Green assembly type foundation pit slope supporting structure and construction method thereof

By using a green prefabricated foundation pit slope support structure, which employs a combination of support membrane, concrete capping, and steel wire rope fixing, the problems of long construction cycle and environmental pollution in foundation pit slope support are solved, achieving a fast and environmentally friendly support effect.

CN119021240APending Publication Date: 2024-11-26BEIJING DONGFANG HUAHUI MUNICIPAL ENG GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411435964.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-15
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

Existing foundation pit slope protection technologies suffer from long construction periods and environmental pollution, especially the concrete spraying process, which causes serious pollution to the surrounding environment.

Method used

The green prefabricated foundation pit slope protection structure is adopted, including a support membrane, concrete capping, fasteners and steel wire ropes. It is prefabricated in the factory and installed on site, and the combination of fasteners and steel wire ropes is used to fix it, replacing the traditional concrete spraying protection.

Benefits of technology

It shortens construction time, avoids environmental pollution, improves the tear resistance and fixation stability of the support membrane, and simplifies the operation process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021240A_ABST
    Figure CN119021240A_ABST
Patent Text Reader

Abstract

The invention relates to a green assembly type foundation pit slope supporting structure and a construction method thereof, and belongs to the technical field of slope supporting, the green assembly type foundation pit slope supporting structure comprises a supporting film, a concrete coping, fasteners and steel wire ropes, the supporting film is laid on a slope, and the concrete coping is fixed to the top of the slope and fixedly connected with the supporting film; the multiple fasteners are arranged, the adjacent fasteners are arranged at intervals, the fasteners penetrate through the supporting film to be fixedly connected with the slope, the steel wire ropes are laid on the supporting film, the steel wire ropes are connected with the adjacent fasteners, and the slope protection structure has the effects of shortening the construction time of slope protection and protecting the surrounding construction environment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of slope support, and in particular to a green assembled foundation pit slope support structure and a construction method thereof. Background Art

[0002] In today's rapidly developing construction industry, foundation pit slope support technology has always been a key link in the construction process. With the increasing awareness of environmental protection and the continuous innovation of construction technology, people are gradually pursuing a green, environmentally friendly and easy-to-construct slope protection structure.

[0003] Steel mesh is often laid on the slope of a shallow foundation pit, fixed by anchor rods, and then concrete is sprayed on the slope to complete the slope protection.

[0004] The process of concrete spraying requires controlling the thickness of the concrete spraying, and it takes time for the concrete to solidify. During the spraying of concrete, it will also cause pollution to the surrounding environment, and there is a defect of a long construction period. Summary of the invention

[0005] In order to shorten the construction time of slope protection and protect the surrounding construction environment, the present application provides a green prefabricated foundation pit slope support structure and a construction method thereof.

[0006] In the first aspect, the present application provides a green prefabricated foundation pit slope support structure, which adopts the following technical solutions: A green assembled foundation pit slope support structure includes a supporting membrane, a concrete top, fasteners and a steel wire rope. The supporting membrane is laid on the slope, and the concrete top is fixed to the top of the slope and fixedly connected to the supporting membrane. There are multiple fasteners, and adjacent fasteners are arranged at intervals. The fasteners penetrate the supporting membrane and are fixedly connected to the slope. The steel wire rope is laid on the supporting membrane and connected to the fasteners close to it.

[0007] By adopting the above technical scheme, the supporting membrane is directly transported from the factory to the construction site, and the supporting membrane is directly laid on the slope. The edge of the supporting membrane is pressed down and fixed to the top of the slope by a prefabricated concrete top. At the same time, the concrete top is directly fixed to the top of the slope by bolts. The supporting membrane is fixed to the slope by fasteners in the middle of the slope, and finally further limited by steel wire ropes. The operation is simple and convenient, which shortens the construction time of slope protection and avoids the pollution to the environment caused by on-site spraying of concrete.

[0008] Optionally, the supporting membrane includes a base layer, a reinforcement layer and a surface layer, the base layer abuts against the slope, the reinforcement layer is composed of a steel mesh, and the surface layer is made of a material with waterproof capability.

