Pre-bending equipment of prestressed composite beam and construction method of prestressed composite beam
By designing prestressed combination beam prebending equipment with adjustable base and clamping mechanism, the problem of difficult reuse of reaction platforms and ground anchors in the prior art and overall instability is solved, and efficient and safe prestressed combination beams are achieved Construction, suitable for a variety of bridge structures.
Patent Information
- Application Number
- CN202411292806.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-14
- Publication Date
- 2024-11-19
AI Technical Summary
In the construction of existing prestressed composite beams, the reaction platform and ground anchor of the single beam prebending method are difficult to reuse, and the double beam bending method is complex and there is a risk of overall instability.
A prestressed composite beam prebending equipment is designed, including an adjustable base, clamping mechanism and top pressure mechanism. The bending of the prefabricated steel beam is achieved through the lifting rod and hydraulic cylinder, avoiding overall instability, and can be reused instead of traditional Reaction platform and ground anchor.
It improves construction efficiency, simplifies processes, enhances safety, reduces production costs, and is suitable for the production of prestressed combined beams in positive and negative bending moment zones.
Smart Images

Figure CN118979443A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of steel-concrete prestressed composite beams with small and medium spans, and in particular to a prestressed composite beam pre-bending device and a prestressed composite beam construction method. Background Art
[0002] Compared with prestressed concrete beams, prestressed composite beams have good pressure-bearing performance, and the beam height and self-weight are significantly reduced, which reduces the pressure-bearing requirements of bridge piers and reduces the cost of bridge piers. Therefore, it has attracted the attention of more and more scholars and has gradually been promoted in China. At present, two methods, single-beam pre-bending and double-beam bending, are used to construct pre-bent composite beams. The construction process of the former is relatively simple, but when loading the I-beam steel beam, it is necessary to make corresponding reaction platforms and ground anchors. The above equipment is difficult to reuse in the later stage, with high investment and low output; the latter solves the problem of difficulty in reusing reaction platforms and ground anchors, but the process is relatively complicated, and the double-beam bending will increase the risk of overall instability of the beam during loading. Summary of the invention
[0003] In order to solve the above problems, the present invention provides a prestressed composite beam pre-bending device and a prestressed composite beam construction method, which can specifically adopt the following technical solutions: The prestressed composite beam pre-bending equipment described in the present invention includes a base, a supporting plate connected to the bottom plate of the prefabricated steel beam is arranged at the center of the base, clamping mechanisms connected to the web of the prefabricated steel beam are arranged on both sides of the base, and a pressing mechanism connected to the top plate of the prefabricated steel beam is arranged above the base. The supporting plate is transformed into a convex arc structure or a concave arc structure by a lifting rod arranged at the bottom, and the pressing mechanism is arranged at the two ends of the convex arc or the center of the concave arc according to the shape of the supporting plate.
[0004] A plurality of lifting rods are evenly spaced along the length direction of the prefabricated steel beam.
[0005] The jacking mechanism comprises vertical guide rods arranged on both sides of the base, and jacking rods arranged across the prefabricated steel beam are slidably sleeved on the vertical guide rods. Jacking hydraulic cylinders located on both sides of the prefabricated steel beam are arranged between the jacking rods and the base.
[0006] A bottom bracket which is slidably connected to the base is arranged at the bottom of the vertical guide rod.
[0007] The jacking rod and the supporting plate are both connected to the prefabricated steel beam through U-shaped bolts.
[0008] The clamping mechanism comprises a support rod arranged on a base, and a horizontal top rod connected to the web of the prefabricated steel beam is arranged on the support rod.
[0009] The horizontal push rods are arranged in multiple groups at even intervals along the length direction of the prefabricated steel beam, and each group of horizontal push rods is symmetrically arranged on both sides of the web of the prefabricated steel beam.
[0010] The construction method of the prestressed composite beam of the present invention is realized by a prestressed composite beam pre-bending device, and comprises the following steps: The first step is to make I-shaped prefabricated steel beams in a prefabricated steel plant according to the design drawings; The second step is to hoist the prefabricated steel beam, install it on the supporting plate of the base, and connect it to the top pressing mechanism. At the same time, it is positioned by the clamping mechanisms on both sides; The third step is to calculate the maximum pre-bending deflection of the prefabricated steel beam through finite element software according to the cross-sectional characteristic value of the prestressed composite beam, and then obtain the elongation / shortening amount of each lifting rod and the prestressing value applied on the prefabricated steel beam; The fourth step is to adjust the height of each lifting rod according to the calculation result of the fourth step, so that the supporting plate is deformed into a convex arc structure or a concave arc structure, and at the same time, the prefabricated steel beam is subjected to corresponding prestressing force by the top pressing mechanism to obtain a pre-bent steel beam; Step 5: Install the formwork on the top plate of the pre-bent steel beam and then pour the concrete bridge deck; The sixth step is to maintain the concrete bridge deck. After the concrete strength reaches 100%, slowly release the prestress. After that, release the connection between it and the top pressure mechanism and the supporting plate to complete the production of the prestressed composite beam.
