Flue gas waste heat recovery control method, related equipment and system

CN118936197APending Publication Date: 2024-11-12XINAO SHUNENG TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411308011.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-19
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

[0003]但是,目前用于进行烟气余热回收的系统中,普遍存在余热回收量无法满足更高要求的问题

Benefits of technology

[0041] To sum up, the flue gas waste heat recovery control method, related equipment and system provided by this application can be used to determine when the difference between the high-temperature heat pump condenser outlet water temperature and the air heat exchanger outlet air temperature reaches the preset heat exchange end difference threshold. , estimate the economic benefits of the heat pump operation condition and the heat pump decommissioning condition at the next moment, compare the economic benefits of the high-temperature heat pump under these two conditions, and control the high-temperature heat pump to the condition with greater economic benefits. run. The high-temperature heat pump in the flue gas waste heat recovery control system provided by this application reduces the temperature of the intermediary water output from the evaporation side of the high-temperature heat pump, that is, reduces the temperature of the intermediary water in the flue gas heat exchanger that exchanges heat with the hot flue gas. The method of large heat exchange end difference increases the heat exchange with the hot flue gas; the high-temperature heat pump extracts the heat of the intermediary water that has absorbed the heat of the flue gas and increases the heat, so that the cold air can completely absorb the heat of the hot flue gas. After heat exchange, it reaches a temperature higher than the hot flue gas. Therefore, this application can increase the amount of waste heat recovery from hot flue gas while ensuring greater economic benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118936197A_ABST
    Figure CN118936197A_ABST
Patent Text Reader

Abstract

The invention discloses a flue gas waste heat recovery control method, related equipment and a flue gas waste heat recovery control system, and relates to the technical field of waste heat recovery. And the economic benefits of the heat pump commissioning working condition and the heat pump splitting working condition at the next moment are estimated, the economic benefits of the two working conditions are compared, and the high-temperature heat pump is controlled to operate in the working condition with the large economic benefits. The heat of the medium water absorbing the heat of the flue gas is extracted through the high-temperature heat pump, and the heat is increased, so that the cold air reaches the temperature higher than that of the hot flue gas on the basis of completely absorbing the heat of the hot flue gas. Therefore, the waste heat recovery amount of the hot flue gas can be increased under the condition that it is guaranteed that the economic benefit is large.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of waste heat recovery technology, and in particular to a flue gas waste heat recovery control method, related equipment and system. Background Art

[0002] Flue gas waste heat recovery is a technology that can recover and utilize waste heat from waste gas generated during industrial production. It can not only effectively reduce energy waste, but also reduce pollutant emissions. With the continuous innovation of technology and the in-depth promotion of its application, flue gas waste heat recovery is expected to play a greater role in the future. Flue gas waste heat recovery is widely used in natural gas boiler heating, gas power plant power generation and other fields. It can also be used in spray drying systems. The spray drying system can disperse the materials to be dried into fine particles like mist, and then contact these particles with the high-temperature flue gas emitted by the gas hot blast furnace to instantly remove most of the moisture, thereby drying the solid matter in the material into powder.

[0003] However, in the systems currently used for recovering waste heat from flue gas, there is a common problem that the amount of waste heat recovered cannot meet higher requirements. Summary of the invention

[0004] In view of this, the present application provides a flue gas waste heat recovery control method, related equipment and system to achieve the purpose of high-demand waste heat recovery.

[0005] In order to achieve the above objectives, the proposed solution is as follows:

[0006] In a first aspect, the present application provides a flue gas waste heat recovery control method, which is applied to a flue gas waste heat recovery control system. The flue gas waste heat recovery control system includes a flue gas heat exchanger, an air heat exchanger, and an intermediate water system arranged between the flue gas heat exchanger and the air heat exchanger; the intermediate water system includes an evaporation side intermediate water circulation loop and a condensation side intermediate water circulation loop; and a high-temperature heat pump connecting the evaporation side intermediate water circulation loop and the condensation side intermediate water circulation loop; the control method includes:

[0007] Collect the IoT data at the current moment, including: high-temperature heat pump condenser water outlet temperature and air heat exchanger outlet air temperature;

[0008] If the difference between the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger is greater than the preset air heat exchange end difference, the outlet water temperature of the high-temperature heat pump condenser is adjusted to be lowered according to the preset difference, and the step of collecting the IoT data at the current moment is returned to execute; the initial setting value of the outlet water temperature of the high-temperature heat pump condenser is the maximum outlet water temperature allowed by the high-temperature heat pump condenser;

[0009] When the difference between the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger reaches the preset heat exchange end difference threshold, the economic benefits of the heat pump operation condition and the economic benefits of the heat pump decoupling condition at the next moment are estimated;

[0010] Compare the economic benefits of the heat pump operation condition at the next moment and the economic benefits of the heat pump decoupling condition, and based on the comparison results, control the high-temperature heat pump to operate in the heat pump operation condition or the heat pump decoupling condition, so that the high-temperature heat pump is in a condition with greater economic benefits.

[0011] In a possible implementation, the economic benefits of the heat pump operation condition at the next moment and the economic benefits of the heat pump disconnection condition are compared, and based on the comparison result, the high-temperature heat pump is controlled to operate in the heat pump operation condition or the heat pump disconnection condition, so that the high-temperature heat pump is in a condition with greater economic benefits, including:

[0012] When the economic benefit of the heat pump operation condition is greater than the economic benefit of the heat pump decoupling condition, the high-temperature heat pump is controlled to operate at the heat pump operation condition;

[0013] When the economic benefit of the heat pump operation condition is less than the economic benefit of the heat pump decoupled operation condition, the high-temperature heat pump is controlled to operate in the heat pump decoupled operation condition.

[0014] The second aspect of the present application provides a flue gas waste heat recovery control device, which is applied to a flue gas waste heat recovery control system. The flue gas waste heat recovery control system includes a flue gas heat exchanger, an air heat exchanger, and an intermediate water system arranged between the flue gas heat exchanger and the air heat exchanger; the intermediate water system includes an evaporation side intermediate water circulation loop and a condensation side intermediate water circulation loop; and a high-temperature heat pump connecting the evaporation side intermediate water circulation loop and the condensation side intermediate water circulation loop; the device includes:

[0015] Collection unit, judgment unit, estimation unit and control unit; wherein:

[0016] A collection unit, used to collect IoT data at the current moment, the IoT data including: a high-temperature heat pump condenser outlet water temperature and an air heat exchanger outlet air temperature judgment unit, used to adjust and lower the high-temperature heat pump condenser outlet water temperature according to the preset difference if the difference between the high-temperature heat pump condenser outlet water temperature and the air heat exchanger outlet air temperature is greater than a preset air heat exchange end difference, and return to execute the step of collecting IoT data at the current moment; the initial setting value of the high-temperature heat pump condenser outlet water temperature is the maximum outlet water temperature allowed by the high-temperature heat pump condenser;

[0017] An estimation unit is used to estimate the economic benefits of the heat pump operation condition and the economic benefits of the heat pump decoupling condition at the next moment until the difference between the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger reaches a preset heat exchange end difference threshold;

[0018] The control unit is used to compare the economic benefits of the heat pump operation condition at the next moment and the economic benefits of the heat pump decoupling condition, and according to the comparison result, control the high-temperature heat pump to operate in the heat pump operation condition or the heat pump decoupling condition, so that the high-temperature heat pump is in a condition with greater economic benefits.

