Construction operation method for anti-floating anchor node

By adopting multi-layered waterproof construction methods on the anti-floating anchor nodes, including base layer cleaning, cement-based permeability crystallization, sealing paste and rubber asphalt waterproof coating, a solid waterproof layer is formed, which solves the problem of poor waterproofing effect in the existing technology. , significantly improves the waterproof performance and durability of the anti-floating anchor rod.

CN118997140APending Publication Date: 2024-11-22SHANDONG QISE NEW MATERIAL TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411229531.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-03
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The existing waterproof construction methods of anti-floating anchors have poor results and are difficult to effectively prevent underground structures from floating due to water or soil buoyancy, affecting the stability and safety of the structure.

Method used

Multi-layered waterproof construction methods are adopted, including base cleaning, cement-based permeability crystallization, sealing paste, water-expansion water-stop ring strips and multi-channel fast-gel rubber asphalt waterproof coating spraying to form a solid waterproof layer to prevent water penetration.

Benefits of technology

Through the combination of multi-layer and materials, the waterproof performance and durability of the anti-floating anchor nodes are significantly improved, ensuring the stability and safety of the structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997140A_ABST
    Figure CN118997140A_ABST
Patent Text Reader

Abstract

The invention discloses an anti-floating anchor rod node construction operation method. The construction method comprises the following operation steps that a pit face formed around a steel bar in the center of a current anti-floating anchor rod node is filled with flexible filler blocks; the pile head of the current anti-floating anchor node serves as the center, and the area within the preset outer side radius range is coated with cement-based permeable crystallization for 2-3 times to form a cement-based permeable crystallization layer; sealing treatment is conducted on the cement-based capillary crystalline layer foundation at the root of the steel bar at the pile head of the current anti-floating anchor rod joint through sealing paste, and a sealing paste layer is obtained; a sealing paste layer foundation formed on the surface of the root of a reinforcing steel bar at the pile head of the current anti-floating anchor rod node is provided with a water-swelling water-stopping ring strip; with the pile head of the current anti-floating anchor node as the center and in the area within the preset outer side radius range, rubber asphalt waterproof paint is constructed and brushed to serve as an additional layer; and carrying out at least two spraying construction treatments of the quick-setting rubber asphalt waterproof paint. According to the method, water permeation can be effectively prevented, the good waterproof effect is achieved, and the waterproof performance and durability of the anti-floating anchor rod joint are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of anti-floating anchor node construction, and in particular to an anti-floating anchor node construction operation method. Background Art

[0002] Anti-floating anchor is a structural support technology used in civil engineering and construction. It is mainly used to avoid or reduce the floating phenomenon of underground structures (such as basements, tunnels, tunnels, etc.) under water or in the soil due to buoyancy.

[0003] When an underground structure is located above the groundwater table or there is moisture in the surrounding soil, the bottom of the structure may be subject to buoyancy from the water or soil, causing the structure to float in whole or in part. This can pose a serious threat to the stability and safety of the structure. The role of anti-floating anchors is to resist the effects of buoyancy by setting anchors at the bottom of the structure to connect the structure to the deeper strata or rock below. These anchors are usually made of high-strength materials such as reinforced concrete or steel. They are fixed to the bottom of the structure and transmit the force generated by buoyancy through anchor points buried deep in the ground.

[0004] The design of anti-floating anchors needs to consider many factors, including groundwater level, mechanical properties of soil, weight of structure, number and arrangement of anchors, etc. Through reasonable design and construction, anti-floating anchors can effectively prevent the floating of underground structures and ensure the stability and safety of the structures.

[0005] Research has found that in waterproofing construction, when encountering anti-floating anchor rods, the waterproofing treatment of the anchor rod details and other positions becomes a key position in the entire waterproofing construction; its treatment results will directly affect the success or failure of the entire waterproofing construction; the current existing technology adopts the method of directly spraying waterproof coating, but this construction method has poor waterproofing effect. Summary of the invention

[0006] To achieve the above object, the technical solution adopted by the present invention is:

[0007] The present invention provides an anti-floating anchor node construction method for waterproofing the anti-floating anchor node, and the construction method comprises the following steps:

[0008] Base cleaning: Use cleaning tools to clean the base surface formed by the cushion layer around the current anti-floating anchor node to obtain a flat base surface; use flexible filler blocks to fill the pit surface formed around the steel bars at the center of the current anti-floating anchor node;

