Support construction process of integrated transverse strake

Through the combined process of integrated horizontal plate and adjustable horizontal support, the vibration, noise and space problems in the traditional support process are solved, safe, low noise and low vibration construction is achieved, adapting to grooves of different widths, and reducing construction Cost and space requirements.

CN118997180AInactive Publication Date: 2024-11-22CEEC ANHUI ELECTRICAL POWER CONSTR NO 1 CO
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411222384.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-02
Publication Date
2024-11-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The traditional steel sheet pile support process has high vibration, high noise, and large space requirements, which block traffic and affect the lives of surrounding residents. It is difficult for the existing technology to effectively solve these problems.

Method used

Adopt the supporting construction process of integrated cross-column boards, the prefabricated cross-column board body and adjustable cross-column assembly are lifted and assembled by lifting equipment to reduce vibration and noise, and the cross-column and slide are fixed by bolts to achieve Close fit to reduce construction space requirements.

Benefits of technology

It effectively reduces vibration and noise during construction, solves the construction space problem, provides safety guarantees for workers, reduces the manufacturing cost of the device, adapts to grooves of different widths, and meets the goal of reducing noise, vibration and space requirements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997180A_ABST
    Figure CN118997180A_ABST
Patent Text Reader

Abstract

The invention discloses a support construction process of an integrated transverse strake, and relates to the technical field of civil engineering and underground engineering, corresponding composition materials of a transverse strake body and a transverse support are customized according to the depth of a groove, after customization, parts are processed firstly, then the transverse strake is pre-assembled, namely, the transverse strake body and the transverse support are pre-assembled, and the transverse strake body and the transverse support are pre-assembled. And then the integrated transverse plate assembly is conveyed to the open space around the groove to be supported and placed within the hoisting radius range of hoisting equipment, the transverse plates are assembled while surveying, setting out and excavating are conducted on the boundary of the groove, the pre-assembled transverse plates are placed in the groove through the hoisting equipment and then installed, and operation can be conducted after installation is completed. Under the condition that vibration, noise and the like are reduced, the problem of construction space is solved, and the problems that in the prior art, a traditional supporting technology is large in vibration, large in noise or large in road space requirement, traffic is blocked, and life of surrounding residents is affected are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of civil engineering and underground engineering, and in particular to a support construction process of an integrated transverse plate. Background Art

[0002] With the development of the city, the status quo of the original underground rainwater and sewage pipe network can no longer meet the needs, and the rainwater and sewage pipe network renovation project came into being. It is necessary to use it during the construction of the renovation project, and support components need to be installed to reduce the risk of soil collapse and ensure the safety of personnel when working in the trench. The traditional steel sheet pile support process has the disadvantages of large vibration, high noise, and large space required. The traditional slope support process requires large road space, blocks traffic, and affects the lives of surrounding residents. In view of the current situation, it is necessary to design a new process that can solve the problem of construction space while reducing vibration, noise, etc. Summary of the invention

[0003] The present invention aims to solve at least one of the technical problems existing in the prior art. To this end, the present invention proposes a support construction process for an integrated horizontal plate, which solves the problems of large vibration, large noise, large road space requirements, traffic obstruction, and impact on the lives of surrounding residents in the traditional support process in the prior art.

[0004] To achieve the above object, the present invention proposes a support construction process for an integrated transverse plate, the support construction process for an integrated transverse plate being characterized by comprising the following steps:

[0005] Step 1: Construction preparation: Customize the materials of the corresponding horizontal plate body and horizontal brace according to the depth of the groove. The horizontal plate body includes several horizontal edges, retaining plates, vertical edges, boot plates, steel bars, inclined ribs and slideways. The horizontal brace includes steel pipes and screw rods. Nuts with the same diameter are welded on both sides of the steel pipes.

[0006] Step 2: Pre-installation of the transverse plate body: A group of transverse plate bodies are provided. First, fix the bottom transverse edging, then fix a retaining plate on the bottom transverse edging, then fix the vertical edging on both sides of the retaining plate, fix several retaining plates between the two vertical edgings, then fix a transverse edging on the top retaining plate; then fix the steel bars vertically on both sides of the retaining plate, then fix the inclined ribs at the connection between the transverse edging and the vertical edging to increase the bearing capacity of the supporting retaining plate, finally fix a pair of slideways on the two vertical edgings, and set several threaded holes at equal distances on both sides of the slideways;

[0007] Pre-installation of cross brace: The cross brace includes a steel pipe, and screw rods with equal pitch but opposite threads are threadedly connected on both sides of the steel pipe. A limit hole is opened in the middle of the steel pipe, and a threaded hole is opened at the end of the screw rod away from the steel pipe to match the threaded hole opened on the slideway;

