Construction method for rapidly constructing giant large-span cave depot tunnel with few people

By using large TBM equipment and prestressed anchor structures in the construction of super-large span tunnels, the problems of slow construction progress and high safety risks in the existing technology are solved, and efficient and safe tunnel excavation and support are achieved.

CN118979746APending Publication Date: 2024-11-19CHINA RAILWAY LIUYUAN GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411084617.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

The existing construction methods of ultra-large span tunnels have problems such as many cross-sections of guide pits, many cross-sections of processes, slow construction progress, large deformation of surrounding rocks during temporary support removal, and high safety risks.

Method used

Large TBM equipment is used to build the tunnel, and a giant large-span tunnel library prestressed anchor structure is applied in the tunnel, and large mechanical equipment is used for excavation and support, forming a top stressed support system to reduce construction personnel and risks.

Benefits of technology

It improves construction efficiency and safety, reduces construction risks and rock mass disturbances, enhances rock mass load-bearing capacity, and simplifies the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979746A_ABST
    Figure CN118979746A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for quickly constructing a huge large-span cave depot tunnel with few people, and relates to the technical field of huge large-span cave depot tunnel construction, which comprises the following steps: step 1, determining the size and spacing of a large TBM tunnel according to the size of a huge large-span cave depot; secondly, a first large TBM tunnel is built through TBM equipment; thirdly, a giant large-span cave depot prestress anchor pulling structure is constructed in the large TBM tunnel; 4, under the giant large-span cave depot prestress anchor pulling structure system, large-scale mechanical equipment is adopted for construction, and the giant large-span cave depot is formed. Large-scale TBM construction is adopted for the top of the cave depot, large-scale mechanical equipment construction is adopted for the lower portion of the cave depot, the number of constructors is greatly reduced, the mechanical construction level is improved, and the construction cost is reduced. The construction risk of the giant large-span cave depot is greatly reduced, a CD, CRD or double-side-wall pilot tunnel method does not need to be adopted, construction from a large section to a small section is not needed either, and the construction efficiency is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of engineering equipment installation, and in particular to a construction method for quickly constructing a giant large-span cavern tunnel by a small number of people. Background Art

[0002] With the rapid development of the national economy and the gradual increase in transportation volume, the number of ultra-large span tunnel projects in the construction and expansion of railways and highways is increasing. Tunnels with an excavation span greater than 18m are ultra-large span tunnels. Ultra-large span tunnels have the characteristics of flatness, large span, and thin arch. For ultra-large span tunnels, CD method, CRD method, double side wall pilot method and multi-pilot method are mostly used at home and abroad for construction. By setting up multiple pilot pits and multiple horizontal and vertical temporary supports, the large section is divided into multiple small sections for construction.

[0003] For giant-span underground station tunnels with a span greater than 25m, the top hole is usually excavated in advance, excavated in layers, and the core is reserved. According to the principle of basic uniformity in the horizontal and vertical directions, the super-large section tunnel is divided into multiple parts for excavation. First, the top-level middle guide tunnel is excavated; then the parts on both sides are excavated in layers from top to bottom, alternating left and right, and initial support is carried out after each part is excavated; finally, the core soil and invert are excavated step by step in layers to form a closed ring support system.

[0004] The above methods not only have many sections of the guide tunnel, but also cannot be constructed with large-scale machinery, with many overlapping processes and slow construction progress. In addition, there are many temporary supports, and the surrounding rock will deform greatly when the temporary supports are removed, which poses a high safety risk. Among them, the excavation of the lower step or the lower layer of the bottom is generally carried out by lifting blasting in layers. Even if large-scale mechanical drilling and blasting is used, the maximum footage is about 4.5m, and the progress is relatively slow. Summary of the invention

[0005] In view of the above technical problems, the present invention discloses a construction method for quickly building a giant large-span tunnel with a small number of people, comprising the following steps:

[0006] Step 1: Determine the size and spacing of large TBM tunnels based on the size of the giant large-span tunnel;

[0007] Step 2: Use TBM equipment to build the first large TBM tunnel;

[0008] Step 3: construct the remaining large TBM tunnels and construct giant large-span tunnel prestressed anchor structures in the large TBM tunnels;

[0009] Step 4: Under the prestressed anchor structure system of the giant large-span tunnel, large-scale mechanical equipment is used to construct and form the giant large-span tunnel.

