Tunnel secondary lining longitudinal pouring integrated construction method

By directly pouring lining side walls and vaults in tunnel construction, the problems of vault holes and resource waste in tunnel construction are solved, construction efficiency and density are improved, and tunnel safety is ensured.

CN118979766APending Publication Date: 2024-11-19CHINA RAILWAY 15TH BUREAU GROUP CORPORATION LIMITED +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411234405.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-04
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

During the secondary lining of the tunnel construction, the casting process of the vault part is prone to form a closed cavity and a void, and the existing technology resources are wasted, increasing construction costs.

Method used

The longitudinal pouring gun is used to directly pour the lining side walls and vaults. The longitudinal pouring trolley and concrete delivery pump system are used to reduce equipment conversion time, improve construction efficiency, and seal and vibration are achieved by tightening rubber rings and tightening belts.

Benefits of technology

It has achieved the reduction of construction equipment conversion time, improved construction efficiency, increased lining density, avoided hollow formation, saved resources, and ensured tunnel safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979766A_ABST
    Figure CN118979766A_ABST
Patent Text Reader

Abstract

The invention discloses a tunnel secondary lining longitudinal pouring integrated construction method. The method comprises the following steps that a lining trolley, a longitudinal pouring trolley and a concrete conveying pump are arranged in a construction tunnel; s2, a concrete conveying pump is controlled to convey concrete grout, the concrete grout is injected into a material distribution mechanism of the lining trolley through a longitudinal pouring gun, and the concrete grout is injected into all feeding windows through the material distribution mechanism; s3, a longitudinal pouring gun enters the top concrete pouring space of the second lining formwork through a plugging box valve on the end plate and moves to the position of the other end; a longitudinal pouring gun is controlled to conduct concrete pouring in situ, and after pouring is full, pause is conducted and vibration is conducted; and then, the longitudinal pouring gun begins to retreat, and supplementary grouting is carried out while longitudinal moving and retreating are carried out so as to prevent disengaging till the sealing box valve is retreated. The method has the advantages that the lining side wall and the vault are directly poured through the longitudinal pouring gun, the conversion time of construction equipment is shortened, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of tunnel construction, and in particular relates to an integrated construction method for longitudinal pouring of a tunnel secondary lining. Background Art

[0002] At present, when constructing the secondary lining of a tunnel, the existing technical means of pouring the vault part mostly use the pouring port to pour upwards, similar to the form of water spraying upwards from a fountain. In actual application, due to the error in the initial support contour of the tunnel and the slope of some tunnels, it is easy to form a closed cavity during the upward gushing of concrete, resulting in the inability to discharge air during the pouring of the vault. In addition, due to the long single pouring time during pouring, the concrete in some areas is easy to initially set, which makes it easy for voids to appear in the pouring of the tunnel top. In addition, two sets of pumping systems are usually used in the existing secondary lining construction, resulting in waste of resources and increased construction costs. There is an urgent need for an integrated pouring method that can effectively solve the voids in the tunnel vault. Summary of the invention

[0003] The purpose of the present invention is to provide an integrated construction method for longitudinal pouring of secondary lining of a tunnel based on the above-mentioned deficiencies of the prior art. The construction method directly pours the lining side walls and the vault through a longitudinal pouring gun, thereby reducing the conversion time of construction equipment and improving construction efficiency.

