Curve pushing intelligent synchronous control construction method

By using intelligent synchronous control method in the over-push construction of curved bridges, combined with temporary piers, tire frames and jack equipment, the problem of steel box beam offset is solved, and the precise control of construction paths and improvement of construction quality is achieved.

CN118997003APending Publication Date: 2024-11-22CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +1
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411140738.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

During the over-pushing construction of curved bridges, steel box beams are prone to shift on both sides, causing the axis to deviate from the theoretical position and affecting the construction quality.

Method used

The intelligent synchronous control construction method of curved pushing is adopted. By setting up temporary piers, tire frames, guide beams and jack equipment, supporting and pushing steel box beams in segments, and using the total station to monitor the position changes of the reference network for real-time correction, control jacks to ensure accuracy.

Benefits of technology

It effectively avoids the deviation of the steel box girder, ensures the accuracy and construction quality of the construction path, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997003A_ABST
    Figure CN118997003A_ABST
Patent Text Reader

Abstract

The invention provides a curve pushing intelligent synchronous control construction method. The curve pushing intelligent synchronous control construction method comprises the steps that S1, a crane moving area is compacted; s2, multiple sets of temporary buttresses are erected on the pushing linear extension line; s3, after the steel box girder is transported in place, the steel box girder is placed on the jig frame, and S4, a propelling scheme is set according to a bridge curve, and jacking strokes of a vertical jack, a propelling jack and a transverse jack are distributed; and S5, a beam falling jack is installed for beam falling, and the pushing equipment and the temporary buttress are dismantled after beam falling is completed. And a pushing scheme is set, and the pushing path of each jack is controlled, so that the steel box girder is pushed according to the preset path, the pushing precision is ensured, and the construction quality and the construction efficiency are ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of steel box girder jacking, and in particular relates to an intelligent synchronous control construction method for curved jacking. Background Art

[0002] Steel box girder, also known as steel plate box girder, is a common structural form for long-span bridges. It is generally used on bridges with larger spans. It is called a steel box girder because it looks like a box. Steel box girders are generally connected by a full welding method, including top plate, bottom plate, web plate, transverse diaphragm, longitudinal diaphragm and stiffening ribs. The top plate is an orthogonal anisotropic bridge deck composed of a cover plate and longitudinal stiffening ribs. Steel box girders are generally installed and constructed using a jacking device, that is, a jacking construction method. During the jacking process for curved bridges, the jacking plan needs to be accurately controlled. During the construction process, the jacking offset of the steel box girders on both sides often occurs, which causes the axis of the steel box bridge to deviate from the theoretical position and affects the construction quality of the steel box bridge.

[0003] Therefore, it is necessary to provide an improved technical solution to address the above-mentioned deficiencies in the prior art. Summary of the invention

[0004] The purpose of the present invention is to overcome the deficiencies in the above-mentioned prior art, and the present invention provides a curve jacking intelligent synchronous control construction method.

[0005] In order to achieve the above object, the present invention provides the following technical solutions:

[0006] A curved jacking intelligent synchronous control construction method comprises the following steps:

[0007] Step S1, setting up a steel box girder assembly site, and performing compaction treatment on the brick slag and gravel filling corresponding to the crane activity area of ​​the assembly site;

[0008] Step S2, setting up multiple groups of temporary piers on the extension line of the jacking line, setting corresponding steel box girder tire frames and jacking equipment above the temporary piers and the constructed bridge deck, setting installation brackets on the constructed bridge deck according to the steel box girder sections, and supporting the joints of two adjacent steel box girder sections;

[0009] Step S3, after the steel box girder is transported to the destination, the steel box girder is placed on the tire frame, a guide beam is arranged at the front end of the steel box girder, and the joints of the steel box girder are welded after the steel box girder is hoisted;

[0010] Step S4, setting a propulsion plan according to the bridge curve, and allocating the jacking strokes of the vertical jack, the propulsion jack, and the transverse jack;

[0011] The steel box beam is lifted up by the vertical jack, the tire frame is removed, and the steel box beam and the guide beam are supported on the crawler on the jacking equipment by the vertical jack. The crawler pushes forward for a stroke through the transverse jack and the thrust jack. The vertical jack lifts up the steel box beam again and separates it from the crawler. The crawler returns to its original position to return to the initial state for the next jacking stroke. During the pushing process, the vertical jack, the thrust jack and the transverse jack are controlled by the controller according to the pushing plan until the steel box beam is pushed into place.

