Construction method for mounting groove body of electric power prefabricated pipe gallery
By using C30 high-strength concrete cushion and precision equipment in the installation of power prefabricated pipe gallery, the problem of unstable sand cushion is solved, higher construction efficiency and system stability are achieved, the construction process is simplified, and the pipe gallery is ensured. System security and flatness.
Patent Information
- Application Number
- CN202411210153.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-26
AI Technical Summary
During the installation and construction of traditional power prefabricated pipe corridors, the sand cushion layer has settled and uneven due to fluidity problems, which increases construction complexity and material waste, affecting the stability and safety of the system, especially in areas with high groundwater levels or complex geological conditions. .
C30 high-strength concrete cushion layer is adopted, and the steps of trough bottoming, limiting racking, fixing of the base frame track, baffle setting and concrete pouring, track installation and adjustment can ensure the flatness and bearing capacity of the cushion layer, and use laser Precision equipment such as leveling and automatic nailing machines simplifies the construction process and realizes one-time completion of the process.
It significantly improves the flatness and bearing capacity of the cushion layer, avoids settlement and displacement risks, simplifies the construction process, reduces material waste and construction complexity, and improves the stability and construction efficiency of the pipeline system.
Smart Images

Figure CN119021271A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of civil engineering, and in particular to a method for constructing a trough body for installing a prefabricated electric power pipe gallery. Background Art
[0002] The power prefabricated pipe gallery is an underground integrated pipe gallery system for power facilities. It is usually used to centrally house municipal pipelines such as electricity, telecommunications, water supply, drainage, and gas. By centrally arranging these pipelines in the underground pipe gallery, the power prefabricated pipe gallery can not only protect various pipelines from the influence of the external environment, but also facilitate maintenance and inspection, and improve the operating efficiency and safety of urban infrastructure. When constructing the power prefabricated pipe gallery, the trough is the basic structure of the corridor, which is responsible for bearing the weight of the corridor and stabilizing it underground. This installation process requires the trough to have sufficient bearing capacity and stability to adapt to various geological conditions and ensure the safety and reliability of the corridor system in long-term use. The precise installation of the trough is crucial to the performance of the entire power prefabricated pipe gallery system, affecting the flatness of the corridor, the stability of the pipes, and the convenience of later maintenance.
[0003] In the traditional installation and construction process of prefabricated power pipe gallery, concrete and sand are usually used to construct the foundation cushion. The construction steps usually include spreading a layer of sand on the concrete cushion to achieve the purpose of leveling. However, due to the fluidity of the sand itself, the cushion is prone to settlement and unevenness, especially in areas with high groundwater levels or complex geological conditions. This phenomenon is particularly obvious. The loss or compression of sand leads to the instability of the cushion, making the pipe gallery drainage system prone to settlement or displacement during long-term use, thereby affecting the stability and safety of the entire system.
[0004] In addition, in traditional construction methods, the cushion layer usually needs to be poured and leveled multiple times. This multi-step construction method not only increases the complexity of construction, but also leads to high material waste and time costs. During the multiple pouring process, due to the complexity of the process and changes in construction conditions, quality control problems are easily caused, further reducing construction efficiency and finished product quality. Summary of the invention
[0005] In view of the shortcomings of the prior art, the present invention provides a method for constructing a trough body for installing a prefabricated power pipe gallery, which solves the problem that the cushion layer is not stable enough when paved with sand.
[0006] To achieve the above objectives, the present invention is implemented through the following technical solutions: A method for installing a trough for a prefabricated power pipe gallery comprises the following steps:
[0007] S1. Digging trench and laying bottom: Use an excavator to dig a trench with a width of 2.2 meters and a height of 1.5 meters to 2 meters, clean the bottom of the trench and use a compactor to compact it as necessary, then use a concrete mixer to prepare concrete with a strength grade of C30, and use a concrete pump truck to pour the concrete to the bottom of the trench to form a cushion layer with a thickness of 10 cm to 12 cm;
[0008] S2, limited placement rack: Use a laser level to mark parallel reference lines with a spacing of 1.2 meters, and use an electric drill to drill multiple symmetrically distributed installation holes with a spacing of 3 meters on the cushion along the reference lines. Then, align one side of the chassis with the parallel reference lines, and keep the chassis closely aligned;
[0009] S3. Fixing the chassis rail: Before installation, reserve cross nails in the installation hole position, align the chassis installation hole with the corresponding cross nails, and then use an automatic nailing machine to fix the chassis rail on the upper surface of the cushion layer;
[0010] S4. Baffle installation and concrete pouring: Baffles that are flush with the height of the chassis are placed on both sides of the chassis track and fixed with temporary support equipment. Then, concrete is poured using a concrete pump truck. C30 concrete is used to further fix the chassis. At this time, the periphery of the chassis is covered with cement, but the upper surface is not covered. After the concrete is completely solidified, the baffles are removed using a formwork remover.