[0008] Step 3: Assembly and installation of transverse plate: transport the integrated transverse plate assembly to the open space around the trench to be supported and place it within the lifting radius of the lifting equipment; measure, lay out and excavate the trench boundary according to the construction drawings; assemble the transverse plates simultaneously during trench excavation; adjust the length of the cross brace according to the actual width of the trench, and set the cross brace between the slideways of the two transverse plate bodies. There are four cross braces, which are symmetrically set between a pair of transverse plate bodies; place the assembled transverse plate directly into the trench through the lifting equipment, adjust a group of transverse plate bodies to make them in an upright state, rotate the steel pipes to make the transverse plate bodies on both sides fit with the soil on both sides respectively, and use bolts to fix the cross brace and the slideway;

[0009] Step 4: Removal of the transverse plates: After the trenching operation is completed, rotate the steel pipe in the opposite direction so that a pair of transverse plates are separated from the soil and tightly abutted against it, and start the lifting equipment to lift out the transverse plates; then carry out subsequent trench backfilling, ground restoration and other work.

[0010] As a further solution of the present invention: the diameter of the steel pipe is 89 mm, the wall thickness is 5 mm, nuts with the same diameter are welded on both sides of the steel pipe, and the nuts are provided with 80 mm internal threads to be connected with the screw rod.

[0011] As a further solution of the present invention: the screw rod adopts round steel with a diameter of 80 mm, and a thread pattern is provided on the outside of the round steel, and the threading directions of the screw rods at both ends are opposite.

[0012] As a further solution of the present invention: the slideway is made of rectangular steel with a length of 2m, a width of 80mm, a height of 60mm and a wall thickness of 5mm, and threaded holes are evenly opened therein.

[0013] As a further solution of the present invention: the installation nodes of the transverse plate body are fixedly connected by bolts.

[0014] As a further solution of the present invention: a limiting hole is opened in the middle of the steel pipe.

[0015] As a further solution of the present invention: a pair of lifting rings are fixedly and symmetrically installed on the transverse edges of the transverse plate body, and the lifting equipment puts the assembled transverse plate into the groove through the lifting rings.

[0016] Compared with the prior art, the present invention has the following beneficial effects:

[0017] 1. By adopting the method of integrated transverse plate bodies and assembled cross braces, after the trench excavation is completed, the method of hoisting the assembled transverse plates with lifting equipment can reduce vibration and noise while solving the problem of construction space. At the same time, through the prefabricated assembly method, after the device is hoisted into the trench, only one set of transverse plate bodies needs to be adjusted to be in an upright state. By rotating the steel pipe, the transverse plate bodies on both sides are respectively fitted with the soil on both sides. The cross braces and the slides are fixedly installed by bolts, providing safety protection for workers working in the trench. In addition, this application has been applied in multiple engineering practices to meet the purpose of reducing construction noise, construction vibration, reducing construction space requirements, and ensuring the safety of workers.

[0018] 2. For grooves of different widths, the length of the cross brace can be adjusted appropriately to adapt to the width. For grooves exceeding the adjusted width, only the cross brace assembly needs to be replaced, thus reducing the manufacturing cost of the device. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 is a process flow chart of the present invention;

[0020] Figure 2 The three-dimensional structure of the integrated horizontal plate of the present invention Figure 1 ;

[0021] Figure 3 The three-dimensional structure of the integrated horizontal plate of the present invention Figure 2 ;

[0022] Figure 4 A side view of the integrated strake of the present invention;

[0023] Figure 5 It is a schematic diagram of the installation of the integrated horizontal plate of the present invention;

[0024] Figure 6 For the present invention Figure 3 Enlarged view of point A.

[0025] In the figure: 1. transverse plate body; 2. transverse brace; 3. groove; 4. transverse edging; 5. retaining plate; 6. vertical edging; 7. steel bar; 8. boot plate; 9. slideway; 10. oblique rib; 11. steel pipe; 12. screw rod; 13. limit hole; 14. lifting ring. DETAILED DESCRIPTION

[0026] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0027] like Figure 1-3 As shown, a support construction process for an integrated transverse plate includes the following steps:

[0028] Step 1: Construction preparation: According to the depth, width, soil quality, groundwater and other conditions of the trench 3 of the construction project, design the specifications and models of each component of the integrated horizontal plate; deepen the design drawings through three-dimensional modeling, and purchase the materials required for the integrated horizontal plate.

[0029] The sizes of the integrated transverse plates can be roughly divided into two types, 2.5m*3m or 3m*3m. In this embodiment, 3m*3m is used. According to the depth of the groove 3, a corresponding number of transverse edgings 4, retaining plates 5, vertical edgings 6, boot plates 8, steel bars 7, diagonal ribs and slideways 9 can be customized.

