Concrete pouring construction and maintenance method for house building

Through the systematic concrete pouring construction and its maintenance methods, the problems of construction quality and efficiency are solved, high-quality building finished products are achieved, and the scientificity and efficiency of construction are ensured.

CN118979626APending Publication Date: 2024-11-19ZHEJIANG WANXIA CONSTRUCT CO LTD
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411398613.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-09
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

During the construction process, the construction quality is affected by the level and mobility of the construction technicians, which makes it difficult to ensure the efficiency and quality of concrete pouring, and insufficient maintenance after construction, which affects the building quality.

Method used

A concrete pouring construction and maintenance method for house buildings, including pre-construction preparation, concrete pouring construction, quality inspection and concrete maintenance, through professional mixing station production, on-site quality control, vibration tamping, crack prevention measures, thermal insulation maintenance, etc. Steps to ensure construction quality and efficiency.

Benefits of technology

Through scientific construction organization and maintenance methods, the construction quality and efficiency are improved, high-quality finished building products are achieved, and the goals of quality, safety, progress and civilized construction are met.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

A house building concrete pouring construction and maintenance method comprises the following steps that S1, preparation work before pouring construction is conducted; s2, concrete pouring construction; s21, bottom plate pouring construction is conducted; s22, wall plate pouring construction is conducted; s221, wallboard pouring preparation work is carried out; s222, wall plate pouring is carried out; S223, wall plate leveling is carried out; s3, quality detection; and S4, concrete curing. Through construction organization deployment, construction preparation, construction and result quality inspection, the process is more reasonable and detailed. And the requirement of high quality can be met while more time is saved for a construction task. And more optimized construction and maintenance methods are adopted, so that the two methods supplement each other to achieve the effect of one plus one greater than two. And the construction procedures are scientifically overlapped, and the construction targets of quality, safety, progress and civilization are comprehensively completed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, in particular to a housing building concrete pouring construction and a maintenance method thereof. Background Art

[0002] With the continuous development of society and the steady improvement of people's living standards, people's requirements for quality of life are getting higher and higher. Construction is closely related to all aspects of people's lives. Therefore, the construction market's demand for high-quality buildings is increasing, and low-quality buildings are gradually being eliminated by the market. In the actual construction process of construction projects, there are many concrete construction processes and the construction process is also relatively complicated. However, as the basic material for engineering construction, whether the construction process is professional will have a direct impact on the quality of the construction project. In the entire process of concrete construction, construction management personnel with high technical levels are required to control the entire construction process in order to effectively improve some common problems in the concrete construction process, thereby ensuring the smooth construction of building concrete construction projects.

[0003] At present, in the process of construction work, affected by some factors (such as the low level of construction technicians, etc.), the construction quality has not been effectively improved. In addition, in the construction of construction projects, the mobility of construction personnel is relatively large, which leads to the inability to guarantee the efficiency of concrete pouring construction work. Similarly, if there is no post-construction care, the finished product after pouring cannot achieve the ideal effect, because the post-construction maintenance also plays a very important role. If the two complement each other, the effect of one plus one is greater than two. In view of the above problems, a concrete pouring construction and maintenance method for house construction is proposed. Summary of the invention

[0004] The purpose of the present invention is to overcome the above-mentioned existing deficiencies and provide a building construction concrete pouring construction and maintenance method thereof.

[0005] To achieve the above object, the present invention provides the following technical solution: a method for pouring concrete for building construction and its maintenance, characterized in that it comprises the following steps:

[0006] S1, preparation work before pouring construction;

[0007] S2, concrete pouring construction;

[0008] S3, quality inspection;

[0009] S4, concrete curing.

[0010] Preferably, the specific operations of step S1 are:

[0011] S11, according to the construction drawings and the initial concrete mix ratio, the concrete supplier and the site will test the concrete separately, adjust the concrete mix ratio, determine the technical procedures and management principles for the production, transportation and pouring of concrete, formulate corresponding anti-cracking technical measures, and pour the concrete continuously in one go without leaving construction joints or cold joints;

[0012] S12, concrete is produced, transported and pumped by professional mixing plants. Professional manufacturers should have technical responsibility capabilities, which is an important part of concrete quality management. The concrete supplier prepares a construction control plan for all procedures from mixing concrete at the mixing plant to transportation to the site and submits it to the construction unit;

[0013] S13, set up an on-site QC team, led by the project chief engineer, to carry out quality control such as concrete crack prevention.