[0012] Step S5, installing the beam-dropping jack to drop the beam, and after the beam is dropped, removing the jacking equipment and temporary piers.

[0013] Preferably, the linearity of the guide beam is adapted to the jacking path, the root of the guide beam is welded to the front end of the steel box beam, the height of the root of the guide beam is greater than the vertical height of the box beam, and is strengthened by reinforcement.

[0014] Preferably, a step is provided on the lower surface of the front end of the guide beam. When the guide beam passes over the pier, the steel pad above the vertical jack is removed to allow the front end of the guide beam to pass over the crawler and the vertical jack, and the guide beam is lifted upward by the vertical jack to offset the downward deflection of the guide beam; a support stack is provided between the guide beam and the crawler, and the guide beam is supported by the crawler so that the guide beam can be pushed forward by the crawler.

[0015] Preferably, a plurality of horizontal displacement reference points and vertical displacement reference points are set on the steel box girder and temporary piers to form a reference network. During the jacking process of the steel box girder, the position change of the reference network is tracked and monitored by a total station, and the steel box girder is corrected when deviation occurs.

[0016] Preferably, the walking machine comprises:

[0017] A bottom plate, the bottom plate is fixed on the top of the temporary pier, a slide groove is supported above the bottom plate by a slide plate, and a support block for supporting the steel box girder is arranged in the slide groove;

[0018] A propulsion jack, which is arranged at one end of the slideway and drives the support block along the jacking direction of the steel box girder;

[0019] The transverse movement jack is arranged on the side of the bottom plate and drives the slideway in the transverse direction of the steel box beam.

[0020] Preferably, the steel box girder is a single-box double-chamber structure, the top plate of the steel box girder adopts an orthogonal anisotropic plate structure with U-ribs and open ribs, the top and bottom plate stiffening ribs and the web plate stiffening ribs are continuous throughout the bridge, the bottom plate of the steel box girder is reinforced at the corresponding jacking equipment, and a "Z"-shaped splicing seam is used between the adjacent steel box girders at both ends.

[0021] Preferably, the mounting bracket includes a base and a row of columns, wherein the base is located directly below the joint of two adjacent sections of steel box girders, rows of columns corresponding to the two sections of steel box girders are provided on both sides of the base, and connecting plates extending to the outer wall of the steel box girder web are provided at both ends of the base, and the connecting plates are detachably connected to the steel box girder web.

[0022] Preferably, on the cast bridge deck, the mounting bracket and the jacking device are spaced apart, and during the jacking process, the mounting bracket is fixed on the steel box girder so as to be lifted and pushed forward along with the steel box girder;

[0023] The spacing between two adjacent jacking devices is matched with the segmented length of the steel box girder. In the two adjacent jacking devices, the installation bracket is removed when it reaches the front jacking device and moved backward to the rear jacking device. As the steel box girder is pushed forward, the joint of the rear steel box girder is fixed and supported in real time.

[0024] Preferably, the temporary pier is supported by 8 steel pipes as columns, a steel section is set on the top of the column as a load-bearing beam, and a concrete foundation is set under the temporary pier.

[0025] Preferably, three groups of temporary piers are set on the extension line of the jacking line, two of the three groups of temporary piers are located on both sides of the existing road to be crossed, and the other is set between the temporary pier corresponding to the jacking direction of the steel box girder to be crossed and the constructed bridge deck.

[0026] Beneficial effects: By setting the jacking plan and controlling the propulsion path of each jack, the steel box girder can be pushed along the preset path, thus ensuring the accuracy of the push and ensuring the construction quality and efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] The drawings constituting a part of the present application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. Among them:

[0028] Figure 1 This is a schematic diagram of the top pushing of a steel box girder in a specific embodiment provided by the present invention;

[0029] Figure 2 It is a schematic structural diagram of a temporary buttress in a specific embodiment provided by the present invention.

[0030] In the figure: 1. Steel box girder; 2. Crawler; 3. Mounting bracket; 4. Temporary pier; 5. Guide beam; 6. Vertical jack; 201. Support block; 202. Transverse jack; 203. Bottom plate; 204. Slideway. DETAILED DESCRIPTION

[0031] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention belong to the scope of protection of the present invention.