[0009] Cement-based penetrating crystallization construction: Apply cement-based penetrating crystallization 2-3 times to the area centered on the pile head of the current anti-floating anchor node and within the preset outer radius to form a cement-based penetrating crystallization layer;

[0010] Sealing paste construction: sealing the cement-based permeable crystal layer at the root of the steel bar at the pile head of the current anti-floating anchor node with a sealing paste to obtain a sealing paste layer;

[0011] Construction of water-swelling water-stop ring strips: Water-swelling water-stop ring strips are installed on the basis of the sealing paste layer formed on the root surface of the steel bars at the pile head of the current anti-floating anchor node;

[0012] Construction of additional layer: Rubber asphalt waterproof coating is applied as additional layer in the area centered on the pile head of the current anti-floating anchor node and within the preset outer radius;

[0013] Apply at least two coats of quick-setting rubber asphalt waterproof coating by spraying.

[0014] Preferably, as an implementable method; the quick-setting liquid rubber waterproof and anti-seepage coating comprises two components, namely, agent A and agent B; wherein, agent A is a spray-coated quick-setting liquid rubber waterproof and anti-seepage material emulsion, which is composed of anionic rubber latex and emulsified asphalt; wherein the rubber latex contains chloroprene latex, styrene butadiene latex or carboxylated styrene butadiene latex, and all are water-based spray materials; agent B is a curing agent, which is an aqueous solution with a concentration of 3.0% to 20.0% prepared from a metal salt electrolyte.

[0015] Preferably, as an implementable embodiment, the preset outer radius is 250mm-280mm.

[0016] Preferably, as an implementable method, during the cement-based infiltration crystallization construction process, the total thickness of the cement-based infiltration crystallization layer formed is not less than 1 mm, and the dosage is not less than 1.5 kg / ㎡.

[0017] Preferably, as an implementable method, the implementation of at least two spraying construction processes of quick-setting rubber asphalt waterproof coatings is specifically the spraying construction process of quick-setting rubber asphalt waterproof coatings;

[0018] Implement the first waterproof spraying construction: spray quick-setting rubber asphalt waterproof coating construction treatment, where the thickness of the first waterproof coating is 1.5mm;

[0019] Implement the second waterproof spray construction: after the first layer of waterproof coating is dry, spray the quick-setting rubber asphalt waterproof coating, and the second layer is 2.5mm thick.

[0020] Preferably, as an implementable embodiment, the cushion layer is a concrete cushion layer.

[0021] Preferably, as an implementable method, after the step of implementing at least two spraying construction treatments of quick-setting rubber asphalt waterproof coating, it also includes constructing a concrete layer on the basis of the waterproof coating.

[0022] Preferably, as an implementable method; in the construction of the concrete layer, a fine stone concrete protective layer is constructed on the basis of the waterproof coating; and then a reinforced concrete structural layer is constructed on the basis of the fine stone concrete protective layer.

[0023] Preferably, as an implementable embodiment, the flexible filler block comprises a mixed plastic particle block of polyethylene, polypropylene, polycarbonate and polyetheretherketone.

[0024] The beneficial effects of the present invention are:

[0025] Analysis of the main methods of the above-mentioned anti-floating anchor node construction method shows that: an anti-floating anchor node construction method specifically includes: base cleaning: using a cleaning tool to clean the base surface formed by the surrounding cushion layer of the current anti-floating anchor node to obtain a flat base surface; using a flexible filler block to fill the pit surface formed around the steel bar at the center of the current anti-floating anchor node; cement-based penetration crystallization construction: brushing cement-based penetration crystallization 2-3 times on the area centered on the pile head of the current anti-floating anchor node and within a preset outer radius to form a cement-based penetration crystallization layer;

[0026] Sealing paste construction: sealing the cement-based permeable crystal layer at the root of the steel bar at the pile head of the current anti-floating anchor node with a sealing paste to obtain a sealing paste layer; water-expandable water-stop ring construction: setting a water-expandable water-stop ring on the basis of the sealing paste layer formed on the root surface of the steel bar at the pile head of the current anti-floating anchor node;

[0027] Construction of additional layer: Apply rubber asphalt waterproof coating as an additional layer in the area centered on the pile head of the current anti-floating anchor node and within the preset outer radius; implement at least two coats of spraying construction of quick-setting rubber asphalt waterproof coating.

[0028] The technical effect of the above anti-floating anchor node construction method is mainly reflected in the waterproof construction. Among them, by cleaning the base surface and filling the flexible filler blocks, the base surface is ensured to be flat and the adhesion of the waterproof layer is increased.