[0014] Preferably, the specific steps of step S2 are:

[0015] S21, bottom slab pouring construction;

[0016] S22, wall panel pouring construction.

[0017] Preferably, the specific operations of step S21 are:

[0018] According to the actual situation that a slope is naturally formed when concrete is pumped, two vibrators are arranged in front and behind each pouring zone;

[0019] The first one is arranged at the concrete unloading point, mainly to solve the problem of compaction of upper concrete;

[0020] The second pass is arranged at the foot of the concrete slope to ensure the compaction of the lower concrete;

[0021] The material should be discharged continuously and evenly, the material discharge in the elevator pit should be symmetrical, and the material discharge joint should be controlled within 3 hours;

[0022] The vibrating rod should be operated with "fast insertion and slow withdrawal". During the vibration, the vibrating rod should be slightly twitched up and down to make the vibration even. The vibration time for each point is generally 20 to 30 seconds. At the same time, the concrete surface is horizontal and no longer sinks significantly, no bubbles appear, and mortar appears on the surface.

[0023] Control the vibration time of the side formwork, and do not directly impact the side formwork when unloading materials;

[0024] During pouring, the poured concrete should be vibrated repeatedly every half an hour during the initial setting time. At the same time, the thick cement mortar on the surface of the poured concrete should be scraped in time according to the design elevation, and smoothed and compacted with a wooden trowel before initial setting.

[0025] Pay attention to controlling the interval time of concrete pouring. The next pouring of concrete should be completed before the initial setting of the previous concrete, generally not more than 2 hours;

[0026] When the foot of the large concrete slope approaches the top formwork, change the direction of concrete pouring, that is, pour from the top back to form a sump where it intersects with the original slope. In addition, consciously strengthen the concrete pouring at the formwork on both sides to gradually reduce the sump into a small pool. Use a flexible shaft pump to drain it in time. This method is used to remove all seepage water in the final stage.

[0027] All water-stop formwork exterior walls must be vibrated and compacted twice with an interval of 1 to 2 hours.

[0028] Preferably, the specific steps of step S22 are:

[0029] S221, preparation for pouring wall panels;

[0030] S222, wall panel casting,

[0031] S223, wall panel leveling.

[0032] Preferably, the specific operations of step S221 are:

[0033] Check whether the template is installed in place, and whether the flatness, verticality and elevation meet the requirements;

[0034] Whether the steel bars meet the design and specification requirements, and whether the steel bar spacing, the thickness of the retained protective layer, and the position of the concrete pad are accurate;

[0035] Check whether the post-casting strip forming formwork, water stop sheet, foundation slab and exterior wall water stop strip have been installed;

[0036] Use fixed pump;

[0037] All engineering data must be completed before concrete pouring.

[0038] Preferably, the specific operations of step S222 are:

[0039] The grouting strip is used as the dividing line later;

[0040] Strictly control the concrete production and transportation process;

[0041] When pouring, corresponding measures can be formulated according to the actual situation;

[0042] Casting is done in sections and layers continuously;

[0043] Before pouring, wet the formwork first, and fill the bottom of the vertical structure wall panel with 50-100mm thick cement mortar with the same mortar mix as the concrete;

[0044] Segregation shall not occur during pouring. The pouring height shall exceed 2m and pouring shall be carried out in conjunction with a string tube.

[0045] The pouring sequence is to pour the exterior wall panels first, with a pouring thickness of 200-300mm, along the four sides of the wall, and then pour from the starting point, in this cycle;

[0046] When concrete is poured into the mold, it must be vibrated with a vibrating rod, and the next concrete pouring should be before the previous concrete begins to set, and the vibrating rod must vibrate it densely.

[0047] Preferably, the specific operations of step S223 are:

[0048] When pouring floor slab concrete, vibrate and level it manually. Use a line or a 2m ruler to level it.

[0049] The floor concrete needs to be compacted twice before initial setting, and finally roughened with a wooden trowel. The flatness of the floor surface is checked with a 2m ruler and controlled within a 5mm error range.

