Pipe jacking construction method based on pipe joint slab staggering control
By setting up testing points in the pipe top construction and using compression and soil cutting treatment technologies, the problem of pipe segmentation caused by silted clay is solved, the construction quality and safety are improved, and the construction is carried out smoothly.
Patent Information
- Application Number
- CN202411069897.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-06
- Publication Date
- 2024-11-19
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the construction of pipe elevation, since the geology of the elevation area is silty clay, the natural settlement displacement of the pipe joints is too large and not fixed, resulting in a mismatch between the pipe joints, affecting the construction quality and safety.
By setting up a detection point to locate the wrong platform area, confirm that the soil under the senior management section is compressed and cut soil until the wrong platform is eliminated, and soil adjustment is used for jacks, drilling machines and electric drills.
Effectively correct the staggering phenomenon between pipes and sections, improve construction quality and safety, and ensure the smooth progress of subsequent construction.
Smart Images

Figure CN118979744A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pipe jacking operations, and in particular to a pipe jacking construction method based on pipe segment misalignment control. Background Art
[0002] With the acceleration of urbanization, underground pipeline construction has become an important part of urban infrastructure. Traditional excavation construction methods not only damage the environment, but also affect urban traffic. Therefore, trenchless construction methods, especially pipe jacking construction methods, have been widely used because of their advantages of no excavation or less excavation, no impact on traffic, and short construction period.
[0003] However, during the pipe jacking construction process, the problem of pipe segment misalignment has always been a key factor affecting construction quality and safety. Since the geology of the jacking area is silty clay, the natural settlement displacement of the pipe segment during the jacking process is too large, and the pipe segments are not fixed with channel steel during the jacking process, resulting in misalignment between the pipe segments, affecting subsequent construction. Therefore, a pipe jacking construction method based on pipe segment misalignment control is proposed, which is of great significance for improving construction quality and safety. Summary of the invention
[0004] The purpose of the present invention is to provide a pipe jacking construction method based on pipe segment misalignment control, aiming to solve the technical problems in the prior art that due to the geology of the jacking area being silty clay, the natural settlement displacement of the pipe segments is too large during the jacking process, and the pipe segments are not fixed with channel steel during the jacking process, resulting in misalignment between the pipe segments, which affects subsequent construction.
[0005] To achieve the above object, the present invention adopts a pipe jacking construction method based on pipe segment misalignment control, comprising the following steps:
[0006] Set up inspection points to locate the pipe joint areas where misalignment occurs;
[0007] Identify the high pipe section and the low pipe section in the two misaligned pipe sections, compress the soil below the high pipe section, and reduce the height of the high pipe section;
[0008] Determine whether there is misalignment between the two pipe sections after the soil is reduced, reconfirm the high pipe section and the low pipe section, cut the soil below the high pipe section, and reduce the height of the high pipe section;
[0009] Repeat the judgment of the error situation until the error situation is eliminated.
[0010] Among them, in the step of confirming the high pipe joint and the low pipe joint in the two misaligned pipe joints, compressing the soil below the high pipe joint to reduce the height of the high pipe joint:
[0011] A jack is set up between the high pipe section and the low pipe section, and the soil below the high pipe section is compressed by the jack.
[0012] Among them, in the step of judging whether there is misalignment between the two pipe sections after the soil is reduced, reconfirming the high pipe section and the low pipe section, cutting the soil below the high pipe section, and reducing the height of the high pipe section:
[0013] Drilling holes in the pipe wall of the high pipe joint using a drilling machine;
[0014] Weld transverse steel bars on the electric drill to cut the soil;
[0015] The bottom silt after soil cutting is washed away to narrow the gap.
[0016] Wherein, in the step of drilling holes in the pipe wall of the high pipe joint using a drilling machine:
[0017] The drilling spacing is 1.5m.
[0018] Among them, in the steps of setting up detection points and locating the misaligned pipe section area:
[0019] Divide the pipe jacking construction area into multiple sub-areas, each of which has multiple detection points;
[0020] Set up testing equipment at the testing point; the testing equipment includes total station, laser scanner, and level;
[0021] The detection data transmitted by the detection device is input to determine whether the sub-area is a misaligned pipe section area.