[0029] During the construction of cement-based penetrating crystallization, a solid waterproof layer is formed by applying the cement-based penetrating crystallization layer. The cement-based penetrating crystallization layer can penetrate into the base surface, fill the pores, and form crystals with the base surface, thereby increasing the waterproof effect.

[0030] When applying the sealant: on the basis of the cement-based permeable crystal layer, the sealant is used for sealing. The sealant can fill the gap between the cement permeable crystal layer and the root of the steel bar, forming a continuous sealing layer and improving the waterproof performance.

[0031] A water-swellable water-stop ring strip is arranged on the sealing paste layer. This ring strip can swell when it contacts water source, forming a physical barrier, effectively preventing water penetration and improving waterproof performance.

[0032] Apply rubber asphalt waterproof coating as an additional layer on the waterproof layer. Rubber asphalt waterproof coating has excellent waterproof performance and durability, which can further enhance the overall waterproof effect.

[0033] Finally, multiple coats of quick-setting rubber asphalt waterproof coating are sprayed: by spraying multiple coats of quick-setting rubber asphalt waterproof coating, the thickness and uniformity of the waterproof layer are increased, and the reliability of waterproofing is improved.

[0034] In summary, this waterproof construction method can effectively prevent water penetration through the combined use of multiple layers and materials, achieve good waterproof effects, and improve the waterproof performance and durability of anti-floating anchor nodes. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 It is a process flow chart of the anti-floating anchor node construction method in an embodiment of the present invention;

[0036] Figure 2 It is a schematic diagram of the waterproof effect of the anti-floating anchor node in an embodiment of the present invention.

[0037] Anti-floating anchor node A; cushion layer B; bottom plate C; cement-based permeable crystal layer 10; additional layer 20; sealing paste layer 30; coating formed by spraying quick-setting rubber asphalt waterproof coating 40; fine stone concrete protective layer 50 and reinforced concrete structural layer 60; water-expanding water-stop ring 70 DETAILED DESCRIPTION

[0038] The present invention will be further described below in conjunction with the accompanying drawings.

[0039] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods. It should be understood that the specific implementation methods described herein are only used to explain the present invention and are not used to limit the present invention.

[0040] Embodiment 1

[0041] See also Figure 1The first embodiment of the present invention provides a method for anti-floating anchor node construction, which is used to perform waterproof construction on the anti-floating anchor node. The construction method includes the following steps:

[0042] S10, base cleaning: use a cleaning tool to clean the base surface formed by the cushion layer around the current anti-floating anchor node to obtain a flat base surface; use flexible filler blocks to fill the pit surface formed around the steel bars at the center position of the current anti-floating anchor node (note that the steel bars of the anchor are installed at the center position);

[0043] S20, cement-based penetration crystallization construction: the area with the pile head (or anchor) of the current anti-floating anchor node as the center and within the preset outer radius of 250mm (with the anchor as the center) (this area includes the center position and the cushion layer around the current anti-floating anchor node) is painted with cement-based penetration crystallization 2-3 times to form a cement-based penetration crystallization layer;

[0044] S30, sealing paste construction: using sealing paste to seal the cement-based permeable crystal layer at the root of the steel bar at the pile head of the current anti-floating anchor node to obtain a sealing paste layer;

[0045] S40, water-swelling water-stop ring construction: a water-swelling water-stop ring is installed on the basis of the sealing paste layer formed on the root surface of the steel bar at the pile head of the current anti-floating anchor node;

[0046] S50, construction of additional layer: the rubber asphalt waterproof coating is applied as an additional layer in the area with the pile head (or anchor) of the current anti-floating anchor node as the center and within the preset outer radius of 250mm (with the anchor as the center) (the additional layer can be applied by spraying or hand brushing);

[0047] S60. Apply at least two coats of quick-setting rubber asphalt waterproof coating by spraying.

[0048] The present invention provides an anti-floating anchor node construction method, and its main construction process can be summarized as follows: base cleaning → cement-based penetration crystallization construction → sealing paste construction → water-expanding water-stop ring construction → additional layer construction → first waterproof spray construction → second waterproof spray construction → protective layer construction.