[0011] S5. Track installation and adjustment: Use a crane to lift the pipes to the calibrated reference line and hole position, and use a torque wrench to connect and fix the pipes to the chassis track. Then use a laser measuring instrument to calibrate the entire track system to ensure its flatness and position accuracy.
[0012] Preferably, in step S1, the working pressure of the compactor is 30 kPa to 50 kPa, and the delivery pressure of the pump truck is 3 MPa to 6 MPa.
[0013] Preferably, in step S2, the accuracy range of the laser level is ±0.5 mm / m, and the rotation speed of the electric drill is 1500 rpm to 2500 rpm.
[0014] Preferably, in step S3, the output force of the automatic nailing machine is 100N to 150N.
[0015] Preferably, in step S4, the pumping pressure of the pump truck is 3MPa-6MPa, and the working pressure of the demolding machine is 20MPa-30MPa.
[0016] Preferably, in step S5, the measurement accuracy of the laser measuring instrument is ±0.2 mm / m.
[0017] Preferably, the base frame is rectangular in shape with two rectangular hollows in the middle, cross-arranged reinforcing ribs are distributed at the hollow positions, and a circle of reinforcing ribs is provided on the periphery.
[0018] The present invention provides a method for installing a trough for a prefabricated power pipe gallery. It has the following beneficial effects:
[0019] 1. The present invention significantly improves the flatness and bearing capacity of the cushion layer by controlling the thickness of the cushion layer and adopting C30 high-strength concrete, solves the problem of cushion layer settlement and unevenness caused by sand fluidity, thereby improving the overall stability of the pipe gallery system and avoiding the risk of settlement or displacement of the pipes due to unbalanced force.
[0020] 2. The present invention can quickly and accurately complete the baseline calibration, drilling and base frame fixing, simplifying the construction process. In addition, by reasonably arranging the steps of cushion layer pouring, frame placement and track fixing, all processes can be completed at one time, avoiding the material waste and construction complexity caused by the secondary pouring in the traditional method, thereby greatly improving the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 is a flow chart of the steps of the present invention;
[0022] Figure 2 It is a schematic diagram of the chassis structure of the present invention;
[0023] Figure 3 It is a schematic diagram of the cross nail structure of the present invention. DETAILED DESCRIPTION
[0024] The following will be combined with the drawings in the specification of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0025] Embodiment 1:
[0026] Please see attached Figure 1 -Attached Figure 3 The embodiment of the present invention provides a method for constructing a trough for installing a prefabricated power pipe gallery, comprising the following steps:
[0027] S1. Digging trench and laying bottom: Use an excavator to dig a trench with a width of 2.2 meters and a height of 1.5 meters to 2 meters, clean the bottom of the trench and use a compactor to compact it as necessary, then use a concrete mixer to prepare concrete with a strength grade of C30, and use a concrete pump truck to pour the concrete to the bottom of the trench to form a cushion layer with a thickness of 10 cm to 12 cm;
[0028] S2, limited placement rack: Use a laser level to mark parallel reference lines with a spacing of 1.2 meters, and use an electric drill to drill multiple symmetrically distributed installation holes with a spacing of 3 meters on the cushion along the reference lines. Then, align one side of the chassis with the parallel reference lines, and keep the chassis closely aligned;
[0029] S3. Fixing the chassis rail: Before installation, reserve cross nails in the installation hole position, align the chassis installation hole with the corresponding cross nails, and then use an automatic nailing machine to fix the chassis rail on the upper surface of the cushion layer;
[0030] S4. Baffle installation and concrete pouring: Baffles that are flush with the height of the chassis are placed on both sides of the chassis track and fixed with temporary support equipment. Then, concrete is poured using a concrete pump truck. C30 concrete is used to further fix the chassis. At this time, the periphery of the chassis is covered with cement, but the upper surface is not covered. After the concrete is completely solidified, the baffles are removed using a formwork remover.
[0031] S5. Track installation and adjustment: Use a crane to hoist the pipes to the calibrated reference line and hole position, and use a torque wrench to connect and fix the pipes to the chassis track. Then use a laser measuring instrument to calibrate the entire track system to ensure its flatness and position accuracy.
[0032] In step S1, the working pressure of the compactor is 30kPa to 50kPa, and the delivery pressure of the pump truck is 3MPa to 6MPa;
[0033] In step S2, the accuracy range of the laser level is ±0.5 mm / m, and the speed of the electric drill is 1500 rpm to 2500 rpm;
[0034] In step S3, the output force of the automatic nailing machine is 100N to 150N;
[0035] In step S4, the pumping pressure of the pump truck is 3MPa-6MPa, and the working pressure of the demoulding machine is 20MPa-30MPa;
[0036] In step S5, the measurement accuracy of the laser measuring instrument is ±0.2 mm / m;
[0037] The base frame is rectangular in shape with two rectangular hollows in the middle. Cross-arranged reinforcing ribs are distributed at the hollow positions, and a circle of reinforcing ribs is provided on the periphery.
