Combined mechanical excavation method for small-section tunnel

By establishing an airside surface at the lower end of the tunnel palm surface and using mechanical equipment for layer-by-layer crushing and excavation, combined with hydraulic splitting and wedge-shaped airside technology, environmental damage and mechanical equipment use in small-section tunnel construction in nature reserves is solved. The problem of this problem has realized a low-noise and efficient tunnel excavation method.

CN118958989APending Publication Date: 2024-11-15SICHUAN JIAOTOU CONSTR ENG CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410944339.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing tunnel construction method is difficult to reduce environmental damage during the construction of small-section tunnels in nature reserves, and the small-section structure limits the use of large-scale mechanical equipment, making it difficult to achieve low noise and low disturbance excavation methods.

Method used

Using the combined mechanical excavation method of small section tunnel, by establishing air-facing surfaces at the lower end of the palm surface, using mechanical equipment to perform crushing and excavation from bottom to top, avoiding drilling and blasting construction, and using drilling holes and hydraulic splitting rods to circle by circle Peel out the rock formation and combine it with the wedge-shaped air-conditioning part to assist in surface repair.

Benefits of technology

It realizes low noise and low disturbance tunnel excavation in nature reserves, reduces environmental damage, improves construction efficiency, and is suitable for mechanical excavation of small-section tunnels.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958989A_ABST
    Figure CN118958989A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of tunnel construction, and discloses a small-section tunnel combined mechanical excavation method which comprises the following steps: establishing a free face, and excavating a rock stratum part between the bottom of a tunnel face and a tunnel ground so as to form a first free face at the bottom of the rock stratum in the tunnel face; rock stratum excavation is conducted, specifically, the rock stratum in the tunnel face above the free face is crushed and excavated from bottom to top; according to the combined mechanical excavation method for the small-section tunnel, the free face is built at the lower end of the tunnel face, then the tunnel face is broken and excavated from bottom to top through mechanical equipment, and large-scale operation equipment does not need to be used; and meanwhile, disturbance caused by blasting construction is avoided, noise is reduced, damage to the natural environment is small, the construction efficiency is improved, and the method is suitable for construction environments such as natural reserves with strict requirements for environmental protection.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel construction, and in particular to a combined mechanical excavation method for a small-section tunnel. Background Art

[0002] At present, there are relatively mature tunnel excavation methods such as shield method, full-section excavation method, and step method. Except for the shield method, most of the other construction methods require the use of drilling and blasting excavation and other methods. For small-section tunnels in nature reserves, it is necessary to reduce damage to the natural environment as much as possible. Therefore, drilling and blasting excavation cannot be used in such environments, and the small-section structure of the tunnel also limits the operating conditions of large machinery and equipment.

[0003] Based on the above reasons, it is necessary to provide a mechanical excavation method that has little damage to the natural environment and is suitable for small-section tunnels. Summary of the invention

[0004] The purpose of the present invention is to overcome the shortcomings of the background technology and provide a method for combined mechanical excavation of a small-section tunnel.

[0005] The embodiments of the present invention are implemented by the following technical solutions:

[0006] A method for combined mechanical excavation of a small-section tunnel comprises the following steps:

[0007] S1. Establishing an open face: excavating the rock layer between the bottom of the tunnel face and the tunnel ground to form a first open face at the bottom of the rock layer in the tunnel face;

[0008] S2. Rock excavation: Crushing and excavating the rock strata within the face above the free face from bottom to top.

[0009] Furthermore, in step S1, when the tunnel face is a whole rock layer, a set of second free-facing surfaces perpendicular to the first free-facing surfaces is excavated in the middle of the tunnel face.

[0010] Furthermore, in step S2, a plurality of circles of splitting points are set on the tunnel face located above the first free face and on both sides of the second free face, and the rock formations in the tunnel face are split and peeled circle by circle from the inside to the outside.

[0011] Furthermore, in step S2, auxiliary trimming is performed on the splitting circle layer from bottom to top and from inside to outside by a breaker hammer.

[0012] Furthermore, the first free-surface and the second free-surface are both composed of a plurality of drill holes arranged in an arrangement, and the drilling depth is 0.8 m.

[0013] Furthermore, the plurality of splitting points are symmetrically arranged on the tunnel faces on both sides of the second free face, and the control spacing between adjacent splitting points is 0.5 m.

