand for renewable energy, offshore wind power, as an important component of clean energy, has received extensive attention for its development and utilization. Offshore wind power has the advantages of high wind speed, stable wind source, and no occupation of land resources. In particular, the wind energy resources in deep sea areas are more stable and abundant, but it also faces a series of technical challenges and construction difficulties.

[0003] At present, the manufacturing and assembly of the foundation buoy of deep-sea floating wind turbines are usually carried out at onshore construction bases, and their construction depends to a large extent on the construction conditions of the onshore construction base, which not only limits the flexibility of construction, but also limits the capacity of the floating wind turbines and the main dimensions of the foundation buoy. With the expansion of the capacity of floating wind turbines used in the deep sea, the main dimensions of the foundation buoys also increase accordingly, so the less efficient wet towing method (placing the foundation buoy directly on the water surface) has to be adopted to transport the foundation buoy to the wind turbine installation dock. The hoisting operation of large-capacity wind turbines also has extremely high requirements for the water depth and crane of the dock. The existing wind turbine installation dock is not suitable for the hoisting operation of large-capacity wind turbines. In addition, the integrated towing process of floating wind turbines at sea is extremely susceptible to bad weather and complex sea conditions, which not only increases the difficulty of offshore towing operations, but also easily causes damage to the floating wind turbine as a whole, thereby reducing the assembly efficiency of floating wind turbines in wind farms and increasing the risk of offshore installation operations.

[0004] Chinese patent CN105460796A discloses an offshore platform wind turbine hoisting system and hoisting method, but it involves the installation of near-shallow sea fixed wind turbines (wind turbines with fixed bases built in near-shallow seas), and the method cannot be used for the assembly of deep-sea floating wind turbines.

[0005] Against the backdrop of continuous advancement in offshore wind power technology, floating wind farms are getting farther and farther offshore, the water depth is getting deeper, and the marine environment is becoming more complex. How to ensure the safety, economy and efficiency of the construction and installation of deep-sea floating wind turbines has become the main problem facing current technological development. Summary of the invention

[0006] The technical problem to be solved by the present invention is that, in view of the inconvenience of the existing deep-sea floating wind turbines in the onshore construction, the present invention provides a method for the offshore batch installation of deep-sea floating wind turbines, which can greatly improve the construction, transportation and installation efficiency of deep-sea floating wind turbines, while significantly reducing construction costs and construction risks.

[0007] In order to solve the above technical problems, the present invention adopts the following technical solutions:

[0008] A method for offshore batch installation of deep sea floating wind turbines, comprising:

[0009] Arrange a floating wind turbine offshore installation platform on the sea surface near a deep-sea wind farm, arrange berthing equipment on the berthing side of the offshore installation platform, and install a main hoist pontoon, an auxiliary hoist pontoon, and a main hoist support pontoon on the main deck of the offshore installation platform, install a main hoist on the main hoist pontoon, install an auxiliary hoist on the auxiliary hoist pontoon, and install a main hoist support on the main hoist support pontoon, the heights of the main hoist pontoon, the auxiliary hoist pontoon, and the main hoist support pontoon are greater than the draft of the floating wind turbine foundation pontoon, and the main hoist and the auxiliary hoist are used to transport the foundation pontoon segmented structure of the floating wind turbine on the transport ship to the main deck of the offshore installation platform, and are used for offshore installation of wind turbine component components;

[0010] The offshore operations are divided into multiple sub-processes that can be interrupted in time. The sub-processes mainly include berthing of transport ships, transfer of basic floating body segment structures, assembly of basic floating body segment structures, transfer of wind turbine components, installation of wind turbine components and launching of floating wind turbine as a whole. Specifically:

[0011] Using a transport ship to transport the basic floating body segment structure to the location of the offshore installation platform;

[0012] Using the main crane and the auxiliary crane on the offshore installation platform, the segmented structures of the single basic floating body are transferred one by one to the main deck of the offshore installation platform;

[0013] completing the offshore assembly of the floating wind turbine foundation buoy and the lashing and fixing of the formed floating wind turbine foundation buoy on the main deck of the offshore installation platform;

[0014] Using a transport ship to load and transport the wind turbine components to the location of the offshore installation platform;

[0015] Using the main crane on the offshore installation platform, assembling the wind turbine components in sequence onto the floating wind turbine foundation buoy to form a floating wind turbine;

[0016] The offshore installation platform increases its draft until the floating wind turbine thereon reaches a free floating state, and the floating wind turbine is towed so that the floating wind turbine is separated from the main deck of the offshore installation platform according to a predetermined route;

[0017] After the floating wind turbine is launched, the above offshore operations are repeated to achieve the offshore batch installation of the floating wind turbine.

