Hydraulic engineering bridge pile foundation construction device

By designing pneumatic cylinders and piston plates, and combining hydraulic cylinders and infrared ranging sensors, automated hammering and atomized dust suppression were achieved in bridge pile foundation construction. This solved the problems of poor atomized dust removal effect and inconvenience of manual support in existing technologies, and improved construction efficiency and equipment lifespan.

CN119021215AInactive Publication Date: 2024-11-26泗洪县水利局 +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411443779.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-16
Publication Date
2024-11-26
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing bridge pile foundation construction equipment suffers from problems such as poor atomization dust removal effect, inconvenience of manual support, and easy wear and tear of the equipment during the pile driving process.

Method used

The device employs a pneumatic cylinder and piston plate design to achieve an upward exhaust and downward suction working state. Combined with a hydraulic cylinder and an infrared ranging sensor, it realizes automated knocking and atomization dust suppression. The reaction force is eliminated by adjusting the plate and shock-absorbing plate, thus extending the service life of the device.

Benefits of technology

It improves the efficiency of hammering and the effect of atomization and dust suppression, realizes automated construction without manual support, and extends the service life of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021215A_ABST
    Figure CN119021215A_ABST
Patent Text Reader

Abstract

The invention discloses a hydraulic engineering bridge pile foundation construction device which comprises a fixing ring seat, a support, a knocking block and a driving mechanism, the support is slidably arranged in the fixing ring seat, a guide ring is fixedly arranged on the support, the knocking block is slidably arranged in the guide ring, a supporting rod is fixedly arranged on the knocking block, and the driving mechanism is fixedly arranged on the supporting rod. A driving mechanism is fixedly arranged at the top end of the support, a pneumatic cylinder is fixedly arranged on the support, a piston plate is fixedly arranged on the supporting rod, the piston plate slides along the pneumatic cylinder in a sealed mode, a plurality of air holes are formed in the top of the pneumatic cylinder, a first one-way valve is arranged in the air holes, and a spraying box is fixedly arranged on the support. The spraying box is connected with the pneumatic cylinder through a pneumatic hose, and a second one-way valve is arranged at the joint of the pneumatic hose and the pneumatic cylinder.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge pile foundation construction, in particular to a water conservancy project bridge pile foundation construction device. Background Art

[0002] During the construction of bridge pile foundations, the pile foundations need to be fixed and driven into the soil. In bridge projects, pile drivers are mostly used to drive the pile foundations into the soil. During this process, strong vibrations are often generated as the pile driver hammers, causing the soil to fly, polluting the working environment and affecting the pile driving work.

[0003] At present, the flying dust caused by pile driving is generally atomized and dusted by an atomizer. For example, the Chinese patent with the publication number CN114482043A proposes a water conservancy construction and environmentally friendly bridge pile foundation construction device. By setting a linkage booster mechanism, the percussion hammer can compress the air and transfer it into the receiving box during the up and down percussion. The water in the receiving box is sprayed out through multiple inclined spray tubes and atomizer heads to achieve the effect of atomization dust removal. When this device is implemented, it is necessary to manually support the device and cannot perform autonomous percussion work. Although it is provided with a soft rubber handle that can effectively reduce vibration, long-term percussion work will still cause damage to the human body. Moreover, the air entering the receiving box is mainly pressed into the receiving box by the upward sliding of the percussion hammer after hitting the pile foundation. The air suction work is mainly to inhale the air when the percussion hammer is reset by the spring. In this process, the spring will be repeatedly compressed and stretched. During long-term use, the spring is prone to fatigue, which reduces the amount of air suction and causes atomization failure.