[0009] By adopting the above technical solution, the steel mesh ensures that the reinforced layer has sufficient tensile resistance, improves the overall tear resistance of the supporting membrane, and at the same time the surface waterproofing blocks rainwater to ensure that the slope is not washed away by rainwater.

[0010] Optionally, the fastener includes a positioning rod and a positioning cap, one end of the positioning rod passes through the supporting membrane and is fixedly connected to the slope, and the other end of the positioning rod is threadedly connected to the positioning cap; a winding column is fixed on the positioning cap, the winding column is arranged parallel to the positioning rod, and the middle or end of the wire rope is wound around the winding column.

[0011] By adopting the above technical solution, the positioning rod penetrates the supporting membrane and fixes it to the slope. The positioning cap limits the supporting membrane to prevent the supporting membrane from moving away from the slope. At the same time, the winding column is used to fix the wire rope.

[0012] Optionally, a first check assembly is provided on the positioning rod, and the first check assembly includes a first side rod, a first connecting rod and a first rotating shaft. A first elongated hole for accommodating the first side rod is provided on the positioning rod, and the first elongated hole is provided along the length direction of the positioning rod. One end of the first side rod is hinged to the positioning rod and the hinge shaft is located in the first elongated hole. One end of the first connecting rod is hinged to the first side rod, and the other end is hinged to the first rotating shaft. The first rotating shaft is slidably arranged inside the positioning rod and the sliding direction slides along the length direction of the positioning rod; the first rotating shaft is pushed away from the positioning cap, and the first connecting rod pushes the end of the first side rod close to the positioning cap out of the first elongated hole; a driving rod for pushing the first rotating shaft is provided on the positioning cap.

[0013] By adopting the above technical solution, when installing the positioning cap, the driving rod is also inserted into the positioning rod, the driving rod pushes the first rotating shaft to move, and the movement of the first rotating shaft drives the first connecting rod to move, and finally the end of the first side rod close to the positioning cap is pushed out of the first long hole, so that the first side rod is in a barb shape relative to the positioning rod, thereby improving the fixing effect of the positioning rod and the slope.

[0014] Optionally, a second check assembly is provided on the positioning rod, the second check assembly includes a second side rod, a second connecting rod and a second rotating shaft, a second elongated hole is provided on the positioning rod for accommodating the second side rod, the second elongated hole is provided along the length direction of the positioning rod, the second elongated hole and the first elongated hole are staggered along the length direction of the positioning rod, and the second elongated hole is located on the side of the first elongated hole close to the positioning cap; one end of the second side rod is hinged to the positioning rod and the hinge shaft is located in the second elongated hole, one end of the second connecting rod is hinged to the second side rod, and the other end is hinged to the second rotating shaft, the second rotating shaft is slidably arranged inside the positioning rod and the sliding direction slides along the length direction of the positioning rod; the second rotating shaft is pushed away from the positioning cap, and the second connecting rod pushes the end of the second side rod close to the positioning cap out of the second elongated hole; the driving rod drives the first rotating shaft to slide while also driving the second rotating shaft to slide.

[0015] By adopting the above technical solution, when installing the positioning cap, the driving rod is also inserted into the positioning rod, and the driving rod pushes the second rotating shaft to move. When the second rotating shaft moves, it drives the second connecting rod to move, and finally the end of the second side rod close to the positioning cap is pushed out of the second long hole, so that the second side rod is in a barb shape relative to the positioning rod, which further improves the fixing effect of the positioning rod and the slope.

[0016] Optionally, one end of the driving rod is rotatably connected to the positioning cap, and the center line of the rotating shaft coincides with the central axis of the driving rod itself. A notch is provided at the end of the driving rod away from the positioning cap, and the notch is cross-shaped and is opened along the length direction of the driving rod; the end of the driving rod away from the positioning cap abuts against the first rotating shaft, and the second rotating shaft is located in the notch and abuts against the bottom of the notch.

