Plugging structure and method for relief well of high-water-head foundation pit
By setting up a water stop structure and surge-resistant structure in the high-head foundation pit decompression well, groundwater is prevented from seeping in and counteracting water pressure, the problems of soil layer surge and seepage during the sealing process are solved, and the foundation stability and long-lasting sealing are enhanced. sex.
Patent Information
- Application Number
- CN202411152783.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-21
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-08-21
AI Technical Summary
During the sealing process of high-head foundation pit decompression wells, the increase in groundwater water pressure leads to the problem of bursting and failure of soil layers around the well and the dispersion of sealing materials. Moreover, if the soil is not reinforced during sealing, it may be damaged by seepage.
Using a sealing structure including a water stop structure and a rush-resistant structure, the water stop structure prevents groundwater from infiltration through a well sleeve and a water stop pad. The anti-surge structure uses shear components and anti-surge blocks to counter water pressure, and the sealing structure prevents groundwater from infiltration. , combine the shrinking member and the waterproof coating layer to improve sealing and stability.
Effectively prevent groundwater from rushing damage to the soil layer around the well, enhance foundation stability, reduce the impact of later corrosion seepage on the main structure, and ensure the effectiveness and durability of sealing.
Smart Images

Figure CN118958347A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pressure relief well construction, in particular to a plugging structure and method for a high-head foundation pit pressure relief well. Background Art
[0002] As the excavation depth of the foundation pit increases, the thickness of the relatively impermeable layer at the bottom of the foundation pit continues to decrease, and the water head difference inside and outside the pit gradually increases. Before the anti-floating structural measures of the main structure are formed, the project will face problems such as structural anti-floating. The current measures taken in the project are basically to first drill pressure relief wells inside and outside the foundation pit, and then extract groundwater to lower the water level during the excavation of the foundation pit, so as to ensure the sudden surge stability at the bottom of the foundation pit during the excavation of the foundation pit, and then seal the pressure relief well after the relevant stability conditions meet the requirements of the specification.
[0003] In the existing technology, the groundwater level in coastal areas is shallow, the recharge source is sufficient and the recharge speed is fast. If the foundation pit is excavated to a deep depth or some pressure relief wells are blocked, the pressure difference between the water head inside and outside the foundation pit faced during the blocking of the pressure relief wells is large. On the one hand, the groundwater flows into the pressure relief well very quickly during the blocking process, and the blocking materials are washed away by the groundwater and cannot effectively block the water. On the other hand, if the soil around the well is not reinforced during the blocking, it may be damaged by groundwater seepage. Summary of the invention
[0004] The purpose of the present invention is to solve at least one of the technical problems existing in the prior art. To this end, the present invention proposes a sealing structure and method for a high-head foundation pit pressure relief well, which can effectively reduce the adverse effects of the gradual increase in groundwater pressure on the sudden gushing and damage of the soil layer around the well during the sealing process of the pressure relief well.
[0005] According to the first aspect of the present invention, the sealing structure of the high-head foundation pit pressure relief well includes a water-stopping structure, which is arranged at the lower end of the structural bottom plate. The water-stopping structure includes a well casing and a water-stopping pad. The well casing is connected to the well wall of the pressure relief well. A plurality of water-stopping wing rings and a plurality of anti-shear components are arranged on the outer wall of the well casing. The plurality of water-stopping wing rings and the plurality of anti-shear components are arranged at intervals along the axial direction. The water-stopping pad is arranged coaxially with the well casing, the water-stopping pad is penetrated in the well casing, and the water-stopping pad is located at one end of the well casing close to the structural bottom plate; an anti-surge structure, which is arranged at the structure At the lower end of the structural bottom plate, the surge-proof structure is located in a relatively impermeable soil layer, the surge-proof structure includes an surge-proof block, the surge-proof block is coaxially arranged with the well casing, the surge-proof block is wrapped and arranged on the outer wall of the well casing, all the water-stop wing rings and all the shear-resistant components are located in the surge-proof block, and the surge-proof block is used to prevent the sudden surge of groundwater to the soil layer around the water-reduction well after the groundwater pressure gradually increases; a plugging structure, the plugging structure is arranged in the water-reduction well, the plugging structure extends from the water-reduction well to the inside of the well casing, and the plugging structure is used to prevent groundwater from surging into the water-stop structure along the water-reduction well.