[0004] Therefore, it is necessary to provide a water conservancy project bridge pile foundation construction device to solve the problems raised in the above background technology. Summary of the invention

[0005] To achieve the above object, the present invention provides the following technical solution: a water conservancy project bridge pile foundation construction device, comprising a fixed ring seat, a bracket, a knocking block and a driving mechanism, wherein the bracket is slidably arranged in the fixed ring seat, a guide ring is fixedly arranged on the bracket, the knocking block is slidably arranged in the guide ring, a support rod is fixedly arranged on the knocking block, and the driving mechanism is fixedly arranged on the top of the bracket;

[0006] A pneumatic cylinder is fixedly arranged on the bracket;

[0007] A piston plate is fixedly arranged on the support rod, and the piston plate slides along the pneumatic cylinder seal;

[0008] A plurality of air holes are provided on the top of the pneumatic cylinder, and a one-way valve is provided in each of the air holes.

[0009] Further, as a preference, a spray box is fixedly arranged on the bracket, the spray box is connected to the pneumatic cylinder via a pneumatic hose, and a second one-way valve is arranged at the interface between the pneumatic hose and the pneumatic cylinder;

[0010] A spray ring is fixedly arranged on the bracket, a plurality of spray rods are fixedly arranged on the spray ring, and the spray ring is connected to the spray box through a hydraulic hose.

[0011] Further, as a preference, the driving mechanism includes a driving seat, a driving rod, a hinged rod and a driving motor, wherein two driving seats are fixedly arranged on the top of the bracket, a driving rod is rotatably arranged between the two driving seats, the driving rod is in a "X" shape, a driving motor for driving the driving rod to rotate is fixedly arranged on the driving seat, and both ends of the hinged rod are respectively hinged to the driving rod and the support rod.

[0012] Further, as a preference, a slide bar is fixedly provided on the bracket;

[0013] The fixed ring seat is provided with a plurality of limiting sliding grooves, and the sliding rod is inserted into the limiting sliding grooves and slides along the limiting sliding grooves.

[0014] Further, as a preference, a hydraulic cylinder is fixedly provided on the fixed ring seat, the hydraulic cylinder is driven by an external hydraulic drive mechanism, a sealing plate is sealingly and slidingly provided in the hydraulic cylinder, a plurality of connecting rods are fixedly provided on the sealing plate, and a shock absorbing plate is fixedly provided on the output end of the connecting rod.

[0015] Further, as a preference, an annular shock absorbing cavity is provided in the shock absorbing plate;

[0016] The slide rod passes through the limiting slide groove and is fixedly provided with an adjustment plate, the adjustment plate is inserted into the annular shock-absorbing cavity and slides along the annular shock-absorbing cavity, and shock-absorbing springs are provided on the upper and lower sides of the adjustment plate, and the other end of the shock-absorbing spring is fixedly connected to the shock-absorbing plate.

[0017] Further, as a preference, a plurality of conical positioning pins are fixedly provided at the bottom end of the fixed ring seat in the vertical direction, and a pressure ring is fixedly provided at the bottom end of the fixed ring seat in the horizontal direction.

[0018] Further, preferably, an infrared distance measuring sensor is embedded in the guide ring, and the infrared distance measuring sensor is used to monitor the distance between the guide ring and the bridge pile foundation;

[0019] A controller is arranged on the top of the bracket, and the controller is electrically connected to the hydraulic drive mechanism, the infrared ranging sensor and the drive motor.

[0020] Compared with the prior art, the present invention provides a hydraulic engineering bridge pile foundation construction device, which has the following beneficial effects:

[0021] In the present invention, the pneumatic cylinder arranged on the bracket and the piston plate arranged on the support rod enable the pneumatic cylinder to realize the working state of upper discharge and lower suction in the process of the knocking block knocking up and down, that is, in the process of the driving mechanism driving the knocking block to slide and knock downward, the energy of the air suction loss of the pneumatic cylinder is low, thereby making the kinetic energy of the knocking block higher when knocking downward, so that the driving force on the knocking block is less affected by the driving force when the driving mechanism drives the spray box to atomize the spray, thereby effectively improving the knocking efficiency of the knocking block, and in the knocking process, through the setting of the adjustment plate and the shock-absorbing plate, when the knocking block knocks on the pile foundation, the reaction force on the knocking block can be effectively eliminated, thereby extending the service life of the entire device, in addition, through the setting of the conical locating pin and the pressure ring, the pile foundation can be knocked without manual support, and in the knocking process, the sliding of the bracket can be adjusted in real time through the hydraulic cylinder, that is, when the pile foundation is knocked and moved downward, the knocking block can always knock on the pile foundation until the pile foundation is driven into the ground, thereby realizing automatic knocking work and further improving its convenience. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0023] Figure 2 It is a schematic cross-sectional view of the overall structure of the present invention;

