Material preparation mechanism and material preparation method
By designing the material preparation mechanism, using the cooperation of the frame, positioning tooling and AGV trolley, the automatic replacement of the loading tray is achieved, solving the cumbersome problems of the replacement process in the existing technology, and improving the replacement efficiency and automation level.
Patent Information
- Application Number
- CN202410607187.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Priority Date
- 2023-05-19
- Filing Date
- 2024-05-15
- Publication Date
- 2024-11-22
AI Technical Summary
When replacing workpieces, the existing circulating feeding device requires manual replacement of the feeding tray set, which leads to cumbersome and inconvenient replacement process.
A material preparation mechanism is designed, including a frame, positioning tooling and AGV trolley. Through the cooperation of the hoisting assembly and the moving assembly, the automatic replacement of the positioning tooling is realized, simplifying the replacement process of the loading tray.
It improves the replacement efficiency and automation of the feeding tray, reduces manual operations, simplifies replacement actions, and improves production efficiency.
Smart Images

Figure CN118992507A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of intelligent manufacturing technology, and in particular to a material preparation mechanism and a material preparation method. Background Art
[0002] In the current circulating feeding device, when a batch of workpieces needs to be replaced with a new batch of workpieces after processing, the feeding tray group in the circulating feeding device needs to be manually removed, and then replaced with a new batch of feeding tray groups. Therefore, how to make the replacement of the feeding tray group of the circulating feeding device more convenient is a problem that needs to be considered. Summary of the invention
[0003] The purpose of the present application is to provide a material preparation mechanism that can be easily replaced, and the material preparation mechanism includes:
[0004] A rack, wherein the rack comprises a rack body and a mounting block, the rack body comprises a transfer port, and the transfer port is communicated with the outside; the mounting block is assembled and fixed to the rack body or the mounting block and the rack body are an integral part, the rack body has a storage area, and the transfer port is an open port corresponding to the storage area;
[0005] A positioning tool, wherein the positioning tool is located in the accommodating area, a transfer area is formed below the positioning tool and the frame, a material preparation area is formed above the positioning tool and the frame, the mounting block faces the accommodating area and protrudes in the width direction relative to the frame, the positioning tool is located above the mounting block in the height direction and the positioning tool is limited to the mounting block, and the positioning tool can move in the height direction under the action of force to separate from the mounting block.
[0006] The above technical solution has the following advantages: the material preparation mechanism has a frame and a positioning tool. The mounting block of the positioning tool and the positioning tool cooperate with each other to limit the positioning tool to the mounting block. The positioning tool can be used to support the loading tray, and the positioning tool can be separated from the mounting block by the upward force. The frame and the lower side of the positioning tool form a transfer area. When replacing the loading tray, you only need to move the positioning tool supporting the loading tray out from the top. Therefore, the present application can facilitate the replacement of the loading tray.
[0007] The object of the present application is also to provide a material preparation mechanism that can be easily replaced, the material preparation mechanism comprising: a frame, the frame comprising a frame body and a mounting block, the frame body comprising a transfer port, the transfer port being connected to the outside; the mounting block is assembled and fixed to the frame body or the mounting block and the frame body are an integral part, the frame body has a storage area, and the transfer port is an open port corresponding to the storage area;
[0008] A positioning tool, the positioning tool is located in the accommodating area, a transfer area is formed below the positioning tool and the frame, a material preparation area is formed above the positioning tool and the frame, the mounting block faces the accommodating area and protrudes in the width direction relative to the frame, the positioning tool is located above the mounting block in the height direction and the positioning tool is limited to the mounting block;
[0009] An AGV trolley comprises a lifting component and a moving component, wherein the lifting component has a first height and a second height, wherein the first height is greater than the second height, wherein the AGV trolley can be located in a transfer area and when the lifting component is at the first height, the lifting component is against the positioning tool, and the mounting block and the positioning tool are separated, and when the lifting component is at the second height, the lifting component is not in contact with the positioning tool, and the positioning tool is limited to the mounting block.
[0010] The above technical solution has the following advantages: the material preparation mechanism has a frame, a positioning tool, and an AGV cart. The mounting block of the positioning tool and the positioning tool cooperate with each other to limit the positioning tool to the mounting block, and the positioning tool can be separated from the mounting block by upward force. A transfer area is formed under the frame and the positioning tool. The AGV cart can enter the transfer area to complete the replacement of the positioning tool, thereby improving the degree of automation.
