Gypsum board wet material anti-blocking stable discharging system

By using scrapers, stirring plates and diverting devices in the wet material discharge system of gypsum board, the problems of blockage and discharge instability caused by changes in wet material moisture are solved, and the stability of wet material flow and production efficiency are improved.

CN119017524APending Publication Date: 2024-11-26CHINA NAT BUILDING MATERIALS TECHCAL INNOVATION & RES INST LIMITED +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411270252.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-11
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

During the gypsum board production process, changes in the moisture content of wet materials lead to clogging and unstable discharge, increasing production costs and labor cleaning needs.

Method used

A gypsum board wet material anti-blocking and stable material discharge system is designed, including scraper and stirring board to prevent wet material from sticking and precipitating, flow detector and PLC controller to adjust the pump body speed, and a shunt device to reduce liquid surface impact. , ensure stable flow of wet materials.

Benefits of technology

Through the use of scraper and stirring plate, wet material adhesion and precipitation are avoided. The flow detector and PLC controller achieve the stability of wet material flow. The diverting device reduces liquid level impact, improves the stability and production of discharge efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119017524A_ABST
    Figure CN119017524A_ABST
Patent Text Reader

Abstract

The invention discloses an anti-blocking stable discharging system for wet gypsum board materials. The anti-blocking stable discharging system comprises a discharging tank, a first pump body, a scraping plate and a stirring plate. The discharging tank is used for containing wet materials and is connected with a discharging head through a first pipeline; the first pump body is arranged on the first pipeline and is used for discharging wet materials in the discharging tank from the discharging head; the scraping plate is arranged in the first pipeline and is driven by the first driving mechanism, so that the scraping plate can move along the inner wall of the first pipeline, and the wet material is prevented from being adhered to the inner wall of the first pipeline; the stirring plate is arranged in the discharging tank, and the scraping plate is driven by a second driving mechanism, so that the stirring plate moves in the discharging tank, the fluidity of the wet materials in the discharging tank from bottom to top is improved, and the wet materials are prevented from generating precipitates at the bottom of the discharging tank; the stability of wet materials in the transportation process can be improved, so that the quality of gypsum boards is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of gypsum board processing, and in particular to a gypsum board wet material anti-blocking and stable material discharging system. Background Art

[0002] During the production of gypsum board, the amount of water required is very high. Too much water will make the gypsum board soft and easy to pierce the molding belt during the molding process; too little water will easily cause the gypsum board to be cast in the mixer; whether it is the casting machine or the piercing of the belt, a large number of people will be required to clean it for a long time before resuming production, which will greatly increase the production cost.

[0003] In the actual production process, the following situations will cause the moisture content of the raw materials of gypsum board to change.

[0004] For example, the wet material itself has a certain viscosity. As the wet material flows in the pipeline, there is a possibility that the wet material adheres to the inner wall of the pipeline, causing the diameter of the pipeline to become smaller, affecting the flow rate of the wet material, and causing the moisture content in the raw material to decrease during the molding process.

[0005] For example, some of the auxiliary materials inside the wet material will settle under the action of gravity. Therefore, as time accumulates, the moisture content in the unit volume of the wet material increases, resulting in an increase in the moisture content in the raw materials during the molding process.

[0006] Inventive content

[0007] The purpose of the present invention is to provide a gypsum board wet material anti-blocking and stable material discharging system to improve the stability of wet material discharging and solve the technical problems existing in the prior art.

[0008] In order to solve the above technical problems, the present invention specifically provides the following technical solutions:

[0009] A gypsum board wet material anti-blocking and stable material discharging system, comprising:

[0010] A discharge tank is used to hold wet material and is connected to a discharge head via a first pipe; a first pump body is arranged on the first pipe and is used to provide power to discharge the wet material in the discharge tank from the discharge head; a flow detector is arranged on the first pipe and is located at the outlet end of the first pump body; a scraper is arranged inside the first pipe, and the scraper is driven by a first driving mechanism so that the scraper can move along the inner wall of the first pipe to avoid the wet material from sticking to the inner wall of the first pipe; a stirring plate is arranged inside the discharge tank, and the scraper is driven by a second driving mechanism so that the stirring plate moves inside the discharge tank to increase the fluidity of the wet material in the discharge tank from bottom to top and avoid the wet material from settling at the bottom of the discharge tank.