[0019] The third aspect of the present application provides a flue gas waste heat recovery control device, comprising at least one processor and a memory connected to the processor, wherein:

[0020] The memory is used to store computer programs;

[0021] The processor is used to execute a computer program so that the flue gas waste heat recovery control device can implement the flue gas waste heat recovery control method as described in any one of the above.

[0022] A fourth aspect of the present application provides a computer program product, comprising computer-readable instructions. When the computer-readable instructions are executed on the computer program product, the computer program product implements the flue gas waste heat recovery control method as described in any one of the above.

[0023] A fifth aspect of the present application provides a flue gas waste heat recovery control system, comprising: a flue gas heat exchanger and an air heat exchanger, wherein the flue gas heat exchanger is connected to a hot flue gas outlet of a system to be recovered, and the air heat exchanger is connected to an air inlet of the system to be recovered;

[0024] An intermediate water system is arranged between the flue gas heat exchanger and the air heat exchanger, the intermediate water system comprising an intermediate water circulation loop on the evaporation side and an intermediate water circulation loop on the condensation side;

[0025] The system also includes a high-temperature heat pump connected to the evaporation-side intermediate water circulation loop and the condensation-side intermediate water circulation loop;

[0026] The intermediate water circulation loop on the evaporation side includes a flue gas heat exchanger output branch and a first heat pump output branch. The flue gas heat exchanger output branch outputs the intermediate water after heat exchange with the hot flue gas to the high-temperature heat pump. The first heat pump output branch inputs the intermediate water after heat exchange with the high-temperature heat pump to the flue gas heat exchanger.

[0027] The intermediate water circulation loop on the condensing side includes an air heat exchanger output branch and a second heat pump output branch. The air heat exchanger output branch is used to transfer the intermediate water that has been heat exchanged with the cold air in the air heat exchanger to the high-temperature heat pump. The second heat pump output branch is used to output the intermediate water that has been heated again after absorbing the heat of the hot flue gas in the high-temperature heat pump to the air heat exchanger.

[0028] In a possible implementation, the intermediate water system further includes:

[0029] Connecting the air heat exchanger with the flue gas heat exchanger, and outputting the intermediate water after heat exchange with the hot flue gas in the flue gas heat exchanger to the first bypass of the air heat exchanger;

[0030] Connect the air heat exchanger and the flue gas heat exchanger, and output the intermediate water after heat exchange with the cold air in the air heat exchanger to the second bypass of the flue gas heat exchanger;

[0031] The first bypass and the second bypass are respectively provided with bypass electric valves for controlling the on and off of the bypass.

[0032] In a possible implementation, the starting point of the first bypass is set at the flue gas heat exchanger output branch, and the end point of the first bypass is set at the second heat pump output branch;

[0033] The starting point of the second bypass is set at the output branch of the air heat exchanger, and the end point of the second bypass is set at the output branch of the first heat pump;

[0034] The flue gas heat exchanger output branch, the second heat pump output branch, the air heat exchanger output branch and the first heat pump output branch are respectively provided with a branch electric valve group, the branch electric valve group includes a first valve and a second valve located on both sides of the bypass starting point or end point, wherein the first valve is located on the side of the branch close to the high-temperature heat pump, and the second valve is located on the side of the branch far from the high-temperature heat pump;

[0035] The valves in the bypass electric valve and the branch electric valve group are closed or opened according to the preset control rules;

[0036] The preset control rules are:

[0037] When the high-temperature heat pump is running in operation, close the bypass electric valve and open the branch electric valve group;

[0038] When the high temperature heat pump is operated in a decoupling condition, the bypass electric valve and the second valve are opened, and the second valve is closed.

[0039] In a possible implementation, a circulating water pump is provided on at least one branch of the high-temperature heat pump.

[0040] In a possible implementation, the flue gas heat exchanger is connected to the hot flue gas outlet of the system to be recovered through a circulating water pump, and the air heat exchanger is connected to the air inlet of the system to be recovered through a circulating water pump.

[0041] In summary, the flue gas waste heat recovery control method, related equipment and system provided by the present application, when judging that the difference between the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger reaches the preset heat exchange end difference threshold, estimates the economic benefits of the heat pump operation condition at the next moment and the economic benefits of the heat pump decoupling condition, compares the economic benefits of the high-temperature heat pump under these two conditions, and controls the high-temperature heat pump to operate under the condition with greater economic benefits. The high-temperature heat pump in the flue gas waste heat recovery control system provided by the present application increases the heat exchange with the hot flue gas by increasing the heat exchange end difference by lowering the temperature of the intermediate water output from the evaporation side of the high-temperature heat pump, that is, lowering the temperature of the intermediate water that exchanges heat with the hot flue gas in the flue gas heat exchanger; by extracting the heat of the intermediate water that absorbs the heat of the flue gas through the high-temperature heat pump and performing heat lifting, the cold air reaches a temperature higher than the hot flue gas after heat exchange on the basis of completely absorbing the heat of the hot flue gas. Therefore, the present application can increase the amount of waste heat recovery from hot flue gas while ensuring greater economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] The above and other features, advantages and aspects of the embodiments of the present disclosure will become more apparent with reference to the following detailed description in conjunction with the accompanying drawings. Throughout the accompanying drawings, the same or similar reference numerals represent the same or similar elements. It should be understood that the drawings are schematic and the originals and elements are not necessarily drawn to scale.

[0043] Figure 1 A schematic diagram of the composition structure of a flue gas waste heat recovery control system based on the gas-to-gas heat exchange principle in the known technology provided in this application;

[0044] Figure 2 A schematic diagram of the composition structure of a flue gas waste heat recovery control system based on the gas-water heat exchange principle in the known technology provided in this application;

[0045] Figure 3 A schematic diagram of a flow chart of the flue gas waste heat recovery control method provided in this application;

[0046] Figure 4 A flow chart showing an example of a flue gas waste heat recovery control method provided in this application;

[0047] Figure 5 The structure diagram of the flue gas waste heat recovery control device provided for this application;

[0048] Figure 6 Schematic diagram of the composition structure of the flue gas waste heat recovery control system provided in this application. DETAILED DESCRIPTION

[0049] The following describes the embodiments of the present application in conjunction with the drawings in the embodiments of the present application. The terms used in the implementation method section of the present application are only used to explain the specific embodiments of the present application, and are not intended to limit the present application.

[0050] The embodiments of the present application are described below in conjunction with the accompanying drawings. Those skilled in the art will appreciate that, with the development of technology and the emergence of new scenarios, the technical solutions provided in the embodiments of the present application are also applicable to similar technical problems.

[0051] The terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and need not be used to describe a specific order or sequential order. It should be understood that the terms used in this way can be interchangeable under appropriate circumstances, which is only to describe the distinction mode adopted by the objects of the same attributes when describing in the embodiments of the present application. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, so that the process, method, system, product or equipment comprising a series of units need not be limited to those units, but may include other units that are not clearly listed or inherent to these processes, methods, products or equipment.

[0052] Taking the flue gas waste heat recovery system used in the spray drying system as an example, various flue gas waste heat recovery systems existing in the known technology are introduced.

