Emergency cofferdam reinforcing method for canal engineering construction

By installing container components and water barriers on the water-welcoming side of the cofferdam during canal construction, combined with buffer energy dissipation devices, the problems of complex reinforcement structure and inconvenient installation are solved, and the rapid reinforcement and impact resistance of the cofferdam are achieved. , avoiding the risk of collapse.

CN118979508APending Publication Date: 2024-11-19CHONGQING JIAOTONG UNIV +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411442478.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-16
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

The existing technology has complex structure and inconvenient installation in canal construction, making it difficult to quickly deal with the risk of collapse during flooding.

Method used

A container-type component is installed in front of the water-welfare side of the cofferdam and heavy objects are installed. Combined with the water barrier to share the impact pressure of the water flow, a combined construction method is adopted to enhance the impact resistance of the cofferdam and reduce the impact force through the buffering and energy dissipation device.

Benefits of technology

The rapid reinforcement of the cofferdam is achieved, the impact resistance and integrity are improved, the risk of collapse is avoided, and the construction is convenient and the cost is low.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979508A_ABST
    Figure CN118979508A_ABST
Patent Text Reader

Abstract

The invention discloses an emergency reinforcing method for a cofferdam in canal engineering construction, which is characterized in that a row of container-like components are arranged in front of the upstream side of the cofferdam, reinforcement is formed by adding heavy objects to the container-like components, and meanwhile, a row of water baffles are arranged in front of the container-like components to stop water and balance the water flow impact pressure. According to the method, emergency reinforcement of the cofferdam of the canal project can be well achieved, the good reinforcement effect is achieved, installation and construction are easy and convenient, the method is implemented at the position where the dam breach danger possibly occurs, the impact resistance of the cofferdam can be rapidly improved, the integrity of the cofferdam is guaranteed, and the cofferdam burst risk is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of canal construction, and in particular relates to an emergency reinforcement method for a cofferdam during canal engineering construction. Background Art

[0002] Canals are an important part of transportation infrastructure and play an important role in promoting economic development and strengthening cultural exchanges. With the vigorous development of my country's inland waterway transportation, canal construction has been continuously strengthened, and cross-basin water system connectivity and the formation of a high-level waterway network have gradually been achieved. Cofferdams are temporary retaining structures used in the construction of water conservancy projects such as canals. Their main function is to prevent water and silt from entering the construction site of the project so that construction work can be carried out in dry foundation pits. During the construction of the canal, the cofferdam can provide a dry and safe environment for construction work to ensure the smooth progress of the construction. As a temporary building, the cofferdam will be demolished after the canal waterway is basically completed. Therefore, the cofferdam type is mostly selected as a relatively economical and simple earth and rock cofferdam. However, for earth and rock cofferdams, especially the transverse earth and rock cofferdams upstream of the waterway foundation pit of the canal waterway straightening section, the cofferdams at this location are subject to greater impact of water flow, and are susceptible to water flow top impact and collapse during floods, which ultimately leads to water flow pouring into the canal waterway foundation pit, affecting the construction progress and even endangering the lives of on-site construction workers.

[0003] The conventional cofferdam reinforcement method is to set a steel plate on the backwater side of the cofferdam for reinforcement support to improve the strength of the cofferdam. For example, CN202220997767.6 once disclosed a cofferdam reinforcement device, which includes a support rod arranged between the side of the cofferdam body close to the building construction area and the ground. The support rod is arranged downward from the side wall of the cofferdam body to the direction away from the cofferdam body. A support base for connecting the support rod and the ground is arranged between the bottom end of the support rod and the ground. An upper support seat for supporting the upper part of the cofferdam body is arranged between the top of the support rod and the cofferdam body near the top of the cofferdam body. A lower support seat for supporting the middle part of the cofferdam body is arranged between the middle part of the support rod and the cofferdam body near the middle of the cofferdam body. This patent application improves the reinforcement stability of the cofferdam body. Another example is a water conservancy and hydropower construction cofferdam reinforcement device and reinforcement method disclosed in CN202311069544.9, a cofferdam reinforcement structure disclosed in CN202323091418.1, etc., all of which belong to similar reinforcement technologies. However, this technology has the defects of complex structure, inconvenient installation and construction of reinforcement devices, and is not conducive to emergency construction use.