[0011] Furthermore, the scraper is an impeller structure, a bearing seat is provided at the axial position of the first pipe, the scraper is arranged on the bearing seat, and the scraper can rotate along the axis of the first pipe; a brush is provided on the edge of the impeller, and the brush is always in contact with the inner wall of the first pipe during the rotation of the scraper; the first driving mechanism is the wet material flowing in the first pipe, and the scraper is driven to rotate by the wet material flowing in the first pipe.

[0012] Furthermore, the stirring plates are provided in multiple groups, which are horizontally arranged at equal intervals at the bottom of the discharge tank; the second driving mechanism is a hydraulic driving rod, which is vertically arranged below the discharge tank, and the action end of the hydraulic telescopic rod passes through the bottom of the discharge tank and is connected to the stirring plate; a rubber telescopic sleeve is provided between the edge of the stirring plate and the bottom plate of the discharge tank, and the two ends of the rubber telescopic sleeve are respectively sealed and connected to the stirring plate and the discharge tank.

[0013] Furthermore, it also includes a flow detector and a PLC controller; wherein the flow detector is used to collect flow data of the wet material at the outlet end of the first pump body to obtain flow data of the discharge head; the PLC controller presets the flow value of the wet material, and adjusts the rotation speed of the first pump body according to the flow data collected by the flow detector, so that the flow value of the wet material at the outlet end of the first pump body is consistent with the wet material flow value preset by the PLC controller.

[0014] Furthermore, it also includes an incremental encoder and a frequency converter; wherein the incremental encoder is used to detect the actual rotation speed of the first pump body and feed the rotation speed back to the PLC controller; the frequency converter is used to receive the control signal of the PLC controller and then adjust the rotation speed of the first pump body.

[0015] Furthermore, a circulation pipeline connected to the discharge tank is provided on the first pipeline between the flow detector and the discharge head; and a pneumatic three-way valve is provided at the connection between the circulation pipeline and the first pipeline.

[0016] Furthermore, it also includes a storage tank for storing wet materials; the storage tank is connected to the storage tank through a second pipeline, and a second pump body is provided on the second pipeline. The second pump body is used to provide power to transport the wet materials in the storage tank to the discharge tank.

[0017] Furthermore, the discharge tank is arranged inside the storage tank, and the side wall of the storage tank is provided with an overflow port at the top; the inner wall of the storage tank is provided with a detection switch below the overflow port; the detection switch is used to send an electrical signal to the PLC controller to control the start-up of the first pump body.

[0018] Furthermore, a diverter device is provided in the discharge tank, so that the wet material entering the discharge tank from the outside passes through the diverter device and then enters the wet material inside the discharge tank, so as to reduce the impact of the wet material entering the discharge tank from the outside on the liquid level of the wet material inside the discharge tank.

[0019] Furthermore, the diversion device includes a conical cylinder and a guide column arranged on the axis position of the discharge tank, and the conical cylinder is sleeved on the guide column; the density of the material making the conical cylinder is less than the density of the wet material, so that the conical cylinder can float on the liquid surface of the wet material in the discharge tank, and the conical cylinder can rise and fall with the rise and fall of the liquid level of the wet material in the discharge tank.

[0020] Compared with the prior art, the invention has the following beneficial effects:

[0021] The present invention provides a gypsum board wet material anti-clogging and stable material discharging system, which prevents the wet material from sticking to the inner wall of the first pipe by arranging a scraper that can move along the inner wall of the first pipe, thereby ensuring the temperature of the wet material flow rate; and increases the fluidity of the wet material from bottom to top in the discharging tank by arranging a stirring plate that can move inside the discharging tank, thereby preventing the wet material from precipitating at the bottom of the discharging tank, and ensuring the stability of the ratio of auxiliary materials and water per unit volume in the wet material.

[0022] Furthermore, the first pump body is PID-regulated through the PLC controller to ensure that the wet material discharge flow rate is consistent with the required flow rate, so as to improve the stability of the wet material discharge.

[0023] Furthermore, a diversion device is provided to divert the wet material entering the discharge tank, thereby playing a buffering role and preventing the wet material from directly impacting the wet material in the discharge tank, thereby reducing the vortex generated on the wet material, thereby improving the stability of the wet material flowing inside the tank. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] In order to more clearly illustrate the implementation methods of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for the implementation methods or the description of the prior art. Obviously, the drawings in the following description are only exemplary, and for ordinary technicians in this field, other implementation drawings can be derived from the provided drawings without creative work.