[0018] The method of the present invention transports the floating wind turbine foundation buoy segmented structures and wind turbine components manufactured on land in batches to the location of an offshore installation platform located near a deep-sea wind farm, and divides the offshore operations into multiple sub-processes that can be interrupted in time: berthing of the transport ship, transfer of the foundation buoy segmented structure, assembly of the foundation buoy segmented structure, transfer of wind turbine components, installation of wind turbine components and launching of the floating wind turbine as a whole, which not only greatly improves the construction, transportation and installation efficiency of deep-sea floating wind turbines, but also significantly reduces construction costs and construction risks.

[0019] Furthermore, the duration of the sub-process of the offshore operation does not exceed 36 hours. In this way, the offshore operation of the present invention does not require long-term continuous operation, which can significantly reduce the requirements for the offshore window period.

[0020] Furthermore, the segmented structures are transported from different construction bases to the main deck of the offshore installation platform according to a predetermined route, and are arranged according to the offshore assembly requirements of the floating wind turbine foundation buoy.

[0021] Furthermore, when all the basic floating body segment structures of a single floating wind turbine are transferred, the transport ship is released from the offshore installation platform to prepare for the next transfer or to start a new round of offshore transportation.

[0022] Furthermore, the basic floating body segmented structure may include columns, heave tanks, buoys, connecting beams and diagonal braces, etc.

[0023] Furthermore, when the transport ship berths at the offshore installation platform, the offshore installation platform adjusts its draft until the main deck of the offshore installation platform is flush with the main deck of the transport ship.

[0024] Furthermore, the offshore installation platform has a wide adjustable draft range, which does not affect the design draft requirements of the floating wind turbine foundation buoy.

[0025] Furthermore, when transporting the basic floating body segmented structure and wind turbine components, multiple transport ships work together to transport the basic floating body segmented structure and wind turbine components to the location of the offshore installation platform without using a production base or a transshipment terminal, thereby improving the utilization rate of the offshore installation platform.

[0026] Furthermore, after the floating wind turbine is installed and launched on the offshore installation platform, it is quickly connected to a mooring system pre-installed at a nearby wind farm site, thereby avoiding long-distance integrated towing operations.

[0027] Furthermore, the method for offshore batch installation of deep-sea floating wind turbines of the present invention is suitable for sea areas with a water depth exceeding 60m, and its operating capacity can be further expanded according to actual needs, and can meet the offshore installation operation requirements of large-capacity deep-sea floating wind turbines.

[0028] Furthermore, the reverse operation process of the deep-sea floating wind turbine offshore batch installation method of the present invention can meet the maintenance requirements of large offshore components. The reverse operation process can be divided into floating loading of the entire floating wind turbine, offshore maintenance of large wind turbine components, and floating launching of the entire floating wind turbine.

[0029] Obviously, the ship and machine resources used by the deep-sea floating wind turbine offshore batch installation method of the present invention mainly include the basic floating body transport ship, the wind turbine transport ship and the floating wind turbine offshore installation platform. The basic floating body transport ship is used to load and transport the basic floating body segmented structure, the wind turbine transport ship is used to transport the tower segment and wind turbine blades, nacelles and hubs and other wind turbine components, and the floating wind turbine offshore installation platform is used for the offshore assembly of the basic floating body, the offshore installation of the wind turbine and the floating and launching of the floating wind turbine as a whole.

[0030] The floating wind turbine offshore installation platform used by the deep-sea floating wind turbine offshore batch installation method of the present invention has the capabilities of berthing large transport ships, offshore lifting of large structures, offshore assembly of segmented structures, offshore installation of wind turbine components, and overall floating and launching of floating wind turbines.