[0010] Furthermore, in the step 1, according to the size of the giant large-span tunnel, the size and spacing of the large TBM tunnels are planned along the top edge of the giant large-span tunnel, and the tunnel spacing is determined as 1 times the TBM tunnel diameter.

[0011] Furthermore, in the step three, a giant large-span tunnel prestressed anchor structure is first constructed in a large TBM tunnel, and then giant large-span tunnel prestressed anchor structures are constructed in the remaining large TBM tunnels along the top edge of the giant large-span tunnel, and a giant large-span tunnel top support system is formed.

[0012] Furthermore, the prestressed anchor structure is a steel cable anchoring structure.

[0013] Furthermore, in step 4, firstly, large-scale rock drilling machinery and equipment are used to excavate the rock mass between the large-scale TBM tunnels, and then a giant large-span cavern prestressed anchor structure is added.

[0014] Furthermore, after the prestressed anchor structure of the giant large-span cavern is added and completed, large-scale rock drilling machinery and equipment are used to excavate the remaining giant large-span cavern rock mass.

[0015] The beneficial effects of the present invention compared with the prior art are:

[0016] 1. This method uses a large TBM to construct the top of the tunnel and large mechanical equipment to construct the lower part of the tunnel, which greatly reduces the number of construction personnel and improves the level of mechanized construction.

[0017] 2. This method uses a large-scale TBM to construct the top of the cavern, which can help understand the rock characteristics on the top of the giant large-span cavern in advance, explore the geology ahead of the giant large-span cavern in advance, and greatly reduce the construction risk of the giant large-span cavern.

[0018] 3. This method does not require the use of CD, CRD or double-side wall pilot pit method, nor does it require the construction of a large section into a small section, which greatly improves the construction efficiency.

[0019] 4. Under the action of the prestressed anchor structure force support system of the giant large-span tunnel, this method has a huge excavation space for the lower rock mass, and the construction is extremely convenient, which greatly improves the construction efficiency.

[0020] 5. This method constructs a giant large-span tunnel prestressed anchor structure in a large TBM tunnel, forming a giant large-span tunnel top force support system, which greatly reduces the safety risk of excavation construction of the rock mass below the giant large-span tunnel.

[0021] 6. This method does not require the reservation of core rock columns, which greatly reduces the construction risk caused by the top settlement of giant spans due to the removal of rock columns.

[0022] 7. This method uses mechanized construction, which causes less disturbance to the rock mass around the tunnel, greatly improves the bearing capacity of the rock mass around the tunnel, and reduces the safety risks of giant large-span tunnel operations. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a schematic diagram of the overall process of the present invention.

[0024] Figure 2 It is a schematic diagram of the overall structure of the present invention.

[0025] Figure 3 This is a construction schematic diagram of step 1 of the present invention.

[0026] Figure 4 This is a construction schematic diagram of step 2 of the present invention.

[0027] Figure 5 This is a schematic diagram of the construction of step three of the present invention. Figure 1

[0028] Figure 6 This is a schematic diagram of the construction of step three of the present invention. Figure 2 .

[0029] Figure 7 This is a construction schematic diagram of step 4 of the present invention. DETAILED DESCRIPTION

[0030] Example: Figure 1 , Figure 2 As shown, a method for quickly constructing a giant large-span tunnel with a small number of people includes the following steps:

[0031] like Figure 3 As shown, step 1, determine the size and spacing of large TBM tunnels based on the size of the giant large-span tunnel.

[0032] In step one, according to the size of the giant large-span tunnel, the size and spacing of the large TBM tunnels are planned along the top edge of the giant large-span tunnel, and the tunnel spacing is determined as 1 times the TBM tunnel diameter.

[0033] As a technical optimization solution of the present invention, through large-scale TBM construction, large-scale mechanical equipment is used to construct the lower part of the cavern, which greatly reduces the number of construction personnel, improves the level of mechanized construction, and can advance the understanding of the rock characteristics at the top of the giant large-span cavern, and explore the geology ahead of the giant large-span cavern in advance, greatly reducing the construction risk of the giant large-span cavern.

[0034] like Figure 4 As shown in step 2, the first large-scale TBM tunnel was built using TBM equipment.