[0050] Preferably, the specific operations of step S3 are:

[0051] Special personnel should be assigned to guard the formwork and steel bars, check whether the formwork and steel bars are deformed at any time, and restore or reinforce them in time;

[0052] The concrete should be vibrated densely, and the action range of the vibrating rod should be controlled within 1.5 times its action radius;

[0053] The vibrating rod should follow the concrete feeding, and the formwork and steel bars should not be vibrated all the time when the vibrating rod vibrates;

[0054] The interval between concrete pouring is to pour the next concrete before the initial setting of the previous concrete, so as to ensure that there is no cold joint during construction;

[0055] The flatness and verticality of the formed concrete meet the requirements of the specifications;

[0056] During pouring, rooms or areas with waterproofing requirements should be lower than the floor structure surface elevation according to design requirements.

[0057] Preferably, the specific operations of step S4 are:

[0058] Cover the concrete surface with a layer of plastic film and blanket. When covering, the plastic film and blanket should be laid overlappingly, and the upper and lower layers should be overlapped and staggered accordingly. No concrete should be exposed, so as to ensure the thermal insulation of the concrete by the thermal insulation material.

[0059] In the first three days after concrete pouring, the concrete is in the temperature rising stage, and the internal temperature of the concrete reaches nearly 70°C. After the concrete pouring is completed and it begins to set, and people can basically walk on it without footprints, it is covered with a layer of plastic film for maintenance, and then covered with a blanket.

[0060] After one week, remove part of the plastic film and water the plants for maintenance. The watering time should be arranged during the day when there is sunshine. The watering maintenance time should be no less than 14 days.

[0061] 12 hours after concrete pouring or after final setting, apply a layer of plastic film with an overlap of more than 100mm between blocks, and then apply two layers of straw bags for thermal insulation maintenance;

[0062] After final setting, uncover the plastic sheet and spray water for curing every 3 to 4 hours;

[0063] The film covering maintenance period is ≥15 days. After the temperature measurement analysis results are available, the technical person in charge shall issue the instruction to remove the thermal insulation maintenance. No other person shall issue the instruction to remove the thermal insulation maintenance without authorization.

[0064] From the 4th day onwards, the cover can be partially uncovered to lay out the lines, and the lines can be covered immediately after being drawn. After reinforcing bars are tied, the shear walls and concealed columns can be partially exposed to close the formwork, and the rest of the parts should still be covered until the insulation instruction is released;

[0065] Atmospheric temperature is measured with a mercury thermometer at about 1m above the natural surface. In an open environment, the microclimate temperature is measured at a height of 1m on the foundation plate.

[0066] The temperature of concrete entering the mold should be measured every 2 hours by inserting a mercury thermometer directly into the newly poured concrete cap to read the temperature directly;

[0067] After the initial setting of concrete, before the thermal insulation and curing is removed, the temperature is measured above the cap and below the membrane cover;

[0068] A dedicated person will listen to the weather forecast for the area. During the insulation maintenance period, if the temperature drops sharply below 8°C, it must be reported to the technical person in charge, and maintenance measures such as adding insulation materials must be taken.

[0069] Compared with the prior art, the present invention has the following beneficial effects:

[0070] The present invention makes the process more rational and detailed through construction organization deployment, construction preparation, construction and quality inspection of results. It can save more time in construction tasks while meeting high quality requirements. It adopts more optimized construction and maintenance methods, so that the two complement each other and achieve the effect of one plus one greater than two. The construction process is scientifically overlapped to fully achieve the goals of quality, safety, progress and civilized construction. DETAILED DESCRIPTION

[0071] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0072] The present invention provides a technical solution: a concrete pouring construction and maintenance method for a building, characterized in that it comprises the following steps:

[0073] S1, preparation work before pouring construction;

[0074] S2, concrete pouring construction;

[0075] S3, quality inspection;

[0076] S4, concrete curing.