[0017] By adopting the above technical solution, the driving rod causes the first side rod and the second side rod to change their postures at the same time, thereby simplifying the complexity of the operation.

[0018] Optionally, a centering positioning piece is fixed on the driving rod, and the centering positioning piece is used to make the center line of the driving rod coincide with the center line of the positioning rod.

[0019] By adopting the above technical solution, the centering positioning member can make the driving rod always located at the center position of the positioning rod, ensuring that the end of the driving rod away from the positioning cap abuts against the first rotating shaft, and the second rotating shaft is located in the notch and abuts against the bottom of the notch.

[0020] Optionally, a slideway is provided on the inner wall of the positioning rod, and the slideway slides along the length direction of the positioning rod. The end of the center positioning piece away from the driving rod is slidably arranged in the slideway, and the sliding direction slides along the length direction of the slideway.

[0021] By adopting the above technical solution, the existence of the slideway plays a limiting role on the centering positioning piece, so that the drive rod cannot rotate inside the positioning rod, ensuring that the end of the drive rod away from the positioning cap abuts against the first rotating shaft, and the second rotating shaft is located in the notch and abuts against the bottom of the notch.

[0022] Optionally, there are two winding poles and they are symmetrically distributed on both sides of the positioning rod. Both winding poles are located on the side wall of the positioning cap close to the positioning rod. The wire rope is wavy after winding around the two winding poles. If the wire rope is straightened from the wavy state to a straight state, the wire rope drives the positioning cap to generate a rotation trend. At this time, the rotation trend of the positioning cap is a tightening trend relative to the positioning rod.

[0023] By adopting the above technical solution, when the slope tends to slide down, the slope generates a thrust on the supporting membrane away from the slope, and the supporting membrane also generates a thrust on the wire rope, causing the wire rope to straighten from a wavy state and change its posture to a straight line. The wire rope then drives the positioning cap to generate a rotation trend. At this time, the rotation trend of the positioning cap is a tightening trend relative to the positioning rod, which will only make the fastener fix the supporting membrane more firmly.

[0024] In the second aspect, the present application provides a construction method of a green assembled foundation pit slope support structure, which adopts the following technical solution: A construction method of a green assembled foundation pit slope support structure comprises the following steps: S1. The concrete capping is prefabricated in the factory and transported to the construction site. The supporting membrane is laid, the concrete capping is fixed on the top of the slope and the edge of the supporting membrane is pressed and fixed; S2. After the supporting membrane is laid, the fasteners are fixed on the slope, and the steel wire rope is laid at the same time, and the middle or end of the steel wire rope is wound on the winding column; S3. Tighten the positioning cap.

[0025] In summary, the present application includes at least one of the following beneficial technical effects: 1. The laying of the supporting membrane replaces the spraying of concrete on the slope, avoiding pollution to the surrounding environment; 2. The arrangement of the first non-return assembly and the second non-return assembly cooperates with the positioning rod to make the positioning rod take the shape of a "barbed rod", thereby improving the stability of the positioning rod after being fixed to the slope; 3. The steel wire rope is arranged in a wavy shape after passing through two winding poles. When the slope shows a downward trend, the slope generates a thrust on the supporting membrane away from the slope, and the supporting membrane also generates a thrust on the steel wire rope, causing the steel wire rope to straighten from a wavy shape and change its posture to a straight line. The steel wire rope drives the positioning cap to generate a rotation trend. At this time, the rotation trend of the positioning cap is a tightening trend relative to the positioning rod, which will only make the fastener fix the supporting membrane more firmly. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a schematic diagram of the structure of an embodiment of the present application; Figure 2 It is a schematic diagram of the structure at the fastener; Figure 3 It is an exploded view of the structure at the fastener; Figure 4 It is a way of winding the wire rope in a wavy shape on the winding pole; Figure 5 It is a partial structural cross-sectional view at the fastener; Figure 6 It is a cross-sectional view of the support membrane.