[0053] Spray drying is one of the main drying technologies nowadays, and is widely used in food, pharmaceutical and chemical industries for products of different properties. The spray drying system can disperse the materials to be dried into fine mist-like particles, and contact these particles with the high-temperature flue gas discharged by the gas hot air furnace, which can instantly remove most of the moisture in the particulate materials, and finally obtain the solid matter in the materials dried into powder.

[0054] Specifically, the above drying process occurs in a spray drying tower in a spray drying system. The drying medium in the spray drying tower is hot air or hot flue gas. The drying medium can be prepared by a gas hot air furnace or a blower in conjunction with a steam heating system.

[0055] The operation process of the spray drying system in the known technology is as follows: the blower pressurizes the cold air and blows it into the gas hot air furnace for combustion. After combustion, the high-temperature flue gas above 200°C enters the spray drying tower to dry the material and then enters the dust removal system. The dust removal system purifies the flue gas and then discharges it from the tail of the spray drying tower. The temperature of the discharged flue gas is 60~120°C. Directly discharging the flue gas at 60~120°C will cause a large amount of heat loss. In the known technology, a flue gas waste heat recovery system based on the gas-to-gas heat exchange principle or a flue gas waste heat recovery system based on the gas-to-water heat exchange principle is used to recover the heat in the discharged flue gas.

[0056] join Figure 1 , the present application provides a schematic diagram of the composition structure of a flue gas waste heat recovery system based on the gas-to-gas heat exchange principle in the known technology.

[0057] The flue gas waste heat recovery system is equipped with an air-to-air heat exchanger between the tail of the spray drying tower and the cold air. Before the cold air enters the gas hot blast furnace, it exchanges heat with the hot flue gas to be discharged from the dust removal system. After preheating, it enters the gas hot blast furnace for combustion. The pre-discharged flue gas is further cooled after passing through the air-to-air heat exchanger before being discharged.

[0058] The implementation principle of the flue gas waste heat recovery system based on the gas-to-gas heat exchange principle in the known technology is direct heat exchange between the flue gas and the cold air.

[0059] See also Figure 2 , the present application provides a schematic diagram of the composition structure of a flue gas waste heat recovery system based on the gas-water heat exchange principle in the known technology.

[0060] The flue gas waste heat recovery system is equipped with an air-water heat exchanger on the flue gas side where the tail of the spray drying tower is located and on the air side where the gas hot blast furnace is located. An intermediate water system is configured between the hot flue gas and the cold air. The intermediate water absorbs the flue gas waste heat to raise its temperature. The heated intermediate water then flows from the flue gas side to the air side to heat the cold air and then feeds back to the flue gas side to continue heat exchange, in an endless cycle.

[0061] The implementation principle of the flue gas waste heat recovery system based on the air-water heat exchange principle in the known technology is to indirectly complete the heat exchange between the flue gas and the cold air through the intermediate water.

[0062] However, the waste heat recovery effect of these two flue gas waste heat recovery systems in the known technology is not good. The heat exchange effect of the flue gas waste heat recovery system based on the gas-to-gas heat exchange principle depends on the performance of the gas-to-gas heat exchanger. The heat transfer coefficient of the gas-to-gas heat exchanger is low, and the heat exchange end difference often needs to be greater than 10°C. For example, for projects in areas such as hot summers and cold winters, the summer inlet air temperature can reach above 30°C. If the ventilation temperature of the machine room is not good, the inlet air temperature will be higher. Due to the limitation of the smoke and air temperature difference, the inlet air temperature does not rise high, which will result in a small amount of waste heat recovery, and it is impossible to utilize the full value chain of the hot flue gas waste heat polarity output in the spray drying system.

[0063] The flue gas waste heat recovery system based on the air-water heat exchange principle uses an intermediate water system to transfer the waste heat in the hot flue gas to the cold air. The air-water heat exchanger has a higher heat transfer system and the heat exchange end difference can be reduced to below 5°C. Compared with the flue gas waste heat recovery system based on the air-to-air heat exchange principle, the waste heat recovery amount of the flue gas waste heat recovery system based on the air-to-water heat exchange principle will increase and the size of the heat exchanger will be reduced accordingly.

[0064] In addition, the air-to-air heat exchanger in the flue gas waste heat recovery system based on the air-to-air heat exchange principle has gas on both sides, and the size of the smoke and air duct is much larger than the water pipe. When arranging on site, it is necessary to consider the accessories such as the elbows and reducers of the smoke and air duct, which is cumbersome and occupies a large space. However, the air-to-water heat exchanger in the flue gas waste heat recovery system based on the air-to-water heat exchange principle occupies less space in the project and has stronger applicability. In the same installation site, the air-to-water heat exchanger has a larger heat exchange capacity. Therefore, the flue gas waste heat recovery system based on the air-to-water heat exchange principle in the prior art has a larger waste heat recovery capacity than the flue gas waste heat recovery system based on the air-to-air heat exchange principle.

[0065] However, due to the temperature difference between hot flue gas and cold air, the temperature of the cold air after absorbing the waste heat of hot flue gas in the two flue gas waste heat recovery systems in the known technologies cannot exceed the temperature of the hot flue gas. There is an upper limit to the waste heat recovery amount, and the waste heat recovery amount cannot be further increased.

[0066] In order to solve the above problems, the present application provides a flue gas waste heat recovery control method, related equipment and system. The present application can greatly increase the waste heat recovery amount of hot flue gas compared with the known technology on the basis of greater economic benefits.

[0067] The flue gas waste heat recovery control system provided in the present application includes a flue gas heat exchanger, an air heat exchanger, and an intermediate water system arranged between the flue gas heat exchanger and the air heat exchanger, wherein the intermediate water system includes an intermediate water circulation loop on the evaporation side and an intermediate water circulation loop on the condensation side; the flue gas waste heat recovery control system provided in the present application also includes a high-temperature heat pump connecting the intermediate water circulation loop on the evaporation side and the intermediate water circulation loop on the condensation side.

[0068] Among them, the high-temperature heat pump is the key to improving the flue gas waste heat recovery rate of the flue gas waste heat recovery control system. On the one hand, the high-temperature heat pump reduces the temperature of the intermediate water output on the evaporation side, that is, reduces the temperature of the intermediate water that exchanges heat with the hot flue gas in the flue gas heat exchanger, so as to increase the heat exchange end difference and increase the heat exchange with the hot flue gas; on the other hand, the high-temperature heat pump will use electricity to reheat the intermediate water that has absorbed the heat of the flue gas, so that the cold air can reach a temperature higher than the hot flue gas after heat exchange on the basis of completely absorbing the heat in the hot flue gas.

[0069] Taking the flue gas waste heat recovery control system used in the spray drying system as an example, the high-temperature hot water produced by the high-temperature heat pump is used to heat the cold air input into the gas hot air furnace in the spray drying system. The higher the air temperature input into the gas hot air furnace, the lower the amount of gas required by the gas hot air furnace, thereby reducing the gas cost.

[0070] From the perspective of the energy cost required for the entire spray drying system and its flue gas waste heat recovery control system, the inventors found that the prices of gas and electricity are different in different time periods. Natural gas prices are usually divided into heating season and non-heating season. Electricity prices may also differ at different times in different seasons. In the non-heating season and high-temperature electricity price period, natural gas prices are lower and electricity prices are higher. This may result in the saved gas cost being lower than the cost of electricity input into the high-temperature heat pump, resulting in an energy inversion.