[0031] The floating wind turbine foundation buoy of the present invention is transported in sections and assembled at sea, thereby improving the utilization rate of the transport ship deck and reducing the hardware requirements for the foundation buoy production base.

[0032] In the method for offshore batch installation of deep-sea floating wind turbines of the present invention, the basic floating body segmented structure and the wind turbine components are dry-towed (transported by transport ships), which reduces the marine transportation time, and multiple transport ships work together to transport from different production bases or transfer terminals to the location of the floating wind turbine offshore installation platform, thereby improving the utilization rate of the mobilized ships and machinery.

[0033] The method for offshore batch installation of deep-sea floating wind turbines of the present invention divides the offshore operation content into multiple sub-processes, mainly including berthing of transport ships, transfer of basic floating body segmented structures, assembly of basic floating body segmented structures, transfer of wind turbine components, installation of wind turbine components and floating and launching of the floating wind turbine as a whole.

[0034] In the offshore operation content of the deep-sea floating wind turbine offshore batch installation method of the present invention, each sub-process lasts for a relatively short time, and the sub-process can be interrupted in time, so long-term continuous operation is not required, which can significantly reduce the requirements for the offshore window period.

[0035] The deep-sea floating wind turbine offshore batch installation method of the present invention can quickly adjust the operating status, complete the separation between the transport ship and the floating wind turbine offshore installation platform in a short time, tie and fix the transferred structural components, and realize the rapid adjustment of the draft of the floating wind turbine offshore installation platform, thereby greatly improving the ability to withstand severe sea conditions.

[0036] Compared with the prior art, the present invention has the following beneficial effects:

[0037] 1. The present invention realizes the assembly of the floating wind turbine foundation buoy on an offshore installation platform located near a deep-sea wind farm. Only the foundation buoy segmented structure is constructed on the foundation buoy construction dock, thereby reducing the requirements for the foundation buoy construction base, avoiding dependence on large docks or launching barges, and making the site selection of the construction base more flexible, thereby effectively reducing the overall construction cost of the foundation buoy.

[0038] 2. The present invention realizes the hoisting of wind turbine components through an offshore installation platform, avoiding the use of wind turbine hoisting docks in the prior art, so that wind turbine installation operations are no longer limited by the bearing capacity of the dock, the water depth of the dock, and the water depth of the waterway, which significantly improves the construction adaptability and efficiency.

[0039] 3. The offshore installation platform of the present invention is arranged on the sea surface near the deep-sea wind farm, and the overall assembly and floating of the floating wind turbine are completed on the offshore installation platform, avoiding the long-distance integrated towing of the floating wind turbine, effectively reducing the risk of offshore construction, and avoiding the call for scarce ship machinery, which is conducive to ensuring the construction progress.

[0040] 4. The basic floating body segmented structure and wind turbine components of the present invention can be transported and installed in batches, which greatly improves the construction efficiency and effectively reduces the construction cost.

[0041] 5. The offshore batch installation of floating wind turbines of the present invention is divided into multiple sub-processes, and each sub-process lasts for a short time. When severe sea conditions are predicted, the current sub-process can be quickly ended and switched to the self-storage mode, so that the offshore operation window period is further extended.

[0042] 6. The offshore installation platform of the present invention solves the problem of offshore operation and maintenance of large components of floating wind turbines, avoids the long-distance round-trip integrated towing operation of floating wind turbines, and greatly improves the operation and maintenance efficiency.

[0043] 7. The present invention reduces the dependence on land infrastructure and promotes the application of large-capacity floating wind turbines to wider sea areas. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0045] Figure 1 It is a stereoscopic diagram of a preferred embodiment of the offshore installation platform of the present invention.

[0046] Figure 2 It is a side view of a preferred embodiment of the offshore installation platform of the present invention.

[0047] Figure 3 This is a schematic diagram of a preferred embodiment of the present invention in which a basic floating body transport ship is loaded with a basic floating body segmented structure at a dock.

