Single-side formwork support installation and construction method for super-thick wall of zero-fertilizer-groove underground space structure
By optimizing the formwork support structure and construction steps, and adopting the single-sided formwork support installation method for ultra-thick walls in ultra-high and wide underground space structures with zero-groove underground space structures, the problem of insufficient load-bearing capacity of traditional formwork support systems in ultra-high and wide underground space structures has been solved, thereby reducing construction costs and improving efficiency. It is particularly suitable for the single-sided formwork support of ultra-thick walls in ultra-high and wide space structures.
Patent Information
- Application Number
- CN202411435878.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-15
- Publication Date
- 2024-11-26
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Traditional formwork support systems have insufficient load-bearing capacity, are difficult to manufacture, and have high installation costs in the construction of ultra-high and wide underground space structures and ultra-thick walls, resulting in low construction efficiency and safety hazards.
The installation method of single-side formwork support for ultra-thick walls in zero-fat underground space structures is adopted, including the erection of double-row ground operation frames, the erection of high-support plate buckle frames, the installation of single-side wall formwork and keel, and the installation of diagonal bracing and horizontal bracing. Combined with self-adhesive waterproof construction and layered concrete pouring, the formwork support structure is optimized and erected in advance.
It effectively reduces construction costs, shortens the construction period, improves construction efficiency, increases the overall structural stability, and reduces the risk of formwork instability. It is especially suitable for single-sided formwork support of ultra-thick walls in ultra-high and wide spatial structures.
Smart Images

Figure CN119021458A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to a method for installing a single-side formwork support for an ultra-thick wall of an underground space structure with a zero-fertilizer trough. Background Art
[0002] With the development of green and economic construction technology, more and more underground space structures are constructed using the open excavation method and zero fertilizer trench method. However, for the construction of ultra-high and wide underground space structures and ultra-thick walls, the traditional formwork support system has technical defects such as insufficient bearing capacity, difficulty in making fixed supports, and high installation costs. If the actual construction needs are to be met, the construction difficulty of the formwork support will be further increased, the installation cost will be further increased, the low construction efficiency will affect the overall construction progress, and the safety hazards caused by insufficient bearing capacity still exist.
[0003] Therefore, developing an economical construction method suitable for single-sided formwork support to improve construction efficiency, reduce construction costs, and improve construction safety performance has become a technical problem that needs to be urgently solved by technicians in the relevant technical field. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a single-sided formwork support installation and construction method for an ultra-thick wall of an underground space structure of a zero-fertilizer trough, so as to at least solve some of the above-mentioned technical problems.
[0005] To achieve the above purpose, the technical solution adopted by the present invention is as follows:
[0006] The installation construction method of the single-side formwork support of the ultra-thick wall of the zero-fertilizer trough underground space structure includes the following steps:
[0007] Step 1: Set up double-row floor-standing operating frames;
[0008] Step 2: Set up the high-support formwork buckle frame;
[0009] Step 3: Installation and construction of single-side wall formwork, rectangular tube secondary keel, and double steel tube main keel;
[0010] Step 4: Install the diagonal brace;
[0011] Step 5: Install horizontal bracing;
[0012] Step 6: Pour wall concrete.
[0013] Furthermore, in the step 1, C18 steel bars with a depth of 180 mm are implanted on the foundation pit supporting piles at heights of 3.5 m and 6.0 m from the top elevation of the raft slab, with an exposed length of 300 mm and a horizontal spacing of 3000 mm.
[0014] Furthermore, after the reinforcement is planted, self-adhesive waterproofing is performed on the side wall, and rubber water stop rings and water stop sheets are added to the reinforcement position and an additional waterproofing layer is added.
[0015] Furthermore, in the step 2, when the high-support formwork frame is erected, the vertical and horizontal spacing is 900mm*900mm*1500mm, the diagonal bars are arranged in 3 spans, and there are 3 horizontal scissors braces, which are respectively located at 1.0m, 5.5m and 7.5m of the bracket; after the high-support formwork frame is erected, the vertical and horizontal steel bars of the wall are tied.
[0016] Furthermore, in step 4, when installing the diagonal brace, the foundation position of the 48.3mm*3.6mm steel pipe diagonal brace with a horizontal spacing of 1500mm is measured and laid out in advance; according to the laid-out points, when tying the raft slab reinforcement, C28 U-ring bolts are embedded.