[0049] S10, base cleaning: use a cleaning tool to clean the base surface formed by the cushion layer around the current anti-floating anchor node to obtain a flat base surface; use flexible filler blocks to fill the pit surface formed around the steel bars at the center position of the current anti-floating anchor node (note that the steel bars of the anchor are installed at the center position);

[0050] S20, cement-based penetration crystallization construction: the area with the pile head (or anchor) of the current anti-floating anchor node as the center and the outer radius of 250mm (with the anchor as the center) (this area includes the center position and the cushion layer around the current anti-floating anchor node) is painted with cement-based penetration crystallization 2-3 times to form a cement-based penetration crystallization layer, and the total thickness of the cement-based penetration crystallization layer is not less than 1mm, and the amount is not less than 1.5kg / ㎡;

[0051] S30, sealing paste construction: using sealing paste to seal the cement-based permeable crystal layer at the root of the steel bar at the pile head of the current anti-floating anchor node to obtain a sealing paste layer;

[0052] S40, water-swelling water-stop ring construction: a water-swelling water-stop ring is installed on the basis of the sealing paste layer formed on the root surface of the steel bar at the pile head of the current anti-floating anchor node;

[0053] S50, construction of additional layer: the rubber asphalt waterproof coating is applied as an additional layer in the area with the pile head (or anchor) of the current anti-floating anchor node as the center and the outer radius of 250mm (with the anchor as the center) (the additional layer can be sprayed or brushed);

[0054] S60. Apply at least two coats of quick-setting rubber asphalt waterproof coating by spraying.

[0055] Implement at least two coats of quick-setting rubber asphalt waterproof coating spraying treatment, including the first waterproof spraying construction: spray quick-setting rubber asphalt waterproof coating with a thickness of 1.5mm, ensure the thickness is uniform, and use the needle puncture method or sampling inspection; the second waterproof spraying construction: spray quick-setting rubber asphalt waterproof coating with a thickness of 1.5mm, ensure the thickness is uniform, and use the needle puncture method or sampling inspection; the next process: after the waterproof layer is accepted, the next process is carried out.

[0056] Analysis of the main methods of the above-mentioned anti-floating anchor node construction method shows that: an anti-floating anchor node construction method, see Figure 2 ; Figure 2 It is a schematic diagram of the waterproof effect of the anti-floating anchor node in the embodiment of the present invention; the technical effect of the above-mentioned anti-floating anchor node construction method is mainly reflected in the waterproof construction. Figure 2 The following structure is schematically shown, including anti-floating anchor node A, cushion layer B and bottom plate C; the layer structure between cushion layer B and bottom plate C is a waterproof layer structure; the waterproof layer structure includes a cement-based permeable crystal layer 10, an additional layer 20, a sealing paste layer 30, a coating layer 40 formed by spraying a quick-setting rubber asphalt waterproof coating, a fine stone concrete protective layer 50, a reinforced concrete structural layer 60, and a water-expandable water-stop ring strip 70;

[0057] Among them, by cleaning the base surface and filling the flexible filler blocks, the base surface is ensured to be flat and the adhesion of the waterproof layer is increased.

[0058] During the construction of cement-based penetrating crystallization, a solid waterproof layer is formed by applying the cement-based penetrating crystallization layer. The cement-based penetrating crystallization layer can penetrate into the base surface, fill the pores, and form crystals with the base surface, thereby increasing the waterproof effect.

[0059] When applying the sealant: on the basis of the cement-based permeable crystal layer, the sealant is used for sealing. The sealant can fill the gap between the cement permeable crystal layer and the root of the steel bar, forming a continuous sealing layer and improving the waterproof performance.

[0060] A water-swellable water-stop ring strip is arranged on the sealing paste layer. This ring strip can swell when it contacts water source, forming a physical barrier, effectively preventing water penetration and improving waterproof performance.

[0061] Apply rubber asphalt waterproof coating as an additional layer on the waterproof layer. Rubber asphalt waterproof coating has excellent waterproof performance and durability, which can further enhance the overall waterproof effect.

[0062] Finally, multiple coats of quick-setting rubber asphalt waterproof coating are sprayed: by spraying multiple coats of quick-setting rubber asphalt waterproof coating, the thickness and uniformity of the waterproof layer are increased, and the reliability of waterproofing is improved.

[0063] In summary, this waterproof construction method can effectively prevent water penetration through the combined use of multiple layers and materials, achieve good waterproof effects, and improve the waterproof performance and durability of anti-floating anchor nodes.

[0064] Preferably, as an implementable method; the quick-setting liquid rubber waterproof and anti-seepage coating comprises two components, namely, agent A and agent B; wherein, agent A is a spray-coated quick-setting liquid rubber waterproof and anti-seepage material emulsion, which is composed of anionic rubber latex and emulsified asphalt; wherein the rubber latex contains chloroprene latex, styrene butadiene latex or carboxylated styrene butadiene latex, and all are water-based spray materials; agent B is a curing agent, which is an aqueous solution with a concentration of 3.0% to 20.0% prepared from a metal salt electrolyte.