[0048] Figure 4 This is a schematic diagram of a preferred example of a basic floating transport vessel of the present invention approaching a floating wind turbine offshore installation platform at sea.

[0049] Figure 5 This is a schematic diagram of the transfer of the basic floating body segmented structure of a preferred embodiment of the present invention to the floating wind turbine offshore installation platform.

[0050] Figure 6 This is a schematic diagram of completing the assembly of a floating wind turbine foundation on a floating wind turbine offshore installation platform according to a preferred embodiment of the present invention.

[0051] Figure 7 This is a schematic diagram of completing the installation of an offshore floating wind turbine on a floating wind turbine offshore installation platform according to a preferred embodiment of the present invention.

[0052] Figure 8 A schematic diagram of a floating wind turbine offshore installation platform according to a preferred embodiment of the present invention implementing the floating wind turbine launching.

[0053] In the figure: 1. transport ship, 2. offshore installation platform, 3. foundation float, 4. wind turbine, 5. column, 6. heave tank, 7. buoy, 8. connecting beam, 9. diagonal brace, 21. side column, 22. center column, 23. buoy, 24. deck box, 25. main crane pontoon, 26. auxiliary crane pontoon, 27. main crane bracket pontoon, 28. main crane, 29. auxiliary crane, 210. main crane bracket, 211. auxiliary crane bracket, 212. watertight door, 213. self-propelled modular transport vehicle. DETAILED DESCRIPTION

[0054] The present invention is further described below in conjunction with specific preferred embodiments and drawings, but the protection scope of the present invention is not limited thereby.

[0055] In the description of the present invention, it should be noted that the terms "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0056] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0057] An embodiment of a method for offshore batch installation of deep-sea floating wind turbines of the present invention comprises: arranging an offshore installation platform of floating wind turbines on the sea surface near a deep-sea wind farm.

[0058] like Figure 1 , Figure 2As shown, the offshore installation platform 2 is a column-stabilized structure, which includes a lower structure and an upper structure. The lower structure mainly includes a side column 21, a central column 22 and a first buoy 23. The diameter of the side column 21 is 18-24m, the diameter of the central column 22 is 8-12m, and the height of the side column 21 and the central column 22 is 32-46m. The upper structure mainly includes a deck box 24, a main suspension pontoon 25, an auxiliary suspension pontoon 26 and a main suspension bracket pontoon 27, and the height of the main suspension pontoon 25, the auxiliary suspension pontoon 26 and the main suspension bracket pontoon 27 is greater than the draft depth of the floating wind turbine foundation buoy 3. The upper part of the side column 21 and the central column 22 is connected to the deck box 24, and the lower part is connected to the buoy 23. The components form a stable structure as a whole to improve the overall strength of the installation platform. The main hoist 28 is located on the main hoist pontoon 25, the auxiliary hoist 29 is located on the auxiliary hoist pontoon 26, and the main hoist bracket 210 is located on the main hoist bracket pontoon 27. The deck box 24 has sufficient deck area to meet the needs of offshore assembly of the floating wind turbine foundation pontoon, offshore hoisting of the wind turbine and overall floating and launching. The deck box 24 is arranged with berthing equipment on the side close to the auxiliary hoist pontoon 26 to facilitate berthing of ships. The deck box 24 is triangular in shape, with a single-side width of 136-172m and a height of 4-7m. The ratio of the displacement volume of the deck box 24 to the enclosed volume when fully submerged is less than 50%. The main hoist 28 and the auxiliary hoist 29 can transfer the floating wind turbine foundation pontoon segmented structure to the deck box 24 and be used for offshore installation of wind turbine components. The auxiliary hoist bracket 211 is installed on the main hoist pontoon 25 to save the main deck area of ​​the deck box 24 and realize the compact arrangement of the auxiliary hoist 29. A plurality of self-propelled modular transport vehicles 213 are arranged on the deck box 24, which are used for transporting the floating wind turbine foundation buoy segmented structure or wind turbine components on the main deck of the deck box 24. The main crane 28 meets the requirements for hoisting wind turbines above 15MW. The boom length of the main crane 28 exceeds 160m, and the height of the main crane buoy 25 at the bottom of the main crane 28 is 24-56m to help further increase the hoisting height of the main crane 28. The floating offshore installation platform moves continuously under the action of environmental loads, but because the main crane 28, the auxiliary crane 29 and the floating wind turbine are all installed on the offshore installation platform 2, the movement of the main crane 28, the auxiliary crane 29 and the floating wind turbine is always synchronized, so the offshore hoisting operation of large-capacity floating wind turbines can be realized without being affected.