[0011] The prestressed composite beam pre-bending equipment provided by the present invention places the prefabricated steel beam on an adjustable base and uses the clamping mechanisms on both sides to position it, thereby avoiding the overall instability of the prefabricated steel beam during the pre-bending process; at the same time, through the cooperation of the lifting rod and the top pressure mechanism, positive bending moment prestressed steel beams and negative bending moment prestressed steel beams are manufactured as required. It has an ingenious structure and is easy to use. It can replace traditional reaction platforms and ground anchors, and can be reused to improve equipment utilization and reduce production costs. The construction method of the prestressed composite beam provided by the present invention simplifies the construction process, is safe and fast, and greatly improves construction efficiency by using the prestressed composite beam pre-bending equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a structural schematic diagram of the prestressed composite beam pre-bending equipment in the present invention.
[0013] Figure 2 yes Figure 1 Schematic diagram of the state during the production of positive moment prestressed composite beams.
[0014] Figure 3 yes Figure 1 Schematic diagram of the state during the production of negative moment prestressed composite beams.
[0015] Figure 4 It is a schematic diagram of the cross-sectional structure of the pre-bent steel beam in the present invention.
[0016] Figure 5 It is a schematic diagram of the cross-sectional structure of the prestressed composite beam in the present invention. DETAILED DESCRIPTION
[0017] The following is a detailed description of an embodiment of the present invention in conjunction with the accompanying drawings. This embodiment is implemented on the premise of the technical solution of the present invention, and a detailed implementation method and a specific working process are given, but the protection scope of the present invention is not limited to the following embodiment.
[0018] like Figure 1 As shown, the prestressed composite beam pre-bending device of the present invention comprises a base 1, a supporting plate 11 connected to the bottom plate of the prefabricated steel beam M is arranged at the center of the base 1, clamping mechanisms connected to the web of the prefabricated steel beam M are arranged on both sides of the base 1, and a pressing mechanism connected to the top plate of the prefabricated steel beam M is arranged above the base 1. The supporting plate 11 is transformed into a convex arc structure (see FIG. 1 ) by a lifting rod 12 arranged at the bottom (a plurality of lifting rods 12 are evenly spaced along the length direction of the prefabricated steel beam M). Figure 2 ) or concave curved structure (see Figure 3 ), the pressing mechanism is arranged at the two ends of the convex arc or the center of the concave arc according to the shape of the supporting plate.
[0019] Specifically, the jacking mechanism includes vertical guide rods 21 arranged on both sides of the base 1, and a jacking rod 22 arranged above the prefabricated steel beam M is slidably sleeved on the vertical guide rods 21, and a jacking hydraulic cylinder 23 located on both sides of the prefabricated steel beam M is arranged between the jacking rod 22 and the base 1. Furthermore, in order to facilitate the adjustment of the relative position of the jacking mechanism and the prefabricated steel beam M, a bottom bracket slidably connected to the base 1 is arranged at the bottom of the single-side vertical guide rod 21 of each jacking mechanism.
[0020] The clamping mechanism includes a support rod 31 arranged on the base 1, and each support rod 31 is provided with a horizontal push rod 32 connected to the web of the prefabricated steel beam M. The above-mentioned horizontal push rods 32 are evenly spaced and arranged in multiple groups along the length direction of the prefabricated steel beam M, and each group of horizontal push rods 32 is symmetrically arranged on both sides of the web of the prefabricated steel beam M.
[0021] Normally, the support plate 11 and the top pressure rod 22 are connected to the prefabricated steel beam M by U-shaped bolts. When the positive moment prestressed composite beam is manufactured, the support plate 11 and the center of the prefabricated steel beam M are fixed, and the top pressure rod 22 is fixedly connected to the prefabricated steel beam M at both ends; when the negative moment prestressed composite beam is manufactured, the support plate 11 and the two ends of the prefabricated steel beam M are fixed, and the top pressure rod 22 is fixedly connected to the prefabricated steel beam M at the center.