[0004] In view of the above situation, how to design a cofferdam reinforcement technology that can effectively realize the emergency reinforcement of the canal project cofferdam, so that it has a good reinforcement effect and is simple and convenient to install and construct, has become a problem that technical personnel in this field need to consider and solve. Summary of the invention

[0005] In view of the deficiencies of the above-mentioned prior art, the technical problem to be solved by the present invention is: how to provide a method for emergency reinforcement of canal project cofferdams, which can effectively realize the emergency reinforcement of canal project cofferdams, has good reinforcement effect and is simple and convenient to install and construct. It can be implemented at the location where the cofferdam may be in danger of breach, which can quickly improve the impact resistance of the cofferdam and ensure the integrity of the cofferdam, and avoid the risk of cofferdam breach.

[0006] In order to solve the above technical problems, the present invention adopts the following technical solutions: A method for emergency reinforcement of a cofferdam during canal engineering construction is characterized in that a row of container-like components are first arranged in front of the water-facing side of the cofferdam, and reinforcement is achieved by adding heavy objects to the container-like components. At the same time, a row of water retaining plates are arranged in front of the container-like components to retain water and balance the impact pressure of the water flow.

[0007] In this way, this method relies on setting a row of container-like components in front of the water-facing side of the cofferdam, so that after loading heavy objects, it can improve the strength of the cofferdam, and at the same time set a row of water retaining plates in front to resist the impact of water flow and even out the impact pressure. In this way, the effects of improving the strength of the cofferdam and resisting the impact of water flow are shared by different components, and a combined construction method can be used on site. While ensuring the reinforcement effect, it greatly improves the convenience of construction and improves the emergency response capability. It can quickly improve the impact resistance of the cofferdam and ensure the integrity of the cofferdam, avoiding the risk of cofferdam collapse.

[0008] As an implementation option, the container-like component is an open gabion mesh, the heavy object is earth or stone, and the water retaining plate is a steel plate or a wooden board or a plastic plate. This has the advantages of simple structure and low construction cost.

[0009] Preferably, the method is implemented using an emergency reinforcement device for cofferdams during canal engineering construction, comprising reinforcement seats arranged in a row in front of the water-facing side of the cofferdam, the reinforcement seats being elongated as a whole and having a fixed inclined surface in contact with the water-facing side of the cofferdam, a plurality of fixed cones with downwardly pointed ends being arranged on the fixed inclined surface, a plurality of weight-increasing grooves for adding weights being arranged on the upper surface of the reinforcement seats, and a row of vertically arranged water retaining plates being in contact with the front side surfaces of the reinforcement seats.

[0010] In this way, when in use, the reinforcement seat is inserted into the water diversion side of the cofferdam by means of the fixed cone, and the fixed slope and the water-facing side are fitted and fixed, and then fixed weights such as earth or pebbles and stones are added into the weight-increasing groove to increase the weight and reinforce the cofferdam. The set water retaining plate can better resist and balance the impact force of the water flow. Therefore, the overall device is used for emergency reinforcement of the cofferdam, which has the advantages of convenient and fast carrying and installation, and reliable and effective reinforcement effect.

[0011] Furthermore, the front side of the water retaining plate is provided with an arc-shaped concave-convex structure which is continuously distributed in a wavy shape along the length direction.

[0012] In this way, the water-facing side surface with the concave and convex arrangement directly faces the impact of the water flow, so that the impact force generated by the water flow can be well dispersed and buffered by the curved surface on the plate, thereby achieving the effect of buffering and dissipating energy.

[0013] Furthermore, a buffering and energy dissipating device is provided between the rear side of the water baffle and the front side of the reinforcement seat, and the buffering and energy dissipating device includes a buffering spring for buffering force.

[0014] In this way, the impact of water flow can be further buffered and dissipated by relying on the buffering and energy dissipation device, and the impact kinetic energy can be converted into spring potential energy and further converted into internal energy for dissipation, which can better reduce the impact of water flow on the cofferdam and improve the reinforcement effect.