[0006] The sealing structure of the high-head foundation pit pressure relief well according to the embodiment of the present invention has at least the following beneficial effects: the water-stop structure and the anti-surge structure are arranged at the lower end of the structural bottom plate, and the groundwater pressure is counteracted by the anti-surge block to prevent groundwater from seeping into the well casing and sealing the pressure relief well at the same time. On the one hand, it can avoid the adverse effects of sudden surge damage to the soil layer around the water reduction well after the groundwater pressure gradually increases, prevent soil infiltration and deformation to enhance the stability of the foundation; on the other hand, it can cut off the pollution path and effectively reduce the influence of the seepage of groundwater on the bottom plate of the main structure after the later corrosion of the well wall.
[0007] According to some embodiments of the present invention, a reducing member is provided at the lower end of the well casing, the well casing is connected to the water reduction well through the reducing member, the reducing member is penetrated in the water reduction well, and the inner diameter of the reducing member gradually decreases in the direction approaching the water reduction well.
[0008] According to some embodiments of the present invention, a waterproof coating layer is provided on the outer wall of the well casing.
[0009] According to some embodiments of the present invention, the shear-resistant assembly includes a plurality of shear-resistant steel bars evenly distributed in a ring shape, and each of the shear-resistant steel bars is respectively provided with a connecting piece and an anchor piece at two opposite ends, the connecting piece and the shear-resistant steel bar are perpendicular to each other, and the connecting piece and the well casing are parallel to each other, the shear-resistant steel bar is connected to the side wall of the well casing through the connecting piece, and the shear-resistant steel bar is anchored in the anti-surge block through the anchor piece.
[0010] According to some embodiments of the present invention, the anti-surge structure further includes a first cushion layer, and the first cushion layer is disposed at the lower end of the anti-surge block.
[0011] According to some embodiments of the present invention, the size of the surge-proof block is larger than the size of the reserved pit of the structure bottom plate.
[0012] According to the second aspect of the present invention, a method for plugging a high-head foundation pit pressure relief well adopts the above-mentioned plugging structure for the high-head foundation pit pressure relief well, comprising:
[0013] S1: Maintain the pressure reduction operation in the pressure relief well, excavate the anti-surge block foundation pit near the pressure relief well, and cut off the pressure relief well at a position higher than the bottom of the anti-surge block foundation pit;
[0014] S2: Maintain the pressure reduction operation in the pressure relief well and fix the well casing to the upper end of the pressure relief well;
[0015] S3: Lay the first cushion layer at the bottom of the pit of the anti-surge block foundation pit, build a concrete formwork after the first cushion layer forms the designed strength, and pour concrete in the concrete formwork to form the anti-surge block;
[0016] S4: After the surge block reaches the designed strength, backfill and compact the surrounding areas of the surge block, construct the structural bottom plate on the upper end of the surge block, and reserve a pit corresponding to the pressure relief well on the structural bottom plate;
[0017] S5: Stop the decompression operation of the decompression well, pump out the overflowing water from the decompression well in the pit, and fill the decompression well with concrete until the water level at the wellhead of the decompression well stops rising;
[0018] S6: Set the water stop pad in the well casing, construct the filling bottom plate in the pit, and make the filling bottom plate flush with the top of the structural bottom plate.
[0019] According to some embodiments of the present invention, in S4, a waterstop is provided on the inner wall of the pit along the circumferential direction, and the waterstop extends from the inside of the structural bottom plate toward the inside of the pit, and the waterstop is used for structural waterstopping.
[0020] According to some embodiments of the present invention, in S5, a waterproofing membrane is laid in the well casing, and the waterproofing membrane extends from the inside of the well casing to the pit.
[0021] According to some embodiments of the present invention, in S6, the compressive strength of the filling bottom plate is greater than the compressive strength of the structural bottom plate.
[0022] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] The present invention is further described below in conjunction with the accompanying drawings and embodiments:
[0024] Figure 1 It is a structural schematic diagram of a plugging structure for a high-head foundation pit pressure relief well according to an embodiment of the first aspect of the present invention;
[0025] Figure 2 yes Figure 1 Structural schematic diagram of the water stop structure;
[0026] Figure 3 yes Figure 2 A top view of the
[0027] Figure 4 It is a construction schematic diagram of S1 in the method for plugging a high-head foundation pit pressure relief well in an embodiment of the second aspect of the present invention;
[0028] Figure 5 It is a construction schematic diagram of S2 in the method for plugging a high-head foundation pit pressure relief well in an embodiment of the second aspect of the present invention;
[0029] Figure 6 It is a construction schematic diagram of S3 and S4 in the method for plugging a high-head foundation pit pressure relief well in an embodiment of the second aspect of the present invention;
[0030] Figure 7 It is a construction schematic diagram of S5 in the method for plugging a high-head foundation pit pressure relief well in an embodiment of the second aspect of the present invention;
[0031] Figure 8 It is a flow chart of a method for sealing a high-head foundation pit pressure relief well according to an embodiment of the second aspect of the present invention.