[0065] Preferably, as an implementable embodiment, the preset outer radius is 250mm-280mm.

[0066] Preferably, as an implementable method, during the cement-based infiltration crystallization construction process, the total thickness of the cement-based infiltration crystallization layer formed is not less than 1 mm, and the dosage is not less than 1.5 kg / ㎡.

[0067] Analysis of the above technical solutions shows that: Research suggests that the total thickness of the cement-based permeable crystal layer is not less than 1mm: By ensuring that the total thickness of the cement-based permeable crystal layer is not less than 1mm, sufficient thickness can be provided to increase the durability and waterproof effect of the waterproof layer. A larger thickness can better resist water pressure and prevent water penetration. At the same time, the amount of cement-based permeable crystal layer is not less than 1.5kg / ㎡: Using sufficient cement-based permeable crystal material, not less than 1.5kg per square meter, can ensure full coverage and penetration of the base surface, fill the pores and form crystals. This can increase the firmness and stability of the waterproof layer and improve the reliability of the waterproof effect.

[0068] In summary, by ensuring that the total thickness of the cement-based permeable crystal layer is not less than 1 mm and using a material dosage of not less than 1.5 kg / ㎡, the above scheme can provide sufficient thickness and material coverage to enhance the performance and durability of the waterproof layer and effectively improve the waterproof effect of the anti-floating anchor node.

[0069] Preferably, as an implementable method, the implementation of at least two spraying construction processes of quick-setting rubber asphalt waterproof coatings is specifically the spraying construction process of quick-setting rubber asphalt waterproof coatings;

[0070] Implement the first waterproof spraying construction: spray quick-setting rubber asphalt waterproof coating construction treatment, where the thickness of the first waterproof coating is 1.5mm;

[0071] Implement the second waterproof spray construction: after the first layer of waterproof coating is dry, spray the quick-setting rubber asphalt waterproof coating, and the second layer is 2.5mm thick.

[0072] Analysis of the above technical solution shows that after the first layer of waterproof coating is dry, the second layer of waterproof spraying is carried out. The same quick-setting rubber asphalt waterproof coating is used for spraying and the thickness of the second layer of waterproof coating is ensured to be 2.5mm, which is slightly thicker than the first layer, but not too much. This can further increase the thickness and uniformity of the waterproof layer and improve the overall waterproof performance.

[0073] In summary, by implementing at least two spraying construction treatments of quick-setting rubber asphalt waterproof coatings, in which the thickness of the first waterproof coating is 1.5 mm and the thickness of the second waterproof coating is also 2.5 mm, the above scheme can provide sufficient waterproof layer thickness and uniformity, and effectively enhance the waterproof effect and durability of the anti-floating anchor node.

[0074] Preferably, as an implementable embodiment, the cushion layer is a concrete cushion layer.

[0075] Preferably, as an implementation method, after step S60, the method further includes constructing a concrete layer on the waterproof coating. The concrete layer is constructed by constructing a fine stone concrete protective layer on the waterproof coating, and then constructing a reinforced concrete structural layer on the fine stone concrete protective layer.

[0076] After step S60, a concrete layer is constructed. This step can provide additional protection and reinforcement for the structure, while increasing the overall stability and durability. A fine stone concrete protective layer is constructed on the basis of the waterproof coating. The fine stone concrete layer can provide better compression and wear resistance, while protecting the waterproof layer from external physical damage and extending the service life of the waterproof layer.

[0077] The reinforced concrete structure layer is constructed on the basis of the fine stone concrete protective layer. This layer can provide higher strength and structural support, and increase the overall stability and bearing capacity.

[0078] Preferably, as an implementable embodiment, the flexible filler block comprises a mixed plastic particle block of polyethylene, polypropylene, polycarbonate and polyetheretherketone.

[0079] In the above technical solution, the flexible filler block includes a mixed plastic particle block of polyethylene, polypropylene, polycarbonate and polyetheretherketone. This filler has the characteristics of softness and durability, can fill the pit surface around the steel bar, and provide better filling effect and waterproof performance.

[0080] In summary, by constructing a concrete layer, a fine stone concrete protective layer and a reinforced concrete structural layer on the basis of a waterproof coating, and using flexible filler blocks, the above scheme can provide better structural protection, strength support and waterproofing effects, and improve the overall performance and durability of the anti-floating anchor node.

