Method for dismantling main pier of old bridge near river

Through the steel sheet pile cofferdam and drainage treatment, the safety hazards and low efficiency of backfill methods in the removal of the main pier of Linhe Old Bridge were solved, and an efficient and safe demolition process was achieved.

CN118979450APending Publication Date: 2024-11-19NO 1 ENG LIMITED OF CR20G +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411115451.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

In the existing main pier removal method of Linhe Old Bridge, the backfill method leads to poor strength of the working platform, prone to seepage and collapse, endangering the safety of the operation in the foundation pit, and low efficiency.

Method used

The steel sheet pile cofferdam is used to form the main pier removal operation area, and a waterless platform is formed through drainage treatment. The main pier columns and pile foundation concrete are successively broken, and the foundation pit is backfilled after inspection to ensure construction safety and efficiency.

Benefits of technology

It provides a safe, water-free high-strength operation site, improves demolition efficiency and safety, and avoids the risks of seepage and collapse.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979450A_ABST
    Figure CN118979450A_ABST
Patent Text Reader

Abstract

The invention belongs to the field of bridge demolition, and particularly discloses a riverside old bridge main pier demolition method which comprises the following steps that S1, a main pier demolition operation area is formed in a riverside cofferdam of a main pier arrangement area; s2, waterproof treatment is conducted on the outer side of the main pier dismantling operation area; s3, water in the main pier dismantling operation area is drained, and then backfilling is conducted; s4, a foundation pit is excavated on the peripheral side of the main pier arrangement area; s5, main pier stand columns and pile foundation concrete are sequentially broken till the preset dismantling height is reached, and meanwhile internal steel bars are cut; and S6, the foundation pit is backfilled after inspection and acceptance, and dismantling of the main pier is completed. According to the construction method, the steel sheet pile cofferdam is adopted to form the main pier dismantling operation area, a drainage backfilling mode is adopted, a safe and waterless working site is provided for main pier dismantling construction, the site is larger, the strength is higher, the main pier dismantling operation efficiency can be improved, and operation is safer.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the field of bridge demolition, and more specifically, to a method for demolishing the main pier of an old riverside bridge. Background Art

[0002] With the continuous development of the city's economy and the increase in traffic volume, the number of bridges has been affected to a certain extent due to the adjustment of spans due to waterway upgrades or the increasing number of overloaded vehicles. Under the repeated action of heavy vehicles, the bridge decks of some bridges are severely worn, and concrete is damaged and cracked in many places. The bridge has varying degrees of damage from the deck system, superstructure to the substructure. Some seriously damaged bridges need to be demolished, and the demolition is carried out from top to bottom.

[0003] At present, when the main pier of the old Linhe Bridge is demolished, part of the waterway needs to be occupied, and a large amount of clay is backfilled to make an operating platform. The clay is easy to spread in the waterway, which leads to low operating efficiency and a certain impact on the safe operation of the waterway. In addition, the strength of the operating platform formed directly by backfilling soil cofferdam is poor, which is prone to water seepage and collapse, endangering the safety of operations in the foundation pit. Summary of the invention

[0004] In view of the defects of the prior art, the present application provides a method for dismantling the main piers of the Linhe Old Bridge, aiming to solve the problem that when dismantling the main piers of the Linhe Old Bridge, directly backfilling the soil to make an operating platform has certain safety hazards and low operating efficiency.

[0005] The present application provides a method for dismantling the main pier of an old bridge in Linhe River, which specifically comprises the following steps:

[0006] S1: The cofferdam on the river side of the main pier setting area forms the main pier dismantling operation area;

[0007] S2: waterproofing the outer side of the main pier demolition operation area;

[0008] S3: draining the water inside the main pier demolition operation area and then backfilling;

[0009] S4: excavating a foundation pit around the area where the main pier is set;

[0010] S5: Remove the main pier columns and pile foundation concrete in sequence until they reach the predetermined demolition height, while cutting the internal steel bars;

[0011] S6: After inspection and acceptance, backfill the foundation pit and complete the removal of the main pier.