[0011] The purpose of the present application is also to provide a material preparation method that can be easily replaced, the material preparation method comprising:
[0012] The AGV trolley enters the transfer area, the lifting assembly of the AGV trolley rises to a first height, the lifting assembly abuts against the positioning tool and moves together to the first height, and the moving assembly of the AGV trolley drives the positioning tool to leave to remove the positioning tool;
[0013] The lifting assembly is located at a first height, the positioning fixture is located above the lifting assembly, the moving assembly drives the AGV trolley to move to the transfer area, the lifting assembly is lowered to a second height, and the mounting block is limitedly matched with the positioning fixture to install the positioning fixture, wherein the first height is greater than the second height;
[0014] The AGV cart leaves the transfer area.
[0015] The above technical solution has the following advantages: the AGV trolley can realize the replacement of the positioning tooling by the movement of the lifting assembly at the first height and the second height, and the action of replacing the positioning tooling is simple.
[0016] The object of the present application is also to provide a material preparation mechanism that can be easily replaced, the material preparation mechanism comprising: a frame, the frame comprising a frame body and a mounting block, the frame body comprising a transfer port, the transfer port being connected to the outside; the mounting block is assembled and fixed to the frame body or the mounting block and the frame body are an integral part, the frame body has a storage area, and the transfer port is an open port corresponding to the storage area;
[0017] A positioning tool, the positioning tool is located in the accommodating area, a transfer area is formed below the positioning tool and the frame, a material preparation area is formed above the positioning tool and the frame, the mounting block faces the accommodating area and protrudes in the width direction relative to the frame, the positioning tool is located above the mounting block in the height direction and the positioning tool is limited to the mounting block;
[0018] A mobile supporting member, wherein the mobile supporting member comprises a lifting assembly and a moving assembly, wherein the lifting assembly has a first height and a second height, wherein the first height is greater than the second height, wherein the mobile supporting member can be located in a transfer area and when the lifting assembly is at the first height, the lifting assembly abuts against the positioning fixture, and the mounting block and the positioning fixture are separated, and when the lifting assembly is at the second height, the lifting assembly does not contact the positioning fixture, and the positioning fixture is limited to the mounting block.
[0019] The purpose of the present application is also to provide a material preparation method that can be easily replaced, the material preparation method comprising:
[0020] The mobile carrier enters the transfer area, the lifting assembly of the mobile carrier rises to a first height, the lifting assembly abuts against the positioning tooling and moves together to the first height, and the mobile assembly of the mobile carrier drives the positioning tooling to leave to remove the positioning tooling;
[0021] The lifting assembly is located at a first height, the positioning fixture is located above the lifting assembly, the moving assembly drives the moving bearing member to move to the transfer area, the lifting assembly is lowered to a second height, and the mounting block is limitedly matched with the positioning fixture to install the positioning fixture, wherein the first height is greater than the second height;
[0022] The mobile carrier leaves the transfer area.
[0023] The above technical solution has the following advantages: the movable bearing member can realize the replacement of the positioning tooling by the movement of the lifting assembly at the first height and the second height, and the action of replacing the positioning tooling is simple.
[0024] The purpose of the present application is also to provide a material preparation mechanism that can be easily replaced, the material preparation mechanism comprising:
[0025] A frame, the frame includes a frame body and a mounting block, the frame body includes a transfer port, and the transfer port is connected to the outside; the mounting block is assembled and fixed to the frame body or the mounting block and the frame body are an integral piece, the frame body has a accommodating area, and the transfer port is an open port corresponding to the accommodating area; the mounting block faces the accommodating area and protrudes in the width direction relative to the frame body; the accommodating area has a transfer area and a material preparation area, the material preparation area is above the mounting block in the height direction, and the transfer area is below the mounting block in the height direction; the mounting block can be used to support a positioning tooling for carrying a loading tray. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 This is a structural diagram of the material preparation mechanism in the application, excluding the AGV trolley.
[0027] Figure 2 This is a schematic diagram of the structure of the AGV trolley for material preparation in the application.
[0028] Figure 3 for Figure 1 The structural diagram of the positioning tooling is not included.
[0029] Figure 4 for Figure 1 Schematic diagram of the top view of the partial rack in use.
[0030] Figure 5 A schematic diagram of the frame structure using a guide frame and guide wheels.
[0031] Figure 6 for Figure 5 An enlarged schematic diagram of some structures in .
[0032] Figure 7 A schematic diagram of a frame structure using guide plates and elastic parts.