[0024] Figure 3 It is a structural schematic diagram of the driving mechanism in the present invention;

[0025] Figure 4 for Figure 1 A magnified schematic diagram of part A;

[0026] Figure 5 It is a schematic diagram of the structure of the adjustment plate and the damping plate in the present invention;

[0027] In the figure: 1. fixed ring seat; 11. slide groove; 12. hydraulic cylinder; 13. sealing plate; 14. connecting rod; 15. shock-absorbing plate; 16. conical fixing pin; 17. pressure ring; 2. bracket; 21. guide ring; 22. pneumatic cylinder; 23. air vent; 24. slide rod; 25. adjustment plate; 26. shock-absorbing spring; 3. knock block; 31. support rod; 32. piston plate; 4. driving mechanism; 41. driving seat; 42. driving rod; 43. hinged rod; 44. driving motor; 5. spray box; 6. spray ring; 61. spray rod. DETAILED DESCRIPTION

[0028] Example: See Figure 1 to Figure 5In an embodiment of the present invention, a water conservancy engineering bridge pile foundation construction device includes a fixed ring seat 1, a bracket 2, a knocking block 3 and a driving mechanism 4, wherein the bracket 2 is slidably arranged in the fixed ring seat 1, a guide ring 21 is fixedly arranged on the bracket 2, the knocking block 3 is slidably arranged in the guide ring 21, a support rod 31 is fixedly arranged on the knocking block 3, and the top of the bracket 2 is fixedly arranged with the driving mechanism 4;

[0029] A pneumatic cylinder 22 is fixedly arranged on the bracket 2;

[0030] A piston plate 32 is fixedly disposed on the support rod 31, and the piston plate 32 slides along the pneumatic cylinder 22 in a sealed manner;

[0031] A plurality of air holes 23 are formed on the top of the pneumatic cylinder 22 , and a one-way valve 1 is disposed in each of the air holes 23 .

[0032] During implementation, the fixed ring seat 1 is sleeved on the outside of the pile foundation, and the conical positioning pin 16 is inserted into the ground so that the pressure ring 17 is close to the ground, and a heavy object is placed on the pressure ring 17, so that the fixed ring seat 1 is completely fixed on the outside of the pile foundation, and automatic knocking can be achieved without manual support. Then, the distance between the guide ring 21 and the pile foundation is detected by the sensor, and then the sealing plate 13 is driven to slide by the hydraulic cylinder 12, thereby driving the entire bracket 2 to slide, so that the knocking block 3 is close to the bridge pile foundation, and then the driving mechanism 4 is used to drive the knocking block 3 to slide up and down to knock the pile foundation. , and then the pile foundation is driven into the ground, and during the knocking process, the piston plate 32 slides along the pneumatic cylinder 22, and when the knocking block 3 knocks downward, the piston plate 32 slides downward at the same time, and the air is sucked into the pneumatic cylinder 22 through the air vent 23, and when the piston plate 32 slides upward, that is, when the driving mechanism 4 lifts up the knocking block 32, the piston plate 32 slides upward at the same time, and under the action of the one-way valve 1, the air in the pneumatic cylinder 22 is squeezed and the air in the pneumatic cylinder 22 is transported to the spray box 5 through the one-way valve 2 and the air hose. After being pressurized, the spray box 5 Water is transported to the spray ring 6 through a hydraulic hose, and water mist is sprayed out by a spray rod 61, thereby realizing atomization dust reduction. In this process, when the driving mechanism 4 drives the knocking block 3 to slide downward, the piston plate 32 slides along the pneumatic cylinder 22 with basically no force, thereby effectively reducing the energy lost by the air suction of the pneumatic cylinder 22, thereby making the impact force of the knocking block 3 stronger and the knocking effect better. When the knocking block 3 strikes the pile foundation, the pile foundation will apply a reaction force to the knocking block 3 while moving downward, thereby causing the knocking block 3 to slide upward and apply this reaction force to the bracket 2. At this time, the knocking block 3 is adjusted along the adjusting plate 25. The sliding of the annular shock-absorbing cavity and the buffering effect of the shock-absorbing spring 26 can effectively absorb this reaction force, thereby ensuring that the knocking block 3 and the driving mechanism 4 will not be damaged. At the same time, in the process of the pile foundation moving downward, the infrared ranging sensor arranged in the guide ring 21 monitors the distance between the pile foundation and the guide ring 21 in real time, and transmits this distance information to the controller. The controller drives the bracket 2 to slide as a whole through the hydraulic cylinder 12 according to the downward movement of the pile foundation, thereby ensuring that the knocking block 3 can effectively knock on the pile foundation during the downward movement of the pile foundation, that is, the pile foundation is driven into the ground, thereby realizing fully automatic knocking of the pile foundation.