[0004] The purpose of the present invention is achieved by the following technical solutions: A tunnel secondary lining longitudinal pouring integrated construction method, characterized in that the construction method comprises the following steps: S1: Lining trolley, longitudinal pouring trolley and concrete pump are arranged in sequence along the longitudinal direction in the construction tunnel; The lining trolley comprises a frame, a secondary lining template and a material distribution mechanism. The secondary lining template is fixed on the frame to form a template for the secondary lining of the tunnel. The space between the secondary lining template and the inner wall of the tunnel constitutes a concrete pouring space. A plurality of pressure sensors are arranged at intervals along the longitudinal direction on the arch of the secondary lining template in the concrete pouring space. A plurality of layers of material feeding windows are respectively provided from bottom to top on the side wall surfaces of both sides of the secondary lining template. The material distribution mechanism is mounted on the frame and connected to each of the material feeding windows. A row of hanging mechanisms is provided along the longitudinal direction on the top of the secondary lining template. An end plate is provided on the end face of the secondary lining template to block the concrete pouring space, and a blocking box valve is provided on the end plate. An end head pressure sensor is also provided on the end plate. The longitudinal grouting trolley comprises a moving frame and a longitudinal grouting gun mechanism, and the longitudinal grouting gun mechanism comprises a grouting pipeline and a longitudinal grouting gun; The concrete delivery pump is connected to the longitudinal pouring gun mechanism; S2: The longitudinal pouring gun is mounted on the hanging mechanism at the top of the second lining formwork, the concrete delivery pump is controlled to pump the concrete slurry into the grouting pipeline of the longitudinal pouring trolley, and the concrete slurry is injected into the distribution mechanism of the lining trolley through the longitudinal pouring gun, and the distribution mechanism injects the concrete slurry into each of the feeding windows; the longitudinal pouring trolley is moved longitudinally so that the longitudinal pouring gun can complete the concrete slurry pouring of each of the feeding windows within the range of the lining trolley; S3: Control the longitudinal pouring trolley to retreat so that the longitudinal pouring gun is detached from the hanging mechanism, and then control the longitudinal pouring trolley to move longitudinally so that the longitudinal pouring gun enters the top concrete pouring space of the second lining formwork through the sealing box valve on the end plate, and moves to the other end position; control the longitudinal pouring gun to pour concrete in situ, and when the end pressure sensor and each pressure sensor located on the end plate detect that the pressure reaches the first set threshold, the pouring of concrete slurry is suspended and vibrated; then start to retract the longitudinal pouring gun, and supplement grouting while moving longitudinally backward to prevent the formation of voids; when the longitudinal pouring gun retreats to the last 1m position and the pressure measured by each pressure sensor reaches the second set threshold, control the longitudinal pouring gun to supplement grouting in sequence after retreating 0.3m each time to prevent the formation of voids after the gun is withdrawn; and repeat this process until the sealing box valve is exited.

[0005] The material distribution mechanism includes a main feed hopper, a primary material distribution trough, a primary feed hopper, a secondary material distribution trough, a secondary feed hopper and a tertiary material distribution trough; the main feed hopper is arranged on the top of the frame and located below the hanging mechanism for receiving the concrete injected by the longitudinal pouring gun; one end of the primary material distribution trough is connected to the main feed hopper, and the other end is connected to the upper feed inlet of the primary feed hopper; the discharge port of the primary feed hopper is connected to three groups of the secondary material distribution troughs, two groups of the secondary material distribution troughs respectively extend into the feed window, and the remaining group of the secondary material distribution troughs is connected to the upper feed inlet of the secondary feed hopper; the discharge port of the secondary feed hopper is connected to the tertiary material distribution trough, and the tertiary material distribution trough extends to the feed window located at the bottom.

[0006] The main feed hopper, the primary feed hopper and the secondary feed hopper are distributed from top to bottom in the height direction.

[0007] The sealing box valve is arranged at the arch position of the end plate, and the main body of the sealing box valve is a steel pipe combination, which includes two sections of steel pipe and four connecting steel bars welded between the two sections of steel pipe, a compression rubber ring is arranged on the connecting steel bar, and a tightening belt is sleeved on the outer side of the compression rubber ring, and the tightening belt is tightened or loosened by the tightening box to control whether the compression rubber ring is pressed and fitted on the outer wall surface of the longitudinal perfusion gun; wherein, longitudinal slots are respectively opened on the compression rubber ring corresponding to the positions of the connecting steel bars, and the radial length of the slots is greater than the diameter of the connecting steel bars, and a fixed pulley and a motor shaft driven by a motor are arranged in the tightening box, one end of the tightening belt is fixed on the box body of the tightening box, and the other end of the tightening belt extends into the tightening box and is guided by the fixed pulley and then wound and fixed on the motor shaft, and the tightening or loosening of the compression rubber ring by the tightening belt is controlled by the forward or reverse rotation of the motor shaft.