[0025] Figure 1 It is a structural schematic diagram of the gypsum board wet material anti-clogging and stable material discharging system of the present invention;

[0026] Figure 2 is a schematic diagram of the structure in the first pipeline;

[0027] Figure 3It is a schematic diagram of the structure of the scraper;

[0028] Figure 4 Schematic diagram of the structure of the stirring plate.

[0029] The numbers in the figure represent the following:

[0030] 1-discharging tank, 2-first pipeline, 3-discharging head, 4-first pump body, 5-flow detector, 6-circulation pipeline, 7-pneumatic three-way valve, 8-storage tank, 9-second pipeline, 10-second pump body, 11-overflow port, 12-detection switch, 13-conical cylinder, 14-guide column, 15-sleeve, 16-bracket;

[0031] 11- stirring plate, 12- hydraulic drive rod, 13- rubber telescopic sleeve;

[0032] 21-scraper, 22-bearing seat, 23-connecting rod, 24-brush. DETAILED DESCRIPTION

[0033] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0034] like Figure 1 As shown, the present invention provides a specific implementation of a gypsum board wet material anti-clogging and stable material discharging system, including a discharging tank 1, a first pump body 4, a scraper 21 and a stirring plate 11.

[0035] The discharge tank 1 is used to contain wet materials and is connected to a discharge head 3 via a first pipe 2 ; the connection between the first pipe 2 and the discharge tank 1 is located below the discharge tank 1 .

[0036] The first pump body 4 is disposed on the first pipeline 2 and is used to provide power to discharge the wet material in the discharge tank 1 from the discharge head 3. In this embodiment, the first pump body 4 is preferably a screw pump.

[0037] The plate 21 is disposed inside the first pipe 2 , and the scraper 21 is driven by the first driving mechanism so that the scraper 21 can move along the inner wall of the first pipe 2 to prevent the wet material from adhering to the inner wall of the first pipe 2 .

[0038] Specifically, a plurality of scrapers 21 may be arranged at equal intervals in the first pipe 2 to clean the inner wall of the first pipe 2 in sections to prevent wet material from adhering.

[0039] The stirring plate 11 is arranged inside the discharge tank 1 , and the scraper 21 is driven by the second driving mechanism, so that the stirring plate 11 moves inside the discharge tank 1 to increase the fluidity of the wet material from bottom to top in the discharge tank 1 and avoid the wet material from settling at the bottom of the discharge tank 1 .

[0040] The stirring plate 11 may be arranged to move in a cycle at a fixed time period, so that the wet material at the bottom of the discharge tank 1 moves upward to be mixed with the wet material above.

[0041] This embodiment provides an example of a scraper 21, such as Figure 2 and Figure 3 As shown:

[0042] The scraper 21 is an impeller structure. The first pipe 2 is provided with a bearing seat 22 at the axial position. The edge of the bearing seat 22 is provided with a plurality of connecting rods 23. The connecting rods 23 are used to achieve relative fixation of the bearing seat inside the first pipe 2.

[0043] The scraper 21 is arranged on the bearing seat 22, and the scraper 21 can rotate along the axis of the first pipe 2; a brush 24 is provided on the edge of the impeller, and the brush 24 is always in contact with the inner wall of the first pipe 2 during the rotation of the scraper 21, and the wet material adhering to the inner wall of the first pipe 2 is cleaned by the brush 24.

[0044] In this embodiment, the first driving mechanism can be a mechanical structure or wet material flowing in the first pipe 2. In this embodiment, the wet material flowing in the first pipe 2 is preferably used to drive the scraper 21 to rotate, providing power for the rotation of the scraper 21.

[0045] This embodiment provides an embodiment of the stirring plate 11, such as Figure 3 As shown:

[0046] A plurality of stirring plates 11 are provided and are horizontally arranged at equal intervals at the bottom of the discharge tank 1 .

[0047] The second driving mechanism is a hydraulic driving rod 12, which is vertically arranged below the discharge tank 1. The action end of the hydraulic telescopic rod passes through the bottom of the discharge tank 1 and is connected to the stirring plate 11. Through the extension and retraction of the hydraulic telescopic rod, the stirring plate 11 moves up and down in the vertical direction, so that the wet material at the bottom of the discharge tank 1 moves upward to be mixed with the wet material above.

[0048] A rubber telescopic sleeve 13 is provided between the edge of the stirring plate 11 and the bottom plate of the discharge tank 1 , and both ends of the rubber telescopic sleeve 13 are respectively sealed with the stirring plate 11 and the discharge tank 1 to ensure the sealing of the bottom of the discharge tank 1 .