[0059] The draft of the offshore installation platform 2 ranges from 32 to 54 m, which is sufficient to meet different functional requirements. The draft during towing is close to the first buoy 23, which is conducive to reducing towing resistance. The draft of the floating wind turbine foundation buoy segmented structure during offshore assembly and offshore hoisting of wind turbine components is located at the side column 21 or the center column 22 to improve the movement performance of the offshore installation platform 2, thereby providing better external conditions for offshore operations. When the floating wind turbine floats off the water, the draft is located at the main hoisting pontoon 25, the auxiliary hoisting pontoon 26 or the main hoisting support pontoon 27, and the draft depth meets the displacement requirements for the floating wind turbine to reach a floating state. The deck box 24 is an equilateral triangle as a whole, and the main hoisting pontoon 25, the auxiliary hoisting pontoon 26 and the main hoisting support pontoon 27 are distributed on the outermost side of the deck to improve the stability of the installation platform during the floating off the water operation. The main suspension pontoon 25 and the main suspension bracket pontoon 27 are distributed at two vertices of the deck box 24, and the auxiliary suspension pontoon 26 is close to the other vertex, but moved 40-80m inward along the deck edge line to help improve the margin of the main deck space layout of the offshore installation platform 2 during the segmented assembly and floating launch of the floating wind turbine 221. Before the floating launch operation, the self-propelled modular transport vehicle 213 is tied and fixed in the pontoon and the watertight door 212 is closed.

[0060] like Figure 3 - Figure 8 As shown, the offshore operation content of the present invention is divided into a plurality of sub-processes that can be interrupted in time, and the sub-processes mainly include berthing of the transport ship, transfer of the basic floating body segment structure, assembly of the basic floating body segment structure, transfer of the wind turbine component components, installation of the wind turbine component components and floating and launching of the floating wind turbine as a whole, specifically:

[0061] Using a transport ship 1 to transport the basic floating body segment structure to the location of the offshore installation platform 2;

[0062] Using the main crane 28 and the auxiliary crane 29 on the offshore installation platform 2, the segmented structures of the single basic floating body are transferred one by one to the main deck of the offshore installation platform 2;

[0063] On the main deck of the offshore installation platform 2, the offshore assembly of the floating wind turbine foundation buoy and the lashing and fixing of the formed floating wind turbine foundation buoy are completed;

[0064] Using a transport ship to load and transport the wind turbine components to the location of the offshore installation platform;

[0065] Using the main crane on the offshore installation platform, assembling the wind turbine components in sequence onto the floating wind turbine foundation buoy to form a floating wind turbine;

[0066] The offshore installation platform increases its draft until the floating wind turbine thereon reaches a free floating state, and the floating wind turbine is towed so that the floating wind turbine is separated from the main deck of the offshore installation platform according to a predetermined route;

[0067] After the floating wind turbine is launched, the above offshore operations are repeated to achieve the offshore batch installation of the floating wind turbine.

[0068] Figure 3 A schematic diagram showing a preferred example of the present invention in which a basic buoy transport ship loads a basic buoy segmented structure at a dock. The basic buoy segmented structure of a floating wind turbine mainly includes a column 5, a heave tank 6, a second buoy 7, a connecting beam 8 and a diagonal brace 9. The basic buoy segmented structure is loaded onto the transport ship 1 by a dock crane. The basic buoy segmented structure is small in size and regular in shape, and is easy to arrange and tie on the transport ship 1, and multiple basic buoy segmented structures can be loaded at one time. Using the transport ship 1 to transport the basic buoy segmented structure can reduce the requirements for the construction of the basic buoy dock, improve the deck utilization rate of the transport ship, the efficiency of marine transportation and the flexibility of marine scheduling.