[0071] In order to solve the above problems, the present application provides a flue gas waste heat recovery control method.

[0072] It should be noted that the executor of this specific embodiment is a controller of a flue gas waste heat recovery control system deployed in a cloud or local group control system. An intelligent algorithm is running in real time in the controller. The intelligent algorithm can calculate in real time the overall energy benefits of the flue gas waste heat recovery system and the flue gas waste heat recovery control system corresponding to the flue gas waste heat recovery system under different operating conditions of the high-temperature heat pump.

[0073] See also Figure 3 , a flow chart of a flue gas waste heat recovery control method provided in the present application.

[0074] Step 101: Collect IoT data at the current moment, wherein the IoT data includes: outlet water temperature of a high-temperature heat pump condenser and outlet air temperature of an air heat exchanger.

[0075] In addition, the current IoT data also includes: flue gas temperature at the inlet of the flue gas heat exchanger, flue gas temperature at the outlet of the flue gas heat exchanger, air temperature at the inlet of the air heat exchanger, water inlet and outlet temperatures of the high-temperature heat pump evaporator, and water inlet temperature of the high-temperature heat pump condenser.

[0076] The IoT data at the current moment can be specifically collected by a temperature sensor installed on the flue gas waste heat recovery control system.

[0077] Specifically, the inlet flue gas temperature of the flue gas heat exchanger is collected by a temperature sensor installed at the inlet of the flue gas heat exchanger, and the outlet flue gas temperature of the flue gas heat exchanger is collected by a temperature sensor installed at the outlet of the flue gas heat exchanger; the inlet air temperature of the air heat exchanger is collected by a temperature sensor installed at the inlet of the air heat exchanger, and the outlet air temperature of the air heat exchanger is collected by a temperature sensor installed at the outlet of the air heat exchanger; the inlet water temperature of the high-temperature heat pump evaporator is collected by a temperature sensor installed at the water inlet of the high-temperature heat pump evaporator, and the outlet water temperature of the high-temperature heat pump evaporator is collected by a temperature sensor installed at the water outlet of the high-temperature heat pump evaporator; the inlet water temperature of the high-temperature heat pump condenser is collected by a temperature sensor installed at the water inlet of the high-temperature heat pump condenser, and the outlet water temperature of the high-temperature heat pump condenser is collected by a temperature sensor installed at the water outlet of the high-temperature heat pump condenser.

[0078] Optionally, the controller collects the outlet water temperature of the high-temperature heat pump condenser through a temperature sensor deployed at the outlet of the high-temperature heat pump condenser, and collects the outlet air temperature of the air heat exchanger through a temperature sensor deployed at the outlet of the air heat exchanger.

[0079] Step 102: If the difference between the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger is greater than the preset air heat exchange end difference, the outlet water temperature of the high-temperature heat pump condenser is adjusted to be lowered according to the preset difference, and the step of collecting the IoT data at the current moment is returned to execute; the initial setting value of the outlet water temperature of the high-temperature heat pump condenser is the maximum outlet water temperature allowed by the high-temperature heat pump condenser.

[0080] It should be noted that the preset air heat exchanger heat exchange end difference is the heat exchange end difference calibrated in the air heat exchanger, specifically the difference between the preset air heat exchanger high temperature side inlet medium temperature and the air heat exchanger low temperature side outlet medium temperature. In this application, the high temperature heat pump condenser water outlet temperature is equivalent to the air heat exchanger high temperature side inlet medium temperature, and the air heat exchanger outlet air temperature is equivalent to the air heat exchanger low temperature side outlet medium temperature.

[0081] It should be noted that the purpose of setting the preset air heat exchanger heat exchange end difference is to ensure the normal operation of the heat exchange mechanism in the air heat exchanger, which can be understood as a protection threshold set in the air heat exchanger. For example, the preset air heat exchanger heat exchange end difference can be set to 7°C.

[0082] It can be understood that the preset air heat exchanger end difference is not the actual heat exchange end difference when the air heat exchanger is actually operating. The actual heat exchange end difference is the difference between the high-temperature heat pump condenser outlet water temperature and the low-temperature side outlet medium temperature of the air heat exchanger in actual operation.

[0083] First, the intelligent algorithm in the controller will set the initial setting value of the high-temperature heat pump condenser outlet water temperature to the maximum outlet water temperature allowed by the high-temperature heat pump condenser. For example, a high-temperature heat pump can generally heat water to 80~120℃, so the initial setting value of the high-temperature heat pump condenser outlet water temperature can be 120℃.

[0084] It should be noted that the outlet water temperature of the high-temperature heat pump condenser takes the highest value. At this time, the heat absorption and heat release of the high-temperature heat pump are both at a low state, and the coefficient of performance COP is also at a low state. At this time, the heat absorbed by the air side of the air heat exchanger is also low. Naturally, the outlet air temperature of the air heat exchanger is also low. At this time, the actual heat exchange end difference of the air heat exchanger is very large, far greater than the preset heat exchange end difference of the air heat exchanger, but at this time, the amount of waste heat recovered from the entire flue gas is very small.

[0085] It is understandable that as the outlet water temperature of the high-temperature heat pump condenser decreases, the actual heat exchange end difference of the air heat exchanger will gradually approach the preset air heat exchange end difference. In this process, more and more heat is absorbed by the air side of the air heat exchanger, that is, the amount of waste heat recovered from the flue gas increases.

[0086] Optionally, the difference between the outlet water temperature of the high-temperature heat pump condenser in actual operation and the outlet medium temperature of the low-temperature side of the air heat exchanger in actual operation is judged to be greater than the preset heat exchange end difference of the air heat exchanger. When the actual heat exchange end difference is greater than the preset heat exchange end difference, a large amount of flue gas waste heat is recovered by lowering the outlet water temperature of the high-temperature heat pump condenser.

[0087] Specifically, the preset difference can be set to 1°C. As long as the actual heat exchange end difference of the air heat exchanger is greater than the preset heat exchange end difference, the high-temperature heat pump condenser outlet water temperature will be lowered by 1°C. After the adjustment, the IoT data will be recollected, and the actual heat exchange end difference will be calculated. The above steps will be repeated until the actual heat exchange end difference is close to the preset heat exchange end difference. At this time, the optimal operating condition is reached for the entire flue gas waste heat recovery system, that is, the operating condition with the largest flue gas waste heat recovery amount.

[0088] Step 103: until the difference between the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger reaches a preset heat exchange end difference threshold, estimate the economic benefits of the heat pump operation condition and the economic benefits of the heat pump de-coupling condition at the next moment.

[0089] It should be noted that the preset heat exchange end difference threshold value may be the preset air heat exchange end difference mentioned above, or a value close to the preset heat exchange end difference threshold value. For example, when the preset air heat exchange end difference is 7°C, the preset heat exchange end difference threshold value may be set to 8°C, 7°C, 6°C, etc., which are values ​​close to 7°C.

[0090] Optionally, when the difference between the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger reaches a preset heat exchange end difference threshold, that is, when the flue gas waste heat recovery amount reaches the maximum, the economic benefits of the heat pump operation condition at the next moment and the economic benefits of the heat pump decoupling condition are estimated.