[0017] Furthermore, in step five, when installing the horizontal braces, a total of 18 48.3mm x 3.6mm steel pipe braces are provided on the wall, of which 5 are full-width braces and 13 are short braces.
[0018] Furthermore, the intersection of the horizontal bracing steel pipe and the main full-frame frame is connected with cross fasteners, and the end is locked with the main beam of the formwork by a 50-type support; the horizontal spacing of the horizontal bracing is 450mm~600mm, and the vertical spacing is 500mm.
[0019] Furthermore, the horizontal full brace is connected to all the formwork frame uprights by fasteners, and the horizontal full brace is extended by butt fasteners; the horizontal short brace is connected to the formwork frame by fasteners of at least three uprights.
[0020] Furthermore, in step six, when pouring wall concrete, a layered and symmetrical pouring method is adopted for the walls on both sides of the space, the pouring height of each layer of concrete is controlled within 0.5m, the upper layer of wall concrete is poured before the lower layer of concrete begins to set, and the time interval for pouring each layer of concrete is controlled within 2 hours.
[0021] Compared with the prior art, the present invention has the following beneficial effects:
[0022] The design of the present invention is scientific and reasonable. By optimizing the formwork support structure and setting it up in advance, and utilizing the high-support formwork buckle frame in the later stage, the construction cost can be effectively reduced. Compared with the standardized triangular steel support or the traditional double-sided formwork with tension bolts, the present invention can effectively save the time for making, hoisting or supporting the formwork on the other side of the standardized support, and can effectively shorten the construction period and improve construction efficiency. The innovative design of the bracing support structure and the high-support formwork frame of the present invention can effectively increase the stability of the overall structure and reduce the risk of formwork instability during construction. It is particularly suitable for single-sided formwork support of ultra-thick walls with ultra-high and wide space structures. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a schematic diagram of the process of the present invention.
[0024] Figure 2 This is a schematic diagram of setting up a double-row floor-standing operating frame of the present invention.
[0025] Figure 3 It is a schematic diagram of setting up the high-support formwork buckle frame of the present invention.
[0026] Figure 4 It is a schematic diagram of a pull tab of the present invention.
[0027] Figure 5 This is a schematic diagram of the installation of diagonal braces at the 1.5m and 2.5m positions of the present invention.
[0028] Figure 6 It is a cross-sectional view of the wall of the present invention.
[0029] Figure 7 for Figure 6 Section view at midpoint 1.
[0030] Figure 8 It is a schematic diagram of the node connection between the brace, diagonal brace and the steel pipe main keel. DETAILED DESCRIPTION
[0031] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0032] Example 1.
[0033] like Figure 1-8 As shown, the method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough provided by the present invention comprises the following steps:
[0034] Step 1: Set up double-row floor-standing operating frames;
[0035] Step 2: Set up the high-support formwork buckle frame;
[0036] Step 3: Installation and construction of single-side wall formwork, rectangular tube secondary keel, and double steel tube main keel;
[0037] Step 4: Install the diagonal brace;
[0038] Step 5: Install horizontal bracing;
[0039] Step 6: Pour wall concrete.
[0040] The design of the present invention is scientific and reasonable. By optimizing the formwork support structure and setting it up in advance, and utilizing the high-support formwork buckle frame in the later stage, the construction cost can be effectively reduced. Compared with the standardized triangular steel support or the traditional double-sided formwork with tension bolts, the present invention can effectively save the time for making, hoisting or supporting the formwork on the other side of the standardized support, and can effectively shorten the construction period and improve construction efficiency. The innovative design of the bracing support structure and the high-support formwork frame of the present invention can effectively increase the stability of the overall structure and reduce the risk of formwork instability during construction. It is particularly suitable for single-sided formwork support of ultra-thick walls with ultra-high and wide space structures.
[0041] Example 2.
[0042] like Figure 1-8 As shown, the method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough provided by the present invention comprises the following steps:
[0043] Step 1: Set up double-row floor-standing operating frames;
[0044] Step 2: Set up the high-support formwork buckle frame;
[0045] Step 3: Installation and construction of single-side wall formwork, rectangular tube secondary keel, and double steel tube main keel;
[0046] Step 4: Install the diagonal brace;
[0047] Step 5: Install horizontal bracing;
[0048] Step 6: Pour wall concrete.