[0015] Furthermore, the buffering and energy dissipation device includes a first fixed seat installed on the rear side of the water baffle or the front side of the reinforcement seat, and two rotating rods that are unfolded into an eight-shaped shape are hingedly arranged on the first fixed seat so as to be horizontally rotatable. The other sides of the two rotating rods are respectively hingedly arranged on a slider, and the slider is slidably sleeved on a horizontally arranged sliding rod. The two ends of the sliding rod are respectively fixed on a second fixed seat, and the second fixed seat is fixedly installed on the front side of the reinforcement seat or the rear side of the water baffle. The buffer spring is sleeved on the sliding rod between the slider and the second fixed seat.

[0016] In this way, when the water retaining plate is subjected to the impact of water flow, the impact pressure drives the two rotating rods to open outward in an eight-shaped shape, and then the slider is pushed to compress the buffer spring to do work, converting the kinetic energy into potential energy and internal energy dissipation. In this way, the impact force in the vertical direction is converted into an impact in the horizontal direction and acts on the second fixed seat, so that the reinforcement seat is no longer subjected to the impact force in the vertical direction, greatly improving the anti-impact and energy dissipation effect.

[0017] Furthermore, the reinforcement seat as a whole has a vertical rectangular front side and a right-angled trapezoidal cross section.

[0018] In this way, the load-bearing and reinforcement effects can be better achieved.

[0019] Furthermore, the overall height of the reinforcement seat is consistent with the height of the cofferdam, so that a better reinforcement effect can be achieved.

[0020] Furthermore, the reinforcement seat is folded in half as a whole, and includes a left half and a right half that are arranged opposite to each other along the length direction, and a folding hinge is provided between the left half and the right half at the joint position on the upper surface.

[0021] In this way, the reinforcement seat can be folded in half for transportation and carrying, which facilitates the convenience of handling, transportation and construction.

[0022] Furthermore, the folding hinge comprises a first hinge half and a second hinge half, the first hinge half being fixedly mounted in a recessed groove on the upper surface of the left half of the reinforcement seat near the docking position, and the second hinge half being fixedly mounted in a recessed groove on the upper surface of the right half of the reinforcement seat near the docking position, a rotating sleeve being fixedly provided on the docking side of the first hinge half, and a rotating shaft being fixedly provided on the docking side of the second hinge half, the rotating shaft being rotatably mounted in the rotating sleeve, and a spacing margin being left between the axial end surface of the rotating sleeve and the rotating shaft and the second hinge fixed position (i.e., the two ends of the rotating shaft) for the rotating shaft to slide along the axial direction; a pair of concave-convex matching structures are respectively designed on the docking side surfaces and the upper surfaces of the left and right halves, the concave-convex matching structures comprising a dovetail groove and a trapezoidal protrusion matching the dovetail groove, one side surface of the trapezoidal shape of the dovetail groove and the trapezoidal protrusion being coplanar with the rear side surface of the reinforcement seat, and the length dimension of the dovetail groove and the trapezoidal protrusion along the direction perpendicular to the rear side surface of the reinforcement seat is less than the sliding margin length of the rotating shaft along the rotating sleeve.

[0023] In this way, when the left and right halves of the reinforcement seat are in the two shapes of folded or unfolded into a long strip, the axial sliding fit of the rotating shaft and the rotating sleeve can be relied on during the shape conversion, so that the trapezoidal protrusion is inserted into the corresponding dovetail groove, thereby realizing the locking and fixing of the structure after the conversion state. In this way, the reinforcement seat will not be easily opened after being folded during transportation, which improves the convenience of transportation. After being unfolded and installed for use, since the left and right halves are fixed on the cofferdam by means of a fixing cone, there is no space for the rotating shaft to slide axially, so that the docking sides of the left and right halves will not be easily rotated and overlapped after being locked and fixed by means of a concave-convex matching structure, which greatly improves the stability and reliability of the structure. During implementation, the water retaining plate can be set as two pieces corresponding to the left and right halves of the reinforcement, so that they can be folded and combined smoothly.