[0091] Specifically, the calculation process of system benefits during the operation of the high-temperature heat pump is as follows:

[0092] First, calculate the hourly heat exchange of the flue gas heat exchanger. The calculation formula is:

[0093] N y =Q y (h y,out -h y,in )

[0094] Among them, N y The hourly heat exchange of the flue gas heat exchanger; Qy is the hot blast stove flue gas flow rate; h y,out h is the flue gas enthalpy at the flue gas heat exchanger outlet; y,in is the enthalpy of flue gas at the inlet of the flue gas heat exchanger. Calculate the hourly heat exchange of the air heat exchanger using the following formula:

[0095] N k =Q k (h k,out -h k,in )=N y ×COP / (COP-1)

[0096] Among them, N k is the hourly heat exchange of the air heat exchanger, Q k is the air flow rate of the hot blast furnace, h k,out h is the enthalpy of air at the outlet of the air heat exchanger; k,in is the enthalpy of air at the inlet of the air heat exchanger; COP is the hourly performance coefficient of the heat pump unit;

[0097] Calculate the hourly input power of the heat pump unit using the following formula:

[0098] N e =N y × (COP-1)

[0099] Among them, N e Input electricity to the heat pump unit hourly;

[0100] Calculate the flue gas temperature at the flue gas heat exchanger outlet, that is, the air temperature at the air heat exchanger outlet. The calculation formula is:

[0101] t y,out =t 4 +△t

[0102] t k,out =t 1 -△t

[0103] Among them, t y,out is the flue gas temperature at the flue gas heat exchanger outlet, t k,out is the outlet air temperature of the air heat exchanger, △t is the heat transfer end difference of the air heat exchanger, t 1 is the heat pump condenser outlet temperature, t 4 is the heat pump evaporator outlet temperature;

[0104] Calculate the gas saving income after the gas hot blast furnace absorbs heat from the incoming air:

[0105] S 1 =N k ×3600×P g / G g

[0106] Among them, S 1 The gas hot blast furnace saves gas revenue hourly after absorbing heat from incoming air. g is the natural gas price in the current quarter, G g is the calorific value of natural gas.

[0107] The net income of the system during the operation of the high-temperature heat pump is:

[0108] △S rbty =S 1 -S 2 = N y ×COP / (COP-1)×(COP×3600×P g / G g -P e )

[0109] P e is the unit price of electricity at the current time of the current quarter;

[0110] Correspondingly, the calculation process of the system benefit during the decoupling of the high-temperature heat pump is as follows:

[0111] The hourly heat transfer capacity of the flue gas heat exchanger is:

[0112] N y =Q y (h y,out -h y,in' )

[0113] The system benefit when the heat pump unit is disconnected is:

[0114] △S rbty1 =N y '×3600×P g / G g -P e ).

[0115] Step 104, compare the economic benefits of the heat pump operation condition at the next moment and the economic benefits of the heat pump decoupling condition, and control the high-temperature heat pump to operate in the heat pump operation condition or the heat pump decoupling condition based on the comparison result, so that the high-temperature heat pump is in the condition with greater economic benefits.

[0116] Specifically, when the economic benefit of the heat pump operation condition is greater than the economic benefit of the heat pump de-coupling condition, the high-temperature heat pump is controlled to operate in the heat pump operation condition, and the intelligent algorithm will continue to determine the current operating condition of the flue gas waste heat recovery control system. If the operating condition of the flue gas waste heat recovery control system is the operation condition, there is no need to change the operating condition; if the operating condition of the flue gas waste heat recovery control system is the de-coupling condition, the operating condition needs to be changed to the operation condition.

[0117] When the economic benefit of the heat pump operation condition is less than the economic benefit of the heat pump decoupling condition, the high-temperature heat pump is controlled to operate in the heat pump decoupling condition, and the intelligent algorithm will continue to determine the current operating condition of the flue gas waste heat recovery control system. If the operating condition of the flue gas waste heat recovery control system is the decoupling condition, there is no need to change the operating condition; if the operating condition of the flue gas waste heat recovery control system is the operation condition, it is necessary to change the operating condition to the decoupling condition.

[0118] It should be noted that before collecting the IoT data at the current moment, the controller will first build in data in the background, specifically the hourly climate database of the location of the flue gas waste heat recovery control system, which is used to predict the air temperature input into the air heat exchanger; the flue gas and air enthalpy value library, the maximum outlet water temperature of the high-temperature heat pump unit condenser and the minimum inlet water temperature of the high-temperature heat pump unit evaporator; the calorific value of natural gas at the location of the flue gas waste heat recovery control system and the hourly performance coefficient curve of the high-temperature heat pump unit.

[0119] The intelligent algorithm in the flue gas waste heat recovery control method provided in this application can calculate the optimal operating point in the entire system hour by hour. The optimal operating point can be understood as a higher-profit operating condition. By comparing the economic benefits of the high-temperature heat pump operation condition with the economic benefits of the high-temperature heat pump decoupling condition, the high-temperature heat pump can be operated at a higher-profit operating condition, thereby maximizing energy benefits.

[0120] To summarize, the flue gas waste heat recovery control method provided in the present application, when it is judged that the difference between the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger reaches a preset heat exchange end difference threshold, estimates the economic benefits of the heat pump operation condition at the next moment and the economic benefits of the heat pump decoupling condition, compares the economic benefits of the high-temperature heat pump under these two conditions, and controls the high-temperature heat pump to operate under the condition with greater economic benefits.

[0121] For example, see Figure 4 , a flow chart showing an example of a flue gas waste heat recovery control method provided in this application.

[0122] It should be noted that Figure 4 This is an example diagram of the operating logic of the flue gas waste heat recovery control method, which can also be called an example diagram of the intelligent algorithm logic running in the controller of the flue gas waste heat recovery control system.

[0123] First, the controller will first build in data in the background, specifically the hourly climate database of the location of the flue gas waste heat recovery control system, which is used to predict the air temperature input into the air heat exchanger; the flue gas and air enthalpy value library, the maximum outlet water temperature of the high-temperature heat pump unit condenser and the minimum inlet water temperature of the high-temperature heat pump unit evaporator; the calorific value of natural gas at the location of the flue gas waste heat recovery control system and the hourly performance coefficient curve of the high-temperature heat pump unit.

[0124] Then, the IoT data is captured. The IoT data is collected through various temperature sensors installed in the flue gas waste heat recovery control system. The IoT data includes the flue gas temperature h at the inlet of the flue gas heat exchanger. y,in and outlet flue gas temperature h y,out , air heat exchanger inlet air temperature h k,in and outlet air temperature h k,out , high temperature heat pump evaporator inlet water temperature t 3 and outlet water temperature t 4 ; High temperature heat pump condenser water inlet temperature t 2 and outlet water temperature t 1 .

[0125] The background built-in data and IoT data are the basis for the subsequent calculation of the economic benefits of the flue gas waste heat recovery control system under different operating conditions.