[0022] Before determining whether the sub-region is a misaligned pipe joint region:
[0023] Preset the error data and compare the detected data with the preset data.
[0024] Wherein, in the step of determining whether the sub-region is a staggered pipe joint region:
[0025] When the detected data matches the preset data, it is determined that the sub-region is a misaligned pipe section region;
[0026] When the detected data does not match the preset data, it is determined that the sub-region is not a misaligned pipe section region.
[0027] Wherein, after the step of inputting the detection data transmitted by the detection device and determining whether the sub-area is a misaligned pipe joint area:
[0028] Establishing a first threshold and a second threshold, wherein the first threshold is less than the second threshold;
[0029] Counting the number of the sub-areas of the misaligned pipe joint area to obtain a statistical value;
[0030] The statistical value, the first threshold value, and the second threshold value are compared to determine the degree of misalignment in the pipe jacking construction area.
[0031] Among them, in the step of comparing the statistical value, the first threshold value, and the second threshold value to determine the degree of misalignment in the pipe jacking construction area:
[0032] When the statistical value is less than or equal to the first threshold, it is judged that the misalignment degree of the pipe jacking construction area is low;
[0033] When the statistical value is between the first threshold and the second threshold, it is judged that the misalignment degree of the pipe jacking construction area is medium;
[0034] When the statistical value is greater than the second threshold, it is determined that the misalignment degree in the pipe jacking construction area is high.
[0035] The present invention provides a pipe jacking construction method based on pipe joint misalignment control, which locates the pipe joint area where misalignment occurs by setting up detection points; confirms the high pipe joint and the low pipe joint of the two misaligned pipe joints, compresses the soil below the high pipe joint, and reduces the height of the high pipe joint; judges whether there is misalignment between the two pipe joints after the soil is reduced, reconfirms the high pipe joint and the low pipe joint, cuts the soil below the high pipe joint, and reduces the height of the high pipe joint; repeatedly judges the misalignment until the misalignment is eliminated; and achieves the correction of the misalignment between the pipe joints, thereby improving the quality and safety of subsequent construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0037] Figure 1 It is a schematic diagram of the steps of the pipe jacking construction method based on pipe segment misalignment control of the present invention.
[0038] Figure 2 It is a flow chart of the steps of the pipe jacking construction method based on pipe segment misalignment control of the present invention.
[0039] Figure 3 It is a schematic diagram of the steps of judging the misalignment degree of the pipe jacking construction area of the present invention.
[0040] Figure 4 It is a flow chart of the steps of locating the misaligned pipe joint area of the present invention.
[0041] Figure 5 It is a flow chart of the steps of judging the misalignment degree of the pipe jacking construction area of the present invention. DETAILED DESCRIPTION
[0042] See also Figure 1 to Figure 5 The present invention provides a pipe jacking construction method based on pipe segment misalignment control, comprising the following steps:
[0043] S100: Set up inspection points to locate misaligned pipe joint areas;
[0044] S200: confirming the high pipe joint and the low pipe joint in the two misaligned pipe joints, compressing the soil below the high pipe joint, and reducing the height of the high pipe joint;
[0045] S300: determining whether there is a misalignment between the two pipe sections after the soil is reduced, reconfirming the high pipe section and the low pipe section, cutting the soil below the high pipe section, and reducing the height of the high pipe section;
[0046] S400: Repeatedly determine the platform error situation until the platform error situation is eliminated.
[0047] In this embodiment, firstly, a detection point is set up to locate the misaligned pipe section area. Then, the high pipe section and the low pipe section of the two misaligned pipe sections are confirmed, and the soil below the high pipe section is compressed to reduce the height of the high pipe section; the specific process is: a jack is set up between the high pipe section and the low pipe section, and the soil below the high pipe section is compressed by the jack. Then, it is determined whether there is a misalignment between the two pipe sections after the soil is reduced, and the high pipe section and the low pipe section are reconfirmed, and the soil below the high pipe section is cut to reduce the height of the high pipe section; the specific process is: a drilling machine with a drilling diameter of 10 cm is used to drill holes in the pipe wall of the high pipe section, and the drilling spacing is 1.5m; transverse steel bars are welded on the electric drill to cut the soil, and chains can be added to the transverse steel bars to expand the cutting range; the bottom silt after cutting the soil is washed to reduce the misalignment. Then the misalignment is judged repeatedly until the misalignment is eliminated.