[0077] Preferably, the specific operations of step S1 are:

[0078] S11, according to the construction drawings and the initial concrete mix ratio, the concrete supplier and the site will test the concrete separately, adjust the concrete mix ratio, determine the technical procedures and management principles for the production, transportation and pouring of concrete, formulate corresponding anti-cracking technical measures, and pour the concrete continuously in one go without leaving construction joints or cold joints;

[0079] S12, concrete is produced, transported and pumped by professional mixing plants. Professional manufacturers should have technical responsibility capabilities, which is an important part of concrete quality management. The concrete supplier prepares a construction control plan for all procedures from mixing concrete at the mixing plant to transportation to the site and submits it to the construction unit;

[0080] S13, set up an on-site QC team, led by the project chief engineer, to carry out quality control such as concrete crack prevention.

[0081] Preferably, the specific steps of step S2 are:

[0082] S21, bottom slab pouring construction;

[0083] S22, wall panel pouring construction.

[0084] Preferably, the specific operations of step S21 are:

[0085] According to the actual situation that a slope is naturally formed when concrete is pumped, two vibrators are arranged in front and behind each pouring zone;

[0086] The first one is arranged at the concrete unloading point, mainly to solve the problem of compaction of upper concrete;

[0087] The second pass is arranged at the foot of the concrete slope to ensure the compaction of the lower concrete;

[0088] The material should be discharged continuously and evenly, the material discharge in the elevator pit should be symmetrical, and the material discharge joint should be controlled within 3 hours;

[0089] The vibrating rod should be operated with "fast insertion and slow withdrawal". During the vibration, the vibrating rod should be slightly twitched up and down to make the vibration even. The vibration time for each point is generally 20 to 30 seconds. At the same time, the concrete surface is horizontal and no longer sinks significantly, no bubbles appear, and mortar appears on the surface.

[0090] Control the vibration time of the side formwork, and do not directly impact the side formwork when unloading materials;

[0091] During pouring, the poured concrete should be vibrated repeatedly every half an hour during the initial setting time. At the same time, the thick cement mortar on the surface of the poured concrete should be scraped in time according to the design elevation, and smoothed and compacted with a wooden trowel before initial setting.

[0092] Pay attention to controlling the interval time of concrete pouring. The next pouring of concrete should be completed before the initial setting of the previous concrete, generally not more than 2 hours;

[0093] When the foot of the large concrete slope approaches the top formwork, change the direction of concrete pouring, that is, pour from the top back to form a sump where it intersects with the original slope. In addition, consciously strengthen the concrete pouring at the formwork on both sides to gradually reduce the sump into a small pool. Use a flexible shaft pump to drain it in time. This method is used to remove all seepage water in the final stage.

[0094] All water-stop formwork exterior walls must be vibrated and compacted twice with an interval of 1 to 2 hours.

[0095] Preferably, the specific steps of step S22 are:

[0096] S221, preparation for pouring wall panels;

[0097] S222, wall panel casting,

[0098] S223, wall panel leveling.

[0099] Preferably, the specific operations of step S221 are:

[0100] Check whether the template is installed in place, and whether the flatness, verticality and elevation meet the requirements;

[0101] Whether the steel bars meet the design and specification requirements, and whether the steel bar spacing, the thickness of the retained protective layer, and the position of the concrete pad are accurate;

[0102] Check whether the post-casting strip forming formwork, water stop sheet, foundation slab and exterior wall water stop strip have been installed;

[0103] Use fixed pump;

[0104] All engineering data must be completed before concrete pouring.

[0105] Preferably, the specific operations of step S222 are:

[0106] The grouting strip is used as the dividing line later;

[0107] Strictly control the concrete production and transportation process;

[0108] When pouring, corresponding measures can be formulated according to the actual situation;

[0109] Casting is done in sections and layers continuously;

[0110] Before pouring, wet the formwork first, and fill the bottom of the vertical structure wall panel with 50-100mm thick cement mortar with the same mortar mix as the concrete;

[0111] Segregation shall not occur during pouring. The pouring height shall exceed 2m and pouring shall be carried out in conjunction with a string tube.

[0112] The pouring sequence is to pour the exterior wall panels first, with a pouring thickness of 200-300mm, along the four sides of the wall, and then pour from the starting point, in this cycle;

[0113] When concrete is poured into the mold, it must be vibrated with a vibrating rod, and the next concrete pouring should be before the previous concrete begins to set, and the vibrating rod must vibrate it densely.