[0126] After that, the maximum outlet water temperature of the high temperature heat pump condenser is t 1,max Assign a value to the high temperature heat pump condenser outlet water temperature t 1 , that is: t 1 =t 1,max ; Then, determine the air temperature t at the air heat exchanger outlet from the captured IoT data k,out , calculate the difference between the highest outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger, and determine whether the difference between the highest outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger is greater than or equal to the preset air heat exchange end heat difference, t 1 -t k,out ≥△t, when the difference between the highest outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger is greater than the preset air heat exchanger end heat difference, the outlet water temperature of the high-temperature heat pump condenser is reduced by 1 degree Celsius, that is: t 1,i =t 1,i-1 -1; execute the above calculation and judgment process again.

[0127] When the difference between the highest outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger reaches the preset end heat difference threshold, the economic benefit S of the heat pump operation condition at the next moment is estimated. rbty And the economic benefits of heat pump decoupling S rbjl .

[0128] Then, determine the economic benefit S of the heat pump operation condition rbty Is it greater than the economic benefit S of the heat pump decoupling condition? rbjl , when S rbty >S rbjlWhen the high temperature heat pump is in operation, it is determined whether the operating condition of the high temperature heat pump is in operation. If the operating condition of the high temperature heat pump is in operation, the operation strategy remains unchanged at the next moment; if the operating condition of the high temperature heat pump is not in operation, the operation strategy is switched at the next moment.

[0129] When S rbty Less than S rbjl When the high-temperature heat pump is in a disconnected condition, it is determined whether the current operating condition of the high-temperature heat pump is a disconnected condition. If the current operating condition of the high-temperature heat pump is a disconnected condition, the operation strategy remains unchanged at the next moment; if the current operating condition of the high-temperature heat pump is not a disconnected condition, the operation strategy is switched at the next moment.

[0130] Optionally, for the above-mentioned flue gas waste heat recovery control method, the present application also provides a flue gas waste heat recovery control device, see Figure 5 , the structural diagram of the flue gas waste heat recovery control device provided in this application.

[0131] like Figure 5 As shown, it includes a collection unit 10, a judgment unit 20, an estimation unit 30 and a control unit 40; wherein:

[0132] The collection unit 10 is used to collect IoT data at the current moment, and the IoT data includes: the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger;

[0133] The judgment unit 20 is used to adjust and lower the high-temperature heat pump condenser outlet water temperature according to the preset difference if the difference between the high-temperature heat pump condenser outlet water temperature and the air temperature at the air heat exchanger outlet is greater than the preset air heat exchange end difference, and return to the step of collecting the IoT data at the current moment; the initial setting value of the high-temperature heat pump condenser outlet water temperature is the maximum outlet water temperature allowed by the high-temperature heat pump condenser;

[0134] The estimation unit 30 is used to estimate the economic benefits of the heat pump operation condition and the economic benefits of the heat pump decoupling condition at the next moment until the difference between the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger reaches a preset heat exchange end difference threshold;

[0135] The control unit 40 is used to compare the economic benefits of the heat pump operation condition at the next moment and the economic benefits of the heat pump decoupling condition, and based on the comparison result, control the high-temperature heat pump to operate in the heat pump operation condition or the heat pump decoupling condition, so that the high-temperature heat pump is in a condition with greater economic benefits.

[0136] Optionally, the present application further provides a flue gas waste heat recovery control device, comprising at least one processor and a memory connected to the processor, wherein:

[0137] The memory is used to store computer programs;

[0138] The processor is used to execute a computer program so that the flue gas waste heat recovery control system control device can implement the flue gas waste heat recovery control method as described in any one of the above.

[0139] Optionally, the present application also provides a computer program product, including computer-readable instructions, which, when executed on the computer program product, enable the computer program product to implement the flue gas waste heat recovery control method as described in any one of the above.

[0140] See also Figure 6 , a schematic diagram of the composition structure of the flue gas waste heat recovery control system provided in this application.

[0141] The flue gas waste heat recovery control system mainly includes a flue gas heat exchanger, an air heat exchanger, a high-temperature heat pump and an intermediate water system.

[0142] The flue gas heat exchanger is connected to the hot flue gas outlet of the system to be recovered, and the air heat exchanger is connected to the air inlet of the system to be recovered. It should be noted that the system to be recovered is any system that requires flue gas waste heat recovery, including but not limited to a spray drying system. This specific embodiment takes the spray drying system as an example of the system to be recovered.

[0143] An intermediate water system is set between the flue gas heat exchanger and the air heat exchanger. The flue gas heat exchanger exchanges heat from the hot flue gas discharged from the hot flue gas outlet of the system to be recovered with the intermediate water in the intermediate water system. The intermediate water that has exchanged heat from the hot flue gas in the intermediate water system is circulated to the air heat exchanger to exchange heat with the cold air at the air inlet of the system to be recovered.

[0144] The intermediate water system comprises an intermediate water circulation loop on the evaporation side and an intermediate water circulation loop on the condensation side, and the high-temperature heat pump connects the intermediate water circulation loop on the evaporation side and the intermediate water circulation loop on the condensation side.

[0145] The intermediate water circulation loop on the evaporation side includes a flue gas heat exchanger output branch and a first heat pump output branch. The flue gas heat exchanger output branch outputs the intermediate water after heat exchange with the hot flue gas to the high-temperature heat pump, and the first heat pump output branch inputs the intermediate water after heat exchange with the refrigerant in the high-temperature heat pump to the flue gas heat exchanger.

[0146] The intermediate water circulation loop on the condensation side includes an air heat exchanger output branch and a second heat pump output branch. The air heat exchanger output branch is used to transfer the intermediate water after heat exchange with the cold air in the air heat exchanger to the high-temperature heat pump, and the second heat pump output branch is used to output the intermediate water heated again by the high-temperature heat pump to the air heat exchanger.

[0147] Optionally, the intermediate water system further includes connecting the air heat exchanger with the flue gas heat exchanger to output the intermediate water after heat exchange with hot flue gas in the flue gas heat exchanger to a first bypass in the air heat exchanger, and connecting the air heat exchanger with the flue gas heat exchanger to output the intermediate water after heat exchange with cold air in the air heat exchanger to a second bypass in the flue gas heat exchanger.

[0148] It should be noted that both the first bypass and the second bypass need to be provided with bypass electric valves for controlling the on and off of the bypass.

[0149] Specifically, the starting point of the first bypass is set on the flue gas output branch, and the end point is set on the second heat pump output branch; the starting point of the second bypass is set on the cold air output branch, and the end point is set on the first heat pump output branch. In addition, the flue gas output branch, the second heat pump output branch, the cold air output branch and the first heat pump output branch are all provided with branch electric valve groups, and the branch electric valve groups include a first valve and a second valve located on both sides of the bypass starting point or end point, the first valve is located on the side of the branch close to the high-temperature heat pump, and the second valve is located on the side of the branch far from the high-temperature heat pump.

[0150] It should be noted that at least one circulating water pump is provided on the intermediate water circulation loop on the evaporation side, and at least one circulating water pump is provided on the intermediate water circulation loop on the condensation side.

[0151] Optionally, the flue gas heat exchanger is connected to the flue gas outlet of the system to be recovered through a circulating water pump; and the air heat exchanger is connected to the air inlet of the system to be recovered through a circulating water pump.

[0152] When the working conditions of the high-temperature heat pump in the flue gas waste heat system in the present application are different, the opening and closing conditions of the bypass electric valve, the branch electric valve group and the circulating water pump are different.