[0008] A boss is arranged on the outer wall surface of the longitudinal pouring gun. When the longitudinal pouring gun is pushed into the top concrete pouring space to the end position, the boss is supported on the valve of the sealing box to limit the position.

[0009] A transversely inserted baffle is arranged at a position of the sealing box valve close to the end plate.

[0010] In step S3, when the longitudinal pouring gun moves longitudinally to the other end position in the top concrete pouring space, the clamping rubber ring is in a relaxed state and is not pressed against the outer wall surface of the longitudinal pouring gun; when the longitudinal pouring gun pours concrete slurry in the top concrete pouring space, the tightening belt is controlled to be tightened to compress the clamping rubber ring to press against the outer wall surface of the longitudinal pouring gun to form a sealing state and keep the longitudinal pouring gun in a fixed position; when the longitudinal pouring gun retreats while grouting, the tightening belt is controlled to be relaxed so that the clamping rubber ring is pressed against the outer wall surface of the longitudinal pouring gun but does not hinder the retreat movement.

[0011] The advantages of the present invention are: (1) The secondary lining trolley and the longitudinal pouring trolley share a concrete pump, saving construction costs; (2) Use the longitudinal pouring gun to directly pour the lining side walls and vaults, reducing the time for construction equipment conversion and improving construction efficiency; (3) Longitudinal pouring of the arch can increase the density of the secondary lining, and the back of the secondary lining will not be empty, thus ensuring the lining quality and tunnel safety; (4) A plugging box valve is set on the top of the end plate. The sealing of the longitudinal grouting gun during grouting is achieved by controlling the tightening belt and the compression rubber ring. The use of the compression rubber ring can absorb vibration and displacement, thereby avoiding structural wear between the vibration generated by the longitudinal grouting gun during vibration and the plugging box valve. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a schematic diagram of the longitudinal pouring integrated pouring trolley grouting on the side wall surface in the present invention; Figure 2 It is a schematic diagram of the longitudinal grouting integrated grouting trolley of the present invention grouting at the arch top; Figure 3 is a cross-sectional view of a lining trolley in the present invention; Figure 4 It is a schematic diagram of the longitudinal injection gun of the present invention extending into the other end of the vault; Figure 5 It is a schematic diagram of the longitudinal pouring gun of the present invention pouring concrete in the vault; Figure 6 A schematic diagram of completing the pouring in the vault and sealing by the baffle in the present invention; Figure 7 For the present invention Figure 5 AA view in. DETAILED DESCRIPTION

[0013] The features of the present invention and other related features are further described in detail below through embodiments in conjunction with the accompanying drawings to facilitate understanding by those skilled in the art: like Figure 1-7 , the marks in the figure are: lining trolley 1, longitudinal pouring trolley 2, concrete delivery pump 3, longitudinal pouring gun 4, grouting pipeline 5, feeding window 6, frame 7, secondary lining template 8, feeding mechanism 9, main feed hopper 901, primary feeding trough 902, primary feed hopper 903, secondary feeding trough 904, secondary feed hopper 905, tertiary feeding trough 906, plugging box valve 10, end plate 11, end pressure sensor 12, pressure sensor 13, boss 14, clamping rubber ring 15, tightening belt 16, baffle 17, connecting steel bar 18, deformation groove 19, tightening box 20, fixed pulley 21, motor shaft 22.

[0014] Example: Figure 1-7 As shown, this embodiment specifically relates to a tunnel secondary lining longitudinal pouring integrated construction method, the construction method comprising the following steps: S1: a lining trolley 1, a longitudinal pouring trolley 2 and a concrete pump 3 are arranged in sequence along the longitudinal direction in the construction tunnel.