[0033] Figure 8 for Figure 7 An enlarged schematic diagram of some structures in .
[0034] Fig. 9 for Figure 1 Schematic diagram of the front structure of the central positioning tooling.
[0035] Fig.10 for Figure 1 Schematic diagram of the reverse structure of the middle positioning tooling.
[0036] Fig.11 for Figure 1 Another embodiment of the enlarged portion of the material preparation mechanism.
[0037] Fig.12 for Figure 1 Another embodiment of the enlarged portion of the material preparation mechanism.
[0038] Reference numerals:
[0039] 1 frame, 10 transfer port, 11 mounting block, 111 positioning pin, 12 transfer area, 13 guide assembly, 131 guide wheel, 132 guide frame, 133 elastic member, 134 guide plate, 14 frame, 141 accommodating area, 142 material preparation area, 2 positioning tool, 21 positioning part, 211 positioning hole, 22 limiting part, 23 processing area, 24 waiting area for processing, 251 first protrusion, 252 second protrusion, 253 third protrusion, 3AGV trolley, 31 lifting assembly, 311 clamping part, 32 moving assembly, 41 first feeding sensor, 42 second feeding sensor, 51 limiting protrusion, 52 limiting accommodating part DETAILED DESCRIPTION
[0040] In order to better understand the technical solution of the present application, the embodiments of the present application are described in detail below with reference to the accompanying drawings.
[0041] It should be clear that the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present application. The up and down, front and back in the following description are based on the height direction and length direction marked in the figure.
[0042] like Figure 1 , this cycle preparation mechanism includes:
[0043] The rack 1 includes a rack body 14 and at least two mounting blocks 11. The rack body 14 includes a transfer port 10. The transfer port 10 is located on one side of the rack body 14 and communicates with the outside. The mounting blocks 11 are fixedly arranged with the rack body 14 or the mounting blocks 11 and the rack body 14 are an integral part. The rack body 14 has a receiving area 141. The transfer port 10 is an open port corresponding to the receiving area 141.
[0044] The positioning tool 2 is located in the accommodating area 141, the transfer area 12 is formed below the positioning tool 2 and the frame 14, the preparation area 142 is formed above the positioning tool 2 and the frame 14, the mounting block 11 faces the accommodating area 141 and protrudes in the width direction relative to the frame 14, the positioning tool 2 is located above the mounting block 11 in the height direction and the positioning tool 2 is limited to the mounting block 11, and the positioning tool 2 can move in the height direction under the action of force to separate from the mounting block 11.
[0045] The use of the AGV trolley 3 can replace the positioning tool 2 together with the loading tray, thereby improving the replacement efficiency and eliminating the need to replace the loading tray in batches.
[0046] like Figure 1 and Figure 2, is another embodiment, a material preparation mechanism, the material preparation mechanism comprises:
[0047] A rack 1, wherein the rack 1 comprises a rack body 14 and at least two mounting blocks 11, wherein the rack body 14 comprises a transfer port 10, wherein the transfer port 10 is located at one side of the rack body 14 and communicates with the outside; wherein the mounting blocks 11 are fixedly arranged with the rack body 14 or the mounting blocks 11 and the rack body 14 are integrally formed, wherein the rack body 14 has a receiving area 141, and the transfer port 10 is an open port corresponding to the receiving area 141;
[0048] A positioning fixture 2, the positioning fixture 2 is located in the accommodating area 141, the lower part of the positioning fixture 2 and the frame 14 form a transfer area 12, the upper part of the positioning fixture 2 and the frame 14 form a material preparation area 142, the mounting block 11 faces the accommodating area 141 and protrudes in the width direction relative to the frame 14, the positioning fixture 2 is located above the mounting block 11 in the height direction and the positioning fixture 2 is limited to the mounting block 11;
[0049] The AGV cart 3 includes a lifting component 31 and a moving component 32. The lifting component 31 has a first height and a second height, and the first height is greater than the second height. The AGV cart 3 can be located in the transfer area 12 and when the lifting component 31 is at the first height, the lifting component 31 is against the positioning tool 2, and the mounting block 11 and the positioning tool 2 are separated. When the lifting component 31 is at the second height, the lifting component 31 is not in contact with the positioning tool 2, and the positioning tool 2 is limited to the mounting block 11.
[0050] The AGV trolley 3 can move into the transfer area 12, lift the positioning tool 2 through the lifting piece, and finally move it out of the transfer area 12. The loading steps are opposite to the unloading steps. The AGV trolley 3 and the positioning tool 2 are intelligentized to improve work efficiency.