[0153] When the high-temperature heat pump is in operation, close the bypass electric valve, open the branch electric valve group, and start the condensing side circulating water pump and the evaporating side circulating water pump;

[0154] When the high-temperature heat pump is in the decoupling condition, open the bypass electric valve and the second valve, close the second valve, start the circulating water pump on the condensing side, and close the circulating water pump on the evaporating side.

[0155] Specifically, when the high-temperature heat pump is in operation, the bypass electric valve A is closed, B and C in the branch electric valve group are opened, the condensing side circulating water pump a and the evaporating side circulating water pump b are turned on, and the heat pump operation strategy is executed.

[0156] When the high-temperature heat pump is in the decoupling condition, open the bypass electric valve A and C in the branch electric valve group, close B in the branch electric valve group, start the condensing side circulating water pump a, close the evaporating side circulating water pump b, and execute the heat pump decoupling strategy.

[0157] It should be noted that the flue gas waste heat recovery control system provided in the present application mainly includes a flue gas heat exchanger on the flue gas side, an air heat exchanger on the air side, an industrial high-temperature heat pump unit, an evaporation side intermediate water system, and a condensation side intermediate water system configured between the flue gas side and the air side. The intermediate water in the evaporation side intermediate water system exchanges heat with the hot flue gas through the flue gas heat exchanger and is then input into the evaporator of the high-temperature heat pump unit to release heat and complete the cycle. After the high-temperature heat pump unit absorbs the waste heat of the flue gas, it is driven by an electric compressor to produce high-temperature hot water, and then the heat is transferred to the cold air through the air heat exchanger through the condensation side intermediate water system to heat the cold air and complete the waste heat recovery of the flue gas.

[0158] The industrial high-temperature heat pump unit includes a high-temperature heat pump unit evaporator and a high-temperature heat pump unit condenser. The high-temperature heat pump unit evaporator is used to absorb heat recovered from the hot flue gas, and the high-temperature heat pump unit condenser is used to release the heat from the hot flue gas and the overall heat after reheating by the high-temperature heat pump.

[0159] The key point that can solve the temperature difference limitation of flue gas heat exchange in the present application is to set up a high-temperature heat pump. The high-temperature heat pump can reduce the temperature of the intermediate water transported from the high-temperature heat pump to the flue gas heat exchanger in the intermediate circulation loop on the evaporation side, that is, reduce the refrigerant inlet temperature on the secondary side of the flue gas heat exchanger, and increase the heat exchange with the hot flue gas in the flue gas heat exchanger by increasing the heat exchange end difference, thereby increasing the heat recovery of flue gas waste heat; on the other hand, the high-temperature heat pump unit will heat the recovered heat in the hot flue gas again to produce high-temperature hot water of 80℃~120℃. Since the performance index COP of the high-temperature heat pump is greater than 1, the heat absorbed on the air side will be greater than the heat released on the flue gas side, so that the temperature of the preheated air input from the air heat exchanger to the gas hot blast furnace can be raised to a temperature higher than the temperature of the hot flue gas discharged from the dust removal system to the flue gas heat exchanger. The higher temperature of the preheated air can reduce the energy consumption of the gas hot blast furnace.

[0160] It should be noted that the heat absorbed by the preheated air input by the gas hot blast furnace is higher than the recovered heat of the hot flue gas. The excess heat is mainly provided by the input power of the high-temperature heat pump. The heat equation between the flue gas side and the air side can be expressed as: heat released by the flue gas side + input power of the high-temperature heat pump = heat absorbed by the air side.

[0161] In summary, the flue gas waste heat recovery control system provided by the present application includes a flue gas heat exchanger, an air heat exchanger, an intermediate water system arranged between the flue gas heat exchanger and the air heat exchanger, and a high-temperature heat pump. The high-temperature heat pump in the flue gas waste heat recovery control system provided by the present application increases the heat exchange with the hot flue gas by increasing the heat exchange end difference by lowering the temperature of the intermediate water output from the evaporation side of the high-temperature heat pump, that is, lowering the temperature of the intermediate water that exchanges heat with the hot flue gas in the flue gas heat exchanger; the heat of the intermediate water that has absorbed the heat of the flue gas is extracted by the high-temperature heat pump and the heat is increased, so that the cold air reaches a temperature higher than the hot flue gas after heat exchange on the basis of completely absorbing the heat of the hot flue gas. Therefore, the present application can increase the amount of waste heat recovery from the hot flue gas while ensuring greater economic benefits.

[0162] It should also be noted that the device embodiments described above are merely schematic, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed over multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. In addition, in the drawings of the device embodiments provided by the present application, the connection relationship between the modules indicates that there is a communication connection between them, which may be specifically implemented as one or more communication buses or signal lines.

[0163] Through the description of the above implementation mode, the technicians in the field can clearly understand that the present application can be implemented by means of software plus necessary general hardware, and of course, it can also be implemented by special hardware including special integrated circuits, special CPUs, special memories, special components, etc. In general, all functions completed by computer programs can be easily implemented by corresponding hardware, and the specific hardware structure used to implement the same function can also be various, such as analog circuits, digital circuits or special circuits. However, for the present application, software program implementation is a better implementation mode in more cases. Based on such an understanding, the technical solution of the present application is essentially or the part that contributes to the prior art can be embodied in the form of a software product, which is stored in a readable storage medium, such as a computer floppy disk, a U disk, a mobile hard disk, a ROM, a RAM, a disk or an optical disk, etc., including a number of instructions to enable a computer device (which can be a personal computer, a training device, or a network device, etc.) to execute the method of each embodiment of the present application.

[0164] In the above embodiments, all or part of the embodiments may be implemented by software, hardware, firmware or any combination thereof. When implemented by software, all or part of the embodiments may be implemented in the form of a computer program product.

[0165] The computer program product includes one or more computer instructions. When the computer program instructions are loaded and executed on the computer, the process or function according to the embodiment of the present application is generated in whole or in part. The computer can be a general-purpose computer, a special-purpose computer, a computer network, or other programmable devices. The computer instructions can be stored in a computer-readable storage medium, or transmitted from one computer-readable storage medium to another computer-readable storage medium. For example, the computer instructions can be transmitted from a website site, a computer, a training device or a data center by wired (e.g., coaxial cable, optical fiber, digital subscriber line (DSL)) or wireless (e.g., infrared, wireless, microwave, etc.) mode to another website site, computer, training device or data center. The computer-readable storage medium can be any available medium that a computer can store or a data storage device such as a training device, a data center, etc. that includes one or more available media integration. Available media can be magnetic media, (e.g., floppy disk, hard disk, tape), optical media (e.g., DVD), or semiconductor media (e.g., solid-state hard disk (SSD)), etc.