[0015] The lining trolley 1 includes a frame 7, a secondary lining template 8 and a material distribution mechanism 9. The secondary lining template 8 is fixed on the frame 7 to form a template for the secondary lining of the tunnel. The space between the secondary lining template 8 and the inner wall of the tunnel constitutes a concrete pouring space. A plurality of pressure sensors 13 are arranged longitudinally at intervals on the arch of the secondary lining template 8 in the concrete pouring space. A plurality of layers of material feeding windows 6 are respectively provided from bottom to top on the side wall surfaces of both sides of the secondary lining template 8. The material distribution mechanism 9 is also installed on the frame 7 and connected to the material feeding windows 6 of each layer. A row of hanging mechanisms 16 are arranged longitudinally on the top of the secondary lining template 8. The hanging mechanisms 16 can facilitate the longitudinal pouring gun 4 on the longitudinal pouring trolley 2 to be hung thereon and pour concrete slurry into the material distribution mechanism 9. An end plate 15 is provided on the end face of the secondary lining template 8 to block the concrete pouring space, and a blocking box valve 10 and an end pressure sensor 12 are provided at the arch position of the end plate 15.

[0016] The longitudinal pouring trolley 2 includes a moving frame and a longitudinal pouring gun mechanism, which includes a grouting pipeline 5 and a longitudinal pouring gun 4. The longitudinal pouring gun 4 can be mounted on a hanging mechanism 16 based on different grouting positions, or extended into the concrete pouring space through a plugging box valve 10. It should be noted that the longitudinal pouring gun 4 has a relatively long grouting steel pipe, and the length of the longitudinal pouring gun 4 that penetrates into the top concrete pouring space is the grouting steel pipe.

[0017] The concrete delivery pump 3 is connected to the longitudinal grouting gun 4 via the grouting pipeline 5 to pump the concrete slurry.

[0018] S2: The longitudinal pouring gun 4 is mounted on the hanging mechanism 16 on the top of the second lining formwork 8, and the concrete delivery pump 3 is controlled to pump the concrete slurry into the grouting pipeline 5 of the longitudinal pouring trolley 2, and the concrete slurry is injected into the distribution mechanism 9 of the lining trolley through the longitudinal pouring gun 4, and the distribution mechanism 9 injects the concrete slurry into each feeding window 6; the longitudinal pouring trolley 2 is moved longitudinally so that the longitudinal pouring gun 4 completes the concrete slurry pouring of each feeding window 6 within the range of the lining trolley 1.

[0019] like Figure 1-3As shown, the material distribution mechanism 9 includes a main feed hopper 901 , a primary material distribution trough 902 , a primary feed hopper 903 , a secondary material distribution trough 904 , a secondary feed hopper 905 , and a tertiary material distribution trough 906 . Among them, the main feed hopper 901 is arranged at the highest position in the middle of the frame 7 and is located directly below the gun head of the longitudinal perfusion gun 4. The feeding mechanism 9 is symmetrically arranged on both sides with the main feed hopper 901 as the symmetry axis. The main feed hopper 901, the first-level feed hopper 903 and the second-level feed hopper 905 are arranged on the frame 7 from top to bottom. One end of the first-level feeding trough 902 is connected to the main feed hopper 901, and the other end is connected to the upper feeding port of the first-level feed hopper 903; the discharge port of the first-level feed hopper 903 is connected to three groups of second-level feeding troughs 904, of which two groups of second-level feeding troughs 904 extend into the feeding window 6 respectively, and the remaining group of second-level feeding troughs 904 is connected to the upper feeding port of the second-level feed hopper 905; the discharge port of the second-level feed hopper 905 is connected to the third-level feeding trough 906, and the third-level feeding trough 906 extends to the feeding window 6 located at the bottom. After the longitudinal pouring gun 4 pours the concrete slurry into the main feed hopper 901, based on the effect of gravity and the inclined setting state of each distribution trough, the concrete slurry flows into the primary feed hopper 903 through the primary distribution trough 902, and then flows into the two lower feeding windows 6 respectively through the two secondary distribution troughs 904, and the remaining secondary distribution trough 904 transfers the concrete slurry to the secondary feed hopper 905, and then pours the concrete slurry into the lowermost feeding window 6 through the tertiary distribution trough 906, forming a pouring of the middle and lower space of the secondary lining of the tunnel.