[0051] like Figure 1 and Fig. 9 The mounting block 11 includes a positioning pin 111, and there are at least two positioning pins 111. The positioning portion 21 includes a positioning hole 211. The distribution and number of the positioning holes 211 correspond to the positioning pin 111. In the present embodiment, four positioning pins 111 and positioning holes 211 are included. When placing the positioning tool 2, it is only necessary to limit the positioning hole 211 within the positioning pin 111. The positioning tool 2 can be located in the correct position by the cooperation of the positioning pin 111 and the positioning hole 211. The mounting block 11 is the positioning pin 111, and the positioning portion 21 is the positioning hole 211. Both are convenient to process, and can realize the positioning function, thereby reducing the processing cost.
[0052] Or, if Fig.11The mounting block 11 has a limiting accommodation portion 52, and the positioning tool 2 includes a positioning portion 21. The positioning portion 21 has a limiting protrusion 51. The shapes of the limiting protrusion 51 and the limiting accommodation portion 52 are adapted to each other. When the positioning tool 2 is placed on the positioning block, the limiting protrusion 51 will be partially in the limiting accommodation portion 52 to complete the horizontal limiting. The positioning tool 2 has better stability after installation.
[0053] Or, if Fig.12 The mounting block 11 has a limiting protrusion 51, and the positioning tool 2 includes a positioning portion 21, and the positioning portion 21 has a limiting accommodation portion 52. The shapes of the limiting protrusion 51 and the limiting accommodation portion 52 are adapted to each other. When the positioning tool 2 is placed on the positioning block, the limiting protrusion 51 will be partially in the limiting accommodation portion 52 to complete the horizontal limitation. The positioning tool 2 after installation has better stability.
[0054] like Figure 1 The material preparation mechanism also includes a first loading sensor 41 and a second loading sensor 42. The first sensor is used to detect whether the front side of the positioning tool 2 is correctly placed, and the second sensor is used to detect whether the rear side of the positioning tool 2 is correctly placed. In this embodiment, the first loading sensor 41 and the second loading sensor 42 are both through-beam sensors and are located at a first height. If the positioning portion 21 of the positioning tool 2 does not properly cooperate with the mounting block 11, the corresponding first loading sensor 41 or the second loading sensor 42 will be blocked, thereby determining whether the positioning tool 2 is correctly placed.
[0055] like Figure 5 and Figure 6 The material preparation mechanism also includes at least one pair of guide components 13, which are fixed to the frame 14. The height of the guide component 13 is higher than the height of the mounting block 11. After the AGV trolley 3 enters, the edge of the positioning tooling 2 will contact the guide component 13. The guide component 13 includes a guide frame 132 and a guide wheel 131. The guide wheel 131 is fixed to the guide frame 132, and the guide frame 132 is fixed to the frame 14. The guide wheel 131 can rotate on the guide frame 132. When the AGV trolley 3 has a certain deviation, the positioning tooling 2 will also have a certain deviation, and the positioning tooling 2 will contact the guide wheel 131. The guide wheel 131 will apply a reaction force to the positioning tooling 2 during the rotation process, so that the positioning tooling 2 can move smoothly into the transfer area 12, which has a buffering effect and improves the reliability of the device.
[0056] Or Figure 7 and Figure 8The material preparation mechanism also includes at least one pair of guide components 13, which are fixed to the frame 14. The height of the guide component 13 is higher than the height of the mounting block 11. After the AGV trolley 3 enters, the edge of the positioning tooling 2 will contact the guide component 13. The guide component 13 includes an elastic member 133 and a guide plate 134. The elastic member 133 is fixed to the frame 14, and the elastic guide plate 134 is fixed to the elastic member 133. The guide plate 134 can move along the compression direction of the elastic member 133. When the AGV trolley 3 has a certain deviation, the positioning tooling 2 will also have a certain deviation, and the positioning tooling 2 will contact the guide plate 134. The guide plate 134 will move along the deformation direction of the elastic member 133, and a reaction force will be applied to the positioning tooling 2, so that the positioning tooling 2 can move smoothly into the transfer area 12, which has a buffering effect and improves the reliability of the device.
[0057] like Fig. 9 and Fig.10 The positioning tooling 2 includes a limiting portion 22, which is located at the lower side of the positioning tooling 2. The lifting component 31 includes a clamping portion 311, which is located at the upper side of the lifting component. The limiting portion 22 is adapted to the clamping portion 311. When the lifting component 31 moves to the first height, the limiting portion 22 and the clamping portion 311 complete the horizontal limiting. During the movement of the AGV trolley 3, the connection between the positioning tooling 2 and the lifting component 31 is more reliably.