Claims

1. A flue gas waste heat recovery control method, characterized in that: Applied to a flue gas waste heat recovery control system, the flue gas waste heat recovery control system comprises a flue gas heat exchanger, an air heat exchanger, and an intermediate water system arranged between the flue gas heat exchanger and the air heat exchanger; the intermediate water system comprises an evaporation side intermediate water circulation loop and a condensation side intermediate water circulation loop; and a high-temperature heat pump connecting the evaporation side intermediate water circulation loop and the condensation side intermediate water circulation loop; The control method comprises: Collecting IoT data at the current moment, the IoT data including: outlet water temperature of a high-temperature heat pump condenser and outlet air temperature of an air heat exchanger; If the difference between the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger is greater than the preset air heat exchange end difference, the outlet water temperature of the high-temperature heat pump condenser is adjusted and lowered according to the preset difference, and the step of collecting IoT data at the current moment is returned to execute; the initial setting value of the outlet water temperature of the high-temperature heat pump condenser is the maximum outlet water temperature allowed by the high-temperature heat pump condenser; Until the difference between the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger reaches a preset heat exchange end difference threshold, the economic benefits of the heat pump operation condition and the economic benefits of the heat pump decoupling condition at the next moment are estimated; The economic benefits of the heat pump operation condition at the next moment and the economic benefits of the heat pump decoupling condition are compared, and based on the comparison result, the high-temperature heat pump is controlled to operate in the heat pump operation condition or the heat pump decoupling condition, so that the high-temperature heat pump is in the condition with greater economic benefits.

2. The flue gas waste heat recovery control method according to claim 1, characterized in that: The comparing the economic benefits of the heat pump operation condition at the next moment and the economic benefits of the heat pump disconnection condition, and controlling the high-temperature heat pump to operate in the heat pump operation condition or the heat pump disconnection condition according to the comparison result, so that the high-temperature heat pump is in the condition with the larger economic benefits, includes: When the economic benefit of the heat pump operation condition is greater than the economic benefit of the heat pump de-energized condition, controlling the high-temperature heat pump to operate in the heat pump operation condition; When the economic benefit of the heat pump operation condition is less than the economic benefit of the heat pump decoupled condition, the high-temperature heat pump is controlled to operate in the heat pump decoupled condition.

3. A flue gas waste heat recovery control device, characterized in that: Applied to a flue gas waste heat recovery control system, the flue gas waste heat recovery control system comprises a flue gas heat exchanger, an air heat exchanger, and an intermediate water system arranged between the flue gas heat exchanger and the air heat exchanger; the intermediate water system comprises an evaporation side intermediate water circulation loop and a condensation side intermediate water circulation loop; and a high-temperature heat pump connecting the evaporation side intermediate water circulation loop and the condensation side intermediate water circulation loop; the device comprises: Collection unit, judgment unit, estimation unit and control unit; wherein: The collection unit is used to collect IoT data at the current moment, wherein the IoT data includes: the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger; The judgment unit is used to adjust and lower the outlet water temperature of the high-temperature heat pump condenser according to the preset difference if the difference between the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger is greater than the preset air heat exchange end difference, and return to the step of collecting the IoT data at the current moment; the initial setting value of the outlet water temperature of the high-temperature heat pump condenser is the maximum outlet water temperature allowed by the high-temperature heat pump condenser; The estimation unit is used to estimate the economic benefits of the heat pump operation condition and the economic benefits of the heat pump decoupling condition at the next moment until the difference between the outlet water temperature of the high-temperature heat pump condenser and the outlet air temperature of the air heat exchanger reaches a preset heat exchange end difference threshold; The control unit is used to compare the economic benefits of the heat pump operation condition and the economic benefits of the heat pump decoupling condition at the next moment, and control the high-temperature heat pump to operate in the heat pump operation condition or the heat pump decoupling condition based on the comparison result, so that the high-temperature heat pump is in the condition with greater economic benefits.

4. A flue gas waste heat recovery control device, characterized in that: The method comprises at least one processor and a memory connected to the processor, wherein: The memory is used to store computer programs; The processor is used to execute the computer program so that the flue gas waste heat recovery control device can implement the flue gas waste heat recovery control method as described in any one of claims 1 to 2.

5. A computer program product, characterized in that It comprises computer-readable instructions, and when the computer-readable instructions are executed on a computer program product, the computer program product implements the flue gas waste heat recovery control method as claimed in any one of claims 1 to 2.

6. A flue gas waste heat recovery control system, characterized in that: include: A flue gas heat exchanger and an air heat exchanger, wherein the flue gas heat exchanger is connected to the hot flue gas outlet of the system to be recovered, and the air heat exchanger is connected to the air inlet of the system to be recovered; An intermediate water system is arranged between the flue gas heat exchanger and the air heat exchanger, the intermediate water system comprising an evaporation side intermediate water circulation loop and a condensation side intermediate water circulation loop; The system further includes a high-temperature heat pump connected to the evaporation-side intermediate water circulation loop and the condensation-side intermediate water circulation loop; The evaporation side intermediate water circulation loop includes a flue gas heat exchanger output branch and a first heat pump output branch. The flue gas heat exchanger output branch outputs the intermediate water after heat exchange with hot flue gas to the high-temperature heat pump. The first heat pump output branch inputs the intermediate water after heat exchange with the high-temperature heat pump to the flue gas heat exchanger. The intermediate water circulation loop on the condensing side includes an air heat exchanger output branch and a second heat pump output branch. The air heat exchanger output branch is used to transfer the intermediate water that has been heat exchanged with the cold air in the air heat exchanger to the high-temperature heat pump. The second heat pump output branch is used to output the intermediate water that has been heated again after absorbing the heat of the hot flue gas in the high-temperature heat pump to the air heat exchanger.

7. The flue gas waste heat recovery control system according to claim 6, characterized in that: The intermediate water system also includes: Connecting the air heat exchanger with the flue gas heat exchanger, and outputting the intermediate water in the flue gas heat exchanger after heat exchange with the hot flue gas to the first bypass of the air heat exchanger; Connecting the air heat exchanger with the flue gas heat exchanger, and outputting the intermediate water after heat exchange with the cold air in the air heat exchanger to the second bypass of the flue gas heat exchanger; The first bypass and the second bypass are respectively provided with bypass electric valves for controlling the on and off of the bypass.

8. The flue gas waste heat recovery control system according to claim 7, characterized in that: The starting point of the first bypass is set at the output branch of the flue gas heat exchanger, and the end point of the first bypass is set at the output branch of the second heat pump; The starting point of the second bypass is set at the output branch of the air heat exchanger, and the end point of the second bypass is set at the output branch of the first heat pump; The flue gas heat exchanger output branch, the second heat pump output branch, the air heat exchanger output branch and the first heat pump output branch are respectively provided with a branch electric valve group, the branch electric valve group includes a first valve and a second valve located at both sides of the bypass starting point or end point, wherein the first valve is located on the side of the branch close to the high-temperature heat pump, and the second valve is located on the side of the branch away from the high-temperature heat pump; The bypass electric valve and the valves in the branch electric valve group are closed or opened according to a preset control rule; The preset control rules are: When the high-temperature heat pump is running in operation, the bypass electric valve is closed and the branch electric valve group is opened; When the high-temperature heat pump is operated in a decoupled condition, the bypass electric valve and the second valve are opened, and the second valve is closed.

9. The flue gas waste heat recovery control system according to claim 8, characterized in that: A circulating water pump is provided on at least one branch of the high-temperature heat pump.

10. The flue gas waste heat recovery control system according to claim 6, characterized in that: The flue gas heat exchanger is connected to the hot flue gas outlet of the system to be recovered through a circulating water pump, and the air heat exchanger is connected to the air inlet of the system to be recovered through a circulating water pump.