[0020] S3: Control the longitudinal pouring trolley 2 to retreat so that the longitudinal pouring gun 4 is disengaged from the hanging mechanism 16, and then a boss 14 is mounted on the outer wall of the steel pipe of the longitudinal pouring gun 4. The boss 14 is annular, and the penetration depth of the longitudinal pouring gun 4 can be limited by the setting of the boss 14 to avoid collision and damage in the top concrete pouring space. Open the baffle 17 on the plugging box valve 10, control the longitudinal pouring trolley 2 to move longitudinally so that the longitudinal pouring gun 4 enters the top concrete pouring space of the second lining formwork 8 through the plugging box valve 10 on the end plate 11, and moves to the other end position of the top concrete pouring space, and stops moving after the boss 14 contacts the plugging box valve 10.

[0021] like Figure 4-7As shown, the plugging box valve 10 is arranged at the arch position of the end plate 11. The main body of the plugging box valve 10 is a steel pipe combination, which includes two sections of steel pipes and four connecting steel bars 18 welded between the two sections of steel pipes. A compression rubber ring 15 is arranged on the connecting steel bar 18. A tightening belt 16 is sleeved on the outer side of the compression rubber ring 15. The tightening belt 16 is tightened or loosened through the tightening box 20 to control whether the compression rubber ring 15 is pressed and fitted on the outer wall surface of the longitudinal injection gun 4. It should be noted that longitudinal slots 19 are respectively opened on the compression rubber ring 15 corresponding to the positions of each connecting steel bar 18. The length of the slot 19 in the radial direction is greater than the diameter of the connecting steel bar 18, so as to facilitate the displacement and deformation of the compression rubber ring 15 when it is compressed; during assembly, the slots 19 on the compression rubber ring 15 are first sleeved on each connecting steel bar 18, and then the ends of the connecting steel bar 18 are welded to the steel pipe. A fixed pulley 21 and a motor shaft 22 driven by a motor are provided in the tightening box 20. One end of the tightening belt 16 is fixed on the box body of the tightening box 20, and the other end of the tightening belt 16 extends into the tightening box 20 and is guided by the fixed pulley 21 and then fixed on the motor shaft 22. The tightening or loosening of the tightening belt 16 on the compression rubber ring 15 is controlled by the forward or reverse rotation of the motor shaft 22.

[0022] The longitudinal pouring gun 4 is controlled to pour concrete in situ, and each pressure sensor 13 and the end sensor 12 are monitored in real time during the pouring process. The pouring progress of the concrete slurry can be known through the changes in the pressure data of each pressure sensor 13 and the end sensor 12, that is, when the pressure data of the pressure sensor 13 increases from 0, it indicates that the concrete slurry has been poured and flowed here. When the end pressure sensor 12 and each pressure sensor 13 located on the end plate 11 all monitor that the pressure reaches the first set threshold, it indicates that the top concrete pouring space has been initially filled with concrete slurry, then the pouring of the concrete slurry is suspended and vibrated. The vibrating method in this embodiment refers to the use of a vibration device to directly vibrate the second lining formwork 8 to make the concrete slurry more dense and remove the empty situation.

[0023] After that, the longitudinal grouting gun 4 starts to be retracted, and supplementary grouting is performed while longitudinally moving back to prevent the longitudinal grouting gun 4 from being withdrawn and causing a gap and void. When the longitudinal grouting gun 4 is retracted to the last 1m position and the pressure measured by each pressure sensor reaches the second set threshold (referring to the pressure required for construction), the longitudinal grouting gun 4 is controlled to be retracted 0.3m each time and supplementary grouting is performed in sequence to prevent voiding after the gun is withdrawn; this is repeated until the longitudinal grouting gun 4 withdraws from the plugging box valve 10, and finally the baffle 17 is inserted into the steel pipe of the plugging box valve 10 to form a plug.