[0024] Furthermore, a plug-in water-blocking device is provided on both sides of the reinforcement seat, and the plug-in water-blocking device includes a plug-in plate, which is movably arranged in slots at both ends of the fixed inclined surface of the reinforcement seat. The plug-in plate is arranged obliquely at the same angle as the fixed inclined surface as a whole and a sharp edge is provided at the outer end. A connecting handle is fixedly arranged horizontally inward on the inner side of the plug-in plate. The connecting handle can be horizontally slidably installed in the corresponding connecting handle slide groove and a rack is arranged on one side of the connecting handle. The teeth of the rack are arranged perpendicular to the axial direction of the connecting handle. The rack on the connecting handle is meshed with a driving gear, and the driving gear is transmission-connected to a plug-in motor. The plug-in motor is installed in the corresponding motor mounting groove.

[0025] In this way, when the reinforcement seat is installed, after the fixed cone on the fixed slope is inserted downward into the water-facing side of the cofferdam, the plug-in water retaining device can be further controlled to work, the plug-in motor is started, and the connecting handle is driven to move horizontally outward through the active gear, so that the plug-in plate extends outward and is inserted into the water-facing side of the cofferdam. The plug-in plate can be used to shield the gap between the reinforcement seat and the water-facing side of the cofferdam, avoiding the impact stress concentration at the gap position caused by the scouring of river water, which makes the gap larger and larger, resulting in the instability of the reinforcement seat. Therefore, the plug-in water retaining device can better avoid water scouring and affect the stability of the reinforcement.

[0026] The above-mentioned reinforcement device has the following usage and working process: when the reinforcement device is not in use, the device is in a storage state, the left half and the right half of the reinforcement base are stacked up and down, and the weight-increasing grooves at corresponding positions contact each other. The pair of concave and convex matching structures located on the upper surfaces of the left half and the right half are locked to limit the relative rotation of the left half and the right half, thereby improving the safety when carrying the device.

[0027] When the reinforcement device is in use, first, the left and right halves are controlled to slide and stagger along the axial direction, so that the locked concave-convex matching structures are released from each other, and the left and right halves can be rotated and unfolded to a horizontal state. Then, the left and right halves are controlled to slide and reset along the axial direction, and at the same time, another pair of concave-convex matching structures are inserted relative to each other to form a match, and the reinforcement seat is locked in a horizontal state. Then, the reinforcement seat is placed on the water-facing side of the canal cofferdam, and the fixing cone is inserted downward into the canal cofferdam. The fixing cone is used to fix the reinforcement seat at the position that needs to be reinforced, and then the weight of the reinforcement seat is increased by adding sand and other objects into the weight-increasing groove, thereby improving the stability of the reinforcement seat.

[0028] After the reinforcement seat is fixed on the canal cofferdam, the plug-in motor is started so that the output shaft of the plug-in motor drives the driving gear to rotate, so that the gear and the rack engage and rotate, and the connecting handle drives the plug-in plate to extend upward and insert into the canal cofferdam, thereby ensuring the anti-seepage property of the gap between the reinforcement seat and the canal cofferdam and improving the reinforcement effect.

[0029] (4) When water flows hit the water retaining plate, due to the wave shape on the front side of the water retaining plate, the impact force generated by the water flow can be initially dispersed and buffered by the curved surface on the water retaining plate. At the same time, the water retaining plate drives the buffer energy dissipation device to operate, converting the vertical impact force into a horizontal impact and acting on the second fixed seat after being buffered by the spring, so that the reinforcement seat is no longer subjected to the vertical impact force, thereby improving the impact resistance of the reinforcement device body.