[0049] In order to facilitate the control of the flow rate of the wet material at the discharge head, the present embodiment further includes a flow detector 5 and a PLC controller.

[0050] The flow detector 5 is arranged on the first pipeline 2 and is located at the outlet end of the first pump body 4; the flow detector 5 is used to collect the flow data of the wet material at the outlet end of the first pump body 4 to obtain the flow data of the discharge head 3; in order to ensure the accuracy of the data, the flow detector 5 is made as close to the discharge head 3 as possible.

[0051] The PLC controller presets the flow value of the wet material, and adjusts the rotation speed of the first pump body 4 according to the flow data collected by the flow detector 5, so that the flow value of the wet material at the outlet end of the first pump body 4 is consistent with the wet material flow value preset by the PLC controller.

[0052] In order to ensure the stability of the PLC controller's control over the first pump body 4, this embodiment also provides an incremental encoder and a frequency converter; wherein the incremental encoder is used to detect the actual rotational speed of the first pump body 4 and feed the rotational speed back to the PLC controller; the frequency converter is used to receive the control signal of the PLC controller and further adjust the rotational speed of the first pump body 4.

[0053] In the actual production process, there is an error between the discharge flow rate and the rated flow rate for a period of time after the discharge head 3 starts to discharge the material. In order to avoid the occurrence of this error, this embodiment provides the following examples.

[0054] A circulation pipeline 6 connected to the discharge tank 1 is provided on the first pipeline 2 between the flow detector 5 and the discharge head 3 ; a pneumatic three-way valve 7 is provided at the connection between the circulation pipeline 6 and the first pipeline 2 .

[0055] In the initial state, under the control of the pneumatic three-way valve 7, the pipeline between the first pipeline 2 and the circulation pipeline 6 is connected, and the pipeline between the first pipeline 2 and the discharge head 3 is closed, so that the wet material in the discharge tank 1 passes through the first pipeline 2 and the circulation pipeline 6 and then returns to the discharge tank 1, forming a circulation pipeline.

[0056] The wet material is first circulated in the circulation pipeline. After the PLC controls and adjusts the wet material flow rate at the discharge end of the first pump body 4, the PLC controller controls the pneumatic three-way valve 7 to open the pipeline between the first pipeline 2 and the discharge head 3, and closes the pipeline between the first pipeline 2 and the circulation pipeline 6, so that the discharge head 3 starts to discharge the material stably.

[0057] In this embodiment, in order to ensure the continuity and stability of the wet material discharge, it is necessary to add wet material to the storage tank 8. Therefore, in this embodiment, it also includes a storage tank 8 for storing wet material; the storage tank 8 is connected to the storage tank 8 through a second pipe 9, and a second pump body 10 is provided on the second pipe 9. The second pump body 10 is used to provide power to transport the wet material in the storage tank 8 to the discharge tank 1; the connection between the second pipe 9 and the storage tank 8 is located below the side wall of the storage tank 8, and the connection between the second pipe 9 and the discharge tank 1 is located at the top of the discharge tank 1.

[0058] Furthermore, in order to ensure the continuity and stability of wet material discharge, the discharge rate of the first pipe 2 must be lower than the feeding rate of the second pipe 9, causing the wet material inside the discharge tank 1 to overflow; therefore, an overflow port 11 is provided at the top of the side wall of the storage tank 8.

[0059] Furthermore, in order to simplify the structure, the discharge tank 1 is arranged inside the storage tank 8, and the discharge tank 1 is located above the inside of the storage tank 8, so that the wet material overflowing from the discharge tank 1 directly flows into the storage tank 8.

[0060] A bracket 16 is provided inside the storage tank 8 , and the hydraulic drive rod 12 is arranged on the bracket 16 .

[0061] Furthermore, in the present embodiment, a detection switch 12 is provided on the inner wall of the storage tank 8 below the overflow port 11; when the detection switch 12 detects the liquid level of the wet material, it indicates that the wet material is about to flow out of the overflow port 11, indicating that the discharge tank 1 is full and can be discharged; the detection switch 12 is used to send an electrical signal to the PLC controller to control the start of the first pump body 4.

[0062] When the storage tank 8 is replenishing the discharge tank 1 , the wet material entering the discharge tank 1 from the second pipe 9 will impact the wet material in the discharge tank 1 and generate air vortexes, thereby affecting and causing errors in the wet material discharged through the first pipe 2 .