[0058] like Fig. 9 The positioning tool 2 includes a first protrusion 251, a second protrusion 252, and a third protrusion 253. The first protrusion 251 is located at the front side of the positioning tool 2, the second protrusion 252 is located at the rear side of the positioning tool 2, and the third protrusion 253 is located between the first protrusion 251 and the second protrusion 252. The positioning tool 2 includes a processing area 23 and an area to be processed 24. The processing area 23 is located between the first protrusion 251 and the third protrusion 253, and the area to be processed 24 is located between the second protrusion 252 and the third protrusion 253. The processing area 23 is located above the transfer area 12, and the area to be processed 24 is located above the transfer area 12. The width of the transfer area 12 is smaller than the width of the transfer port 10. The positioning tool 2 can be used for a circulating loading device. The processing area 23 and the area to be processed 24 are respectively stacked with multiple loading trays. After all the loading trays are loaded, the loading trays of the processing area 23 and the area to be processed 24 can be replaced at one time following the positioning tool 2, thereby improving production efficiency.
[0059] A material preparation method, the material preparation method comprising:
[0060] The AGV trolley 3 enters the transfer area 12, the lifting assembly 31 of the AGV trolley 3 rises to a first height, the lifting assembly 31 abuts against the positioning tool 2 and moves together to the first height, and the moving assembly 32 of the AGV trolley 3 drives the positioning tool 2 to leave to remove the positioning tool 2;
[0061] The lifting assembly 31 is located at a first height, the positioning fixture 2 is located above the lifting assembly 31, the moving assembly 32 drives the AGV trolley 3 to move to the transfer area 12, the lifting assembly 31 is lowered to a second height, and the mounting block 11 is limitedly matched with the positioning fixture 2 to install the positioning fixture 2, wherein the first height is greater than the second height;
[0062] The AGV trolley 3 leaves the transfer area 12. Through this replacement method, there is no need for manual operation to replace the loading tray, which improves the automation level of the equipment and improves production efficiency.
[0063] When the positioning tool 2 is removed, after the jacking assembly 31 and the positioning tool 2 move upward, the first loading sensor 41 and the second loading sensor 42 detect whether the positioning tool 2 passes by. If the positioning tool 2 does not pass by, the jacking assembly 31 continues to move upward. If the positioning tool 2 passes by, the jacking assembly 31 stops moving. When the first loading sensor 41 and the second loading sensor 42 detect obstruction at the same time, it means that the positioning tool 2 is passing by. When the first loading sensor 41 and the second loading sensor 42 cannot detect obstruction, it means that the positioning tool 2 has passed the detection position, and the jacking assembly 31 stops moving. The first loading sensor 41 and the second loading sensor 42 can detect whether the positioning tool 2 has moved into place, thereby improving the reliability of the device.
[0064] When installing the positioning tool 2, after the jacking assembly 31 descends, the first loading sensor 41 and the second loading sensor 42 detect whether the positioning tool 2 passes by. If the positioning tool 2 does not pass by, the jacking assembly 31 continues to move downward. If the positioning tool 2 passes by, the jacking assembly 31 stops moving. When the first loading sensor 41 and the second loading sensor 42 detect obstruction at the same time, it means that the positioning tool 2 is passing by. When the first loading sensor 41 and the second loading sensor 42 cannot detect obstruction, it means that the positioning tool 2 has passed the detection position, and the jacking assembly 31 stops moving. The first loading sensor 41 and the second loading sensor 42 can detect whether the positioning tool 2 has moved into place, thereby improving the reliability of the device.