[0030] The present invention has the following characteristics: (1) The present invention can be quickly constructed at the location where the canal cofferdam may breach, provide emergency reinforcement, ensure the integrity of the cofferdam, avoid the breach of the cofferdam, and protect the safety and progress of construction. (2) The reinforcement device body adopts a reinforcement seat with a right-angle trapezoidal structure that is larger at the top and smaller at the bottom. The design of the fitting surface with the canal cofferdam helps to improve the stability of the device. (3) The mutual cooperation of the various components of the folding unit realizes the unfolding and storage of the reinforcement device, which is convenient for transportation and storage, and provides the ability of rapid deployment. (4) The design of the water retaining plate and the buffer energy dissipation device, especially the wavy structure of the water retaining plate, can effectively disperse and buffer the impact force of the water flow and improve the impact resistance of the device. At the same time, the synergistic effect of the various components in the buffer energy dissipation device further enhances the absorption and dispersion of the impact force. (5) The setting of the plug-in water retaining device further ensures the close connection and fixation between the reinforcement device and the canal cofferdam.

[0031] In summary, the present invention can well realize the emergency reinforcement of the cofferdam of the canal project, has a good reinforcement effect and is simple and convenient to install and construct. It can be implemented at the location where the cofferdam may be breached, which can quickly improve the impact resistance of the cofferdam and ensure the integrity of the cofferdam, avoiding the risk of cofferdam breach. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 It is a schematic structural diagram of a cofferdam emergency reinforcement device for canal engineering construction adopted in a preferred embodiment of the present invention.

[0033] Figure 2 for Figure 1 Schematic diagram of the reinforcement device in use.

[0034] Figure 3 for Figure 1 Schematic diagram of the folded state of the reinforcement device shown.

[0035] Figure 4 for Figure 1 A schematic diagram of the enlarged structure in the middle.

[0036] Figure 5 for Figure 1 The reinforcement device shown is a schematic diagram showing the structure of the internal plug-in water retaining device.

[0037] Figure 6 for Figure 5 Enlarged schematic diagram of the structure at point B in the middle.

[0038] Figure 7 for Figure 1 Schematic diagram of the disassembled structure of the folding hinge of the reinforcement device shown. DETAILED DESCRIPTION

[0039] The present invention is further described in detail below in conjunction with specific implementation modes.

[0040] Preferred implementation method: A method for emergency reinforcement of cofferdams during canal engineering construction, characterized in that a row of container-like components are first arranged in front of the water-facing side of the cofferdam, and reinforcement is achieved by adding heavy objects to the container-like components. At the same time, a row of water retaining plates are arranged in front of the container-like components to retain water and balance the impact pressure of the water flow.

[0041] In this way, this method relies on setting a row of container-like components in front of the water-facing side of the cofferdam, so that after loading heavy objects, it can improve the strength of the cofferdam, and at the same time set a row of water retaining plates in front to resist the impact of water flow and even out the impact pressure. In this way, the effects of improving the strength of the cofferdam and resisting the impact of water flow are shared by different components, and a combined construction method can be used on site. While ensuring the reinforcement effect, it greatly improves the convenience of construction and improves the emergency response capability. It can quickly improve the impact resistance of the cofferdam and ensure the integrity of the cofferdam, avoiding the risk of cofferdam collapse.

[0042] In this embodiment, the method is implemented by using a canal engineering construction cofferdam emergency reinforcement device, see Figure 1-Figure 7 The emergency reinforcement device for the cofferdam of the canal engineering construction includes reinforcement seats 1 arranged in a row in front of the water-facing side of the cofferdam. The reinforcement seat 1 is in a long strip shape as a whole and has a fixed inclined surface 2 that is in contact with the water-facing side of the cofferdam. The fixed inclined surface 2 is provided with a plurality of fixed cones 3 with downwardly pointed ends. The upper surface of the reinforcement seat is provided with a plurality of weight-increasing grooves 4 for adding weights. A row of vertically arranged water retaining plates 5 are also provided in contact with the front side surface of the reinforcement seat.

[0043] In this way, when in use, the reinforcement seat is inserted into the water diversion side of the cofferdam by means of the fixed cone, and the fixed slope and the water-facing side are fitted and fixed, and then fixed weights such as earth or pebbles and stones are added into the weight-increasing groove to increase the weight and reinforce the cofferdam. The set water retaining plate can better resist and balance the impact force of the water flow. Therefore, the overall device is used for emergency reinforcement of the cofferdam, which has the advantages of convenient and fast carrying and installation, and reliable and effective reinforcement effect.