[0032] In the description of the present invention, the terms "longitudinal", "lateral", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific orientation. Therefore, they should not be understood as limitations on the present invention. The terms "connected" and "connected" used in the present invention should be understood in a broad sense. For example, they can be fixed connections or detachable connections; they can be directly connected or indirectly connected through intermediate components. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0033] The present invention will be described in detail below with reference to the accompanying drawings and in combination with embodiments. It should be noted that the embodiments and features in the embodiments of the present invention can be combined with each other without conflict.

[0034] like Figure 1-2 As shown, a curve jacking intelligent synchronous control construction method includes the following steps: Step S1, setting up a steel box girder 1 assembly site, and filling brick slag and gravel in the assembly site corresponding to the crane activity area for compaction.

[0035] Step S2, set up multiple groups of temporary piers 4 on the extension line of the jacking line, set up corresponding steel box girder 1 tire frame and jacking equipment above the temporary piers 4 and the constructed bridge deck, the jacking equipment includes a crawler 2 and a vertical jack 6, the jacking equipment is arranged at the bottom of the steel box girder 1, to ensure that the crawler jack falls under the web, it is necessary to set a widened crawler bracket, each jacking point is divided into two pairs in the transverse direction of the bridge, and two jacking equipment are symmetrically arranged along the center line of the box girder.

[0036] According to the steel box girder 1, a mounting bracket 3 is arranged on the constructed bridge deck to support the joint of two adjacent sections of the steel box girder 1;

[0037] Step S3, after the steel box girder 1 is transported to the destination, the steel box girder 1 is hoisted and placed on the tire frame, a guide beam 5 is arranged at the front end of the steel box girder 1, and after the steel box girder 1 is hoisted, the joints of the steel box girder 1 are welded;

[0038] Step S4, setting a pushing plan according to the bridge curve, allocating the number of pushing times and the pushing strokes of the vertical jack 6, the pushing jack and the transverse jack 202 during each pushing, and calculating the specific position of the steel box girder 1 during each pushing. After each pushing, the actual position of the steel box girder 1 is compared with the calculated position, and the position of the steel box girder 1 is accurately adjusted.

[0039] During the pushing process, firstly, the steel box girder 1 is lifted up by the vertical jack 6, the tire frame is removed and the vertical jack 6 is dropped so that the steel box girder 1 and the guide beam 5 are supported on the crawler 2 on the pushing device, and the crawler 2 is pushed forward for a stroke by the transverse jack 202 and the pushing jack, and the vertical jack 6 lifts up the steel box girder 1 again to separate it from the crawler 2, and the crawler 2 returns to its original position to return to the initial state for the next pushing stroke. After each pushing is completed, the axis displacement monitoring is required, and the displacement deviation exceeds the set limit (10cm) and needs to be corrected. The axis displacement monitoring requires the welding of the total station prism as the reference point at the large and small mileage ends of the right flange plate of the steel box girder 1. During the pushing process, the vertical jack 6, the pushing jack and the transverse jack 202 are controlled by the controller according to the pushing plan until the steel box girder 1 is pushed into place;

[0040] Step S5, installing the beam-dropping jack to drop the beam, and after the beam is dropped, removing the jacking equipment and the temporary pier 4.

[0041] In an optional embodiment, the guide beam 5 reduces the construction internal force of the steel box girder 1 during the jacking process, increases the jacking span, and plays a guiding role. The linearity of the guide beam 5 is compatible with the jacking path. The guide beam 5 and the steel box girder 1 together constitute a multi-span continuous beam. Only by performing a force analysis on the whole can the component design of the guide beam 5 be determined. The root of the guide beam 5 is welded to the front end of the steel box girder 1. The root height of the guide beam 5 is greater than the vertical height of the box type, and is reinforced by reinforcement. The guide beam 5 and the steel beam are connected in the form of welding reinforcement. At the same time, in order to increase the stability of the guide beam 5, 4 reinforcement flat joints are set. When the guide beam 5 and the steel beam are assembled and welded, a large horse plate is used to connect the joints to increase the connection strength, measure and lay out accurately, and ensure that the linearity of the guide beam 5 meets the jacking line type.

[0042] The lower surface of the front end of the guide beam 5 is provided with a step platform. When the guide beam 5 passes over the pier, the steel pad above the vertical jack 6 is removed to make the front end of the guide beam 5 pass over the crawler 2 and the vertical jack 6, and the guide beam 5 is lifted up by the vertical jack 6 to offset the deflection of the guide beam 5; a support pile is placed between the guide beam 5 and the crawler 2, and the guide beam 5 is supported by the crawler 2 so that the guide beam 5 can be pushed forward by the crawler 2. When the guide beam 5 cannot be smoothly put on the pier, it can be assisted by two pier-facing jacks set on the nose bridge of the guide beam 5.