[0027] Explanation of the reference numerals in the accompanying drawings: 1. Support membrane; 11. Base layer; 12. Reinforced layer; 13. Surface layer; 2. Concrete top layer; 3. Fastener; 31. Positioning rod; 311. First long hole; 312. Second long hole; 313. Slide; 32. Positioning cap; 321. Winding column; 4. Wire rope; 5. First non-return assembly; 51. First side rod; 52. First connecting rod; 53. First rotating shaft; 6. Second non-return assembly; 61. Second side rod; 62. Second connecting rod; 63. Second rotating shaft; 7. Drive rod; 71. Notch; 8. Centering locator. DETAILED DESCRIPTION

[0028] The following is combined with Figure 1-Figure 6 This application is described in further detail.

[0029] The embodiment of the present application discloses a green assembled foundation pit slope support structure.

[0030] refer to Figure 1 and Figure 2 A green assembled foundation pit slope support structure includes a supporting membrane 1, a concrete capping 2, fasteners 3 and a steel wire rope 4. The supporting membrane 1 and the concrete capping 2 are prefabricated in the factory and transported to the construction site. The supporting membrane 1 is laid on the slope, and the supporting membrane 1 extends to the top of the slope. The concrete capping 2 is hoisted so that the concrete capping 2 presses the part of the supporting membrane 1 located at the top of the slope, and the concrete capping 2 is fixed to the top of the slope by bolts. The supporting membrane 1 is fixed to the inclined surface of the slope by fasteners 3, and finally the steel wire rope 4 is laid on the supporting membrane 1 and the steel wire rope 4 is fixed to the fasteners 3. There are multiple fasteners 3 and steel wire ropes 4. For ease of observation, not all fasteners 3 and steel wire ropes 4 are drawn in the drawings of this application. Adjacent fasteners 3 are arranged at intervals, and can be staggered in a plum blossom pile style, or arranged in a rectangular array. All steel wire ropes 4 are in a mesh shape.

[0031] refer to Figure 2 and Figure 3 The fastener 3 includes a positioning rod 31 and a positioning cap 32. One end of the positioning rod 31 penetrates the supporting membrane 1 and is inserted into the slope and fixedly connected to the slope. The other end of the positioning rod 31 is threadedly connected to the positioning cap 32. A winding post 321 is fixed on the positioning cap 32. The winding post 321 is arranged parallel to the positioning rod 31. There are two winding posts 321. Both of the two winding posts 321 are located on the side wall of the positioning cap 32 close to the positioning rod 31. The two winding posts 321 are symmetrically arranged with the center point of the positioning cap 32. The middle part or the end of the steel wire rope 4 is wound on the winding post 321.

[0032] refer to Figure 3 and Figure 4If the positioning cap 32 is close to the end of the wire rope 4, the end of the wire rope 4 can be directly fixed on the winding pole 321. If the positioning cap 32 is close to the middle of the wire rope 4, the wire rope 4 will be wavy after winding around the two winding poles 321; if the wire rope 4 is straightened from the wavy state to a straight line, the wire rope 4 drives the positioning cap 32 to generate a rotation trend. At this time, the rotation trend of the positioning cap 32 is a tightening trend relative to the positioning rod 31.

[0033] When the slope shows a downward trend, the slope generates a thrust on the supporting membrane 1 away from the slope, and the supporting membrane 1 also generates a thrust on the wire rope 4, causing the wire rope 4 to straighten from a wavy state to a straight line. The wire rope 4 drives the positioning cap 32 to rotate. At this time, the rotation trend of the positioning cap 32 is a tightening trend relative to the positioning rod 31, which will only make the fastener 3 fix the supporting membrane 1 more firmly.