[0063] Therefore, in this embodiment, a diverter device is provided in the discharge tank 1, so that the wet material entering the discharge tank 1 from the outside passes through the diverter device and then enters the wet material inside the discharge tank 1, so as to reduce the impact of the wet material entering the discharge tank 1 from the outside on the liquid surface of the wet material inside the discharge tank 1.

[0064] This embodiment also provides an embodiment of a flow dividing device, such as Figure 1 As shown:

[0065] The flow dividing device comprises a conical cylinder 13 and a guide column 14 arranged on the axis position of the discharge tank 1. A sleeve is arranged inside the conical cylinder 13 at the axis position, and the sleeve is sleeved on the guide column 14. The density of the material making the conical cylinder 13 is less than the density of the wet material, so that the conical cylinder 13 can float on the liquid surface of the wet material in the discharge tank 1; thereby, the conical cylinder 13 can rise and fall with the rise and fall of the liquid surface of the wet material in the discharge tank 1.

[0066] The wet material entering the discharge tank 1 through the second pipe 9 or the wet material entering the discharge tank 1 through the circulation pipe 6 is diverted by the slope of the conical cylinder 13 and slides into the wet material in the discharge tank 1 without causing impact on the wet material in the discharge tank 1.

[0067] The present invention provides a specific implementation method of a control method for a gypsum board wet material anti-blocking and stable material discharging system, comprising the following steps:

[0068] 1) PLC controls the second pump body 10 so that the wet material in the storage tank 8 enters the discharge tank 1;

[0069] 2) When the detection switch 12 in the discharge tank 1 detects wet material, an electrical signal is sent to the PLC controller to start the first pump body 4; at the same time, the wet material overflowing from the discharge tank 1 flows back to the storage tank 8 through the overflow port 11;

[0070] 3) The initial state of the pneumatic three-way valve 7 is to connect the pipeline between the first pipeline 2 and the circulation pipeline 6, and close the pipeline between the first pipeline 2 and the discharge head 3, so that the wet material in the discharge tank 1 passes through the first pipeline 2 and the circulation pipeline 6 and then returns to the discharge tank 1 to form a circulation pipeline;

[0071] 4) The PLC controller adjusts the first pump body 4 so that the flow value of the wet material at the outlet end of the first pump body 4 is consistent with the wet material flow value preset by the PLC controller;

[0072] 5) When the flow rate value of the wet material at the outlet end of the first pump body 4 is consistent with the wet material flow rate value preset by the PLC controller, the pneumatic three-way valve 7 opens the pipeline between the first pipeline 2 and the discharge head 3, closes the pipeline between the first pipeline 2 and the circulation pipeline 6, and realizes the discharge of the wet material through the discharge head 3;

[0073] 6) During the discharging process, the PLC controller adjusts the first pump body 4 in real time so that the flow value of the wet material at the outlet end of the first pump body 4 is consistent with the wet material flow value preset by the PLC controller.

[0074] The above embodiments are only exemplary embodiments of the present application and are not intended to limit the present application. The protection scope of the present application is defined by the claims. Those skilled in the art may make various modifications or equivalent substitutions to the present application within the essence and protection scope of the present application, and such modifications or equivalent substitutions shall also be deemed to fall within the protection scope of the present application.

Claims

1. A gypsum board wet material anti-blocking and stable material discharging system, characterized in that: include A discharge tank (1) is used to contain wet materials and is connected to a discharge head (3) via a first pipe (2); A first pump body (4) is arranged on the first pipeline (2); the first pump body (4) is used to provide power to discharge the wet material in the discharge tank (1) from the discharge head (3); a scraper (21) arranged inside the first pipe (2), the scraper (21) being driven by a first driving mechanism so that the scraper (21) can move along the inner wall of the first pipe (2) to prevent the wet material from adhering to the inner wall of the first pipe (2); The stirring plate (11) is arranged inside the discharge tank (1), and the scraper (21) is driven by a second driving mechanism, so that the stirring plate moves inside the discharge tank (1) to increase the fluidity of the wet material in the discharge tank (1) from bottom to top, thereby preventing the wet material from settling at the bottom of the discharge tank (1).