[0035] like Figure 5 , Figure 6As shown, in step three, the remaining large TBM tunnels are constructed, and giant large-span tunnel prestressed anchor structures are constructed in the large TBM tunnels.

[0036] In step 3, firstly, a giant large-span tunnel prestressed anchor structure is constructed in a large TBM tunnel, and then the giant large-span tunnel prestressed anchor structure is constructed in the remaining large TBM tunnels along the top edge of the giant large-span tunnel, and a giant large-span tunnel top support system is formed. The prestressed anchor structure is a steel cable anchor structure. The specific construction steps of the steel cable anchor structure are as follows:

[0037] S1. First, drill holes in a large TBM tunnel using drilling equipment;

[0038] S2, inserting the cable structure into the drilled hole in the large TBM tunnel;

[0039] S3. Anchoring agent is poured into the front end of the drilled hole in the large TBM tunnel to make the steel cable structure more stable when combined with the drilled hole;

[0040] S4. Tension the stabilized steel cable structure and lock and anchor the steel cable structure.

[0041] As a technical optimization scheme of the present invention, a giant large-span tunnel prestressed anchor structure is constructed in a large TBM tunnel to form a giant large-span tunnel top force support system, which greatly reduces the safety risk of excavation construction of the lower rock mass of the giant large-span tunnel. In addition, under the action of the giant large-span tunnel prestressed anchor structure force support system, the lower rock mass excavation space is huge, the construction is extremely convenient, and the construction work efficiency is greatly improved.

[0042] like Figure 2 , Figure 7 As shown, step four, under the prestressed anchor structure system of the giant large-span tunnel, large-scale mechanical equipment is used to construct and form the giant large-span tunnel.

[0043] First, large-scale rock drilling machinery and equipment are used to excavate the rock mass between the large TBM tunnels, and then a prestressed anchor structure for a giant large-span tunnel is added. After the prestressed anchor structure for the giant large-span tunnel is added and completed, large-scale rock drilling machinery and equipment are used to excavate the remaining rock mass for the giant large-span tunnel.

[0044] As a technical optimization solution of the present invention, mechanized construction can less disturb the rock mass around the tunnel, greatly improve the bearing capacity of the rock mass around the tunnel, and reduce the safety risks of giant large-span tunnel operations.

[0045] The above are only preferred specific implementation modes of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical solutions and inventive concepts of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A method for quickly building a giant large-span tunnel with a small number of people. It is characterized in that The steps include: Step 1: Determine the size and spacing of large TBM tunnels based on the size of the giant large-span tunnel; Step 2: Use TBM equipment to build the first large TBM tunnel; Step 3: construct the remaining large TBM tunnels and construct giant large-span tunnel prestressed anchor structures in the large TBM tunnels; Step 4: Under the prestressed anchor structure system of the giant large-span tunnel, large-scale mechanical equipment is used to construct and form the giant large-span tunnel.

2. A method for rapidly constructing a giant large-span tunnel with a small number of people as claimed in claim 1, Features: In the step 1, according to the size of the giant large-span tunnel, the size and spacing of the large TBM tunnels are planned along the top edge of the giant large-span tunnel, and the tunnel spacing is determined as 1 times the TBM tunnel diameter.

3. A method for rapidly constructing a giant large-span tunnel with a small number of people as claimed in claim 1, Features: In the step three, firstly, a giant large-span tunnel prestressed anchor structure is constructed in a large TBM tunnel, and then giant large-span tunnel prestressed anchor structures are constructed in the remaining large TBM tunnels along the top edge of the giant large-span tunnel, and a giant large-span tunnel top support system is formed.

4. A method for rapidly constructing a giant large-span tunnel with a small number of people as claimed in claim 3, Features: The prestressed anchor structure is a steel cable anchoring structure.

5. A method for rapidly constructing a giant large-span tunnel with a small number of people as claimed in claim 1, Features: In the step 4, firstly, large-scale rock drilling machinery is used to excavate the rock mass between the large-scale TBM tunnels, and then a giant large-span cavern prestressed anchor structure is added.

6. A method for rapidly constructing a giant large-span tunnel with a small number of people as claimed in claim 5, Features: After adding and completing the prestressed anchor structure of the giant large-span cavern, large-scale rock drilling machinery and equipment are used to excavate the remaining giant large-span cavern rock mass.