[0014] Furthermore, both sides and the middle of the first free surface and both sides and the middle of the second free surface also have wedge-shaped free parts, and the inner diameter of the end of the wedge-shaped free part facing the tunnel face is larger than the inner diameter of the end facing the rock formation interior.

[0015] Furthermore, the taper between the two ends of the wedge-shaped free-side portion is 5°.

[0016] Furthermore, the wedge-shaped free-surface portion is composed of a plurality of at least partially overlapping drill holes.

[0017] In addition, in step S2, when the rock layer in the tunnel face is an oblique rock layer and / or a horizontal rock layer, the oblique rock layer is peeled layer by layer from bottom to top along the direction of the rock layer in the tunnel face.

[0018] The technical solution of the embodiment of the present invention has at least the following advantages and beneficial effects:

[0019] The combined mechanical excavation method for small-section tunnels of the present invention establishes an open face at the lower end of the tunnel face, and then uses mechanical equipment to crush and excavate the tunnel face from bottom to top, without the need for large-scale operating equipment; at the same time, it also avoids disturbances caused by blasting construction, reduces noise generation, causes little damage to the natural environment, improves construction efficiency, and is suitable for construction environments with strict environmental protection requirements such as nature reserves. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a front view schematic diagram of the combined mechanical excavation of a small end face tunnel in the first embodiment of the present invention;

[0021] Figure 2 It is a side view schematic diagram of the combined mechanical excavation of a small end face tunnel in the first embodiment of the present invention;

[0022] Figure 3 It is a front view of the wedge-shaped free-side portion in the first embodiment of the present invention;

[0023] Figure 4 A schematic front view of the combined mechanical excavation of a small end face tunnel in the second embodiment of the present invention Figure 1 ;

[0024] Figure 5 A schematic front view of the combined mechanical excavation of a small end face tunnel in the second embodiment of the present invention Figure 2 ;

[0025] Figure 6 It is a side view schematic diagram of combined mechanical excavation of a small end face tunnel in the second embodiment of the present invention;

[0026] Icons: 1-palm face, 2-first free surface, 20-drill hole, 3-second free surface, 4-wedge-shaped free part, 5-ground, 6-water drill, 7-hydraulic splitting rod, 8-breaking hammer, 9-splitting point. DETAILED DESCRIPTION

[0027] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0028] Embodiment 1:

[0029] Reference Figures 1 to 3 This embodiment provides a method for combined mechanical excavation of a small-section tunnel, comprising the following steps:

[0030] S1. Establishing an open face: First, excavate the rock layer between the bottom of the tunnel face 1 and the tunnel ground 5. The rock layer can be a whole rock layer, a horizontal rock layer or an inclined rock layer. A first open face 2 is formed at the bottom of the rock layer in the tunnel face 1. The width of the first open face 2 is slightly smaller than the width of the lower end of the tunnel face 1. The height of the first open face 2 is formed one by one by drilling holes 20. Therefore, the height of the first open face 2 is approximately equal to the drilling diameter of the water-grinding drill 6.

[0031] S2. Rock excavation: The rock strata in the tunnel face 1 above the free face are crushed and excavated from bottom to top. During the process, a breaker hammer 8 can also be used for excavation and crushing.

[0032] In this embodiment, when the tunnel face 1 is a whole rock layer, two sets of mutually perpendicular free faces need to be established when establishing free faces, that is, Figure 1 A set of second free-facing surfaces 3 perpendicular to the first free-facing surfaces 2 is excavated in the middle of the tunnel face 1, and the tunnel faces 1 on the left and right sides of the second free-facing surfaces 3 are symmetrical.

[0033] The first free-facing surface 2 and the second free-facing surface 3 are both composed of a plurality of arranged drill holes 20, and the depth of the drill holes 20 is 0.8 m. Therefore, the depths of the first free-facing surface 2 and the second free-facing surface 3 are both 0.8 m.

[0034] Reference Figure 1In the rock excavation step, a plurality of circles of splitting points 9 are arranged on the tunnel face 1 located above the first free face 2 and on both sides of the second free face 3. In this embodiment, there are four circles of splitting points 9. The four circles of dry splitting points 9 are symmetrically arranged on the tunnel face 1 on both sides of the second free face 3, and the control spacing between adjacent splitting points 9 is 0.5m. When the rock is excavated, the plurality of splitting points 9 are split circle by circle from the inside to the outside by the hydraulic splitting rods 7, so that the rock is peeled off layer by layer.