[0065] As another embodiment, a material preparation mechanism includes: a frame 1, the frame 1 includes a frame body 14 and at least two mounting blocks 11, the frame body 14 includes a transfer port 10, the transfer port 10 is located on one side of the frame body 14 and communicates with the outside; the mounting block 11 is fixedly arranged with the frame body 14 or the mounting block 11 and the frame body 14 are an integral part, the frame body 14 has a receiving area 141, and the transfer port 10 is an open port corresponding to the receiving area 141;
[0066] A positioning fixture 2, the positioning fixture 2 is located in the accommodating area 141, the lower part of the positioning fixture 2 and the frame 14 form a transfer area 12, the upper part of the positioning fixture 2 and the frame 14 form a material preparation area 142, the mounting block 11 faces the accommodating area 141 and protrudes in the width direction relative to the frame 14, the positioning fixture 2 is located above the mounting block 11 in the height direction and the positioning fixture 2 is limited to the mounting block 11;
[0067] The mobile supporting member 3 includes a lifting component 31 and a moving component 32. The lifting component 31 has a first height and a second height, and the first height is greater than the second height. The mobile supporting member 3 can be located in the transfer area 12 and when the lifting component 31 is at the first height, the lifting component 31 is against the positioning tool 2, and the mounting block 11 and the positioning tool 2 are separated. When the lifting component 31 is at the second height, the lifting component 31 is not in contact with the positioning tool 2, and the positioning tool 2 is limited to the mounting block 11.
[0068] The material preparation method of the material preparation mechanism comprises the following steps:
[0069] The mobile carrier 3 enters the transfer area 12, the lifting component 31 of the mobile carrier 3 rises to a first height, the lifting component 31 abuts against the positioning tool 2 and moves together to the first height, and the moving component 32 of the mobile carrier 3 drives the positioning tool 2 to leave to remove the positioning tool 2;
[0070] The lifting assembly 31 is located at a first height, the positioning fixture 2 is located above the lifting assembly 31, the moving assembly 32 drives the moving bearing member 3 to move to the transfer area 12, the lifting assembly 31 is lowered to a second height, and the mounting block 11 is limitedly matched with the positioning fixture 2 to install the positioning fixture 2, wherein the first height is greater than the second height;
[0071] The mobile carrier 3 leaves the transfer area 12 .
[0072] As another embodiment, a material preparation mechanism includes: a frame 1, wherein the frame 1 includes a frame body 14 and a mounting block 11, the frame body 14 includes a transfer port 10, and the transfer port 10 is connected to the outside; the mounting block 11 is assembled and fixed to the frame body 14 or the mounting block 11 and the frame body 14 are an integral piece, the frame body 14 has a accommodating area 141, and the transfer port 10 is a corresponding open port of the accommodating area 141; the mounting block 11 faces the accommodating area 141 and protrudes in the width direction relative to the frame body 14; the accommodating area has a transfer area 12 and a material preparation area 142, the material preparation area 142 is above the mounting block 11 in the height direction, and the transfer area 12 is below the mounting block 11 in the height direction; the mounting block can be used to support a positioning tooling for carrying a loading tray.
[0073] It should be noted that the above embodiments are only used to illustrate the present invention and are not intended to limit the technical solutions described in the present invention. Although the present invention has been described in detail in this specification with reference to the above embodiments, it should be understood by those skilled in the art that the present invention can still be modified or replaced by equivalents, and all technical solutions and improvements thereof that do not depart from the spirit and scope of the present invention should be covered by the claims of the present invention.
Claims
1. A material preparation mechanism, characterized in that: The material preparation mechanism comprises: A frame (1), the frame (1) comprising a frame body (14) and a mounting block (11), the frame body (14) comprising a transfer port (10), the transfer port (10) being in communication with the outside; the mounting block (11) and the frame body (14) are assembled and fixed, or the mounting block (11) and the frame body (14) are an integral part, the frame body (14) has a receiving area (141), and the transfer port (10) is an open port corresponding to the receiving area (141); A positioning tool (2), the positioning tool (2) is located in the accommodating area (141), a transfer area (12) is formed below the positioning tool (2) and the frame (14), a material preparation area (142) is formed above the positioning tool (2) and the frame (14), the mounting block (11) faces the accommodating area (141) and protrudes in the width direction relative to the frame (14), the positioning tool (2) is located above the mounting block (11) in the height direction and the positioning tool (2) is limited to the mounting block (11), and the positioning tool (2) can move in the height direction to separate from the mounting block (11) under the action of force.