[0049] In step 1, C18 steel bars with a depth of 180 mm are planted at 3.5 m and 6.0 m from the top elevation of the raft slab on the foundation pit support piles, with an exposed length of 300 mm and a horizontal spacing of 3000 mm. After the steel bar planting is completed, the side wall is self-adhesive waterproofing construction is carried out, and rubber water stop rings and water stop sheets are added to the steel bar planting position and an additional waterproof layer is added.
[0050] Based on Example 1, this Example 2 provides a more preferred method for erecting a double-row ground-based operating frame, specifically: in the step 1, C18 steel bars with a depth of 180mm are implanted at heights of 3.5m and 6.0m from the top elevation of the raft slab on the foundation pit support piles, with an exposed length of 300mm and a horizontal spacing of 3000mm. After the reinforcement is planted, the side wall is self-adhesive and waterproof, and rubber water stop rings and water stop plates are added to the reinforcement planting position, and an additional waterproof layer is added. The design of the present invention is scientific and reasonable, and the construction cost can be effectively reduced by optimizing the structural type of the formwork support, erecting it in advance, and utilizing the later high-support formwork buckle frame. Compared with the standardized triangular steel support or the traditional double-sided formwork with tension bolts, the present invention can effectively save the time for making, hoisting or supporting the formwork on the other side of the standardized support, and can effectively shorten the construction period and improve construction efficiency. The innovative design of the bracing support structure and the high-support formwork body of the present invention can effectively increase the stability of the overall structure and reduce the risk of formwork instability during construction. It is particularly suitable for single-sided formwork support of ultra-thick walls in ultra-high and wide space structures.
[0051] Example 3.
[0052] like Figure 1-8 As shown, the method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough provided by the present invention comprises the following steps:
[0053] Step 1: Set up double-row floor-standing operating frames;
[0054] Step 2: Set up the high-support formwork buckle frame;
[0055] Step 3: Installation and construction of single-side wall formwork, rectangular tube secondary keel, and double steel tube main keel;
[0056] Step 4: Install the diagonal brace;
[0057] Step 5: Install horizontal bracing;
[0058] Step 6: Pour wall concrete.
[0059] In the step 2, when the high-support formwork buckle frame is erected, the vertical and horizontal spacing is 900mm*900mm*1500mm, the diagonal bars are arranged in 3 spans, and there are 3 horizontal scissors braces, which are respectively located at 1.0m, 5.5m and 7.5m of the bracket; after the high-support formwork buckle frame is erected, the vertical and horizontal steel bars of the wall are tied.
[0060] Based on Example 1, this Example 3 provides a more preferred method for erecting a high-support formwork buckle frame, specifically: in the step 2, when the high-support formwork buckle frame is erected, the vertical and horizontal spacing is 900mm*900mm*1500mm, the diagonal bars are arranged in 3 spans, and there are 3 horizontal scissors braces, which are respectively located at 1.0m, 5.5m and 7.5m of the bracket; after the erection of the high-support formwork buckle frame, the vertical and horizontal steel bars of the wall are tied. The design of the present invention is scientific and reasonable, and the construction cost can be effectively reduced by optimizing the structural type of the formwork bracket, erecting it in advance, and utilizing the high-support formwork buckle frame in the later stage. Compared with the standardized triangular steel support or the traditional double-sided formwork with tension bolts, the present invention can effectively save the time of making, hoisting or supporting the formwork on the other side of the standardized bracket, and can effectively shorten the construction period and improve the construction efficiency. The innovative design of the bracing support structure and the high-support formwork body of the present invention can effectively increase the stability of the overall structure and reduce the risk of formwork instability during construction. It is particularly suitable for single-sided formwork support of ultra-thick walls in ultra-high and wide space structures.
[0061] Example 4.
[0062] like Figure 1-8 As shown, the method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough provided by the present invention comprises the following steps:
[0063] Step 1: Set up double-row floor-standing operating frames;
[0064] Step 2: Set up the high-support formwork buckle frame;
[0065] Step 3: Installation and construction of single-side wall formwork, rectangular tube secondary keel, and double steel tube main keel;
[0066] Step 4: Install the diagonal brace;
[0067] Step 5: Install horizontal bracing;
[0068] Step 6: Pour wall concrete.
[0069] In step 4, when installing the diagonal brace, the foundation position of the 48.3mm*3.6mm steel pipe diagonal brace with a horizontal spacing of 1500mm is measured and laid out in advance; according to the laid-out points, when tying the raft reinforcement, C28 U-ring bolts are embedded.