[0114] Preferably, the specific operations of step S223 are:

[0115] When pouring floor slab concrete, vibrate and level it manually. Use a line or a 2m ruler to level it.

[0116] The floor concrete needs to be compacted twice before initial setting, and finally roughened with a wooden trowel. The flatness of the floor surface is checked with a 2m ruler and controlled within a 5mm error range.

[0117] Preferably, the specific operations of step S3 are:

[0118] Special personnel should be assigned to guard the formwork and steel bars, check whether the formwork and steel bars are deformed at any time, and restore or reinforce them in time;

[0119] The concrete should be vibrated densely, and the action range of the vibrating rod should be controlled within 1.5 times its action radius;

[0120] The vibrating rod should follow the concrete feeding, and the formwork and steel bars should not be vibrated all the time when the vibrating rod vibrates;

[0121] The interval between concrete pouring is to pour the next concrete before the initial setting of the previous concrete, so as to ensure that there is no cold joint during construction;

[0122] The flatness and verticality of the formed concrete meet the requirements of the specifications;

[0123] During pouring, rooms or areas with waterproofing requirements should be lower than the floor structure surface elevation according to design requirements.

[0124] Preferably, the specific operations of step S4 are:

[0125] Cover the concrete surface with a layer of plastic film and blanket. When covering, the plastic film and blanket should be laid overlappingly, and the upper and lower layers should be overlapped and staggered accordingly. No concrete should be exposed, so as to ensure the thermal insulation of the concrete by the thermal insulation material.

[0126] In the first three days after concrete pouring, the concrete is in the temperature rising stage, and the internal temperature of the concrete reaches nearly 70°C. After the concrete pouring is completed and it begins to set, and people can basically walk on it without footprints, it is covered with a layer of plastic film for maintenance, and then covered with a blanket.

[0127] After one week, remove part of the plastic film and water the plants for maintenance. The watering time should be arranged during the day when there is sunshine. The watering maintenance time should be no less than 14 days.

[0128] 12 hours after concrete pouring or after final setting, apply a layer of plastic film with an overlap of more than 100mm between blocks, and then apply two layers of straw bags for thermal insulation maintenance;

[0129] After final setting, uncover the plastic sheet and spray water for curing every 3 to 4 hours;

[0130] The film covering maintenance period is ≥15 days. After the temperature measurement analysis results are available, the technical person in charge shall issue the instruction to remove the thermal insulation maintenance. No other person shall issue the instruction to remove the thermal insulation maintenance without authorization.

[0131] From the 4th day onwards, the cover can be partially uncovered to lay out the lines, and the lines can be covered immediately after being drawn. After reinforcing bars are tied, the shear walls and concealed columns can be partially exposed to close the formwork, and the rest of the parts should still be covered until the insulation instruction is released;

[0132] Atmospheric temperature is measured with a mercury thermometer at about 1m above the natural surface. In an open environment, the microclimate temperature is measured at a height of 1m on the foundation plate.

[0133] The temperature of concrete entering the mold should be measured every 2 hours by inserting a mercury thermometer directly into the newly poured concrete cap to read the temperature directly;

[0134] After the initial setting of concrete, before the thermal insulation and curing is removed, the temperature is measured above the cap and below the membrane cover;

[0135] A dedicated person should listen to the weather forecast for the area. During the insulation maintenance period, if the temperature drops sharply below 8°C, it must be reported to the technical person in charge, and maintenance measures such as adding insulation materials must be taken.

[0136] Raw material requirements

[0137] Project technical requirements

[0138] The cement used in preparing commercial pumpable concrete should comply with the current national standards for "Portland Cement, Ordinary Portland Cement", "Slag Portland Cement, Pozzolana Portland Cement, and Fly Ash Portland Cement".

[0139] Coarse aggregate: The ratio of the maximum particle size of coarse aggregate to the diameter of the conveying pipe.

[0140] Pumping height: 50m or less 50~100m or more 100m or more

[0141] The ratio should not be greater than 1:3, preferably 1:3 to 1:4, and between 1:4 and 1:

[0142] Coarse aggregate should be continuously graded, and the content of needle-like particles should not be greater than 10%.