[0048] Among them, detection points are set up to locate the misaligned pipe joint area; the high pipe joint and the low pipe joint of the two misaligned pipe joints are confirmed, and the soil below the high pipe joint is compressed to reduce the height of the high pipe joint; it is determined whether there is a misalignment between the two pipe joints after the soil is reduced, and the high pipe joint and the low pipe joint are reconfirmed, and the soil below the high pipe joint is cut to reduce the height of the high pipe joint; the misalignment is repeatedly determined until the misalignment is eliminated; the misalignment between the corrected pipe joints is achieved, thereby improving the quality and safety of subsequent construction.
[0049] Further, in the step of setting up detection points and locating the misaligned pipe joint area;
[0050] S111: Divide the pipe jacking construction area into a plurality of sub-areas, each of which has a plurality of detection points;
[0051] S112: Setting up testing equipment at the testing point; wherein the testing equipment includes a total station, a laser scanner, and a level;
[0052] S113: input the detection data transmitted by the detection equipment, preset misalignment data, compare the detection data with the preset data, and determine whether the sub-area is a misaligned pipe section area.
[0053] In this embodiment, the pipe jacking construction area is first divided into multiple sub-areas, and each sub-area is provided with multiple detection points. Then, detection equipment is set up at the detection points; wherein the detection equipment includes a total station, a laser scanner, and a level. Then, the detection data transmitted by the detection equipment is input, the preset misalignment data is preset, and the detection data is compared with the preset data to determine whether the sub-area is a misaligned pipe section area. The judgment results are as follows: 1. When the detection data matches the preset data, it is determined that the sub-area is a misaligned pipe section area; 2. When the detection data does not match the preset data, it is determined that the sub-area is not a misaligned pipe section area.
[0054] It is assumed that the pipe jacking construction area is divided into n sub-areas, and each sub-area is provided with multiple detection points. Then detection equipment is set up at the detection point; wherein the detection equipment includes a total station, a laser scanner, and a level. Then the detection data transmitted by the detection equipment is input, and the preset misalignment data is preset as the horizontal angle between the two misaligned pipe sections is β, where β≠0. The detection data is compared with the preset data to determine whether the sub-area is a misaligned pipe section area. The judgment results are as follows: 1. When the detection data matches the preset data, it means that there is a horizontal angle between the two misaligned pipe sections, and the sub-area is judged to be a misaligned pipe section area; 2. When the detection data does not match the preset data, it means that the horizontal angle between the two misaligned pipe sections is 0, and the sub-area is judged not to be a misaligned pipe section area.
[0055] Further, after the step of inputting the detection data transmitted by the detection device to determine whether the sub-area is a misaligned pipe joint area:
[0056] S121: establishing a first threshold and a second threshold, wherein the first threshold is smaller than the second threshold;
[0057] S122: Counting the number of the sub-areas of the staggered pipe joint area to obtain a statistical value;
[0058] S123: Compare the statistical value, the first threshold value, and the second threshold value to determine the degree of misalignment in the pipe jacking construction area.
[0059] In this embodiment, firstly, a first threshold and a second threshold are set, wherein the first threshold is less than the second threshold. Then, the number of the sub-areas of the misaligned pipe section area is counted to obtain a statistical value. Then, the statistical value, the first threshold, and the second threshold are compared to determine the degree of misalignment of the pipe jacking construction area; the judgment result is: 1. When the statistical value is less than or equal to the first threshold, the degree of misalignment of the pipe jacking construction area is judged to be low; 2. When the statistical value is between the first threshold and the second threshold, the degree of misalignment of the pipe jacking construction area is judged to be medium; 3. When the statistical value is greater than the second threshold, the degree of misalignment of the pipe jacking construction area is judged to be high.
[0060] It is assumed that the pipe jacking construction area is divided into n sub-areas, the first threshold is set to 2, and the second threshold is set to 5. Then the number of the sub-areas of the misaligned pipe section area is counted to obtain the statistical value. Then the statistical value, the first threshold, and the second threshold are compared to determine the degree of misalignment in the pipe jacking construction area; the judgment results are: 1. When the statistical value is 3 or 4, the misalignment degree of the pipe jacking construction area is judged to be low; 2. When the statistical value is 5 or above, the misalignment degree of the pipe jacking construction area is judged to be medium; 3. When the statistical value is 0 to 2, the misalignment degree of the pipe jacking construction area is judged to be high; the construction volume of construction workers can be planned according to the degree of misalignment.