2. A material preparation mechanism, characterized in that: The material preparation mechanism comprises: A frame (1), the frame (1) comprising a frame body (14) and a mounting block (11), the frame body (14) comprising a transfer port (10), the transfer port (10) being located on one side of the frame body (14) and communicating with the outside; the mounting block (11) and the frame body (14) are fixedly arranged or the mounting block (11) and the frame body (14) are integrally formed, the frame body (14) has a receiving area (141), and the transfer port (10) is an open port corresponding to the receiving area (141); A positioning tool (2), the positioning tool (2) being located in the accommodating area (141), a transfer area (12) being formed below the positioning tool (2) and the frame (14), a material preparation area (142) being formed above the positioning tool (2) and the frame (14), the mounting block (11) facing the accommodating area (141) and protruding in the width direction relative to the frame (14), the positioning tool (2) being located above the mounting block (11) in the height direction and the positioning tool (2) being limited to the mounting block (11); An AGV trolley (3), the AGV trolley (3) comprising a lifting component (31) and a moving component (32), the lifting component (31) having a first height and a second height, the first height being greater than the second height, the AGV trolley (3) being able to be located in a transfer area (12) and when the lifting component (31) is at the first height, the lifting component (31) is against the positioning fixture (2), the mounting block (11) and the positioning fixture (2) are separated, and when the lifting component (31) is at the second height, the lifting component (31) is not in contact with the positioning fixture (2), and the positioning fixture (2) is limited to the mounting block (11).
3. The material preparation mechanism according to claim 1 or 2, characterized in that: There are at least two mounting blocks, and the positioning tool (2) comprises a positioning portion (21). One of the mounting block (11) and the positioning portion (21) has a limiting convex portion (51), and the other of the mounting block (11) and the positioning portion (21) has a limiting accommodating portion (52). The limiting accommodating portion (52) is recessed inwardly in a height direction, and the limiting convex portion (51) is at least partially located in the limiting accommodating portion (52).
4. The material preparation mechanism according to claim 1 or 2, characterized in that: The mounting block (11) comprises positioning pins (111), and there are at least two positioning pins (111). The positioning tool (2) comprises positioning holes (211), and the distribution and number of the positioning holes (211) correspond to those of the positioning pins (111). The positioning pins (111) and the positioning holes (211) are limitedly matched.
5. The material preparation mechanism according to claim 1 or 2, characterized in that: The material preparation mechanism further comprises a first material loading sensor (41) and a second material loading sensor (42), wherein the first sensor is used to detect whether the front side of the positioning tool (2) is correctly placed, and the second sensor is used to detect whether the rear side of the positioning tool (2) is correctly placed.
6. The material preparation mechanism according to any one of claims 1 to 5, characterized in that: The material preparation mechanism further comprises at least one pair of guide assemblies (13), wherein the guide assemblies (13) are fixed to the frame (14), the height of the guide assemblies (13) is higher than the height of the mounting block (11), the guide assemblies (13) comprise a guide frame (132) and a guide wheel (131), the guide wheel (131) is fixed to the guide frame (132), the guide frame (132) is fixed to the frame (14), and the guide wheel (131) can rotate on the guide frame (132).
7. The material preparation mechanism according to any one of claims 1 to 5, characterized in that: The material preparation mechanism also includes at least one pair of guide assemblies (13), wherein the guide assemblies (13) are fixed to the frame (14), the height of the guide assemblies (13) is higher than the height of the mounting block (11), and the guide assemblies (13) include an elastic member (133) and a guide plate (134), wherein the elastic member (133) is fixed to the frame (14), the elastic guide plate (134) is fixed to the elastic member (133), and the guide plate (134) can move along the compression direction of the elastic member (133).
8. The material preparation mechanism according to any one of claims 2 to 7, characterized in that: The positioning tool (2) includes a limiting portion (22), and the limiting portion (22) is located at the lower side of the positioning tool (2); the lifting component (31) includes a clamping portion (311), and the clamping portion (311) is located at the upper side of the lifting component (31); the limiting portion (22) is adapted to the clamping portion (311); when the AGV trolley (3) is located at the first loading height, the limiting portion (22) and the clamping portion (311) are limited.
9. The material preparation mechanism according to any one of claims 1 to 8, characterized in that: The positioning tool (2) comprises a first protrusion (251), a second protrusion (252), and a third protrusion (253); the first protrusion (251) is located at the front side of the positioning tool (2); the second protrusion (252) is located at the rear side of the positioning tool (2); the third protrusion (253) is located between the first protrusion (251) and the second protrusion (252); the positioning tool (2) comprises a processing area (23) and a waiting area (24); the processing area (23) is located between the first protrusion (251) and the third protrusion (253); the waiting area (24) is located between the second protrusion (252) and the third protrusion (253); the processing area (23) is located above the transfer area (12); and the waiting area (24) is located above the transfer area (12).