[0034] refer to Figure 2 and Figure 5 The interior of the positioning rod 31 is hollow, and the end of the positioning rod 31 away from the positioning cap 32 is in a pointed cone shape. The positioning rod 31 is provided with a first elongated hole 311 and a second elongated hole 312, both of which are provided along the length direction of the positioning rod 31, and the second elongated hole 312 is located on the side of the first elongated hole 311 away from the pointed cone end of the positioning rod 31. In this embodiment, there are two first elongated holes 311 and two elongated holes 312, and both are symmetrically provided on the positioning rod 31. The second elongated hole 312 and the first elongated hole 311 are arranged in a staggered shape along the length direction of the positioning rod 31, and in this embodiment, the staggered difference is 90 degrees.

[0035] refer to Figure 2 and Figure 5 The positioning rod 31 is provided with a first check assembly 5 and a second check assembly 6. The second check assembly 6 is located near the second long hole 312, and the first check assembly 5 is located near the first long hole 311. The first check assembly 5 includes a first side bar 51, a first connecting rod 52 and a first rotating shaft 53. One end of the first side bar 51 is hinged to the positioning rod 31 and the hinge shaft is located in the first long hole 311. The other end of the first side bar 51 swings in a direction away from or close to the positioning rod 31. The first side bar 51 is located in the first long hole 311 in a stored state. One end of the first connecting rod 52 is hinged to the first side bar 51, and the other end is hinged to the first rotating shaft 53. The first rotating shaft 53 is slidably arranged inside the positioning rod 31 and slides along the length direction of the positioning rod 31. The length of the first rotating shaft 53 is the same as the inner diameter of the positioning rod 31, that is, the end of the first rotating shaft 53 slides against the inside of the positioning rod 31.

[0036] refer to Figure 2 and Figure 5The second non-return assembly 6 includes a second side bar 61, a second connecting rod 62 and a second rotating shaft 63. The second elongated hole 312 is located on the side of the first elongated hole 311 close to the positioning cap 32. One end of the second side bar 61 is hinged to the positioning rod 31 and the hinge axis is located in the second elongated hole 312. The other end of the second side bar 61 swings in a direction away from or close to the positioning rod 31. The second side bar 61 is located in the second elongated hole 312 in the storage state. One end of the second connecting rod 62 is hinged to the second side bar 61, and the other end is hinged to the second rotating shaft 63. The second rotating shaft 63 is slidably arranged inside the positioning rod 31 and slides along the length direction of the positioning rod 31. The length of the second rotating shaft 63 is the same as the inner diameter of the positioning rod 31, and the end of the second rotating shaft 63 is in sliding contact with the inner wall of the positioning rod 31.

[0037] The second rotating shaft 63 and the first rotating shaft 53 are pushed away from the positioning cap 32 , the second connecting rod 62 pushes the end of the second side rod 61 close to the positioning cap 32 out of the second elongated hole 312 , and the first connecting rod 52 pushes the end of the first side rod 51 close to the positioning cap 32 out of the first elongated hole 311 .

[0038] refer to Figure 2 , Figure 3 and Figure 5 , a driving rod 7 for pushing the first rotating shaft 53 and the second rotating shaft 63 to move is provided on the positioning cap 32. One end of the driving rod 7 is rotatably connected to the positioning cap 32, and the center line of the rotating shaft coincides with the central axis of the driving rod 7 itself. A notch 71 is provided at the end of the driving rod 7 away from the positioning cap 32. The notch 71 is cross-shaped and is provided along the length direction of the driving rod 7. A centering positioning member 8 is fixed on the driving rod 7. The centering positioning member 8 is triangular-shaped. In this embodiment, two centering positioning assemblies are provided and symmetrically arranged on the driving rod 7. A slideway 313 is provided on the inner wall of the positioning rod 31. The slideway 313 slides along the length direction of the positioning rod 31. The end of the centering positioning member 8 away from the driving rod 7 is slidably arranged in the slideway 313, and the sliding direction slides along the length direction of the slideway 313. When the driving rod 7 is in use, the end of the driving rod 7 away from the positioning cap 32 abuts against the first rotating shaft 53, and the second rotating shaft 63 is located in the notch 71 and abuts against the bottom of the notch 71.