[0061] What is disclosed above is only a preferred embodiment of the present invention, and it certainly cannot be used to limit the scope of rights of the present invention. Ordinary technicians in this field can understand that all or part of the processes of the above embodiment and equivalent changes made according to the claims of the present invention still fall within the scope of the invention.
Claims
1. A pipe jacking construction method based on pipe segment misalignment control, characterized in that: The steps include: Set up inspection points to locate the pipe joint areas where misalignment occurs; Identify the high pipe section and the low pipe section in the two misaligned pipe sections, compress the soil below the high pipe section, and reduce the height of the high pipe section; Determine whether there is misalignment between the two pipe sections after the soil is reduced, reconfirm the high pipe section and the low pipe section, cut the soil below the high pipe section, and reduce the height of the high pipe section; Repeat the judgment of the error situation until the error situation is eliminated.
2. The pipe jacking construction method based on pipe segment misalignment control according to claim 1, characterized in that: In the step of confirming the high pipe section and the low pipe section of the two misaligned pipe sections, compressing the soil below the high pipe section to reduce the height of the high pipe section: A jack is set up between the high pipe section and the low pipe section, and the soil below the high pipe section is compressed by the jack.
3. The pipe jacking construction method based on pipe segment misalignment control according to claim 1, characterized in that: In the step of judging whether there is misalignment between the two pipe sections after the soil is reduced, reconfirming the high pipe section and the low pipe section, cutting the soil below the high pipe section, and reducing the height of the high pipe section: Drilling holes in the pipe wall of the high pipe joint using a drilling machine; Weld transverse steel bars on the electric drill to cut the soil; The bottom silt after soil cutting is washed away to narrow the gap.
4. The pipe jacking construction method based on pipe segment misalignment control according to claim 3 is characterized in that: In the step of drilling holes in the pipe wall of the high pipe joint using a drilling machine: The drilling spacing is 1.5m.
5. The pipe jacking construction method based on pipe segment misalignment control according to claim 1, characterized in that: In the steps of setting up inspection points and locating misaligned pipe joint areas: Divide the pipe jacking construction area into multiple sub-areas, each of which has multiple detection points; Setting up testing equipment at the testing points; The testing equipment includes total station, laser scanner and level; The detection data transmitted by the detection device is input to determine whether the sub-area is a misaligned pipe section area.
6. The pipe jacking construction method based on pipe segment misalignment control according to claim 5, characterized in that: Before the step of determining whether the sub-region is a misaligned pipe joint region: Preset the error data and compare the detected data with the preset data.
7. The pipe jacking construction method based on pipe segment misalignment control according to claim 6, characterized in that: In the step of determining whether the sub-region is a staggered pipe section region: When the detected data matches the preset data, it is determined that the sub-region is a misaligned pipe section region; When the detected data does not match the preset data, it is determined that the sub-region is not a misaligned pipe section region.
8. The pipe jacking construction method based on pipe segment misalignment control according to claim 5, characterized in that: After inputting the detection data transmitted by the detection device and determining whether the sub-area is a misaligned pipe section area: Establishing a first threshold and a second threshold, wherein the first threshold is less than the second threshold; Counting the number of the sub-areas of the misaligned pipe joint area to obtain a statistical value; The statistical value, the first threshold value, and the second threshold value are compared to determine the degree of misalignment in the pipe jacking construction area.
9. The pipe jacking construction method based on pipe segment misalignment control according to claim 8, characterized in that: In the step of comparing the statistical value, the first threshold value, and the second threshold value to determine the degree of misalignment in the pipe jacking construction area: When the statistical value is less than or equal to the first threshold, it is judged that the misalignment degree of the pipe jacking construction area is low; When the statistical value is between the first threshold and the second threshold, it is judged that the misalignment degree of the pipe jacking construction area is medium; When the statistical value is greater than the second threshold, it is determined that the misalignment degree in the pipe jacking construction area is high.