[0032] Reference numerals:
[0033] Water-stop structure 100, well casing 110, water-stop wing ring 111, shear-resistant assembly 112, shear-resistant steel bar 1121, connecting piece 1122, anchor piece 1123, reducing piece 113, water-stop pad 120, flange ring 121, flange plate 122;
[0034] The surge-resistant structure 200, the surge-resistant block 210, and the first cushion layer 220;
[0035] Blocking structure 300;
[0036] A structural base plate 400, a filling base plate 410, a second cushion layer 420, and a filling cushion layer 421;
[0037] Impermeable soil layer 10, water reduction well 20, water pump 30, anti-surge foundation pit 40, pit 50, water stop belt 51. DETAILED DESCRIPTION
[0038] This section will describe in detail the specific embodiments of the present invention. The preferred embodiments of the present invention are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the present invention, but it cannot be understood as a limitation on the scope of protection of the present invention.
[0039] In the description of the present invention, it should be understood that descriptions involving orientations, such as up, down, front, back, left, right, etc., and orientations or positional relationships indicated are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0040] In the description of the present invention, "several" means one or more, "more" means more than two, "greater than", "less than", "exceed" etc. are understood as not including the number itself, and "above", "below", "within" etc. are understood as including the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.
[0041] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.
[0042] refer to Figures 1 to 8 The plugging structure of a high-head foundation pit pressure relief well according to an embodiment of the present invention is described.
[0043] like Figures 1 to 8 As shown, the sealing structure of the high-head foundation pit pressure relief well according to the first embodiment of the present invention includes a water-stop structure 100, which is arranged at the lower end of the structural bottom plate 400. The water-stop structure 100 includes a well casing 110 and a water-stop pad 120. The well casing 110 is connected to the well wall of the pressure relief well. A plurality of water-stop wing rings 111 and a plurality of shear-resistant components 112 are arranged on the outer wall of the well casing 110. The plurality of water-stop wing rings 111 and the plurality of shear-resistant components 112 are arranged at intervals along the axial direction. The water-stop pad 120 is arranged coaxially with the well casing 110, and the water-stop pad 120 is penetrated in the well casing 110. The water-stop pad 120 is located at one end of the well casing 110 close to the structural bottom plate 400; the anti-surge structure 200, the anti-surge structure 20 0 is arranged at the lower end of the structural bottom plate 400, the anti-surge structure 200 is located in the relatively impermeable soil layer 10, the anti-surge structure 200 includes an anti-surge block 210, the anti-surge block 210 is coaxially arranged with the well casing 110, the anti-surge block 210 is wrapped and arranged on the outer wall of the well casing 110, all the water-stop wing rings 111 and all the shear components 112 are located in the anti-surge block 210, and the anti-surge block 210 is used to prevent the sudden surge of the soil layer around the water reduction well 20 after the groundwater pressure gradually increases; the plugging structure 300, the plugging structure 300 is arranged in the water reduction well 20, and is straddled between the well casing 110 and the water reduction well 20, and the plugging structure 300 is used to prevent groundwater from surging into the water-stop structure 100 along the water reduction well 20.
[0044] The geographical location advantage of coastal areas makes coastal land a rare resource. Therefore, in order to improve the utilization efficiency of land resources, high-rise buildings continue to emerge. It should be noted that the groundwater in coastal areas is adequately supplied by the nearby seawater recharge source, and its groundwater level is shallow and fluctuates with tidal fluctuations. However, as the excavation depth of the foundation pit increases, the thickness of the relatively impermeable layer at the bottom of the foundation pit continues to decrease, the head difference inside and outside the pit gradually increases, and the safety factor of the sudden surge stability at the bottom of the pit will be less than 1.0. Before the anti-floating structural measures of the main structure are formed, it will face problems such as structural anti-floating.