[0022] The construction method of the prestressed composite beam of the present invention is specifically described through the following two embodiments.
[0023] Embodiment 1: The method of preparing a positive moment prestressed composite beam by using the prestressed composite beam pre-bending device comprises the following steps: The first step is to manufacture an I-shaped prefabricated steel beam M in a prefabricated steel plant according to the design drawings; The second step is to hoist the prefabricated steel beam M, install it on the supporting plate 11 of the base 1, and connect it to the top pressing mechanism, and at the same time, position it through the clamping mechanisms on both sides; Specifically, the prefabricated steel beam M is placed on the supporting plate 11, and the bottom plate of the prefabricated steel beam M at the mid-span is fixed by U-shaped bolts; then, the two pressing mechanisms are respectively moved to the two ends of the prefabricated steel beam M, and the top plates of the prefabricated steel beam M at both ends are fixed to the pressing rods 22 by U-shaped bolts; finally, the length of the horizontal pressing rods 32 on both sides of the prefabricated steel beam M is adjusted so that the ends thereof are pressed against the web of the prefabricated steel beam M to avoid overall instability of the prefabricated steel beam M during the subsequent prestressing process.
[0024] The third step is to calculate the maximum pre-bending deflection of the prefabricated steel beam M by finite element software according to the cross-sectional characteristic value of the prestressed composite beam, and then obtain the elongation / shortening amount of each lifting rod 12 and the prestressing value applied on the prefabricated steel beam M; Step 4: According to the calculation result of step 4, the height of each lifting rod 12 is adjusted to deform the supporting plate 11 into a convex arc structure (see Figure 2 ), at the same time, by adjusting the length of the top pressure rod 22, the corresponding prestress is applied to both ends of the prefabricated steel beam M to obtain a pre-bent steel beam; Step 5: Pre-bend the steel beam (see Figure 4 ) The formwork is installed on the top plate and then the concrete bridge deck is poured (see Figure 5 ); The sixth step is to maintain the concrete bridge deck. After the concrete strength reaches 100%, the prestress is slowly released. After that, the connection between the prestressed bridge deck and the supporting plate 11, the jacking rod 22 and the horizontal jacking rod 32 is released to complete the production of the prestressed composite beam.
[0025] Embodiment 2: The negative moment prestressed composite beam is prepared by the prestressed composite beam pre-bending device, comprising the following steps: The first step is to manufacture an I-shaped prefabricated steel beam M in a prefabricated steel plant according to the design drawings; The second step is to hoist the prefabricated steel beam M, install it on the supporting plate 11 of the base 1, and connect it to the top pressing mechanism, and at the same time, position it through the clamping mechanisms on both sides; Specifically, the prefabricated steel beam M is placed on the supporting plate 11, and the bottom plates at both ends of the prefabricated steel beam M are fixed by U-shaped bolts; then, a pressing mechanism is moved to the mid-span of the prefabricated steel beam M, and the top plate of the prefabricated steel beam M is fixed to the pressing rod 22 by U-shaped bolts; finally, the length of the horizontal pressing rods 32 on both sides of the prefabricated steel beam M is adjusted so that the ends thereof are pressed against the web of the prefabricated steel beam M to avoid overall instability of the prefabricated steel beam M during the subsequent prestressing process.
[0026] The third step is to calculate the maximum pre-bending deflection of the prefabricated steel beam M by finite element software according to the cross-sectional characteristic value of the prestressed composite beam, and then obtain the elongation / shortening amount of each lifting rod 12 and the prestressing value applied on the prefabricated steel beam M; Step 4: According to the calculation result of step 4, the height of each lifting rod 12 is adjusted to deform the supporting plate 11 into a concave arc structure (see Figure 3 ), at the same time, by adjusting the length of the top pressure rod 22, a corresponding prestress is applied to the mid-span of the prefabricated steel beam M to obtain a pre-bent steel beam; Step 5: Pre-bend the steel beam (see Figure 4 ) The formwork is installed on the top plate and then the concrete bridge deck is poured (see Figure 5 ); The sixth step is to maintain the concrete bridge deck. After the concrete strength reaches 100%, the prestress is slowly released. After that, the connection between the prestressed bridge deck and the supporting plate 11, the jacking rod 22 and the horizontal jacking rod 32 is released to complete the production of the prestressed composite beam.