[0044] The front side of the water retaining plate 5 is provided with a wave-shaped arc-shaped concave-convex structure which is continuously distributed along the length direction.

[0045] In this way, the water-facing side surface with concave and convex configuration directly faces the impact of the water flow, so that the impact force generated by the water flow can be well dispersed and buffered by the curved surface on the board. The effect of buffering and energy dissipation is achieved. During implementation, the water retaining plate can be a steel plate, a wooden plate, or a plastic plate. The reinforcement seat can be made of metal material or plastic material.

[0046] A buffering and energy dissipating device is also provided between the rear side of the water baffle 5 and the front side of the reinforcement seat, and the buffering and energy dissipating device includes a buffering spring 11 for buffering force.

[0047] In this way, the impact of water flow can be further buffered and dissipated by relying on the buffering and energy dissipation device, and the impact kinetic energy can be converted into spring potential energy and further converted into internal energy for dissipation, which can better reduce the impact of water flow on the cofferdam and improve the reinforcement effect.

[0048] Among them, the buffering energy dissipation device includes a first fixed seat 6 installed on the rear side of the water baffle or the front side of the reinforcement seat, and two rotating rods 7 that are unfolded in an eight-shaped shape are hingedly arranged on the first fixed seat 6 so as to be horizontally rotatable. The other sides of the two rotating rods 7 are respectively hingedly arranged on a slider 8, and the slider 8 is slidably sleeved on a horizontally arranged sliding rod 9. The two ends of the sliding rod 9 are respectively fixed on a second fixed seat 10, and the second fixed seat 10 is fixedly installed on the front side of the reinforcement seat or the rear side of the water baffle. The buffer spring 11 is sleeved on the sliding rod between the slider and the second fixed seat.

[0049] In this way, when the water retaining plate is subjected to the impact of water flow, the impact pressure drives the two rotating rods to open outward in an eight-shaped shape, and then the slider is pushed to compress the buffer spring to do work, converting the kinetic energy into potential energy and internal energy dissipation. In this way, the impact force in the vertical direction is converted into an impact in the horizontal direction and acts on the second fixed seat, so that the reinforcement seat is no longer subjected to the impact force in the vertical direction, greatly improving the anti-impact and energy dissipation effect.

[0050] The reinforcement seat 1 as a whole has a vertical rectangular front side and a right-angled trapezoidal cross section.

[0051] In this way, the load-bearing and reinforcement effects can be better achieved.

[0052] The overall height of the reinforcement seat 1 is consistent with the height of the cofferdam, so that a better reinforcement effect can be achieved.

[0053] The reinforcement seat 1 is folded in half as a whole, and includes a left half and a right half that are arranged opposite to each other along the length direction, and a folding hinge is provided between the left half and the right half at the joint position on the upper surface.

[0054] In this way, the reinforcement seat can be folded in half for transportation and carrying, which facilitates the convenience of handling, transportation and construction.

[0055] The folding hinge comprises a first hinge half 12 and a second hinge half 13. The first hinge half 12 is fixedly mounted in a groove on the upper surface of the left half of the reinforcement base close to the docking position, and the second hinge half 13 is fixedly mounted in a groove on the upper surface of the right half of the reinforcement base close to the docking position. A rotating sleeve 14 is fixedly arranged on the docking side of the first hinge half 12, and a rotating shaft 15 is fixedly arranged on the docking side of the second hinge half 13. The rotating shaft 15 is rotatably mounted in the rotating sleeve 14, and the axial end surface of the rotating sleeve and the rotating shaft are connected to the first hinge half 12. A spacing margin is left between the two hinge fixing positions (i.e., the two ends of the rotating shaft) for the rotating shaft to slide along the axial direction; a pair of concave-convex matching structures are designed on the mating side surfaces and the upper surface of the left half and the right half, and the concave-convex matching structure includes a dovetail groove 16 and a trapezoidal protrusion 17 matching the dovetail groove, and one side of the trapezoidal shape of the dovetail groove and the trapezoidal protrusion is coplanar with the rear side surface of the reinforcement seat, and the length dimension of the dovetail groove and the trapezoidal protrusion along the direction perpendicular to the rear side surface of the reinforcement seat is less than the sliding margin length of the rotating shaft along the rotating sleeve.