[0143] Fine aggregate should be medium sand with a fineness modulus of 2.5 to 3.2; the sand passing through a 0.315mm sieve hole should be no less than 15%; and it should have good grading.

[0144] The water used to prepare pumped concrete should comply with the provisions of the current national standard "Standard for Water for Concrete Mixing".

[0145] The quality of fly ash as an admixture should comply with the relevant provisions of the current national standards "Fly ash used in cement and concrete", "Technical regulations for the application of fly ash in concrete and mortar" and "Ready-mixed concrete".

[0146] Mix design

[0147] The mixing station shall design the concrete mix ratio according to the concrete technical parameters and conduct trial mix. The final mix ratio shall be delivered to the site for thermal engineering review by the technical person in charge of the site management department. Mix ratio requirements.

[0148] Project technical requirements

[0149] Mix proportion design of pumped concrete should comply with the relevant provisions of the current national standards "Ordinary Concrete Mix Design Code" (JGJ55), "Concrete Structure Engineering Construction Quality Acceptance Code" (GB50204), "Concrete Strength Test and Evaluation Standard" (GB / T50107) and "Ready-mixed Concrete".

[0150] The slump of pumped concrete shall be selected in accordance with the provisions of the current national standard "Code for Acceptance of Construction Quality of Concrete Structure Engineering" (GB50204).

[0151] Slump selection value

[0152] Pumping height (m) 30 or less 30-60 60-100 100 or more

[0153] Slump(mm)100~140140~160160~180180~200

[0154] Project technical requirements

[0155] A commercial concrete mixing station shall be selected for trial pairing and required to submit the preliminary mix proportion and mix proportion design information of all concrete for this project to the owner and on-site supervisor.

[0156] According to the preliminary mix ratio, test blocks are made according to each concrete strength grade, and pressure tests are carried out after standard curing for 28 days. The mix ratio of the concrete strength grade is adjusted according to the pressure test results.

[0157] If the mix ratio needs to be provided as early as possible during construction, more test blocks can be made for rapid inspection or pressure testing at an earlier age to ensure that the test blocks with the mix ratio reach the trial strength of concrete.

[0158] The mix design should comply with the relevant provisions of the current national standards "Code for Design of Ordinary Concrete Mix" (JGJ55), "Code for Acceptance of Construction Quality of Concrete Structure Engineering" (GB50204), "Concrete Strength Test and Evaluation Standard" (GB / T50107) and "Ready-mixed Concrete".

[0159] Specific requirements

[0160] The ratio of the maximum particle size of the crushed stone to the inner diameter of the conveying pipe should be less than or equal to 1:5

[0161] The minimum cement dosage is 300kg / m 3

[0162] The slump of concrete is 80~180mm

[0163] It is advisable to add appropriate amount of admixture

[0164] Technical parameters of concrete

[0165] Project Technical Parameters

[0166] The binder uses cement with a strength grade of 42.5

[0167] The coarse aggregate is crushed stone with a particle size of 5 to 25 mm, and the mud content is controlled to be ≤ 1%.

[0168] Coarse sand in fine aggregate, with a coarseness ratio of 2.4 to 2.8, and mud content controlled to ≤ 3%

[0169] The quality of the external admixture, grade II ground ash, must meet the relevant testing standards

[0170] Admixture uses high-efficiency water reducer as plasticizer to improve pumping effect

[0171] Use retarder to reduce production and transportation pressure. The retarding effect is 3-4h, and the initial setting time is ≥6h

[0172] The slump is controlled at 120mm+20mm

[0173] Sampling is carried out on site according to the specifications as the basis for concrete strength testing. The mixing station should implement technical monitoring of on-site sampling as necessary. The concrete strength must meet the requirements of "mathematical statistics". Concrete specimens under the same curing conditions should be made according to the specifications.

[0174] Through construction organization deployment, construction preparation, construction and quality inspection of results, the process is made more rational and detailed. It can save more time for construction tasks while meeting high quality requirements. More optimized construction and maintenance methods are adopted, so that the two complement each other and achieve the effect of one plus one greater than two. Scientifically overlap the construction process to fully achieve the goals of quality, safety, progress and civilized construction.