[0039] refer to Figure 6 The supporting membrane 1 includes a base layer 11, a reinforcement layer 12 and a surface layer 13. The base layer 11 is in contact with the slope, the reinforcement layer 12 is composed of a steel mesh, and the surface layer 13 is made of a waterproof material.

[0040] The implementation principle of a green assembled foundation pit slope support structure in an embodiment of the present application is as follows: the supporting membrane 1 is directly transported from the factory to the construction site, the supporting membrane 1 is directly laid on the slope, and the edge of the supporting membrane 1 is pressed down and fixed to the top of the slope by a prefabricated concrete top 2 at the top of the slope. At the same time, the concrete top 2 is directly fixed to the top of the slope by bolts, and the supporting membrane 1 is fixed to the slope by fasteners 3 at the middle of the slope, and the positioning rod 31 passes through the supporting membrane 1 and is inserted into the slope, and the positioning cap 32 and the driving rod 7 are connected to the positioning rod 31, and finally, the steel wire rope 4 is laid, and further limiting is performed by the steel wire rope 4. The operation is simple and convenient, which shortens the construction time of slope protection and avoids the pollution to the environment caused by on-site spraying of concrete.

[0041] The embodiment of the present application also discloses a construction method of a green assembled foundation pit slope support structure.

[0042] The following steps are involved: S1, the concrete capping 2 is prefabricated in the factory and transported to the construction site, the supporting membrane 1 is laid, the concrete capping 2 is fixed on the top of the slope and the edge of the supporting membrane 1 is pressed and fixed; S2. After the supporting membrane 1 is laid, the fastener 3 is fixed on the slope, and the steel wire rope 4 is laid at the same time, and the middle or end of the steel wire rope 4 is wound on the winding pole 321; S3, tighten the positioning cap 32.

[0043] The embodiments of this specific implementation method are all preferred embodiments of the present application, and are not intended to limit the protection scope of the present application. Therefore, all equivalent changes made based on the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A green assembled foundation pit slope support structure, characterized by: The invention comprises a supporting membrane (1), a concrete top (2), a fastener (3) and a steel wire rope (4), wherein the supporting membrane (1) is laid on the side slope, the concrete top (2) is fixed to the top of the side slope and is fixedly connected to the supporting membrane (1); a plurality of fasteners (3) are provided, and adjacent fasteners (3) are arranged at intervals, the fasteners (3) penetrate the supporting membrane (1) and are fixedly connected to the side slope, the steel wire rope (4) is laid on the supporting membrane (1), and the steel wire rope (4) is connected to the fasteners (3) adjacent to the fasteners (3) .

2. A green assembled foundation pit slope support structure according to claim 1, characterized in that: The supporting membrane (1) comprises a base layer (11), a reinforcement layer (12) and a surface layer (13); the base layer (11) is in contact with the slope, the reinforcement layer (12) is composed of a steel mesh, and the surface layer (13) is made of a material having waterproof capability.

3. The green assembled foundation pit slope support structure according to claim 1 is characterized by: The fastener (3) comprises a positioning rod (31) and a positioning cap (32); one end of the positioning rod (31) penetrates the supporting membrane (1) and is fixedly connected to the slope, and the other end of the positioning rod (31) is threadedly connected to the positioning cap (32); a winding post (321) is fixed to the positioning cap (32); the winding post (321) is arranged parallel to the positioning rod (31), and the middle part or the end part of the steel wire rope (4) is wound around the winding post (321).

4. The green assembled foundation pit slope support structure according to claim 3 is characterized by: The positioning rod (31) is provided with a first non-return assembly (5), the first non-return assembly (5) comprising a first side rod (51), a first connecting rod (52) and a first rotating shaft (53); the positioning rod (31) is provided with a first long hole (311) for receiving the first side rod (51); the first long hole (311) is provided along the length direction of the positioning rod (31); one end of the first side rod (51) is hinged to the positioning rod (31) and the hinge shaft is located in the first long hole (311); one end of the first connecting rod (52) is hinged to the first side rod (51) and the other end is hinged to the first rotating shaft (53); the first rotating shaft (53) is slidably arranged inside the positioning rod (31) and the sliding direction slides along the length direction of the positioning rod (31); The first rotating shaft (53) is pushed in a direction away from the positioning cap (32), and the first connecting rod (52) pushes the end of the first side rod (51) close to the positioning cap (32) out of the first elongated hole (311); a driving rod (7) for pushing the first rotating shaft (53) is provided on the positioning cap (32).