[0012] The above technical scheme conceived by the present application, compared with the prior art, because the present application forms the main pier demolition operation area through a cofferdam and adopts the drainage backfilling method, a safe and water-free working site is provided for the main pier demolition construction, and the site is larger and stronger, which can achieve the beneficial effects of improving work efficiency and making operations safer.

[0013] As further preferred embodiment, in step S1, the cofferdam is formed by sequentially arranging a plurality of steel sheet piles, and each of the steel sheet piles is vertically arranged.

[0014] By adopting the above technical solution, steel sheet piles are arranged in sequence to enclose the main pier demolition operation area, which is convenient for construction, and the main pier demolition operation area has high strength, which is convenient for demolition operations.

[0015] As a further preferred embodiment, a total station is used to locate the laying position of the steel sheet piles before laying the steel sheet piles.

[0016] By adopting the above technical solution, the accuracy of the setting position of each steel sheet pile is improved, avoiding the need for adjustment of the steel sheet piles after setting, thereby improving construction efficiency.

[0017] As a further preferred embodiment, when the steel sheet piles are laid out, a detachable guide frame is provided in the river channel, and the guide frame is provided with guide grooves for the steel sheet piles to pass through.

[0018] By adopting the above technical solution, the steel sheet piles can be placed on the same straight line during installation, further improving the accuracy of the steel sheet pile installation position, and reinforcing both sides of the steel sheet piles to avoid deformation of the steel sheet piles during installation.

[0019] As a further preferred embodiment, the steel sheet piles are laid using a vibrating hammer to sink them, and a laser instrument is used to ensure that they sink vertically.

[0020] By adopting the above technical solution, the efficiency of laying out the steel sheet piles is improved, and the vertical arrangement and structural stability of the steel sheet piles are ensured.

[0021] As a further preference, two adjacent steel sheet piles are connected by any one of welding, snap-fit ​​connection and bolt connection.

[0022] By adopting the above technical solution, two adjacent steel sheet piles are connected by using a suitable connection method according to actual construction needs, so as to improve the connection stability after the steel sheet piles are set.

[0023] As a further preference, the cross-section of each of the steel sheet piles along the horizontal direction is wavy.

[0024] By adopting the above technical solution, the weight of the steel sheet piles is reduced and the structural strength of the steel sheet piles is improved, thereby preventing the steel sheet piles from being deformed under the pressure of water.

[0025] As further preferred, in step S2, the waterproofing treatment is performed by setting a seal or backfilling soil between two adjacent steel sheet piles and between the steel sheet piles and the river bank.

[0026] By adopting the above technical solution, the sealing between the steel sheet piles is improved, preventing river water from entering the main pier demolition operation area.

[0027] As a further preferred embodiment, in step S4, multiple slopes are provided in the foundation pit, and a working platform is left between two adjacent slopes.

[0028] By adopting the above technical solution, multiple slopes are set up and working platforms are left to facilitate construction workers to work downward in sequence.

[0029] As a further preference, the height of each level of the slope is not greater than 3m, and the slope ratio is not steeper than 1:1.

[0030] By adopting the above technical solution, the stability of the foundation pit is improved, making it safer for construction workers to work in the foundation pit.

[0031] In general, the above technical solutions conceived by this application have the following technical advantages compared with the prior art:

[0032] This application uses a steel sheet pile cofferdam to form the main pier demolition operation area, and adopts a drainage backfill method to provide a safe and water-free work site for the main pier demolition construction. The site is larger and stronger, which can improve the efficiency of the main pier demolition operation and make the operation safer. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Figure 1 is a flow chart of the method provided in the embodiment of the present application;

[0034] Figure 2 is a schematic diagram of a top view of the cofferdam structure provided in an embodiment of the present application;

[0035] Figure 3 This is a schematic diagram of the first state of assembly of the steel sheet pile and the guide frame provided in an embodiment of the present application;

[0036] Figure 4 It is a schematic diagram of the second state of the steel sheet pile and guide frame assembly provided in an embodiment of the present application.