[0045] There are usually some problems in the plugging construction process of the pressure relief wells of high-head foundation pits in coastal areas. On the one hand, since the groundwater in coastal areas is connected to seawater, groundwater is corrosive to building materials. The well wall of the pressure relief well is prone to corrosion damage under the long-term action of groundwater. The groundwater seeps upward along the well wall of the pressure relief well left in the bottom plate structure, causing the steel bars of the main structure bottom plate 400 to be corroded, and the material properties of the structural bottom plate 400 are affected. On the other hand, the groundwater level in coastal areas is shallow, and the recharge source is sufficient and the recharge speed is fast. If the foundation pit is excavated at a deep depth or after plugging some pressure relief wells, the water head difference pressure inside and outside the foundation pit is large. During the plugging process, groundwater will flow into the pressure relief well at a high speed, causing the plugging materials to be dispersed by groundwater and unable to effectively plug and stop water. If the soil around the water relief well 20 is not reinforced during plugging, it may even be damaged by groundwater seepage.
[0046] like Figure 1 and Figure 2 As shown, the water stop structure 100 and the surge resistance structure 200 are buried at the lower end of the structural bottom plate 400, wherein the well casing 110 is axially arranged at the upper end of the water reduction well 20, and the diameter and thickness of the well casing 110 are the same as those of the pressure relief well, and the surge resistance block 210 is wrapped and straddled on the outer wall of the well casing 110 and the water reduction well 20, and covers and wraps the connection between the well casing 110 and the water reduction well 20. Two water stop wing rings 111 and two shear assemblies 112 are axially spaced on the outer peripheral wall of the well casing 110, and the shear assemblies 112 include at least eight shear steel bars 1121 uniformly distributed in an annular shape, and all the water stop wing rings 111 and shear steel bars 1121 are located in the surge resistance block 210. A water stop pad 120 is provided near the upper end of the well casing 110, and a plugging structure 300 is provided in the water reduction well 20, and the plugging structure 300 extends upward to the inside of the well casing 110 in the water reduction well 20, thereby forming a multiple blocking structure in combination with the plugging structure 300 and the anti-surge block 210. Thus, the water stop structure 100 and the anti-surge structure 200 are provided at the lower end of the structural bottom plate 400, and the anti-surge block 210 is used to counteract the groundwater water pressure, prevent the groundwater from penetrating into the well casing 110, and simultaneously plug the pressure relief well, which can avoid the adverse effects of the sudden surge damage to the soil layer around the water reduction well 20 after the groundwater water pressure gradually increases, prevent the soil from infiltration and deformation to enhance the stability of the foundation, and on the other hand, cut off the pollution path, effectively reducing the effect of the seepage of the groundwater on the main structure bottom plate 400 after the well wall is corroded in the later stage.
[0047] Specifically, the water stop pad 120 is fixed and installed in the well casing 110 through a flange, wherein the flange includes a flange ring 121, a flange plate 122 and bolts, and the flange ring 121, the water stop pad 120 and the flange plate 122 are all provided with bolt holes of the same size and number, and the flange ring 121, the water stop pad 120 and the flange plate 122 are connected by bolts. Further, the diameter of the flange plate 122 is the same as the outer diameter of the flange ring 121, the diameter of the water stop pad 120 is the same as the outer diameter of the flange ring 121, the thickness of the flange ring 121 is not less than 20mm, the thickness of the flange plate 122 should be 5mm to 10mm, and the water stop pad 120 is polyvinyl chloride rubber plastic, and its thickness is 1mm to 2mm.
[0048] Specifically, the well casing 110 is made of stainless steel, a waterproof coating layer is provided on the outer wall of the well casing 110, and the diameter of the well casing 110 is greater than 300 mm.
[0049] Specifically, the water stop wing ring 111 is annularly sleeved on the well casing 110, and the water stop wing ring 111 is made of steel.
[0050] Specifically, the planar shape of the surge block 210 is a square when viewed from top to bottom, and its shape is a cube, and the surge block 210 is underwater impermeable concrete, and its label is the same as the concrete of the structural base plate 400, that is, the compressive strength of the surge block 210 is consistent with the compressive strength of the structural base plate 400.
[0051] Specifically, the surge-proof block 210 is flush with the upper portion of the well casing 110 , and the structural bottom plate 400 is disposed over and on the surge-proof block 210 and the well casing 110 .