[0056] In this way, when the left and right halves of the reinforcement seat are in the two shapes of folded or unfolded into a long strip, the axial sliding fit of the rotating shaft and the rotating sleeve can be relied on during the shape conversion, so that the trapezoidal protrusion is inserted into the corresponding dovetail groove, thereby realizing the locking and fixing of the structure after the conversion state. In this way, the reinforcement seat will not be easily opened after being folded during transportation, which improves the convenience of transportation. After being unfolded and installed for use, since the left and right halves are fixed on the cofferdam by means of a fixing cone, there is no space for the rotating shaft to slide axially, so that the docking sides of the left and right halves will not be easily rotated and overlapped after being locked and fixed by means of a concave-convex matching structure, which greatly improves the stability and reliability of the structure. During implementation, the water retaining plate can be set as two pieces corresponding to the left and right halves of the reinforcement, so that they can be folded and combined smoothly.

[0057] Among them, a plug-in water-blocking device is also provided on both sides of the reinforcement seat, and the plug-in water-blocking device includes a plug-in plate 18, which is movably arranged in slots 19 at both ends of the fixed inclined surface of the reinforcement seat. The plug-in plate is arranged obliquely at the same angle as the fixed inclined surface and a sharp edge is opened at the outer end. A connecting handle 20 is fixedly arranged horizontally inward on the inner side of the plug-in plate. The connecting handle can be horizontally slidably installed in the corresponding connecting handle slide groove and a rack is arranged on one side of the connecting handle. The teeth of the rack are arranged perpendicular to the axial direction of the connecting handle. The rack on the connecting handle is meshed with a driving gear 21, and the driving gear 21 is transmission-connected to a plug-in motor 22, and the plug-in motor 22 is installed in the corresponding motor mounting groove.

[0058] In this way, when the reinforcement seat is installed, after the fixed cone on the fixed slope is inserted downward into the water-facing side of the cofferdam, the plug-in water retaining device can be further controlled to work, the plug-in motor is started, and the connecting handle is driven to move horizontally outward through the active gear, so that the plug-in plate extends outward and is inserted into the water-facing side of the cofferdam. The plug-in plate can be used to shield the gap between the reinforcement seat and the water-facing side of the cofferdam, avoiding the impact stress concentration at the gap position caused by the scouring of river water, which makes the gap larger and larger, resulting in the instability of the reinforcement seat. Therefore, the plug-in water retaining device can better avoid water scouring and affect the stability of the reinforcement.

[0059] As another feasible option, the container-like component is an open gabion mesh, the heavy object is earth or stone, and the water retaining plate is a steel plate, a wooden board or a plastic plate. This has the advantages of simple structure and low construction cost.

Claims

1. A method for emergency reinforcement of cofferdams in canal engineering construction, characterized in that: First, a row of container-like components is set in front of the water-facing side of the cofferdam, and heavy objects are added to the container-like components to form reinforcement. At the same time, a row of water retaining plates is set in front of the container-like components to retain water and balance the impact pressure of the water flow.

2. The method for emergency reinforcement of cofferdams for canal engineering construction as claimed in claim 1, characterized in that: The container-like component is an open gabion mesh, the heavy object is earth or stone, and the water retaining plate is a steel plate, a wooden plate or a plastic plate.

3. The method for emergency reinforcement of cofferdams for canal engineering construction as claimed in claim 1, characterized in that: The method is implemented by using an emergency reinforcement device for cofferdams during canal engineering construction, the emergency reinforcement device for cofferdams during canal engineering construction includes reinforcement seats arranged in a row in front of the water-facing side of the cofferdam, the reinforcement seats are in the shape of an elongated strip as a whole and have a fixed inclined surface in contact with the water-facing side of the cofferdam, a plurality of fixed cones with downwardly pointed ends are arranged on the fixed inclined surface, a plurality of weight-increasing grooves for adding weights are arranged on the upper surface of the reinforcement seats, and a row of vertically arranged water retaining plates are also arranged in contact with the front side surfaces of the reinforcement seats.