[0070] Based on Example 1, this Example 4 provides a more preferred method for installing diagonal braces, specifically: in step 4, when installing the diagonal braces, the foundation position of the 48.3mm*3.6mm steel pipe diagonal braces with a horizontal spacing of 1500mm is measured and laid out in advance; according to the laid-out points, when tying the raft slab reinforcement, C28 U-ring bolts are pre-embedded. Compared with the standardized triangular steel supports or the traditional double-sided formwork with tension bolts, the present invention can effectively save the time for making, hoisting or supporting the formwork on the other side of the standardized bracket, effectively shorten the construction period, and improve construction efficiency. The innovative design of the bracing support structure shared with the high formwork frame of the present invention can effectively increase the stability of the overall structure and reduce the risk of formwork instability during construction. It is particularly suitable for single-sided formwork support of ultra-thick walls with ultra-high and wide space structures.
[0071] Example 5.
[0072] like Figure 1-8 As shown, the method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough provided by the present invention comprises the following steps:
[0073] Step 1: Set up double-row floor-standing operating frames;
[0074] Step 2: Set up the high-support formwork buckle frame;
[0075] Step 3: Installation and construction of single-side wall formwork, rectangular tube secondary keel, and double steel tube main keel;
[0076] Step 4: Install the diagonal brace;
[0077] Step 5: Install horizontal bracing;
[0078] Step 6: Pour wall concrete.
[0079] In step five, when installing the horizontal braces, a total of 18 48.3mm x 3.6mm steel pipe braces are provided on the wall, of which 5 are full-width braces and 13 are short braces.
[0080] The intersection of the horizontal bracing steel pipe and the main full-frame frame is connected with cross fasteners, and the ends are locked with 50-type support braces and the main beam of the formwork; the horizontal spacing of the horizontal braces is 450mm~600mm, and the vertical spacing is 500mm.
[0081] The horizontal full brace is connected to all the formwork uprights with fasteners, and the horizontal full brace is extended with butt fasteners; the horizontal short brace is connected to at least three uprights of the formwork with fasteners.
[0082] Based on Example 1, this Example 5 provides a more preferred method for installing horizontal braces, specifically: in step 5, when installing horizontal braces, a total of 18 48.3mmx3.6mm steel pipe braces are set on the wall, of which 5 are full-width full braces and 13 are short braces. The intersection of the horizontal brace steel pipe and the main full-frame frame is connected by a cross buckle fastener, and the end is locked with the main beam of the formwork by a 50-type support brace; the horizontal brace has a lateral spacing of 450mm to 600mm, and a vertical spacing of 500mm. The horizontal full brace is connected to all the formwork frame uprights by fasteners, and the extension of the horizontal full brace is extended by a butt fastener; the horizontal short brace is connected to the formwork frame by at least three upright fasteners. Compared with the standardized triangular steel support or the traditional double-sided formwork with tension bolts, the present invention can effectively save the time of making, hoisting or supporting the formwork on the other side of the standardized bracket, and can effectively shorten the construction period and improve the construction efficiency. The innovative design of the bracing support structure and the high-support formwork body of the present invention can effectively increase the stability of the overall structure and reduce the risk of formwork instability during construction. It is particularly suitable for single-sided formwork support of ultra-thick walls in ultra-high and wide space structures.
[0083] Example 6.
[0084] like Figure 1-8 As shown, the method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough provided by the present invention comprises the following steps:
[0085] Step 1: Set up double-row floor-standing operating frames;
[0086] Step 2: Set up the high-support formwork buckle frame;
[0087] Step 3: Installation and construction of single-side wall formwork, rectangular tube secondary keel, and double steel tube main keel;
[0088] Step 4: Install the diagonal brace;
[0089] Step 5: Install horizontal bracing;
[0090] Step 6: Pour wall concrete.
[0091] In step six, when pouring wall concrete, a layered and symmetrical pouring method is adopted for the walls on both sides of the space, the pouring height of each layer of concrete is controlled within 0.5m, the upper layer of wall concrete is poured before the lower layer of concrete begins to set, and the time interval for pouring each layer of concrete is controlled within 2 hours.