[0030] The cross brace 2 of the integrated cross plate adopts a steel pipe 11 with a diameter of 89 mm and a wall thickness of 5 mm. Nuts of the same diameter are welded on both sides of the steel pipe 11. The nuts are provided with an 80 mm internal thread to connect with the screw rod 12, and a hole with a diameter of 20 mm is opened at the center of the steel pipe 11 to facilitate later construction.

[0031] The integrated horizontal plate screw rod 12 is made of round steel with a diameter of 80 mm, and a thread pattern is opened on the outside of the round steel. The threading directions of the screw rods 12 at both ends are opposite. If the directions are the same, the horizontal brace 2 will not be centered when tightened later.

[0032] The integrated transverse inner slideway 9 is made of rectangular steel with a length of 2m, a width of 80mm, a height of 60mm and a wall thickness of 5mm, and threaded holes are evenly provided therein.

[0033] Step 2: Pre-installation of the transverse plate body 1: The transverse plate body 1 is provided with a group, first fix the bottom transverse edging 4, then fix a retaining plate 5 on the bottom transverse edging 4, then fix the vertical edging 6 on both sides of the retaining plate 5, fix several retaining plates 5 between the two vertical edgings 6, then fix a transverse edging 4 on the top retaining plate 5; then fix the steel bars 7 vertically on both sides of the retaining plate 5, then fix the inclined ribs at the connection between the transverse edging 4 and the vertical edging 6 to increase the bearing capacity of the supporting retaining plate, finally fix a pair of slideways 9 on the two vertical edgings 6, and set several threaded holes equidistantly on both sides of the slideways 9, thus completing the installation of the transverse plate body 1 on one side, and each installation node is fixedly connected by bolts; follow the same steps to complete the installation of the transverse plate body 1 on the other side.

[0034] Pre-installation of the cross brace 2: The cross brace 2 includes a steel pipe 11, and screw rods 12 with equal pitches but opposite threads are threadedly connected on both sides of the steel pipe 11. A limiting hole 13 is opened in the middle of the steel pipe 11, and a threaded hole is opened at one end of the screw rod 12 away from the steel pipe 11, which matches the threaded hole opened on the slideway 9.

[0035] Step 3: Assembly and installation of transverse plate: transport the integrated transverse plate assembly to the open space around the trench 3 to be supported and place it within the lifting radius of the lifting equipment. According to the construction drawings, measure, lay out and excavate the boundary of the trench 3. During the excavation of the trench 3, assemble the transverse plates simultaneously. Adjust the length of the cross brace 2 according to the actual width of the trench 3, and set the cross brace 2 between the slideways 9 of the two transverse plate bodies 1. There are four cross braces 2, which are symmetrically set between a pair of transverse plate bodies 1. A pair of lifting rings 14 are fixedly and symmetrically installed on the transverse edging 4 of the transverse plate body 1. The lifting equipment directly places the assembled transverse plate into the trench 3 through the lifting rings 14, adjusts a group of transverse plate bodies 1 to be in an upright state, and by rotating the steel pipe 11, the transverse plate bodies 1 on both sides are respectively fitted with the soil on both sides, and the cross brace 2 and the slideway 9 are fixedly installed by bolts. By inserting the tool into the limit hole 13 on the steel pipe 11, the rotation tool facilitates the rotation of the steel pipe 11.

[0036] After the assembly of the horizontal plates is completed, the workers can go down to the groove 3 to work.

[0037] Step 4: Removal of the horizontal plate: After the trench 3 operation is completed, the steel pipe 11 is rotated in the opposite direction to separate the pair of horizontal plate bodies 1 from the soil body and start the lifting equipment to lift the horizontal plate out. Then, the trench 3 is backfilled and the ground is restored.

[0038] Working principle:

[0039] By adopting the method of integrated horizontal plate body 1 and assembled horizontal brace 2, after the trench 3 is excavated, the method of hoisting the assembled horizontal plate with lifting equipment can solve the problem of construction space while reducing vibration, noise, etc. At the same time, the prefabricated assembly method only needs to adjust one set of horizontal plate body 1 after the device is hoisted into the trench 3, so that it is in an upright state, and by rotating the steel pipe 11, the horizontal plate body 1 on both sides is respectively fitted with the soil on both sides, and the horizontal brace 2 and the slide 9 are fixedly installed by bolts, providing a safety guarantee for the workers working in the lower trench 3. Through multiple engineering practice applications, the purpose of reducing construction noise, construction vibration, reducing construction space requirements, and ensuring the safety of workers is met.

[0040] In the description of the present invention, it should be understood that the terms "upper", "lower", "left", "right", etc. indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, and a specific direction structure and operation, and therefore, cannot be understood as a limitation on the present invention. In addition, "first" and "second" are only for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise specified, "multiple" means two or more.