[0081] It should be noted that the pile head of the anti-floating anchor is usually located at the bottom of the underground structure. The pile head refers to the end of the anchor, which transmits the force generated by buoyancy by fixing it to the anchor point at the bottom of the structure. Specifically, the pile head of the anti-floating anchor node is generally located at the foundation part of the underground structure and connected to the bottom plate or bottom beam of the structure. In this way, the anchor can be connected to the deeper strata or rocks underground through the pile head to resist the buoyancy generated by groundwater or soil.

[0082] The above description is only used to illustrate the technical solution of the present invention rather than to limit it. Other modifications or equivalent substitutions made to the technical solution of the present invention by ordinary technicians in this field should be included in the scope of the claims of the present invention as long as they do not depart from the spirit and scope of the technical solution of the present invention.

Claims

1. A method for construction of an anti-floating anchor node, characterized in that: It is used to waterproof the floating anchor node, and the construction method includes the following steps: Base cleaning: Use cleaning tools to clean the base surface formed by the cushion layer around the current anti-floating anchor node to obtain a flat base surface; use flexible filler blocks to fill the pit surface formed around the steel bars at the center of the current anti-floating anchor node; Cement-based penetrating crystallization construction: Apply cement-based penetrating crystallization 2-3 times to the area centered on the pile head of the current anti-floating anchor node and within the preset outer radius to form a cement-based penetrating crystallization layer; Sealing paste construction: sealing the cement-based permeable crystal layer at the root of the steel bar at the pile head of the current anti-floating anchor node with a sealing paste to obtain a sealing paste layer; Construction of water-swelling water-stop ring strips: Water-swelling water-stop ring strips are installed on the basis of the sealing paste layer formed on the root surface of the steel bars at the pile head of the current anti-floating anchor node; Construction of additional layer: Rubber asphalt waterproof coating is applied as additional layer in the area centered on the pile head of the current anti-floating anchor node and within the preset outer radius; Apply at least two coats of quick-setting rubber asphalt waterproof coating by spraying.

2. The anti-floating anchor node construction method according to claim 1 is characterized by: The quick-setting liquid rubber waterproof and anti-seepage coating comprises two components, namely, agent A and agent B; wherein, agent A is a spray-coated quick-setting liquid rubber waterproof and anti-seepage material emulsion, which is composed of anionic rubber latex and emulsified asphalt; wherein the rubber latex comprises chloroprene latex, styrene butadiene latex or carboxylated styrene butadiene latex, and all are water-based spray materials; agent B is a curing agent, which is an aqueous solution with a concentration of 3.0% to 20.0% prepared from a metal salt electrolyte.

3. The anti-floating anchor node construction method according to claim 1 is characterized by: The preset outer radius is 250mm-280mm.

4. The anti-floating anchor node construction method according to claim 1 is characterized by: During the cement-based penetration crystallization construction process, the total thickness of the cement-based penetration crystallization layer formed is not less than 1 mm, and the dosage is not less than 1.5 kg / ㎡.

5. The anti-floating anchor node construction method according to claim 1 is characterized by: The at least two spraying construction processes of the quick-setting rubber asphalt waterproof coating are specifically the spraying construction processes of the quick-setting rubber asphalt waterproof coating; Implement the first waterproof spraying construction: spray quick-setting rubber asphalt waterproof coating construction treatment, where the thickness of the first waterproof coating is 1.5mm; Implement the second waterproof spray construction: after the first layer of waterproof coating is dry, spray the quick-setting rubber asphalt waterproof coating, and the second layer is 2.5mm thick.

6. The anti-floating anchor node construction method according to claim 5 is characterized by: The cushion layer is a concrete cushion layer.

7. The anti-floating anchor node construction method according to claim 6 is characterized by: After the step of implementing at least two spraying construction treatments of the quick-setting rubber asphalt waterproof coating, the method also includes constructing a concrete layer on the basis of the waterproof coating.

8. The anti-floating anchor node construction method according to claim 7 is characterized by: The concrete layer is constructed, and a fine stone concrete protective layer is constructed on the basis of the waterproof coating; and then a reinforced concrete structural layer is constructed on the basis of the fine stone concrete protective layer.

9. The anti-floating anchor node construction method according to claim 1, characterized in that: The flexible filling block comprises a mixed plastic particle block of polyethylene, polypropylene, polycarbonate and polyetheretherketone.