[0069] like Figure 4 , Figure 5 and Figure 6 The schematic diagram of the preferred embodiment of the present invention showing the basic floating transport ship berthing alongside the floating wind turbine offshore installation platform, the schematic diagram of the basic floating segmented structure being transferred to the floating wind turbine offshore installation platform, and the schematic diagram of the floating wind turbine offshore installation platform completing the offshore wind turbine foundation assembly are respectively shown. Before the transport ship 1 berths, the offshore installation platform 2 adjusts the draft to the berthing draft state, so that the main deck of the deck box 24 of the offshore installation platform 2 is as flush as possible with the main deck of the transport ship 1 to facilitate the transfer of the basic floating segmented structure, and at the same time improves the hydrostatic stiffness to reduce the impact of the placement and movement of the basic floating segmented structure on the floating state of the offshore installation platform 2. After the transport ship 1 berths alongside the offshore installation platform 2, the basic floating segmented structure is transferred one by one to the main deck of the deck box 24 of the offshore installation platform 2 through the main crane 28 and auxiliary crane 29 of the offshore installation platform 2. The basic floating segmented structure is transported from different production bases or transfer terminals to the location of the floating wind turbine offshore installation platform according to the predetermined route, and the main deck of the offshore installation platform 2 is arranged according to the offshore assembly requirements. When all the floating wind turbine foundation buoy segment structures are transferred, the transport ship 1 is separated from the offshore installation platform 2 to prepare for the next transfer or a new round of maritime transportation. After that, the offshore assembly of the foundation buoy segment structures is completed on the main deck of the offshore installation platform 2, and the formed foundation buoy 3 is tied and fixed.

[0070] Figure 7The schematic diagram of the floating wind turbine offshore installation platform of the preferred embodiment of the present invention is shown. The wind turbine components (wind turbine tower segment structure and wind turbine unit structure module) and the basic floating body segment structure adopt similar loading and transportation methods. After the wind turbine component transport ship and the offshore installation platform 2 are berthed, the main crane 28 of the offshore installation platform 2 is directly used to carry out the offshore installation of the floating wind turbine.

[0071] Figure 8 The schematic diagram of the floating wind turbine offshore installation platform of the preferred embodiment of the present invention is shown. After the offshore assembly of the floating wind turbine foundation buoy segmented structure and the offshore hoisting of the wind turbine components are completed, the floating wind turbine floating and launching operation is started. When the draft of the offshore installation platform 2 reaches the deck box 24, the binding and fixation of the floating wind turbine 4 and the offshore installation platform 2 are gradually released. After the draft of the offshore installation platform 2 reaches the main suspension pontoon 25, the auxiliary suspension pontoon 26 and the main suspension support pontoon 27, the draft continues to increase until the floating wind turbine 4 is close to reaching the floating state. The draft of the offshore installation platform 2 is further increased rapidly. When the vertical gap between the floating wind turbine 4 and the offshore installation platform 2 exceeds 1m, it is determined that the two have been separated. Under the towing action of other ships, the floating wind turbine 4 gradually moves away from the deck box 24 of the offshore installation platform 2 along the predetermined route, and then the offshore installation platform 2 returns to the berthing draft state.

[0072] By repeating the above-mentioned offshore operations, the offshore batch installation of floating wind turbines can be achieved.

[0073] The above is only a specific implementation scheme of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the art can make many possible changes and modifications to the technical scheme of the present invention by using the technical content disclosed above without departing from the scope of the technical scheme of the present invention, or modify it into an equivalent embodiment of equivalent changes. Therefore, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical scheme of the present invention should fall within the protection scope of the technical scheme of the present invention.