[0027] Compared with the prior art, the present invention has the following advantages: (1) The present invention solves the problem that the reaction platform and the anchor device are difficult to reuse when the traditional single beam is pre-bent and loaded, thereby improving the construction efficiency and greatly improving the production efficiency; (2) The present invention has a high degree of automation, and the curvature of the supporting plate of the adjustable base is controlled by a plurality of lifting rods, which has a high degree of refinement and greatly improves the construction accuracy; (3) The construction process of the present invention is simple and convenient, and is expected to be widely promoted in the construction of pre-bent prestressed composite beams in the future; (4) The pre-bent prestressed composite beam produced by the present invention is not only suitable for the positive bending moment zone in a simply supported beam bridge and a continuous beam bridge, but also suitable for the negative bending moment zone in a continuous beam bridge; (5) The present invention has important significance for the future development of pre-bent prestressed composite beam bridges in China.
[0028] In summary, the present invention has simple construction procedures, the adjustable base can be reused, the construction efficiency is high, the degree of automation is high, and it can be prefabricated for pre-bent prestressed composite beams suitable for the negative bending moment zone of continuous beams. It has broad application prospects in future bridge construction.
[0029] It should be noted that, in the description of the present invention, terms indicating orientation or positional relationships, such as "front", "rear", "left", "right", "vertical", "horizontal", "inside", "outside", etc., are based on the orientation or positional relationships shown in the drawings and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
Claims
1. A prestressed composite beam pre-bending device, characterized in that: It includes a base, a supporting plate connected to the bottom plate of the prefabricated steel beam is arranged at the center of the base, clamping mechanisms connected to the web of the prefabricated steel beam are arranged on both sides of the base, and a pressing mechanism connected to the top plate of the prefabricated steel beam is arranged above the base. The supporting plate is transformed into a convex arc structure or a concave arc structure by a lifting rod arranged at the bottom, and the pressing mechanism is arranged at the two ends of the convex arc or the center of the concave arc according to the shape of the supporting plate.
2. The prestressed composite beam pre-bending device according to claim 1 is characterized in that: A plurality of lifting rods are evenly spaced along the length direction of the prefabricated steel beam.
3. The prestressed composite beam pre-bending device according to claim 1, characterized in that: The jacking mechanism comprises vertical guide rods arranged on both sides of the base, and jacking rods arranged across the prefabricated steel beam are slidably sleeved on the vertical guide rods. Jacking hydraulic cylinders located on both sides of the prefabricated steel beam are arranged between the jacking rods and the base.
4. The prestressed composite beam pre-bending device according to claim 3 is characterized in that: A bottom bracket which is slidably connected to the base is arranged at the bottom of the vertical guide rod.
5. The prestressed composite beam pre-bending device according to claim 3 is characterized in that: The jacking rod and the supporting plate are both connected to the prefabricated steel beam through U-shaped bolts.
6. The prestressed composite beam pre-bending device according to claim 1, characterized in that: The clamping mechanism comprises a support rod arranged on a base, and a horizontal top rod connected to the web of the prefabricated steel beam is arranged on the support rod.
7. The prestressed composite beam pre-bending device according to claim 6, characterized in that: The horizontal push rods are arranged in multiple groups at even intervals along the length direction of the prefabricated steel beam, and each group of horizontal push rods is symmetrically arranged on both sides of the web of the prefabricated steel beam.
8. A construction method of a prestressed composite beam, implemented by the prestressed composite beam pre-bending device according to any one of claims 1 to 7, characterized in that: The steps include: The first step is to make I-shaped prefabricated steel beams in a prefabricated steel plant according to the design drawings; The second step is to hoist the prefabricated steel beam, install it on the supporting plate of the base, and connect it to the top pressing mechanism. At the same time, it is positioned by the clamping mechanisms on both sides; The third step is to calculate the maximum pre-bending deflection of the prefabricated steel beam through finite element software according to the cross-sectional characteristic value of the prestressed composite beam, and then obtain the elongation / shortening amount of each lifting rod and the prestressing value applied on the prefabricated steel beam; The fourth step is to adjust the height of each lifting rod according to the calculation result of the fourth step, so that the supporting plate is deformed into a convex arc structure or a concave arc structure, and at the same time, the prefabricated steel beam is subjected to corresponding prestressing force by the top pressing mechanism to obtain a pre-bent steel beam; Step 5: Install the formwork on the top plate of the pre-bent steel beam and then pour the concrete bridge deck; The sixth step is to maintain the concrete bridge deck. After the concrete strength reaches 100%, slowly release the prestress. After that, release the connection between it and the top pressure mechanism and the supporting plate to complete the production of the prestressed composite beam.