[0043] When facing the pier, first retract the vertical jack 6 to the bottom, then use the vertical jack 6 to push the step platform upward, place the pad support stack on the crawler 2, and then retract the vertical jack 6, so that the guide beam 5 can be pushed through the crawler 2.

[0044] After the steel beam is pushed close to the tail pier and the guide beam 5 exceeds the rear end to meet the requirements of removal, a 130t or 160t truck crane is used to remove the guide beam 5: first use the crane hook to hang the front section of the guide beam 5; remove the bolts and take down the connecting plate; lift the crane arm; lift the guide beam 5 onto the transport vehicle for transportation; remove the guide beam 5 section by section (a total of 2 sections) to avoid large overhangs of the steel beam.

[0045] In an optional embodiment, a plurality of horizontal displacement reference points and vertical displacement reference points are set on the steel box girder 1 and the temporary pier 4 to form a reference network. During the jacking process of the steel box girder 1, the position change of the reference network is tracked and monitored by a total station. When deviation occurs, the steel box girder 1 is corrected, and the monitored position change of the reference network is input into the control system. The control system can be a computer, so as to compare the parameters of the data of each jack according to the comparison results, and provide correction data. The control system controls each jack for correction.

[0046] The monitoring is carried out by using Leica total station. After the location of the points is selected on site according to the design drawings, the monitoring signs are installed. Small prisms are embedded in the columns, guide beams 5, and steel box beams 1. In order to avoid the monitoring signs being damaged during the monitoring period, they are clearly marked with paint and uniformly numbered. The small angle method, the sight line method, the polar coordinate method, and the forward intersection method can be used for horizontal displacement observation. The method used depends on the on-site conditions.

[0047] The analysis of monitoring results belongs to the link of monitoring data collation and submission, and is also the most important part of monitoring work. The content of deformation analysis includes deformation data processing and analysis, physical interpretation of deformation and various aspects of deformation prediction.

[0048] The walking machine 2 includes a bottom plate 203, a slide 204, a propulsion jack, a transverse jack 202, and a hydraulic pump station. The bottom plate 203 is fixed on the top of the temporary pier 4, for example, by welding or bolting. A slide 204 is supported by a slide plate above the bottom plate 203. The slide 204 is a square groove welded by steel plates, and the lower part is a flat surface. The slide plate is a polytetrafluoroethylene plate, and silicone oil can be applied in between to reduce the friction resistance of the sliding surface. A support block 201 for supporting the steel box beam 1 is provided in the slide 204, and a 5cm rubber plate or a high-density wooden board is placed on the upper part, so that the local force of the main beam can be balanced and the support The support block 201 is square, with a width that matches the inner cavity of the slide slot 204 and a length that is smaller than the slide slot 204; the thrust jack is arranged at one end of the slide slot 204, and the length of the slide slot 204 is square and corresponds to the pushing square, so as to drive the support block 201 along the pushing direction of the steel box girder 1; multiple transverse jacks 202 are arranged on the side of the base plate 203 to drive the slide slot 204 along the transverse direction of the steel box girder 1, and the side of the base plate 203 is provided with a hinge point corresponding to the transverse jack 202 and a stop plate corresponding to the slide slot 204, and multiple transverse jacks 202 are evenly distributed on both sides of the base plate 203.

[0049] The hydraulic pump station is connected to the propulsion jack, the transverse jack 202 and the vertical jack 6 respectively through a plurality of solenoid valves, and the control system is connected to each solenoid valve for control.

[0050] In an optional embodiment, the steel box girder 1 is a single-box double-chamber structure. The top plate of the steel box girder 1 adopts an orthogonal anisotropic plate structure with U ribs and open ribs. The top and bottom plate stiffening ribs and the web stiffening ribs are continuous throughout the bridge. When the bottom plates of different thicknesses are butt-jointed, the thickness change is performed on the outside of the box to keep the inside of the box smooth. The connections between the box body and the block segments are all welded. The design is optimized based on the design drawings of the steel box girder 1. 16mmQ345qc steel plates are used to strengthen the bottom plate of the steel box girder 1 corresponding to the jacking equipment (the corner between the bottom plate of the steel box girder 1 and the web), and a "Z"-shaped splicing seam is used between the adjacent steel box girders 1 at both ends. A mounting bracket 3 is provided at each segment joint (splicing position) according to the segment opening to play a supporting and adjustment role.