[0033] In this embodiment, Figure 1 A spray box 5 is fixedly mounted on the bracket 2, and the spray box 5 is connected to the pneumatic cylinder 22 via a pneumatic hose, and a check valve 2 is disposed at the interface between the pneumatic hose and the pneumatic cylinder 22;

[0034] A spray ring 6 is fixedly disposed on the bracket 2 , and a plurality of spray rods 61 are fixedly disposed on the spray ring 6 . The spray ring 6 is connected to the spray box 5 via a hydraulic hose.

[0035] In particular, the one-way valve 1 can only allow external air to enter the pneumatic cylinder 22, and the one-way valve 2 can only discharge the air in the pneumatic cylinder 22. When the piston plate 31 slides downward, the external air enters the pneumatic cylinder 22 through the air vent 23, and the kinetic energy loss during the air intake process is low. When the piston plate 31 slides upward, the air in the pneumatic cylinder 22 is pressed into the spray box 5 and the water in the spray box 5 is pressed to the spray rod 61 and sprayed to form water mist. The energy required in this process is relatively high, so that the driving mechanism 4 does not need to consume excess energy when driving the knocking block 3 to knock downward, so that the knocking effect of the knocking block 3 is better. When the knocking is completed and spraying is required, the driving mechanism 4 provides power support, so as to avoid affecting the knocking efficiency of the knocking block 3 while spraying. The knocking and spraying are knocked first and then sprayed, that is, when dust appears after knocking, spray dust reduction is performed, which effectively improves the dust reduction effect.

[0036] In this embodiment, Figure 3 The driving mechanism 4 includes a driving seat 41, a driving rod 42, a hinged rod 43 and a driving motor 44, wherein two driving seats 41 are fixedly arranged on the top of the bracket 2, a driving rod 42 is rotatably arranged between the two driving seats 41, and the driving rod 42 is in a "X" shape. A driving motor 44 for driving the driving rod 42 to rotate is fixedly arranged on the driving seat 41, and both ends of the hinged rod 43 are hinged to the driving rod 42 and the support rod 31 respectively.

[0037] In this embodiment, Figure 2 and Figure 4 , a slide bar 24 is fixedly provided on the bracket 2;

[0038] The fixing ring seat 1 is provided with a plurality of limiting sliding grooves 11 , and the sliding rods 24 are inserted into the limiting sliding grooves 11 and slide along the limiting sliding grooves 11 .