[0038] Specifically, in step S1, by using a compactor to compact the bottom of the trench as necessary, the bearing capacity and stability of the bottom of the trench can be effectively improved, ensuring the uniformity and firmness of the cushion layer during subsequent construction. Using C30 strength grade concrete to cast the cushion layer can provide higher structural strength and compressive resistance, especially when bearing the weight of the power corridor and external loads. The thickness of the cushion layer is controlled between 10cm and 12cm, which helps to optimize construction costs and material usage while ensuring the durability of the structure. In step S2, using a laser level to mark parallel reference lines can ensure the high consistency and levelness of the chassis installation. To reduce the errors that may occur in the subsequent installation process, the electric drill drills symmetrically distributed installation holes with a spacing of 3m, making the fixation of the chassis more stable and reliable. The chassis is aligned with the parallel reference line and kept in a close state, which can improve the stability of the overall structure and ensure that the track system can remain flat for a long time after installation, reducing potential safety hazards caused by structural deviation; in step S3, cross nails are reserved in the installation hole position before installation to ensure that the fixing point of the chassis track is stable and accurately positioned. It is fixed by an automatic nailing machine, which not only improves the construction efficiency, but also ensures the consistency of the fixing force, reducing the possible safety hazards in manual operation. Error, this fixing method effectively enhances the overall stability of the chassis track, ensures that it will not loosen or shift during long-term use, thereby improving the safety and service life of the pipe gallery system; in step S4, baffles are placed on both sides of the chassis track and fixed with temporary support equipment, which can prevent leakage during concrete pouring, thereby ensuring the quality and appearance of concrete pouring. When the concrete pump truck is pouring, by reasonably controlling the pumping pressure, it can ensure that the concrete evenly covers the periphery of the chassis, enhancing the bonding strength between the chassis and the cushion layer. After the concrete solidifies, the baffles are removed using a demolding machine. The working pressure regulation of the demolding machine effectively reduces The labor intensity during the construction process is reduced, while ensuring the accuracy of demolding and avoiding damage to the cast structure. In step S5, a crane is used to lift the pipes to the calibrated reference line and hole position. The high-precision operation of the crane reduces the deviation during the installation process and ensures the accurate connection between the pipes and the chassis rails. When the torque wrench is used to fix the pipes, the torque can be precisely controlled to avoid excessive or insufficient tightening of the bolts and ensure the reliability of the connection. Finally, the calibration of the laser measuring instrument ensures the flatness and position accuracy of the entire track system, effectively improving the stability of the overall structure and ensuring the safety and reliability of the corridor system during operation.
[0039] Embodiment 2:
[0040] In a large-scale urban power infrastructure project, the construction team needs to lay prefabricated power pipe corridors underground to integrate multiple power and communication lines. The project construction area is located in an area with high groundwater levels and complex geological conditions. Traditional construction methods have problems such as cushion settlement, inaccurate baseline calibration, and low construction efficiency. Therefore, the construction team decided to adopt the prefabricated power pipe corridor installation trough construction method of the present invention to overcome these challenges.
[0041] Construction process:
[0042] First, at the construction site, an excavator was used to dig a 2.2-meter-wide and 1.8-meter-high trench. The depth was determined according to the geological conditions on site. After the trench bottom was cleaned, a compactor was used to compact the trench bottom. The working pressure was set to 40kPa to ensure the flatness and bearing capacity of the trench bottom. Subsequently, the construction team used concrete mixers and pump trucks to pour C30 strength grade concrete into the trench bottom, forming a cushion layer with a thickness of 11 cm. This cushion layer provided a solid foundation for the stable installation of the pipe gallery and significantly improved its flatness. The cushion layer was initially After the first step solidified, the construction workers used a laser level to mark parallel reference lines with a spacing of 1.2 meters on the cushion layer. The accuracy of the laser level was controlled within ±0.5mm / m to ensure the high accuracy of the reference line calibration. Subsequently, an electric drill was used to drill multiple symmetrically distributed installation holes on the marked reference line with a hole spacing of 3 meters. The speed of the electric drill was set to 2000rpm to ensure the accuracy of the drilling. The chassis was accurately aligned to the reference line and ensured the close fit and alignment between the chassis. After the chassis was placed, the construction workers inserted the prefabricated cross nails into the The size of the cross nails in the installation hole is 12cm to ensure sufficient fixing strength. Then, the chassis track is fixed to the cushion layer by an automatic nailing machine. The output force of the nailing machine is 120N. This process ensures the firmness of the chassis track and the stability of the overall structure. Baffles that are level with the chassis height are placed on both sides of the chassis track, and temporary support equipment is used to fix the baffles to prevent the baffles from shifting during concrete pouring. Subsequently, a concrete pump truck is used to pour C30 concrete again, and the pumping pressure is set to 5MPa to ensure that the concrete is evenly covered. The base frame is further fixed around it. After the concrete is completely solidified, the baffle is removed using a demolding machine to ensure the integrity of the entire structure. Finally, the prefabricated power pipes are hoisted to the reference line and hole positions using a crane. The crane has a lifting capacity of 15 tons, which ensures the safety and accuracy of the hoisting process. After the pipes are in place, a torque wrench is used to fix them to the base frame rails. The torque is set to 150Nm to ensure the tightening effect. Subsequently, a laser measuring instrument is used to accurately calibrate the entire track system to ensure the flatness of the track and the accuracy of the position.