[0052] It should be noted that, in order to facilitate the insertion of the well casing 110 into the pressure relief well, in the actual construction process, the well casing 110 with a diameter smaller than the pressure relief well is usually used, and then the well casing 110 and the pressure relief well are filled and plugged by using hemp and oil paste, etc. However, this method has the risk of not sealing tightly. Figure 1 As shown, in some specific embodiments of the present invention, a reducing member 113 is provided at the lower end of the well casing 110, and the well casing 110 is connected to the water reduction well 20 through the reducing member 113. The reducing member 113 is penetrated in the water reduction well 20, and the inner diameter of the reducing member 113 gradually decreases in the direction approaching the water reduction well 20. Through the reducing connection, the stability and structural strength of the connection between the well casing 110 and the water reduction well 20 can be increased, and at the same time, the sealing of the connection part can be effectively improved, reducing the possibility of sudden infiltration of groundwater.
[0053] In some specific embodiments of the present invention, the shear assembly 112 includes a plurality of shear steel bars 1121 uniformly arranged in a ring shape, and each of the two opposite ends of the shear steel bar 1121 is respectively provided with a connecting piece 1122 and an anchoring piece 1123, the connecting piece 1122 and the shear steel bar 1121 are perpendicular to each other, the connecting piece 1122 and the well casing 110 are parallel to each other, the shear steel bar 1121 is connected to the side wall of the well casing 110 through the connecting piece 1122, and the shear steel bar 1121 is anchored in the anti-surge block 210 through the anchoring piece 1123. Figure 3 As shown, the shear steel bars 1121 of a single shear assembly 112 are all arranged on the outer wall of the well casing 110 along the circumferential direction. In this specific embodiment, 8 shear steel bars 1121 are provided, and the 8 shear steel bars 1121 are arranged in a plane ring shape and one end connected to the well casing 110 points to the center of the circle of the well casing 110. The shear steel bars 1121 are bent 90° through the connecting piece 1122 and welded to the well casing 110 in a full welding manner, and are bent 180° through the anchor 1123 and anchored in the anti-surge block 210. Further, the model of the shear steel bars 1121 is consistent with the main structure.
[0054] In some specific embodiments of the present invention, the surge-resistant structure 200 further includes a first cushion layer 220, which is disposed at the lower end of the surge-resistant block 210. The first cushion layer 220 can fill and balance the surface unevenness between the structural bottom plate 400 and the foundation, disperse the load transferred from the structural bottom plate 400 to the foundation, reduce local stress concentration, and help protect the structural bottom plate 400 and the foundation to ensure that the structural bottom plate 400 is placed on a stable foundation, thereby improving the stability and safety of the structure and ensuring that the connection between the structural bottom plate 400 and the foundation is firm and reliable.
[0055] like Figures 1 to 4 As shown, according to the second aspect of the present invention, the method for plugging a high-head foundation pit pressure relief well comprises:
[0056] S1: Maintain the pressure reduction operation in the pressure relief well, excavate a foundation pit of the anti-surge block 210 near the pressure relief well, and cut off the pressure relief well at a position higher than the bottom of the foundation pit of the anti-surge block 210;
[0057] S2: Maintain the pressure reduction operation in the pressure relief well, and fix the well casing 110 to the upper end of the pressure relief well;
[0058] S3: Laying the first cushion layer 220 at the bottom of the pit of the anti-surge block 210, building a concrete formwork after the first cushion layer 220 has formed a designed strength, and pouring concrete in the concrete formwork to form the anti-surge block 210;
[0059] S4: After the surge block 210 reaches the designed strength, the surroundings of the surge block 210 are backfilled and compacted, a structural bottom plate 400 is constructed on the upper end of the surge block 210, and a pit 50 corresponding to the pressure relief well is reserved on the structural bottom plate 400;
[0060] S5: Stop the decompression operation of the decompression well, pump out the overflowing water from the decompression well 20 in the pit 50, and fill the decompression well 20 with concrete until the water level at the wellhead of the decompression well 20 stops rising;
[0061] S6: The water stop pad 120 is arranged in the well casing 110 , and a filling bottom plate 410 is constructed in the pit 50 , and the filling bottom plate 410 is made flush with the top of the structural bottom plate 400 .
[0062] In S4 , a waterstop 51 is provided on the inner wall of the pit 50 along the circumferential direction. The waterstop 51 extends from the inside of the structural bottom plate 400 toward the inside of the pit 50 . The waterstop 51 is used for structural water stopping.
[0063] In some specific embodiments of the present invention, in S5 , a waterproof roll is laid in the well casing 110 , and the waterproof roll extends from the inside of the well casing 110 to the pit 50 .