5. The green assembled foundation pit slope support structure according to claim 4 is characterized by: The positioning rod (31) is provided with a second non-return assembly (6), the second non-return assembly (6) comprising a second side rod (61), a second connecting rod (62) and a second rotating shaft (63); the positioning rod (31) is provided with a second long hole (312) for receiving the second side rod (61); the second long hole (312) is provided along the length direction of the positioning rod (31); the second long hole (312) and the first long hole (311) are staggered along the length direction of the positioning rod (31). The second elongated hole (312) is located on a side of the first elongated hole (311) close to the positioning cap (32); one end of the second side rod (61) is hinged to the positioning rod (31) and the hinge axis is located in the second elongated hole (312); one end of the second connecting rod (62) is hinged to the second side rod (61) and the other end is hinged to the second rotating shaft (63); the second rotating shaft (63) is slidably arranged inside the positioning rod (31) and the sliding direction slides along the length direction of the positioning rod (31); The second rotating shaft (63) is pushed in a direction away from the positioning cap (32), and the second connecting rod (62) pushes the end of the second side rod (61) close to the positioning cap (32) out of the second elongated hole (312); the driving rod (7) drives the first rotating shaft (53) to slide and also drives the second rotating shaft (63) to slide.

6. The green assembled foundation pit slope support structure according to claim 5 is characterized by: One end of the driving rod (7) is rotatably connected to the positioning cap (32), and the center line of the rotation axis coincides with the center axis of the driving rod (7). The end of the driving rod (7) away from the positioning cap (32) is provided with a notch (71), the notch (71) is cross-shaped, and the notch (71) is provided along the length direction of the driving rod (7); the end of the driving rod (7) away from the positioning cap (32) is in contact with the first rotation axis (53), and the second rotation axis (63) is located in the notch (71) and in contact with the bottom of the notch (71).

7. The green assembled foundation pit slope support structure according to claim 6 is characterized by: A centering positioning piece (8) is fixed on the driving rod (7), and the centering positioning piece (8) is used to make the center line of the driving rod (7) coincide with the center line of the positioning rod (31).

8. The green assembled foundation pit slope support structure according to claim 7 is characterized by: A slideway (313) is provided on the inner wall of the positioning rod (31), and the slideway (313) slides along the length direction of the positioning rod (31). The end of the center positioning member (8) away from the driving rod (7) is slidably arranged in the slideway (313), and the sliding direction slides along the length direction of the slideway (313).

9. The green assembled foundation pit slope support structure according to claim 3 is characterized by: Two winding posts (321) are provided and symmetrically distributed on both sides of the positioning rod (31). The two winding posts (321) are both located on the side wall of the positioning cap (32) close to the positioning rod (31). After the steel wire rope (4) passes around the two winding posts (321), it is in a wavy shape. If the steel wire rope (4) is straightened from the wavy shape to a straight shape, the steel wire rope (4) drives the positioning cap (32) to generate a rotation trend. At this time, the rotation trend of the positioning cap (32) is a tightening trend relative to the positioning rod (31).

10. A construction method using a green assembled foundation pit slope support structure as claimed in claim 3, characterized in that: The following steps are involved: S1, the concrete capping (2) is prefabricated in the factory and transported to the construction site, the supporting membrane (1) is laid, the concrete capping (2) is fixed on the top of the slope and the edge of the supporting membrane (1) is pressed and fixed; S2. After the supporting membrane (1) is laid, the fastener (3) is fixed on the slope, and the steel wire rope (4) is laid at the same time, and the middle or end of the steel wire rope (4) is wound around the winding column (321); S3. Tighten the positioning cap (32).