[0051] After the steel box girder 1 is divided into blocks horizontally, a diagonal brace is set at each longitudinal reinforcing rib on both sides of the web of the beam block that is not a box. The material can be angle steel and channel steel. The web of this beam block is the web of the beam block at the division of the steel box girder 1; the support point of the diagonal brace is set at the junction of the transverse diaphragm and the top and bottom plates. After adding the diagonal brace, the longitudinal bending stiffness and transverse torsional stiffness of each beam block are basically consistent, ensuring the safety of the lifting process. After each beam block is hoisted to the temporary support, the displacement of each beam block is basically the same, reducing the displacement difference at the longitudinal welding point and the residual stress after welding.

[0052] In an optional embodiment, the mounting bracket 3 includes a base and a row of columns. The base is a square structure formed by welding steel sections laid on an existing road surface. The base is located directly below the joint of two adjacent sections of steel box girders 1. Rows of columns corresponding to the two sections of steel box girders 1 are provided on both sides of the base. The rows of columns can be I-beams with a support plate on the top. Connecting plates extending to the outer wall of the web of the steel box girder 1 are provided at both ends of the base. The connecting plates are detachably connected to the web of the steel box girder 1, and can be connected by bolts or welding and cutting. During the jacking process, the base fixes the steel box girder 1 so that the steel box girder 1 can be supported no matter where it is. In an optional embodiment, concrete is poured in the base or concrete counterweights are placed to ensure the stability of the steel box girder 1 during the pushing process.

[0053] In an optional embodiment, in order to ensure that the installation bracket 3 does not interfere with the jacking equipment, on the cast bridge deck, the installation bracket 3 and the jacking equipment are spaced apart, the connecting plate is detachably connected to the web of the steel box girder 1, and the joint is between two adjacent jacking equipment. During the jacking process, the installation bracket 3 is fixed on the steel box girder 1 so as to rise and fall with the steel box girder 1 and be pushed forward, thereby being connected to the steel box girder 1 as a whole to ensure real-time support.

[0054] The spacing between two adjacent jacking devices is adapted to the segmented length of the steel box girder 1. A mounting bracket 3 is arranged in the two adjacent jacking devices. When the mounting bracket 3 arrives at the front jacking device along with the steel box girder 1, it is removed and moved backward to the rear jacking device, so that the joint crosses the jacking device. After the jacking joint of the steel box girder 1 crosses the jacking device, the mounting bracket 3 supports the joint of the next steel box girder 1, and is fixed by a connecting plate and supported in real time as the jacking proceeds.

[0055] The connecting plate has a certain width and is located at both ends of the base and between two corresponding rows of columns, so that the two steel box beams 1 at the joint can be connected to ensure uniform force.

[0056] In an optional embodiment, the temporary pier 4 is supported by 8 steel pipes as columns, a steel section is set on the top of the column as a load-bearing beam, and a concrete foundation is set under the temporary pier 4.

[0057] In an optional embodiment, three groups of temporary piers 4 are set on the extension line of the jacking line, two of the three groups of temporary piers 4 are located on both sides of the existing road to be crossed, and the other is set between the temporary pier 4 in the jacking direction corresponding to the steel box girder 1 to be crossed and the constructed bridge deck.

[0058] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention are within the scope of protection of the pending claims of the present invention.

Claims

1. A curve jacking intelligent synchronous control construction method, characterized in that: The following steps are involved: Step S1, setting up a steel box girder assembly site, and performing compaction treatment on the brick slag and gravel filling corresponding to the crane activity area in the assembly site; Step S2, setting up multiple groups of temporary piers on the extension line of the jacking line, setting corresponding steel box girder tire frames and jacking equipment above the temporary piers and the constructed bridge deck, setting installation brackets on the constructed bridge deck according to the steel box girder sections, and supporting the joints of two adjacent steel box girder sections; Step S3, after the steel box girder is transported to the destination, the steel box girder is placed on the tire frame, a guide beam is arranged at the front end of the steel box girder, and the joints of the steel box girder are welded after the steel box girder is hoisted; Step S4, setting a propulsion plan according to the bridge curve, and allocating the jacking strokes of the vertical jack, the propulsion jack, and the transverse jack; The steel box beam is lifted up by the vertical jack, the tire frame is removed, and the steel box beam and the guide beam are supported on the crawler on the jacking equipment by the vertical jack. The crawler pushes forward for a stroke through the transverse jack and the thrust jack. The vertical jack lifts up the steel box beam again and separates it from the crawler. The crawler returns to its original position to return to the initial state for the next jacking stroke. During the pushing process, the vertical jack, the thrust jack and the transverse jack are controlled by the controller according to the pushing plan until the steel box beam is pushed into place. Step S5, installing the beam-dropping jack to drop the beam, and after the beam is dropped, removing the jacking equipment and temporary piers.