[0092] Based on Example 1, this Example 6 provides a more preferred method for pouring wall concrete, specifically: in step 6, when pouring wall concrete, a layered and symmetrical pouring method is adopted for the walls on both sides of the space, the pouring height of each layer of concrete is controlled within 0.5m, and the upper layer of wall concrete is poured before the lower layer of concrete begins to set, and the time interval for pouring each layer of concrete is controlled within 2 hours. Compared with the standardized triangular steel support or the traditional double-sided formwork with tension bolts, the present invention can effectively save the time for making, hoisting or supporting the formwork on the other side of the standardized support, effectively shorten the construction period, and improve construction efficiency. The innovative design of the bracing support structure shared by the high formwork frame of the present invention can effectively increase the stability of the overall structure and reduce the risk of formwork instability during construction. It is particularly suitable for single-sided formwork support of ultra-thick walls with ultra-high and wide space structures.
[0093] The invention provides a construction method for an economical single-sided formwork support for ultra-thick walls suitable for ultra-high and wide underground zero-fertilizer trough space structures, aiming to improve construction safety, save material costs, and speed up construction progress. By optimizing the design and installation steps of the formwork support, this method can effectively support ultra-thick walls, reduce the complexity and construction cost of the formwork support system while maintaining structural stability.
[0094] The invention discloses a construction method for a single-sided formwork support for an ultra-thick wall of an ultra-high and wide underground zero-fertilizer trough space structure, which can complete the casting of the walls on both sides of the underground passage at one time.
[0095] Compared with the traditional single-sided formwork of the standardized triangular steel bracket or the double-sided formwork of the tension bolts, the invention saves the time of manufacturing, hoisting or installing the formwork bracket on the other side of the standardized triangular bracket, which can effectively save construction time, reduce safety risks and construction costs.
[0096] The invention discloses a method for installing a single-side formwork support for an ultra-thick wall of a zero-fertilizer trough underground space structure, comprising the following steps:
[0097] Step 1: Set up double-row ground operation frames. On the foundation pit support piles, from the top elevation of the raft slab, C18 steel bars with a depth of 180mm are implanted at a height of 3.5m and 6.0m. The exposed length is 300mm and the horizontal spacing is 3000mm. After the reinforcement is completed, the self-adhesive waterproofing of the side wall is constructed. Rubber water stop rings, water stop sheets and additional waterproofing layers are added to the reinforcement parts, such as Figure 2 shown.
[0098] Step 2: After setting up the high-support formwork buckle frame (1. Vertical and horizontal spacing 900mmx900mmx1500mm, diagonal bars are arranged in 3 spans, and there are 3 horizontal scissor braces, located at 1.0m, 5.5m, and 7.5m of the bracket respectively; 2. It is used as an operating frame for wall binding), the vertical and horizontal reinforcement of the wall is bound, and then the single-side wall formwork, rectangular tube secondary keel, and double steel tube main keel are installed. In order to control the flatness of the formwork, the pull tab is fixed by the present invention, such as Figure 3 and Figure 4 shown.
[0099] Step 3: Install the diagonal brace. Measure and lay out the foundation position of the 48.3x3.6mm steel pipe diagonal brace with a horizontal spacing of 1500mm in advance. When tying the raft reinforcement, embed the C28 U-ring bolts according to the layout points. Figure 5 shown.
[0100] Step 4: Install horizontal braces. To ensure the stability of the wall side wall formwork, the wall is equipped with 18 48.3x3.6mm steel pipe braces, including 5 full-width braces and 13 short braces. The intersections between the horizontal brace steel pipes and the main full-frame frame are all connected with cross buckles, and the ends are locked with 50-type braces and the main beam of the formwork.
[0101] The horizontal full brace is connected to all the formwork frame poles with fasteners, and the horizontal full brace itself is extended with butt fasteners; the horizontal short brace is connected to the support frame with at least three pole fasteners. The horizontal spacing of the horizontal brace is 450mm~600mm, and the vertical spacing is 500mm. Figure 6-Figure 8 shown.
[0102] Step 5: Concrete pouring. When pouring wall concrete, the layered and symmetrical pouring method is adopted for both sides of the space. The pouring height of each layer of concrete should be controlled within 0.5m. In order to eliminate the lateral pressure of the newly poured concrete on the formwork to the maximum extent and ensure the continuity of the pouring of the wall waterproof concrete, the upper layer of concrete is poured when the lower layer of concrete is about to set. The time interval for pouring each layer of concrete is controlled within 2 hours. If calculated according to the time of commercial concrete production, the time interval for pouring each layer of concrete is controlled within 4 to 6 hours.