[0024] When the longitudinal pouring gun 4 moves longitudinally to the other end position in the top concrete pouring space, the clamping rubber ring 15 is in a relaxed state and is not pressed against the outer wall surface of the longitudinal pouring gun 4; when the longitudinal pouring gun 4 is pouring concrete slurry in the top concrete pouring space, the tightening belt 16 is controlled to be tightened to compress the clamping rubber ring 15 to press it against the outer wall surface of the longitudinal pouring gun 4 to form a sealing state and keep the longitudinal pouring gun 4 in a fixed position; when the longitudinal pouring gun 4 is retreating while grouting, the tightening belt 16 is controlled to be relaxed so that the clamping rubber ring 15 is pressed against the outer wall surface of the longitudinal pouring gun 4 but does not hinder its retreating movement.

[0025] The beneficial effects of this embodiment are: (1) The secondary lining trolley and the longitudinal pouring trolley share a concrete pump, saving construction costs; (2) Use the longitudinal pouring gun to directly pour the lining side walls and vaults, reducing the time for construction equipment conversion and improving construction efficiency; (3) Longitudinal pouring of the arch can increase the density of the secondary lining, and the back of the secondary lining will not be empty, thus ensuring the lining quality and tunnel safety; (4) A plugging box valve is set on the top of the end plate. The sealing of the longitudinal grouting gun during grouting is achieved by controlling the tightening belt and the compression rubber ring. The use of the compression rubber ring can absorb vibration and displacement, thereby avoiding structural wear between the vibration generated by the longitudinal grouting gun during vibration and the plugging box valve.

Claims

1. A method for integrating longitudinal pouring of secondary tunnel lining. Features The construction method comprises the following steps: S1: Lining trolley, longitudinal pouring trolley and concrete pump are arranged in sequence along the longitudinal direction in the construction tunnel; The lining trolley comprises a frame, a secondary lining template and a material distribution mechanism. The secondary lining template is fixed on the frame to form a template for the secondary lining of the tunnel. The space between the secondary lining template and the inner wall of the tunnel constitutes a concrete pouring space. A plurality of pressure sensors are arranged at intervals along the longitudinal direction on the arch of the secondary lining template in the concrete pouring space. A plurality of layers of material feeding windows are respectively provided from bottom to top on the side wall surfaces of both sides of the secondary lining template. The material distribution mechanism is mounted on the frame and connected to each of the material feeding windows. A row of hanging mechanisms is provided along the longitudinal direction on the top of the secondary lining template. An end plate is provided on the end face of the secondary lining template to block the concrete pouring space, and a blocking box valve is provided on the end plate. An end head pressure sensor is also provided on the end plate. The longitudinal grouting trolley comprises a moving frame and a longitudinal grouting gun mechanism, and the longitudinal grouting gun mechanism comprises a grouting pipeline and a longitudinal grouting gun; The concrete delivery pump is connected to the longitudinal pouring gun mechanism; S2: The longitudinal pouring gun is mounted on the hanging mechanism at the top of the second lining formwork, the concrete delivery pump is controlled to pump the concrete slurry into the grouting pipeline of the longitudinal pouring trolley, and the concrete slurry is injected into the distribution mechanism of the lining trolley through the longitudinal pouring gun, and the distribution mechanism injects the concrete slurry into each of the feeding windows; the longitudinal pouring trolley is moved longitudinally so that the longitudinal pouring gun can complete the concrete slurry pouring of each of the feeding windows within the range of the lining trolley; S3: Control the longitudinal pouring trolley to retreat so that the longitudinal pouring gun is detached from the hanging mechanism, and then control the longitudinal pouring trolley to move longitudinally so that the longitudinal pouring gun enters the top concrete pouring space of the second lining formwork through the sealing box valve on the end plate, and moves to the other end position; control the longitudinal pouring gun to pour concrete in situ, and when the end pressure sensor and each pressure sensor located on the end plate detect that the pressure reaches the first set threshold, the pouring of concrete slurry is suspended and vibrated; then start to retract the longitudinal pouring gun, and supplement grouting while moving longitudinally backward to prevent the formation of voids; when the longitudinal pouring gun retreats to the last 1m position and the pressure measured by each pressure sensor reaches the second set threshold, control the longitudinal pouring gun to supplement grouting in sequence after retreating 0.3m each time to prevent the formation of voids after the gun is withdrawn; and repeat this process until the sealing box valve is exited.