[0175] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A concrete pouring construction and maintenance method for building construction, characterized in that: The following steps are included: S1, preparation work before pouring construction; S2, concrete pouring construction; S3, quality inspection; S4, concrete curing.

2. A building construction concrete pouring construction and maintenance method according to claim 1, characterized in that: The specific operations of step S1 are: S11, according to the construction drawings and the initial concrete mix ratio, the concrete supplier and the site will test the concrete separately, adjust the concrete mix ratio, determine the technical procedures and management principles for the production, transportation and pouring of concrete, formulate corresponding anti-cracking technical measures, and pour the concrete continuously in one go without leaving construction joints or cold joints; S12, concrete is produced, transported and pumped by professional mixing plants. Professional manufacturers should have technical responsibility capabilities, which is an important part of concrete quality management. The concrete supplier prepares a construction control plan for all procedures from mixing concrete at the mixing plant to transportation to the site and submits it to the construction unit; S13, set up an on-site QC team, led by the project chief engineer, to carry out quality control such as concrete crack prevention.

3. A building construction concrete pouring construction and maintenance method according to claim 1, characterized in that: The specific steps of step S2 are: S21, bottom slab pouring construction; S22, wall panel pouring construction.

4. A building construction concrete pouring construction and maintenance method according to claim 3, characterized in that: The specific operations of step S21 are: According to the actual situation that a slope is naturally formed when concrete is pumped, two vibrators are arranged in front and behind each pouring zone; The first one is arranged at the concrete unloading point, mainly to solve the problem of compaction of upper concrete; The second pass is arranged at the foot of the concrete slope to ensure the compaction of the lower concrete; The material should be discharged continuously and evenly, the material discharge in the elevator pit should be symmetrical, and the material discharge joint should be controlled within 3 hours; The vibrating rod should be operated in a "fast insertion and slow withdrawal" way. During the vibration, the vibrating rod should be slightly twitched up and down to make the vibration even. The vibration time for each point is generally 20 to 30 seconds. At the same time, the concrete surface is horizontal and no longer sinks significantly, no bubbles appear, and mortar appears on the surface. Control the vibration time of the side formwork, and do not directly impact the side formwork when unloading materials; During pouring, the poured concrete should be vibrated repeatedly every half an hour during the initial setting time. At the same time, the thick cement mortar on the surface of the poured concrete should be scraped in time according to the design elevation, and smoothed and compacted with a wooden trowel before initial setting. Pay attention to controlling the interval time of concrete pouring. The next pouring of concrete should be completed before the initial setting of the previous concrete, generally not more than 2 hours; When the foot of the large concrete slope approaches the top formwork, change the direction of concrete pouring, that is, pour from the top back to form a sump where it intersects with the original slope. In addition, consciously strengthen the concrete pouring at the formwork on both sides to gradually reduce the sump into a small pool. Use a flexible shaft pump to drain it in time. This method is used to remove all seepage water in the final stage. All water-stop formwork exterior walls must be vibrated and compacted twice with an interval of 1 to 2 hours.

5. A building construction concrete pouring construction and maintenance method according to claim 3, characterized in that: The specific steps of step S22 are: S221, preparation for wall panel pouring; S222, wall panel casting, S223, wall panel leveling.

6. A building construction concrete pouring construction and maintenance method according to claim 5, characterized in that: The specific operations of step S221 are: Check whether the template is installed in place, and whether the flatness, verticality and elevation meet the requirements; Whether the steel bars meet the design and specification requirements, and whether the steel bar spacing, the thickness of the retained protective layer, and the position of the concrete pad are accurate; Check whether the post-casting strip forming formwork, water stop sheet, foundation slab and exterior wall water stop strip have been installed; Use fixed pump; All engineering data must be completed before concrete pouring.

7. A building construction concrete pouring construction and maintenance method according to claim 5, characterized in that: The specific operations of step S222 are: The grouting strip is used as the dividing line later; Strictly control the concrete production and transportation process; When pouring, corresponding measures can be formulated according to the actual situation; Casting is done in sections and layers continuously; Before pouring, wet the formwork first, and fill the bottom of the vertical structure wall panel with 50-100mm thick cement mortar with the same mortar mix as the concrete; Segregation shall not occur during pouring. The pouring height shall exceed 2m and pouring shall be carried out in conjunction with a string tube. The pouring sequence is to pour the exterior wall panels first, with a pouring thickness of 200-300mm, along the four sides of the wall, and then pour from the starting point, in this cycle; When concrete is poured into the mold, it must be vibrated with a vibrating rod, and the next concrete pouring should be before the previous concrete begins to set, and the vibrating rod must vibrate it densely.