[0039] In this embodiment, Figure 1 A hydraulic cylinder 12 is fixedly arranged on the fixed ring seat 1, and the hydraulic cylinder 12 is driven by an external hydraulic driving mechanism. A sealing plate 13 is sealingly and slidingly arranged in the hydraulic cylinder 12, and a plurality of connecting rods 14 are fixedly arranged on the sealing plate 13. A shock absorbing plate 15 is fixedly arranged at the output end of the connecting rod 14.

[0040] In this embodiment, Figure 4 , the shock absorbing plate 15 is provided with an annular shock absorbing cavity;

[0041] The slide rod 24 passes through the limiting slide groove 11 and is fixedly provided with an adjustment plate 25, the adjustment plate 25 is inserted into the annular shock-absorbing cavity and slides along the annular shock-absorbing cavity, and shock-absorbing springs 26 are provided on the upper and lower sides of the adjustment plate 25, and the other end of the shock-absorbing spring 26 is fixedly connected to the shock-absorbing plate 15.

[0042] In particular, the adjustment plate 25 and the shock-absorbing plate 15 are provided to effectively reduce vibration and eliminate the reaction force on the knocking block 3 when knocking occurs, thereby preventing the knocking block 3 and the driving mechanism 4 from being damaged, thereby extending the overall service life of the device. In addition, the impact force transmitted to the fixed ring seat 1 by the bracket 2 can be reduced, that is, ensuring that the fixed ring seat 1 always remains fixed during the knocking process, thereby ensuring that the knocking can be carried out continuously and effectively without manual support, thereby further improving its convenience.

[0043] In this embodiment, Figure 1 A plurality of conical positioning pins 16 are fixedly arranged at the bottom end of the fixed ring seat 1 in the vertical direction, and a pressure ring 17 is fixedly arranged at the bottom end of the fixed ring seat 1 in the horizontal direction.

[0044] In this embodiment, an infrared distance measuring sensor is embedded in the guide ring 21, and the infrared distance measuring sensor is used to monitor the distance between the guide ring 21 and the bridge pile foundation;

[0045] A controller is disposed on the top of the bracket 2 , and the controller is electrically connected to the hydraulic drive mechanism, the infrared ranging sensor and the drive motor 44 .

[0046] During implementation, an infrared ranging sensor is used to monitor the distance between the guide ring 21 and the bridge pile foundation in real time, that is, to monitor the downward movement distance of the pile foundation, and then adjust the bracket 2 to slide, ensuring that the knocking block 3 can always knock on the pile foundation to prevent empty collisions, thereby further improving the knocking efficiency of the knocking block 3.

[0047] In summary, when the present invention is implemented, the pneumatic cylinder 22 arranged on the bracket 2 and the piston plate 32 arranged on the support rod 31 enable the pneumatic cylinder 22 to achieve an upper discharge and lower suction working state during the up and down knocking of the knocking block, that is, when the driving mechanism 4 drives the knocking block 3 to slide and knock downward, the energy lost by the air suction of the pneumatic cylinder 22 is low, thereby making the kinetic energy of the knocking block 3 higher when knocking downward, so that when the driving mechanism 4 drives the spray box 5 to atomize the spray, the driving force on the knocking block 3 is less affected, thereby effectively improving the knocking efficiency of the knocking block 3, and During the knocking process, by setting the adjusting plate 25 and the shock absorbing plate 15, the reaction force exerted on the knocking block 3 when it knocks on the pile foundation can be effectively eliminated, thereby extending the service life of the entire device. In addition, by setting the conical positioning pin 16 and the pressure ring 17, the pile foundation can be knocked without manual support, and during the knocking process, the sliding of the bracket 2 can be adjusted in real time through the hydraulic cylinder 12, that is, when the pile foundation is knocked down, the knocking block 3 can always knock on the pile foundation until the pile foundation is driven into the ground, thereby realizing automated knocking work and further improving its convenience.