[0037] Throughout the drawings, the same reference numerals are used to denote the same elements or structures, wherein:

[0038] 1. Steel sheet piles; 2. Guide frame. DETAILED DESCRIPTION

[0039] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0040] Reference Figure 1-4 The present application discloses a method for dismantling the main pier of an old bridge in Linhe River, which comprises the following steps:

[0041] S1: Determine the area where the main pier of the old bridge is set up, and form the main pier removal operation area on the cofferdam on its river side; in this embodiment, the cofferdam is formed by arranging a number of steel sheet piles 1 in sequence, and the cofferdam is a semi-enclosed structure; the steel sheet piles 1 are arranged vertically during construction, and the cross-section of each steel sheet pile 1 along the horizontal direction is wavy, which reduces the mass of the steel sheet piles 1 and improves the structural strength of the steel sheet piles 1, and avoids the deformation of the steel sheet piles 1 under the pressure of water, wherein each steel sheet pile 1 is positioned by a total station before being arranged, so as to improve the accuracy of the setting position of each steel sheet pile 1; the steel sheet piles 1 need to be inspected, hoisted, and stacked after entering the site: the steel sheet piles 1 are generally inspected for material and appearance, so as to correct the steel sheet piles 1 that do not meet the requirements, so as to reduce the difficulties in the piling process, and the loading and unloading of the steel sheet piles 1 should be carried out by two-point hoisting, and the location for stacking the steel sheet piles 1 is selected on a flat and solid site that will not undergo large subsidence and deformation due to the weight, and is convenient for transportation to the piling construction site.

[0042] Reference Figure 3-4 When the steel sheet piles 1 are laid out, a detachable guide frame 2 is first set in the river channel. A guide groove for the steel sheet piles 1 to pass through is opened on the guide frame 2, and the guide groove is opened along the length direction of the guide frame; in this embodiment, a crane is used to hang the guide frame 2, and the guide frame 2 is fixedly connected to the mechanical arm of the crane. Initially, the guide frame 2 is perpendicular to the river bank, and the steel sheet piles 1 are laid out along the direction of the guide groove. The steel sheet piles 1 are vertically inserted into the guide groove. The guide groove can make the adjacent steel sheet piles 1 be located on the same straight line when laid out, thereby improving the accuracy of the installation position of the steel sheet piles 1. After the previous steel sheet pile 1 is laid out, the crane drives the guide frame forward one unit position. In order to continue to lay the next steel sheet pile 1, until the steel sheet pile 1 perpendicular to the river bank is laid, the crane removes the guide frame 2 and rotates the guide frame 2 to be parallel to the river bank, and then lays the steel sheet pile 1 parallel to the river bank, and completes the laying of all steel sheet piles 1 in sequence according to the above steps; further, the guide frame 2 can also reinforce both sides of the steel sheet pile 1 to prevent the steel sheet pile 1 from deforming during laying. After the guide frame 2 is set on the water surface, the steel sheet pile 1 is laid. The steel sheet pile 1 is laid using a vibrating hammer to make it sink, and a laser instrument is used to ensure its vertical sinking, thereby improving the laying efficiency of the steel sheet pile 1 and ensuring its vertical setting.

[0043] In order to improve the stability of the overall structure of the cofferdam, any one of welding, snap-fit ​​connection and bolt connection is used between two adjacent steel sheet piles 1 to connect several steel sheet piles 1 into a whole, thereby making it stronger and more stable.

[0044] S2: waterproofing the outer side of the main pier demolition operation area; specifically, the waterproofing treatment is performed by setting a rubber seal between two adjacent steel sheet piles 1 and between the steel sheet pile 1 and the river bank or by backfilling with soil, so as to improve the sealing between two adjacent steel sheet piles 1 and between the steel sheet pile 1 and the river bank, so as to prevent water in the waterway from infiltrating into the main pier demolition operation area.