[0103] The design of the present invention is scientific and reasonable. By optimizing the formwork support structure and setting it up in advance, and utilizing the high-support formwork buckle frame in the later stage, the construction cost can be effectively reduced. Compared with the standardized triangular steel support or the traditional double-sided formwork with tension bolts, the present invention can effectively save the time for making, hoisting or supporting the formwork on the other side of the standardized support, and can effectively shorten the construction period and improve construction efficiency. The innovative design of the bracing support structure and the high-support formwork frame of the present invention can effectively increase the stability of the overall structure and reduce the risk of formwork instability during construction. It is particularly suitable for single-sided formwork support of ultra-thick walls with ultra-high and wide space structures.
[0104] Finally, it should be noted that the above embodiments are only preferred embodiments of the present invention to illustrate the technical solution of the present invention, but not to limit it, and certainly not to limit the patent scope of the present invention. Any changes or modifications that are made to the main design concept and spirit of the present invention without any substantial meaning, and the technical problems they solve are still consistent with the present invention, should be included in the protection scope of the present invention; in addition, the direct or indirect application of the technical solution of the present invention in other related technical fields is also included in the patent protection scope of the present invention.
Claims
1. A method for installing a single-side formwork support for an ultra-thick wall of a zero-fertilizer trough underground space structure, characterized in that: The following steps are involved: Step 1: Set up double-row floor-standing operating frames; Step 2: Set up the high-support formwork buckle frame; Step 3: Installation and construction of single-side wall formwork, rectangular tube secondary keel, and double steel tube main keel; Step 4: Install the diagonal brace; Step 5: Install horizontal bracing; Step 6: Pour wall concrete.
2. The method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough according to claim 1 is characterized in that: In the step 1, C18 steel bars with a depth of 180 mm are implanted at heights of 3.5 m and 6.0 m from the top elevation of the raft slab on the foundation pit supporting piles, with an exposed length of 300 mm and a horizontal spacing of 3000 mm.
3. The method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough according to claim 2 is characterized in that: After the reinforcement is planted, self-adhesive waterproofing construction is carried out on the side walls, and rubber water stop rings and water stop plates are added to the reinforcement locations, as well as an additional waterproofing layer.
4. The method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough according to claim 1 is characterized in that: In the step 2, when the high-support formwork buckle frame is erected, the vertical and horizontal spacing is 900mm*900mm*1500mm, the diagonal bars are arranged in 3 spans, and there are 3 horizontal scissors braces, which are respectively located at 1.0m, 5.5m and 7.5m of the bracket; after the high-support formwork buckle frame is erected, the vertical and horizontal steel bars of the wall are tied.
5. The method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough according to claim 1 is characterized in that: In step 4, when installing the diagonal brace, the foundation position of the 48.3mm*3.6mm steel pipe diagonal brace with a horizontal spacing of 1500mm is measured and laid out in advance; according to the laid-out points, when tying the raft reinforcement, C28 U-ring bolts are embedded.
6. The method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough according to claim 1 is characterized in that: In step five, when installing the horizontal braces, a total of 18 48.3mm x 3.6mm steel pipe braces are provided on the wall, of which 5 are full-width braces and 13 are short braces.
7. The method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough according to claim 6 is characterized in that: The intersection of the horizontal bracing steel pipe and the main full-frame frame is connected with cross fasteners, and the ends are locked with 50-type support braces and the main beam of the formwork; the horizontal spacing of the horizontal braces is 450mm~600mm, and the vertical spacing is 500mm.
8. The method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough according to claim 6 is characterized in that: The horizontal full brace is connected to all the formwork uprights with fasteners, and the horizontal full brace is extended with butt fasteners; the horizontal short brace is connected to at least three uprights of the formwork with fasteners.
9. The method for installing and constructing a single-side formwork support for an ultra-thick wall of an underground space structure of a zero fertilizer trough according to claim 1 is characterized in that: In step six, when pouring wall concrete, a layered and symmetrical pouring method is adopted for the walls on both sides of the space, the pouring height of each layer of concrete is controlled within 0.5m, the upper layer of wall concrete is poured before the lower layer of concrete begins to set, and the time interval for pouring each layer of concrete is controlled within 2 hours.