10. A material preparation method, characterized in that: The following steps are involved: The AGV trolley (3) enters the transfer area (12), the lifting component (31) of the AGV trolley (3) rises to a first height, the lifting component (31) abuts against the positioning tool (2) and moves together to the first height, and the moving component (32) of the AGV trolley (3) drives the positioning tool (2) to leave to remove the positioning tool (2); The lifting assembly (31) is located at a first height, the positioning fixture (2) is located above the lifting assembly (31), the moving assembly (32) drives the AGV trolley (3) to move to the transfer area (12), the lifting assembly (31) descends to a second height, and the mounting block (11) and the positioning fixture (2) are limitedly matched to install the positioning fixture (2), wherein the first height is greater than the second height; The AGV trolley (3) leaves the transfer area (12).
11. The material preparation method according to claim 10, characterized in that: The material preparation mechanism comprises a first loading sensor (41) and a second loading sensor (42). When the positioning tool (2) is removed, after the lifting assembly (31) and the positioning tool (2) move upward, the first loading sensor (41) and the second loading sensor (42) detect whether the positioning tool (2) passes by. If the positioning tool (2) does not pass by, the lifting assembly (31) continues to move upward. If the positioning tool (2) passes by, the lifting assembly (31) stops moving.
12. The material preparation method according to claim 11, characterized in that: When installing the positioning tool (2), after the lifting assembly (31) descends, the first loading sensor (41) and the second loading sensor (42) detect whether the positioning tool (2) passes by; if the positioning tool (2) does not pass by, the lifting assembly (31) continues to move downward; if the positioning tool (2) passes by, the lifting assembly (31) stops moving.
13. A material preparation mechanism, characterized in that: The material preparation mechanism comprises: A frame (1), the frame (1) comprising a frame body (14) and a mounting block (11), the frame body (14) comprising a transfer port (10), the transfer port (10) being in communication with the outside; the mounting block (11) and the frame body (14) are fixedly arranged or the mounting block (11) and the frame body (14) are integrally formed, the frame body (14) has a receiving area (141), and the transfer port (10) is an open port corresponding to the receiving area (141); A positioning tool (2), the positioning tool (2) being located in the accommodating area (141), a transfer area (12) being formed below the positioning tool (2) and the frame (14), a material preparation area (142) being formed above the positioning tool (2) and the frame (14), the mounting block (11) facing the accommodating area (141) and protruding in the width direction relative to the frame (14), the positioning tool (2) being located above the mounting block (11) in the height direction and the positioning tool (2) being limited to the mounting block (11); A movable support (3), wherein the movable support (3) comprises a lifting component (31) and a movable component (32), wherein the lifting component (31) has a first height and a second height, wherein the first height is greater than the second height, wherein the movable support (3) can be located in a transfer area (12) and when the lifting component (31) is at the first height, the lifting component (31) abuts against the positioning fixture (2), and the mounting block (11) and the positioning fixture (2) are separated; and when the lifting component (31) is at the second height, the lifting component (31) does not contact the positioning fixture (2), and the positioning fixture (2) is limited to the mounting block (11).
14. A material preparation method, characterized in that: The following steps are involved: The mobile carrier (3) enters the transfer area (12), the lifting component (31) of the mobile carrier (3) rises to a first height, the lifting component (31) abuts against the positioning tool (2) and moves together to the first height, and the moving component (32) of the mobile carrier (3) drives the positioning tool (2) to leave to remove the positioning tool (2); The lifting assembly (31) is located at a first height, the positioning fixture (2) is located above the lifting assembly (31), the moving assembly (32) drives the moving bearing member (3) to move to the transfer area (12), the lifting assembly (31) descends to a second height, and the mounting block (11) and the positioning fixture (2) are limitedly matched to install the positioning fixture (2), wherein the first height is greater than the second height; The mobile carrier (3) leaves the transfer area (12).
15. A material preparation mechanism, characterized in that: The material preparation mechanism comprises: A frame (1), the frame (1) comprising a frame body (14) and a mounting block (11), the frame body (14) comprising a transfer port (10), the transfer port (10) being in communication with the outside; the mounting block (11) being assembled and fixed to the frame body (14) or the mounting block (11) and the frame body (14) being an integral piece, the frame body (14) having a receiving area (141), the transfer port (10) being an open port corresponding to the receiving area (141); the mounting block (11) facing the receiving area (141) and protruding in the width direction relative to the frame body (14); the receiving area having a transfer area (12) and a material preparation area (142), the material preparation area (142) being above the mounting block (11) in the height direction, and the transfer area (12) being below the mounting block (11) in the height direction; the mounting block can be used to support a positioning tool for carrying a loading tray.