[0045] S3: Use the existing pumping device to drain the water inside the main pier demolition operation area and then backfill with sand and soil to form a platform for construction work in the main pier demolition operation area.

[0046] S4: Excavate a foundation pit around the main pier area; set up multiple slopes in the foundation pit, each slope height is no more than 3m, the slope ratio is no steeper than 1:1, to improve the stability of the foundation pit and make it safer for construction workers to work in the foundation pit. A working platform for external excavation equipment to pass is left between two adjacent slopes, so that construction workers can work downward in sequence.

[0047] S5: Remove the main pier columns and pile foundation concrete in turn until they reach the predetermined demolition height, and cut the internal steel bars at the same time; use multiple excavators with pickaxes to remove the main pier columns and pile foundations, and use the construction breaks to cut and regularize the steel bars;

[0048] S6: After checking and accepting the extent of the main pier column removal, backfill the foundation pit to complete the main pier removal.

[0049] It should be understood that expressions such as "include" and "may include" used in this application indicate the existence of the disclosed functions, operations or constituent elements, and do not limit one or more additional functions, operations and constituent elements. In this application, terms such as "include" and / or "have" may be interpreted as indicating specific characteristics, numbers, operations, constituent elements, components or combinations thereof, but may not be interpreted as excluding the existence or possibility of adding one or more other characteristics, numbers, operations, constituent elements, components or combinations thereof.

[0050] It should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0051] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0052] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0053] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present application shall be included in the scope of protection of the present application.

Claims

1. A method for dismantling the main pier of an old bridge near a river, characterized in that: The steps include: S1: The cofferdam on the river side of the main pier setting area forms the main pier dismantling operation area; S2: waterproofing the outer side of the main pier demolition operation area; S3: draining the water inside the main pier demolition operation area and then backfilling; S4: excavating a foundation pit around the area where the main pier is set; S5: Remove the main pier columns and pile foundation concrete in sequence until they reach the predetermined demolition height, while cutting the internal steel bars; S6: After inspection and acceptance, backfill the foundation pit and complete the removal of the main pier.

2. A method for dismantling the main pier of an old riverside bridge as claimed in claim 1, characterized in that: In the step S1, the cofferdam is formed by sequentially arranging a plurality of steel sheet piles, and each of the steel sheet piles is arranged vertically.

3. A method for dismantling the main pier of an old riverside bridge as claimed in claim 2, characterized in that: Before the steel sheet piles are laid, a total station is used to locate the laying positions of the steel sheet piles.

4. A method for dismantling the main pier of an old riverside bridge as claimed in claim 2, characterized in that: When the steel sheet piles are laid out, a detachable guide frame is arranged in the river channel, and a guide groove for the steel sheet piles to pass through is opened on the guide frame.

5. The method for dismantling the main pier of an old riverside bridge as claimed in claim 2, characterized in that: The steel sheet piles are laid using a vibrating hammer to sink them, and a laser instrument is used to ensure that they sink vertically.

6. A method for dismantling the main pier of an old riverside bridge as claimed in claim 2, characterized in that: The two adjacent steel sheet piles are connected by welding, snap-fit ​​connection or bolt connection.

7. A method for dismantling the main pier of an old riverside bridge as claimed in claim 2, characterized in that: The cross section of each of the steel sheet piles along the horizontal direction is wavy.

8. The method for dismantling the main pier of an old riverside bridge as claimed in claim 2, characterized in that: In step S2, the waterproofing treatment is performed by setting a seal or backfilling soil between two adjacent steel sheet piles and between the steel sheet piles and the river bank.

9. The method for dismantling the main pier of an old riverside bridge according to claim 1, characterized in that: In step S4, multiple levels of slopes are arranged in the foundation pit, and a working platform is left between two adjacent levels of slopes.

10. A method for dismantling the main pier of an old riverside bridge as claimed in claim 9, characterized in that: The height of each level of slope is not more than 3m, and the slope ratio is not steeper than 1:1.