[0043] This embodiment is different from the prior art in that the cushion layer in the traditional method is usually leveled with sand, which easily leads to settlement and unevenness problems, while the present invention completely solves this problem by adopting high-strength concrete and precise thickness control. The traditional construction method is complicated and easily leads to material waste. The present invention simplifies the construction process, reduces material waste and construction costs by reasonably arranging the construction steps and completing all the processes at one time. The traditional method has low accuracy in baseline calibration and base frame fixing, while the present invention significantly improves the construction accuracy through precise equipment use and optimized construction methods, thereby ensuring the long-term stability and safety of the tunnel system.
[0044] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A method for installing a trough for a prefabricated power pipe gallery, characterized in that: The following steps are involved: S1. Digging trench and laying bottom: Use an excavator to dig a trench with a width of 2.2 meters and a height of 1.5 meters to 2 meters, clean the bottom of the trench and use a compactor to compact it as necessary, then use a concrete mixer to prepare concrete with a strength grade of C30, and use a concrete pump truck to pour the concrete to the bottom of the trench to form a cushion layer with a thickness of 10 cm to 12 cm; S2, limited placement rack: Use a laser level to mark parallel reference lines with a spacing of 1.2 meters, and use an electric drill to drill multiple symmetrically distributed installation holes with a spacing of 3 meters on the cushion along the reference lines. Then, align one side of the chassis with the parallel reference lines, and keep the chassis closely aligned; S3. Fixing the chassis rail: Before installation, reserve cross nails in the installation hole position, align the chassis installation hole with the corresponding cross nails, and then use an automatic nailing machine to fix the chassis rail on the upper surface of the cushion layer; S4. Baffle installation and concrete pouring: Baffles that are flush with the height of the chassis are placed on both sides of the chassis track and fixed with temporary support equipment. Then, concrete is poured using a concrete pump truck. C30 concrete is used to further fix the chassis. At this time, the periphery of the chassis is covered with cement, but the upper surface is not covered. After the concrete is completely solidified, the baffles are removed using a formwork remover. S5. Track installation and adjustment: Use a crane to lift the pipes to the calibrated reference line and hole position, and use a torque wrench to connect and fix the pipes to the chassis track. Then use a laser measuring instrument to calibrate the entire track system to ensure its flatness and position accuracy.
2. The method for constructing a prefabricated power pipe gallery installation slot according to claim 1, characterized in that: In the step S1, the working pressure of the compactor is 30 kPa to 50 kPa, and the delivery pressure of the pump truck is 3 MPa to 6 MPa.
3. The method for constructing a prefabricated power pipe gallery installation slot according to claim 1, characterized in that: In the step S2, the accuracy range of the laser level is ±0.5 mm / m, and the rotation speed of the electric drill is 1500 rpm to 2500 rpm.
4. The method for constructing a prefabricated power pipe gallery installation slot according to claim 1, characterized in that: In the step S3, the output force of the automatic nailing machine is 100N to 150N.
5. The method for constructing a prefabricated power pipe gallery installation slot according to claim 1, characterized in that: In the step S4, the pumping pressure of the pump truck is 3MPa-6MPa, and the working pressure of the mold removal machine is 20MPa-30MPa.
6. The method for constructing a prefabricated power pipe gallery installation slot according to claim 1, characterized in that: In step S5, the measurement accuracy of the laser measuring instrument is ±0.2 mm / m.
7. The method for constructing a prefabricated power pipe gallery installation slot according to claim 1, characterized in that: The base frame is rectangular in shape, with two rectangular hollows in the middle, cross-arranged reinforcing ribs distributed at the hollow positions, and a circle of reinforcing ribs is arranged on the periphery.