[0048] What is described above is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A hydraulic engineering bridge pile foundation construction device, characterized in that: The invention comprises a fixed ring seat (1), a bracket (2), a knocking block (3) and a driving mechanism (4), wherein the bracket (2) is slidably arranged in the fixed ring seat (1), a guide ring (21) is fixedly arranged on the bracket (2), the knocking block (3) is slidably arranged in the guide ring (21), a support rod (31) is fixedly arranged on the knocking block (3), and the driving mechanism (4) is fixedly arranged at the top end of the bracket (2); A pneumatic cylinder (22) is fixedly arranged on the bracket (2); A piston plate (32) is fixedly arranged on the support rod (31), and the piston plate (32) slides sealingly along the pneumatic cylinder (22); The top of the pneumatic cylinder (22) is provided with a plurality of air holes (23), and a one-way valve is arranged in each of the air holes (23).

2. A hydraulic engineering bridge pile foundation construction device according to claim 1, characterized in that: A spray box (5) is fixedly mounted on the bracket (2), the spray box (5) is connected to the pneumatic cylinder (22) via a pneumatic hose, and a second one-way valve is arranged at the interface between the pneumatic hose and the pneumatic cylinder (22); A spray ring (6) is fixedly arranged on the bracket (2), a plurality of spray rods (61) are fixedly arranged on the spray ring (6), and the spray ring (6) is connected to the spray box (5) via a hydraulic hose.

3. A hydraulic engineering bridge pile foundation construction device according to claim 1, characterized in that: The driving mechanism (4) comprises a driving seat (41), a driving rod (42), a hinged rod (43) and a driving motor (44), wherein two driving seats (41) are fixedly arranged on the top of the bracket (2), a driving rod (42) is rotatably arranged between the two driving seats (41), the driving rod (42) is in a "X" shape, a driving motor (44) for driving the driving rod (42) to rotate is fixedly arranged on the driving seat (41), and two ends of the hinged rod (43) are respectively hinged to the driving rod (42) and the support rod (31).

4. A hydraulic engineering bridge pile foundation construction device according to claim 1, characterized in that: A slide bar (24) is fixedly arranged on the bracket (2); The fixed ring seat (1) is provided with a plurality of limiting sliding grooves (11), and the sliding rod (24) is inserted into the limiting sliding grooves (11) and slides along the limiting sliding grooves (11).

5. A hydraulic engineering bridge pile foundation construction device according to claim 4, characterized in that: A hydraulic cylinder (12) is fixedly arranged on the fixed ring seat (1), and the hydraulic cylinder (12) is driven by an external hydraulic drive mechanism. A sealing plate (13) is sealingly and slidably arranged in the hydraulic cylinder (12), and a plurality of connecting rods (14) are fixedly arranged on the sealing plate (13). A shock absorbing plate (15) is fixedly arranged at the output end of the connecting rod (14).

6. A hydraulic engineering bridge pile foundation construction device according to claim 5, characterized in that: The shock absorbing plate (15) is provided with an annular shock absorbing cavity; The slide rod (24) passes through the limiting slide groove (11) and is fixedly provided with an adjustment plate (25); the adjustment plate (25) is inserted into the annular shock-absorbing cavity and slides along the annular shock-absorbing cavity; shock-absorbing springs (26) are provided on both the upper and lower sides of the adjustment plate (25); the other end of the shock-absorbing spring (26) is fixedly connected to the shock-absorbing plate (15).

7. A hydraulic engineering bridge pile foundation construction device according to claim 1, characterized in that: A plurality of conical positioning pins (16) are fixedly arranged at the bottom end of the fixed ring seat (1) in the vertical direction, and a pressure ring (17) is fixedly arranged at the bottom end of the fixed ring seat (1) in the horizontal direction.

8. A hydraulic engineering bridge pile foundation construction device according to claim 5, characterized in that: An infrared distance measuring sensor is embedded in the guide ring (21), and the infrared distance measuring sensor is used to monitor the distance between the guide ring (21) and the bridge pile foundation; A controller is arranged on the top of the bracket (2), and the controller is electrically connected to the hydraulic drive mechanism, the infrared distance measuring sensor and the drive motor (44).