8. A building construction concrete pouring construction and maintenance method according to claim 5, characterized in that: The specific operations of step S223 are: When pouring floor slab concrete, vibrate and level it manually. Use a line or a 2m ruler to level it. The floor concrete needs to be compacted twice before initial setting, and finally roughened with a wooden trowel. The flatness of the floor surface is checked with a 2m ruler and controlled within a 5mm error range.

9. A building construction concrete pouring construction and maintenance method according to claim 1, characterized in that: The specific operations of step S3 are: Special personnel should be assigned to guard the formwork and steel bars, check whether the formwork and steel bars are deformed at any time, and restore or reinforce them in time; The concrete should be vibrated densely, and the action range of the vibrating rod should be controlled within 1.5 times its action radius; The vibrating rod should follow the concrete feeding, and the formwork and steel bars should not be vibrated all the time when the vibrating rod vibrates; The interval between concrete pouring is to pour the next concrete before the initial setting of the previous concrete, so as to ensure that there is no cold joint during construction; The flatness and verticality of the formed concrete meet the requirements of the specifications; During pouring, rooms or areas with waterproofing requirements should be lower than the floor structure surface elevation according to design requirements.

10. A building construction concrete pouring construction and maintenance method according to claim 1, characterized in that: The specific operations of step S4 are: Cover the concrete surface with a layer of plastic film and blanket. When covering, the plastic film and blanket should be laid overlappingly, and the upper and lower layers should be overlapped and staggered accordingly. No concrete should be exposed, so as to ensure the thermal insulation of the concrete by the thermal insulation material. In the first three days after concrete pouring, the concrete is in the temperature rising stage, and the internal temperature of the concrete reaches nearly 70°C. After the concrete pouring is completed and it begins to set, and people can basically walk on it without footprints, it is covered with a layer of plastic film for maintenance, and then covered with a blanket. After one week, remove part of the plastic film and water the plants for maintenance. The watering time should be arranged during the day when there is sunshine. The watering maintenance time should be no less than 14 days. 12 hours after concrete pouring or after final setting, apply a layer of plastic film with an overlap of more than 100mm between blocks, and then apply two layers of straw bags for thermal insulation maintenance; After final setting, uncover the plastic sheet and spray water for curing every 3 to 4 hours; The film covering maintenance period is ≥15 days. After the temperature measurement analysis results are available, the technical person in charge shall issue the instruction to remove the thermal insulation maintenance. No other person shall issue the instruction to remove the thermal insulation maintenance without authorization. From the 4th day onwards, the cover can be partially uncovered to lay out the lines, and the lines can be covered immediately after being drawn. After reinforcing bars are tied, the shear walls and concealed columns can be partially exposed to close the formwork, and the rest of the parts should still be covered until the insulation instruction is released; Atmospheric temperature is measured with a mercury thermometer at about 1m above the natural surface. In an open environment, the microclimate temperature is measured at a height of 1m on the foundation plate. The temperature of concrete entering the mold should be measured every 2 hours by inserting a mercury thermometer directly into the newly poured concrete cap to read the temperature directly; After the initial setting of concrete, before the thermal insulation and curing is removed, the temperature is measured above the cap and below the membrane cover; A dedicated person should listen to the weather forecast for the area. During the insulation maintenance period, if the temperature drops sharply below 8°C, it must be reported to the technical person in charge, and maintenance measures such as adding insulation materials must be taken.

Citation Information

Patent Citations

  • Large-volume concrete beneficial for controlling temperature and shrinkage crack and construction process thereof

    CN103073240A

  • Concrete structure basement anti-crack and anti-seepage construction method

    CN108049494A

  • Concrete cast-in-place process for building construction

    CN117627153A

  • Bracking-resistant method for high-strength concrete

    CN1319485A

  • Large-size concrete thermal insulation maintenance structure

    CN202895448U