4. The method for emergency reinforcement of cofferdams for canal engineering construction as claimed in claim 3, characterized in that: The front side of the water retaining plate is provided with an arc-shaped concave-convex structure which is continuously distributed in a wave-like shape along the length direction.

5. The method for emergency reinforcement of cofferdams for canal engineering construction as claimed in claim 3, characterized in that: A buffering and energy dissipating device is also arranged between the rear side surface of the water baffle and the front side surface of the reinforcement seat, and the buffering and energy dissipating device includes a buffering spring for buffering force.

6. The method for emergency reinforcement of cofferdams for canal engineering construction as claimed in claim 5, characterized in that: The buffering energy dissipation device includes a first fixed seat installed on the rear side of the water baffle or the front side of the reinforcement seat, and two rotating rods that are unfolded in an eight-shaped shape are hingedly arranged on the first fixed seat so as to be horizontally rotatable. The other sides of the two rotating rods are respectively hingedly arranged on a slider, and the slider is slidably sleeved on a horizontally arranged sliding rod. The two ends of the sliding rod are respectively fixed on a second fixed seat, and the second fixed seat is fixedly installed on the front side of the reinforcement seat or the rear side of the water baffle. The buffer spring is sleeved on the sliding rod between the slider and the second fixed seat.

7. The method for emergency reinforcement of cofferdams for canal engineering construction as claimed in claim 3, characterized in that: The reinforcement seat as a whole has a vertical rectangular front side and a right-angled trapezoidal cross section; the overall height of the reinforcement seat is consistent with the height of the cofferdam.

8. The method for emergency reinforcement of cofferdams for canal engineering construction as claimed in claim 3, characterized in that: The reinforcement seat is folded in half as a whole, and comprises a left half and a right half that are arranged opposite to each other along the length direction, and a folding hinge is arranged between the left half and the right half at the joint position of the upper surface.

9. The method for emergency reinforcement of cofferdams for canal engineering construction as claimed in claim 8, characterized in that: The folding hinge comprises a first hinge half body and a second hinge half body, the first hinge half body being fixedly mounted in a recessed groove on the upper surface of the left half body of the reinforcement seat near the docking position, and the second hinge half body being fixedly mounted in a recessed groove on the upper surface of the right half body of the reinforcement seat near the docking position, and the docking side of the first hinge half body is fixedly provided with a rotating sleeve, and the docking side of the second hinge half body is fixedly provided with a rotating shaft, and the rotating shaft is rotatably mounted in the rotating sleeve, and a spacing margin is left between the axial end surface of the rotating sleeve and the rotating shaft and the second hinge fixed position (i.e., the two ends of the rotating shaft) for the rotating shaft to achieve axial sliding; a pair of concave-convex matching structures are respectively designed on the docking side surfaces and upper surfaces of the left and right half bodies, the concave-convex matching structures comprising a dovetail groove and a trapezoidal protrusion matching the dovetail groove, one side surface of the trapezoidal shape of the dovetail groove and the trapezoidal protrusion is coplanar with the rear side surface of the reinforcement seat, and the length dimension of the dovetail groove and the trapezoidal protrusion along the direction perpendicular to the rear side surface of the reinforcement seat is less than the sliding margin length of the rotating shaft along the rotating sleeve.

10. The method for emergency reinforcement of cofferdams for canal engineering construction as claimed in claim 3, characterized in that: A plug-in water retaining device is also provided on both sides of the reinforcement seat, and the plug-in water retaining device includes a plug-in plate, which is movably arranged in slots at both ends of the fixed inclined surface of the reinforcement seat. The plug-in plate is arranged obliquely as a whole and has a sharp edge at the outer end. A connecting handle is fixedly arranged horizontally inward on the inner side of the plug-in plate. The connecting handle can be horizontally slidably installed in the corresponding connecting handle slide groove and a rack is arranged on one side of the connecting handle. The teeth of the rack are arranged perpendicular to the axial direction of the connecting handle. The rack on the connecting handle is meshed with a driving gear, and the driving gear is connected to a plug-in motor for transmission. The plug-in motor is installed in the corresponding motor mounting groove.