[0064] In some specific embodiments of the present invention, in S6 , the compressive strength of the filling bottom plate 410 is greater than the compressive strength of the structural bottom plate 400 .
[0065] The following is a specific embodiment to illustrate the plugging method of the high-head foundation pit pressure relief well.
[0066] S1: Figure 4 As shown, the pump 30 in the pressure relief well is kept in pressure reduction operation, and the groundwater is pumped out of the foundation pit by connecting the pump 30 to the water pipe, so as to ensure the anti-surge stability of the relatively impermeable soil layer 10 at the bottom of the foundation pit and the dry operation requirements at the bottom of the pit;
[0067] Excavate the foundation pit to the bottom elevation of the designed pit, measure and locate near the pressure relief well and mark the plane size of the anti-surge block 210 at the bottom of the pit, adopt the construction method of slope excavation according to the preset excavation boundary, and use an excavator to dig to the bottom of the anti-surge pit;
[0068] S2: Figure 5 As shown, the pump 30 in the pressure relief well maintains the pressure relief operation, the pressure relief well is cut off at a position 300 mm higher than the bottom of the anti-surge pit, and a sand grinder is used to repair and level the cut-off position of the pressure relief well, and the inner and outer wall surfaces within 50 mm below the wellhead of the pressure relief well are polished and smoothed so as to be used for welding with the well casing 110;
[0069] The water pipe of the water pump 30 is propped up to prevent the gravity of the water pipe from being supported on the well casing 110, and then the water pipe of the water pump 30 is passed through the prefabricated well casing 110, so that the well casing 110 and the pressure relief well are connected and kept in a vertical state, and the well casing 110 and the pressure relief well are welded in a full welding manner at the overlapping position of the well casing 110 and the pressure relief well;
[0070] S3: Figure 6 As shown, after the weld is naturally cooled, a first cushion layer 220 is laid at the bottom of the pit of the anti-surge block 210. After the first cushion layer 220 forms the designed strength, a concrete formwork is erected according to a preset size, and the same type of anti-seepage underwater concrete as the structural bottom plate 400 is poured in the concrete formwork, and the pouring height of the concrete is flush with the wellhead height of the well casing 110, located at the bottom of the foundation pit;
[0071] S4: Figure 6 As shown, after the concrete of the surge-proof block 210 forms a predetermined strength, the second cushion layer 420 of the structural bottom plate 400 is laid according to the drawings, steel bars are tied, a concrete formwork is supported, and concrete is poured, and a cubic reserved pit 50 with a plane size of 1m×1m and a thickness the same as that of the structural bottom plate 400 is reserved at the position corresponding to the pressure relief well;
[0072] It should be noted that the reserved steel bars of the structural base 400 need to be exposed from the concrete surface, with a reserved length of 50 mm, and are welded to the subsequent steel bars of the pit 50. A steel plate waterstop 51 is provided along the four sides of the middle depth of the pit 50. The width of the steel plate waterstop 51 is 200 mm, of which 100 mm is cast in the concrete of the structural base 400, and the other 100 mm is cast in the concrete of the reserved pit 50 for structural water stopping.
[0073] S5: Figure 7 As shown, when the structural bottom plate 400 meets the anti-floating requirements, a water pump 30 is placed at the reserved pit 50 of the structural bottom plate 400, the water pump 30 of the pressure relief well is turned off to stop pumping water, and the water pump 30 of the pressure relief well is slowly lifted out of the pressure relief well for recovery;
[0074] It should be noted that when the pumping pump 30 of the groundwater pressure relief well stops pumping water, groundwater will gush out from the wellhead of the well casing 110 into the reserved pit 50 of the structural bottom plate 400. The pumping pump 30 in the reserved pit 50 is connected to an external water pipe to pump the gushing water into a permanent water collection well set on the structural bottom plate 400. The water collection well is provided with a pumping pump 30 to centrally pump the groundwater out of the foundation pit.