[0035] By hydraulically splitting the rock from bottom to top and from inside to outside, it is possible to avoid the use of drilling and blasting for excavation, reduce the disturbance of the rock formation and the damage to the environment, and generate low noise.

[0036] Reference Figure 2 In the rock excavation step, the cleavage circle can also be assisted in surface trimming from bottom to top and from inside to outside by using a breaker hammer 8.

[0037] In addition, refer to Figure 1 and Figure 3 Both sides and the middle of the first free face 2 and both sides and the middle of the second free face 3 are also provided with wedge-shaped free parts 4, wherein the inner diameter of the end of the wedge-shaped free part 4 facing the tunnel face 1 is larger than the inner diameter of the end facing the inside of the rock formation, which can release the concentrated stress in the rock formation and create better working conditions for splitting construction.

[0038] In this embodiment, the taper between the two ends of the wedge-shaped free-side portion 4 is 5°.

[0039] It should be noted that in the above embodiment, when the rock layer is Grade V surrounding rock, the hole arrangement of the above-mentioned first free surface 2 and the second free surface 3 can be used in combination with a breaker 8 for excavation without splitting; when the rock layer is Grade III or IV surrounding rock, the construction must be carried out strictly in accordance with the splitting steps.

[0040] Reference Figure 3 It is easy to understand that the wedge-shaped free-side portion 4 is composed of a plurality of at least partially overlapping bore holes 20 .

[0041] Embodiment 2:

[0042] Reference Figures 4 to 6 , the rock layer is Figure 4 When the inclined rock layer is Figure 5 In the case of horizontal rock layers as shown, the inclined rock layers can be peeled off layer by layer from bottom to top along the direction of the rock layers in the tunnel face 1 without using splitting construction.

[0043] In particular, Figure 4 When peeling off the rock layers, it is necessary to peel off layer by layer from the lower right side to the upper left side.

[0044] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A combined mechanical excavation method for a small-section tunnel, characterized in that: The steps include: S1. Establishing an open face: Excavating the rock layer between the bottom of the tunnel face and the tunnel ground to form a first open face at the bottom of the rock layer within the tunnel face; S2. Rock excavation: Crushing and excavating the rock strata within the face above the free face from bottom to top.

2. The combined mechanical excavation method for small-section tunnels according to claim 1, characterized in that: In step S1, when the tunnel face is a whole rock layer, a set of second free faces perpendicular to the first free faces is excavated in the middle of the tunnel face.

3. The combined mechanical excavation method for small-section tunnels according to claim 2, characterized in that: In step S2, a plurality of circles of splitting points are set on the tunnel face located above the first free face and on both sides of the second free face, and the rock layer in the tunnel face is split and peeled circle by circle from the inside to the outside.

4. The combined mechanical excavation method for small-section tunnels according to claim 3, characterized in that: In step S2, auxiliary trimming of the splitting ring layer is performed from bottom to top and from inside to outside by a breaker hammer.

5. The combined mechanical excavation method for small-section tunnels according to claim 2, characterized in that: The first free-facing surface and the second free-facing surface are both composed of a plurality of drill holes arranged in an arrangement, and the drilling depth is 0.8m.

6. The combined mechanical excavation method for small-section tunnels according to claim 3, characterized in that: The plurality of splitting points are symmetrically arranged on the tunnel faces on both sides of the second free face, and the spacing between adjacent splitting points is 0.5m.

7. The combined mechanical excavation method for a small-section tunnel according to any one of claims 2 to 6, characterized in that: Both sides and the middle of the first free surface and both sides and the middle of the second free surface also have wedge-shaped free parts, and the inner diameter of the end of the wedge-shaped free part facing the tunnel face is larger than the inner diameter of the end facing the rock formation interior.

8. The combined mechanical excavation method for small-section tunnels according to claim 7, characterized in that: The taper between the two ends of the wedge-shaped free-side portion is 5°.

9. The combined mechanical excavation method for small-section tunnels according to claim 7, characterized in that: The wedge-shaped free-side portion is composed of a plurality of at least partially overlapping drilled holes.

10. The combined mechanical excavation method for small-section tunnels according to claim 1, characterized in that: In step S2, when the rock strata in the tunnel face are oblique rock strata and / or horizontal rock strata, the oblique rock strata are peeled layer by layer from bottom to top along the direction of the rock strata in the tunnel face.

Citation Information

Cited By

  • Mine tunnel tunneling mining method

    CN119145866A