2. The curve pushing intelligent synchronous control construction method according to claim 1 is characterized in that: The linearity of the guide beam is adapted to the jacking path. The root of the guide beam is welded to the front end of the steel box beam. The height of the root of the guide beam is greater than the vertical height of the box beam and is strengthened by reinforcement.

3. The curve pushing intelligent synchronous control construction method according to claim 2 is characterized in that: A step is provided on the lower surface of the front end of the guide beam. When the guide beam passes the pier, the steel pad above the vertical jack is removed to allow the front end of the guide beam to pass over the crawler and the vertical jack. The guide beam is lifted upward by the vertical jack to offset the downward deflection of the guide beam. A support stack is placed between the guide beam and the crawler to support the guide beam through the crawler so that the guide beam can be pushed forward by the crawler.

4. The curve pushing intelligent synchronous control construction method according to claim 1 is characterized in that: A number of horizontal and vertical displacement reference points are set on the steel box girder and temporary piers to form a reference network. During the jacking process of the steel box girder, the position changes of the reference network are tracked and monitored by a total station, and the steel box girder is corrected when deviation occurs.

5. The curve jacking intelligent synchronous control construction method according to claim 4 is characterized in that: Walking machine includes: A bottom plate, the bottom plate is fixed on the top of the temporary pier, a slide groove is supported above the bottom plate by a slide plate, and a support block for supporting the steel box girder is arranged in the slide groove; A propulsion jack, which is arranged at one end of the slideway and drives the support block along the jacking direction of the steel box girder; The transverse movement jack is arranged on the side of the bottom plate and drives the slideway in the transverse direction of the steel box beam.

6. The curve jacking intelligent synchronous control construction method according to claim 1 is characterized in that: The steel box girder is a single-box double-chamber structure. The top plate of the steel box girder adopts an orthogonal anisotropic plate structure with U-ribs and open ribs. The top and bottom plate stiffening ribs and the web plate stiffening ribs are continuous throughout the bridge. The bottom plate of the steel box girder is reinforced at the corresponding jacking equipment, and a "Z"-shaped splicing seam is used between the adjacent steel box girders at both ends.

7. The curve jacking intelligent synchronous control construction method according to claim 1 is characterized in that: The mounting bracket includes a base and a row of columns. The base is located directly below the joint of two adjacent sections of steel box girders. Rows of columns corresponding to the two sections of steel box girders are provided on both sides of the base. Connecting plates extending to the outer wall of the steel box girder web are provided at both ends of the base. The connecting plates are detachably connected to the steel box girder web.

8. The curve jacking intelligent synchronous control construction method according to claim 7 is characterized in that: On the cast bridge deck, the mounting brackets and the jacking equipment are distributed at intervals. During the jacking process, the mounting brackets are fixed on the steel box girder so as to rise and fall with the steel box girder and be pushed forward; The spacing between two adjacent jacking devices is matched with the segmented length of the steel box girder. In the two adjacent jacking devices, the installation bracket is removed when it reaches the front jacking device and moved backward to the rear jacking device. As the steel box girder is pushed forward, the joint of the rear steel box girder is fixed and supported in real time.

9. The curve jacking intelligent synchronous control construction method according to claim 1 is characterized in that: The temporary pier is supported by 8 steel pipes as columns, steel sections are set on the top of the columns as load-bearing beams, and a concrete foundation is set under the temporary pier.

10. The curve jacking intelligent synchronous control construction method according to claim 9 is characterized in that: Three groups of temporary piers are set up on the extension line of the jacking line. Two of the three groups of temporary piers are located on both sides of the existing road to be crossed, and the other one is set between the temporary pier corresponding to the jacking direction of the steel box girder to be crossed and the constructed bridge deck.

Citation Information

Cited By

  • Construction method of large-span and large-height-difference steel box girder pushing system

    CN119663749A

  • Sectional hoisting structure of special-shaped bridge steel box girder and construction method thereof

    CN120625494A