2. A tunnel secondary lining longitudinal pouring integrated construction method according to claim 1, Features The material distribution mechanism includes a main feed hopper, a primary material distribution trough, a primary feed hopper, a secondary material distribution trough, a secondary feed hopper and a tertiary material distribution trough; the main feed hopper is arranged on the top of the frame and located below the hanging mechanism for receiving the concrete injected by the longitudinal pouring gun; one end of the primary material distribution trough is connected to the main feed hopper, and the other end is connected to the upper feed inlet of the primary feed hopper; the discharge port of the primary feed hopper is connected to three groups of the secondary material distribution troughs, two groups of the secondary material distribution troughs respectively extend into the feed window, and the remaining group of the secondary material distribution troughs is connected to the upper feed inlet of the secondary feed hopper; the discharge port of the secondary feed hopper is connected to the tertiary material distribution trough, and the tertiary material distribution trough extends to the feed window located at the bottom.

3. A tunnel secondary lining longitudinal pouring integrated construction method according to claim 2, Features The main feed hopper, the primary feed hopper and the secondary feed hopper are distributed from top to bottom in the height direction.

4. A tunnel secondary lining longitudinal pouring integrated construction method according to claim 1, Features The sealing box valve is arranged at the arch position of the end plate, and the main body of the sealing box valve is a steel pipe combination, which includes two sections of steel pipe and four connecting steel bars welded between the two sections of steel pipe, a compression rubber ring is arranged on the connecting steel bar, and a tightening belt is sleeved on the outer side of the compression rubber ring, and the tightening belt is tightened or loosened by the tightening box to control whether the compression rubber ring is pressed and fitted on the outer wall surface of the longitudinal perfusion gun; wherein, longitudinal slots are respectively opened on the compression rubber ring corresponding to the positions of the connecting steel bars, and the radial length of the slots is greater than the diameter of the connecting steel bars, and a fixed pulley and a motor shaft driven by a motor are arranged in the tightening box, one end of the tightening belt is fixed on the box body of the tightening box, and the other end of the tightening belt extends into the tightening box and is guided by the fixed pulley and then wound and fixed on the motor shaft, and the tightening or loosening of the compression rubber ring by the tightening belt is controlled by the forward or reverse rotation of the motor shaft.

5. A tunnel secondary lining longitudinal pouring integrated construction method according to claim 4, Features A boss is arranged on the outer wall surface of the longitudinal pouring gun. When the longitudinal pouring gun is pushed into the top concrete pouring space to the end position, the boss is supported on the valve of the sealing box to limit the position.

6. A tunnel secondary lining longitudinal pouring integrated construction method according to claim 4, Features A transversely inserted baffle is arranged at a position of the sealing box valve close to the end plate.

7. A tunnel secondary lining longitudinal pouring integrated construction method according to claim 5, Features In step S3, when the longitudinal pouring gun moves longitudinally to the other end position in the top concrete pouring space, the clamping rubber ring is in a relaxed state and is not pressed against the outer wall surface of the longitudinal pouring gun; when the longitudinal pouring gun pours concrete slurry in the top concrete pouring space, the tightening belt is controlled to be tightened to compress the clamping rubber ring to press against the outer wall surface of the longitudinal pouring gun to form a sealing state and keep the longitudinal pouring gun in a fixed position; when the longitudinal pouring gun retreats while grouting, the tightening belt is controlled to be relaxed so that the clamping rubber ring is pressed against the outer wall surface of the longitudinal pouring gun but does not hinder the retreat movement.