[0041] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", etc. should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0042] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. A support construction process for an integrated horizontal plate, characterized in that: The following steps are involved: Step 1: Construction preparation: The materials of the corresponding transverse plate body (1) and the transverse brace (2) are customized according to the depth of the groove (3). The transverse plate body (1) includes a plurality of transverse edges (4), a retaining plate (5), a vertical edge (6), a boot plate (8), a steel bar (7), an inclined rib (10) and a slideway (9). The transverse brace (2) includes a steel pipe (11) and a screw rod (12). Nuts of the same diameter are welded on both sides of the steel pipe (11); Step 2: Pre-installation of the transverse plate body (1): The transverse plate body (1) is provided with a group, first fixing the bottom transverse edging (4), then fixing a retaining plate (5) on the bottom transverse edging (4), then fixing vertical edging (6) on both sides of the retaining plate (5), fixing a plurality of retaining plates (5) between the two vertical edgings (6), then fixing a transverse edging (4) on the top retaining plate (5); then fixing vertical steel bars (7) on both sides of the retaining plate (5), then fixing an inclined rib (10) at the connection between the transverse edging (4) and the vertical edging (6) to increase the bearing capacity of the retaining plate, finally fixing a pair of slideways (9) on the two vertical edgings (6), and fixing a plurality of threaded holes at equal distances on both sides of the slideways (9); The cross brace (2) is pre-installed: the cross brace (2) comprises a steel pipe (11), screw rods (12) with equal pitch but opposite threads are threadedly connected on both sides of the steel pipe (11), a limiting hole (13) is provided in the middle of the steel pipe (11), and a threaded hole is provided at one end of the screw rod (12) away from the steel pipe (11), which matches the threaded hole provided on the slideway (9); Step 3: Assembling and installing the horizontal plate: transport the integrated horizontal plate assembly to the open space around the trench (3) to be supported and place it within the lifting radius of the lifting equipment; measure, lay out and excavate the boundary of the trench (3) according to the construction drawings; During the excavation of the trench (3), the assembly of the transverse plates is carried out simultaneously; the length of the cross brace (2) is adjusted according to the actual width of the trench (3), and the cross brace (2) is arranged between the slideways (9) of the two transverse plate bodies (1). Four cross braces (2) are arranged, and are symmetrically arranged between a pair of transverse plate bodies (1); the assembled transverse plates are directly placed into the trench (3) by means of a lifting device, and a group of transverse plate bodies (1) are adjusted to be in an upright state, and the transverse plate bodies (1) on both sides are respectively fitted with the soil on both sides by rotating the steel pipe (11), and the cross brace (2) and the slideway (9) are fixedly installed by bolts; Step 4: Removal of the transverse plates: After the trench (3) operation is completed, the steel pipe (11) is rotated in the opposite direction so that a pair of transverse plate bodies (1) are separated from the tight contact with the soil, and the lifting equipment is started to lift out the transverse plates; then subsequent trench (3) backfilling, ground restoration and other work are carried out.

2. The support construction process of the integrated horizontal plate according to claim 1 is characterized in that: The steel pipe (11) has a diameter of 89 mm and a wall thickness of 5 mm. Nuts with the same diameter are welded on both sides of the steel pipe (11). The nuts are provided with 80 mm internal threads to be connected with the screw rod (12).

3. The support construction process of the integrated horizontal plate according to claim 1 is characterized in that: The screw rod (12) is made of round steel with a diameter of 80 mm, and a thread pattern is formed on the outside of the round steel. The thread patterns of the screw rods (12) at both ends are formed in opposite directions.

4. The support construction process of the integrated horizontal plate according to claim 1 is characterized in that: The slideway (9) is made of rectangular steel with a length of 2m, a width of 80mm, a height of 60mm and a wall thickness of 5mm, and threaded holes are evenly provided therein.

5. The support construction process of the integrated horizontal plate according to claim 1 is characterized in that: The installation nodes of the transverse plate body (1) are fixedly connected by bolts.

6. The support construction process of the integrated horizontal plate according to claim 1 is characterized in that: A limiting hole (13) is provided in the middle of the steel pipe (11).

7. The support construction process of the integrated horizontal plate according to claim 1 is characterized in that: A pair of lifting rings (14) are fixedly and symmetrically installed on the transverse edge (4) of the transverse plate body (1), and the lifting equipment puts the assembled transverse plate into the groove (3) through the lifting ring (14).

Citation Information

Patent Citations

  • Box-type groove supporting structure and supporting method

    CN114687362A

  • Trapezoidal groove supporting structure for pipeline construction and construction method thereof

    CN114892680A

  • Novel assembly type supporting tool for pipe network groove

    CN220927885U