[0075] Keep the pumping operation of the pump 30 in the pit 50, insert a pipe with a diameter of 200mm into the pressure relief well, the upper end of which is fixed to the bracket made on site with a steel wire rope, and the lower end is about 0.5m away from the bottom of the pressure relief well;
[0076] Furthermore, a measuring rope with a scale is lowered along with the conduit, and is artificially lifted along with the underwater self-compacting concrete pouring surface during the pouring process to determine the depth of the conduit buried in the self-compacting concrete during the pouring process of the underwater self-compacting concrete. The minimum depth requirement for the conduit to be buried in the underwater self-compacting concrete is 1.1m to 1.5m, so as to ensure that the underwater self-compacting concrete surges upward from the bottom, and at the same time, to prevent the underwater self-compacting concrete being poured during the pouring process from being washed away by a large amount of groundwater. Of course, in order to prevent the conduit from being unable to be pulled out of the underwater self-compacting concrete in the end, the depth of the conduit buried in the underwater self-compacting concrete does not exceed 6m;
[0077] Pour underwater self-compacting concrete along the conduit into the pressure relief well. During the pouring process, pay attention to the water inflow and water level changes at the wellhead. Pay attention to the scale of the measuring rope to determine the buried depth of the conduit. When the conduit is buried 3m deep in the self-compacting concrete, lift the conduit upward to ensure its minimum buried depth.
[0078] When the amount of groundwater inflow at the wellhead is observed to continue to decrease and the water level at the wellhead does not rise after pumping is stopped, the underwater self-compacting concrete pouring is stopped, the conduit is pulled out of the pressure relief well, the pump 30 is turned off and the conduit is lifted out of the pit 50;
[0079] S6: The water stop pad 120, the flange plate 122 and the flange ring 121 are tightly connected by bolts, and the water stop flange pad is located between the flange plate 122 and the flange ring 121 to ensure the water stop effect;
[0080] Clean the inner wall of the well casing 110 above the flange 122 installed, lay waterproofing membrane inside the well casing 110 and at the bottom of the pit 50, and extend the waterproofing membrane vertically upward along the wall of the well casing 110 to the pit 50. The waterproofing membrane in the pit 50 covers the pit bottom and extends vertically upward along the wall of the pit 50 by 100 mm;
[0081] It should be noted that a filling cushion layer 421 is also provided at the bottom of the filling base plate 410, wherein the filling cushion layer 421 is used to fill the reserved pits 50 of the second cushion layer 420, and the filling base plate 410 is used to fill the reserved pits 50 of the structural base plate 400. Specifically, micro-expansive concrete with a grade higher than the concrete of the structural base plate 400 is poured on the waterproof membrane, and the pouring height of the concrete is flush with the bottom of the structural base plate 400 to form a filling cushion layer 421 structure, and the same model of rear-connected steel bars as the structural base plate 400 are connected and tied with the reserved steel bars by welding, and the micro-expansive concrete with a grade higher than the concrete of the structural base plate 400 is used to pour the pits 50, and the pouring height of the concrete is flush with the top of the structural base plate 400 to form a filling base plate 410 structure.
[0082] It should be noted that the joints between different waterproof membranes should be bonded with sealant to form an integral structure to ensure the water-stopping effect of the waterproof membrane.
[0083] The embodiments of the present invention are described in detail above with reference to the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of ordinary technicians in the technical field without departing from the purpose of the present invention.
Claims
1. A plugging structure for a high-head foundation pit pressure relief well, characterized in that: include: A water-stop structure (100), the water-stop structure (100) being arranged at the lower end of a structural bottom plate (400), the water-stop structure (100) comprising a well casing (110) and a water-stop pad (120), the well casing (110) being connected to the well wall of the pressure relief well, a plurality of water-stop wing rings (111) and a plurality of anti-shear components (112) being arranged on the outer wall of the well casing (110), the plurality of water-stop wing rings (111) and the plurality of anti-shear components (112) being arranged at intervals along the axial direction, the water-stop pad (120) being arranged coaxially with the well casing (110), the water-stop pad (120) being inserted into the well casing (110), and the water-stop pad (120) being located at one end of the well casing (110) close to the structural bottom plate (400); An anti-surge structure (200), the anti-surge structure (200) being arranged at the lower end of a structural bottom plate (400), the anti-surge structure (200) being located in a relatively impermeable soil layer (10), the anti-surge structure (200) comprising an anti-surge block (210), the anti-surge block (210) being arranged coaxially with the well casing (110), the anti-surge block (210) being wrapped around the outer wall of the well casing (110), all the water stop wing rings (111) and all the anti-shear components (112) being located in the anti-surge block (210), and the anti-surge block (210) being used to prevent sudden surges to the soil layer around the water reduction well (20) after the groundwater pressure gradually increases; A plugging structure (300) is provided in the water reduction well (20), the plugging structure (300) extends from the water reduction well (20) to the interior of the well casing (110), and the plugging structure (300) is used to prevent groundwater from flowing into the water stopping structure (100) along the water reduction well (20).