Claims

1. A method for offshore batch installation of deep sea floating wind turbines, characterized in that include: Arrange a floating wind turbine offshore installation platform on the sea surface near a deep-sea wind farm, arrange berthing equipment on the berthing side of the offshore installation platform, and install a main hoist pontoon, an auxiliary hoist pontoon, and a main hoist support pontoon on the main deck of the offshore installation platform, install a main hoist on the main hoist pontoon, install an auxiliary hoist on the auxiliary hoist pontoon, and install a main hoist support on the main hoist support pontoon, the heights of the main hoist pontoon, the auxiliary hoist pontoon, and the main hoist support pontoon are greater than the draft of the floating wind turbine foundation pontoon, and the main hoist and the auxiliary hoist are used to transport the foundation pontoon segmented structure of the floating wind turbine on the transport ship to the main deck of the offshore installation platform, and are used for offshore installation of wind turbine component components; The offshore operations are divided into several sub-processes, including the berthing of transport ships, the transfer of the basic floating body segment structure, the assembly of the basic floating body segment structure, the transfer of wind turbine components, the installation of wind turbine components and the floating launch of the floating wind turbine as a whole, specifically: Using a transport ship to transport the basic floating body segment structure to the location of the offshore installation platform; Using the main crane and the auxiliary crane on the offshore installation platform, the segmented structures of the single basic floating body are transferred one by one to the main deck of the offshore installation platform; completing the offshore assembly of the floating wind turbine foundation buoy and the lashing and fixing of the formed floating wind turbine foundation buoy on the main deck of the offshore installation platform; Using a transport ship to load and transport the wind turbine components to the location of the offshore installation platform; Using the main crane on the offshore installation platform, assembling the wind turbine components in sequence onto the floating wind turbine foundation buoy to form a floating wind turbine; The offshore installation platform increases its draft until the floating wind turbine thereon reaches a free floating state, and the floating wind turbine is towed so that the floating wind turbine is separated from the main deck of the offshore installation platform according to a predetermined route; After the floating wind turbine is launched, the above offshore operations are repeated to achieve the offshore batch installation of the floating wind turbine.

2. The method for offshore batch installation of deep sea floating wind turbines according to claim 1 is characterized in that: The duration of the sub-process of the offshore operation does not exceed 36 hours, and the sub-process can be interrupted in time.

3. The method for offshore batch installation of deep sea floating wind turbines according to claim 1 is characterized in that: The segmented structures are transported from different construction bases to the main deck of the offshore installation platform according to a predetermined route, and are arranged according to the requirements for offshore assembly of floating wind turbine foundation buoys.

4. The method for offshore batch installation of deep sea floating wind turbines according to claim 1 is characterized in that: When all the basic floating body segment structures of a single floating wind turbine are transferred, the transport ship is released from the offshore installation platform to prepare for the next transfer or start a new round of marine transportation.

5. The method for offshore batch installation of deep sea floating wind turbines according to claim 1 is characterized in that: When the transport ship berths at the offshore installation platform, the offshore installation platform adjusts its draft until the main deck of the offshore installation platform is flush with the main deck of the transport ship.

6. The method for offshore batch installation of deep sea floating wind turbines according to claim 1 is characterized in that: The adjustable draft range of the offshore installation platform meets the design draft requirements of the floating wind turbine foundation buoy.

7. The method for offshore batch installation of deep sea floating wind turbines according to claim 1 is characterized in that: When transporting the basic floating body segmented structure and wind turbine components, multiple transport ships are used to work together to transport the basic floating body segmented structure and wind turbine components located at different production bases or transfer docks to the location of the offshore installation platform.

8. The method for offshore batch installation of deep sea floating wind turbines according to claim 1 is characterized in that: After the floating wind turbine is installed and launched on the offshore installation platform, it is quickly connected to a mooring system pre-laid at a nearby wind farm machine site to avoid long-distance integrated towing operations.

9. The method for offshore batch installation of deep sea floating wind turbines according to claim 1, characterized in that: It is suitable for sea areas with a water depth of more than 60m and meets the offshore installation requirements of large-capacity deep-sea floating wind turbines.

10. The method for offshore batch installation of deep sea floating wind turbines according to claim 1, characterized in that: The offshore installation platform is suitable for operation and maintenance of large offshore components, and the operation process of the offshore installation platform for operation and maintenance of large offshore components is divided into floating loading of the entire floating wind turbine, offshore operation and maintenance of large wind turbine components, and floating launching of the entire floating wind turbine.

Citation Information

Patent Citations

  • Offshore platform fan lifting system and lifting method

    CN105460796A