2. The gypsum board wet material anti-blocking and stable material discharging system according to claim 1 is characterized in that: The scraper (21) is an impeller structure, the first pipe (2) is provided with a bearing seat (22) at an axial position, the scraper (21) is arranged on the bearing seat (22), and the scraper (21) can rotate along the axis of the first pipe (2); A brush (24) is provided on the edge of the scraper (21), and the brush (24) is always in contact with the inner wall of the first pipe (2) during the rotation of the scraper (21); The first driving mechanism is the wet material flowing in the first pipe (2), and the wet material flowing in the first pipe (2) drives the scraper (21) to rotate.

3. The gypsum board wet material anti-blocking and stable material discharging system according to claim 1, characterized in that: The stirring plates (11) are provided in a plurality of groups and are horizontally arranged at equal intervals at the bottom of the discharge tank (1); the second driving mechanism is a hydraulic driving rod (12), the hydraulic driving rod (12) is vertically arranged below the discharge tank (1), and the action end of the hydraulic telescopic rod (12) passes through the bottom of the discharge tank (1) and is connected to the stirring plates (11); A rubber telescopic sleeve (13) is provided between the edge of the stirring plate (11) and the bottom plate of the discharge tank (1), and the two ends of the rubber telescopic sleeve (13) are respectively sealedly connected to the stirring plate (11) and the discharge tank (1).

4. The gypsum board wet material anti-blocking and stable material discharging system according to claim 1, characterized in that: It also includes a flow detector (5) and a PLC controller; The flow detector (5) is arranged on the first pipeline (2) and is located at the outlet end of the first pump body (4); the flow detector (5) is used to collect flow data of the wet material at the outlet end of the first pump body (4) to obtain flow data of the discharge head (3); The PLC controller presets a flow value of the wet material, and adjusts the rotation speed of the first pump body (4) based on the flow data collected by the flow detector (5), so that the flow value of the wet material at the outlet end of the first pump body (4) is consistent with the wet material flow value preset by the PLC controller.

5. The gypsum board wet material anti-blocking and stable material discharging system according to claim 4, characterized in that: Also includes incremental encoders and frequency converters; The incremental encoder is used to detect the actual rotation speed of the first pump body (4) and feed the rotation speed back to the PLC controller; the frequency converter is used to receive the control signal of the PLC controller and further adjust the rotation speed of the first pump body (4).

6. The gypsum board wet material anti-blocking and stable material discharging system according to claim 5, characterized in that: A circulation pipeline (6) connected to the discharge tank (1) is provided on the first pipeline (2) between the flow detector (5) and the discharge head (3); a pneumatic three-way valve (7) is provided at the connection between the circulation pipeline (6) and the first pipeline (2).

7. The gypsum board wet material anti-blocking and stable material discharging system according to claim 6, characterized in that: It also includes a storage tank (8) for storing wet material; the storage tank (8) is connected to the storage tank (8) through a second pipeline (9); a second pump body (10) is provided on the second pipeline (9); the second pump body (10) is used to provide power to transport the wet material in the storage tank (8) to the discharge tank (1).

8. The gypsum board wet material anti-blocking and stable material discharging system according to claim 7, characterized in that: The discharge tank (1) is arranged inside the storage tank (8), and the side wall of the discharge tank (1) is provided with an overflow port (11) at the top; A detection switch (12) is provided on the inner wall of the discharge tank (1) below the overflow port (11). The detection switch (12) is used to send an electrical signal to a PLC controller when the liquid level of the wet material in the discharge tank (1) exceeds the position of the detection switch (12), so as to control the start of the first pump body (4).

9. The gypsum board wet material anti-blocking and stable material discharging system according to claim 1 or 8, characterized in that: The discharge tank (1) is provided with a diverter device, so that the wet material entering the discharge tank (1) from the outside passes through the diverter device and then enters the wet material inside the discharge tank (1), so as to reduce the impact of the wet material entering the discharge tank (1) from the outside on the liquid surface of the wet material inside the discharge tank (1).

10. The gypsum board wet material anti-blocking and stable material discharging system according to claim 9, characterized in that: The flow dividing device comprises a conical cylinder (13) and a guide column (14) arranged at an axial position of the discharge tank (1); a sleeve (15) is arranged inside the conical cylinder (13) at an axial position, and the sleeve (15) is sleeved on the guide column (14); The density of the material making the conical tube (13) is less than the density of the wet material, so that the conical tube (13) can float on the liquid surface of the wet material in the discharge tank (1), and the conical tube (13) can rise and fall with the rise and fall of the liquid surface of the wet material in the discharge tank (1).