2. The plugging structure of the high-head foundation pit pressure relief well according to claim 1 is characterized in that: A reducing member (113) is provided at the lower end of the well casing (110), and the well casing (110) is connected to the water reduction well (20) via the reducing member (113). The reducing member (113) is inserted into the water reduction well (20), and the inner diameter of the reducing member (113) gradually decreases in a direction approaching the water reduction well (20).
3. The plugging structure of the high-head foundation pit pressure relief well according to claim 1 is characterized in that: A waterproof coating layer is provided on the outer wall of the well casing (110).
4. The plugging structure of the high-head foundation pit pressure relief well according to claim 1 is characterized in that: The shear-resistant assembly (112) comprises a plurality of ring-shaped uniformly distributed shear-resistant steel bars (1121), each of the shear-resistant steel bars (1121) being provided with a connecting piece (1122) and an anchoring piece (1123) at opposite ends thereof, the connecting piece (1122) and the shear-resistant steel bars (1121) being perpendicular to each other, the connecting piece (1122) and the well casing (110) being parallel to each other, the shear-resistant steel bars (1121) being connected to the side wall of the well casing (110) via the connecting piece (1122), and the shear-resistant steel bars (1121) being anchored in the anti-surge block (210) via the anchoring piece (1123).
5. The plugging structure of the high-head foundation pit pressure relief well according to claim 1 is characterized in that: The surge-resistant structure (200) further comprises a first cushion layer (220), wherein the first cushion layer (220) is arranged at the lower end of the surge-resistant block (210).
6. The plugging structure of the high-head foundation pit pressure relief well according to claim 1 is characterized in that: The size of the surge-proof block (210) is larger than the size of the reserved pit of the structural bottom plate (400).
7. A method for plugging a high-head foundation pit pressure relief well, using the plugging structure for a high-head foundation pit pressure relief well according to any one of claims 1 to 6, characterized in that: include: S1: maintaining the pressure reduction operation in the pressure relief well, excavating the anti-surge block (210) foundation pit near the pressure relief well, and cutting off the pressure relief well at a position higher than the bottom of the anti-surge block (210) foundation pit; S2: Maintain the pressure reduction operation in the pressure relief well, and fix the well casing (110) to the upper end of the pressure relief well; S3: laying the first cushion layer (220) at the bottom of the pit of the anti-surge block (210), building a concrete formwork after the first cushion layer (220) has formed a designed strength, and pouring concrete in the concrete formwork to form the anti-surge block (210); S4: After the anti-surge block (210) reaches the designed strength, the surroundings of the anti-surge block (210) are backfilled and compacted, a structural bottom plate (400) is constructed on the upper end of the anti-surge block (210), and a pit (50) corresponding to the pressure relief well is reserved on the structural bottom plate (400); S5: stopping the decompression operation of the decompression well, pumping out the gushing water overflowing from the decompression well (20) in the pit (50), and filling the decompression well (20) with concrete until the water level at the wellhead of the decompression well (20) no longer rises; S6: The water stop pad (120) is arranged in the well casing (110), a filling bottom plate (410) is constructed in the pit (50), and the filling bottom plate (410) is made flush with the top of the structural bottom plate (400).
8. The method for plugging a high-head foundation pit pressure relief well according to claim 7, characterized in that: In S4, a waterstop (51) is provided on the inner wall of the pit (50) along the circumferential direction, and the waterstop (51) extends from the inside of the structural base plate (400) toward the inside of the pit (50), and the waterstop (51) is used for structural water stopping.
9. The method for plugging a high-head foundation pit pressure relief well according to claim 7, characterized in that: In S5, a waterproof roll is laid in the well casing (110), and the waterproof roll extends from the inside of the well casing (110) to the pit (50).
10. The method for plugging a high-head foundation pit pressure relief well according to claim 7, characterized in that: In S6, the compressive strength of the filling base plate (410) is greater than the compressive strength of the structural base plate (400).
Citation Information
Patent Citations
Underground building bottom plate water burst well pit solid seal method and auxiliary water lowering device
CN103174154A
Well sealing end pipe for sealing dewatering well and dewatering well sealing method
CN108149701A
Waterproof casing pipe structure of dewatering well point and construction technology of waterproof casing pipe structure
CN115961635A
Plugging device and method for well shut-in after ultrahigh water level
CN118327014A
Rapid plugging device for precipitation well in building basement
CN204080836U