Differential protection integral loop inspection device, system and method

CN119024084APending Publication Date: 2024-11-26STATE GRID JIBEI ELECTRIC POWER CO LTD TANGSHAN POWER SUPPLY CO +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411410092.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-10
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

In the differential protection verification, the existing technology has problems such as insufficient load current, resulting in inaccurate phase measurement, long turnover operation time, low working efficiency and prone to protection errors. It is difficult to verify the correctness of the circuit in the event of power outage, which affects the power. System safety and efficiency.

Method used

Design a differential protection overall circuit inspection device, including a time synchronization module, an MCU controller, a large current generator, a current sampling unit and a liquid crystal display screen, and check the primary side of the current circuit by generating an industrial frequency sinusoidal current with a unified reference. Wiring, secondary side wiring and protection device are provided to prevent polarity errors and reduce shut-off operation.

Benefits of technology

It realizes effective verification of differential protection function in the event of power outage, improves the quality and efficiency of differential protection acceptance, reduces the possibility of problems during power transmission, and ensures the safe and efficient operation of the power system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119024084A_ABST
    Figure CN119024084A_ABST
Patent Text Reader

Abstract

The invention discloses a differential protection integral loop testing device, system and method, and the device comprises a time synchronization module which is used for decoding a received satellite time service signal into a second pulse time service signal; the controller is connected to the output end of the time synchronization module so as to acquire the second pulse time service signal and generate a control signal according to a set initial phase and amplitude by taking the second pulse time service signal as a reference; a large current generator connected to the controller and used for generating a power frequency sinusoidal current according to the control signal so as to provide the power frequency sinusoidal current to a load; and the current sampling unit is connected to the large current generator and is used for sampling the power frequency sinusoidal current and feeding back a sampling result to the controller, so that the controller adjusts the control signal according to the sampling result. According to the invention, multiple paths of sine power frequency current with the same reference and controllable amplitudes and phases can be generated at any position, so that differential protection verification can be carried out more intuitively and conveniently, and polarity errors of a current loop are prevented.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of electric power maintenance, and in particular relates to a differential protection overall loop inspection device, system and method. Background Art

[0002] At present, the main protection for lines, transformers and busbars in power systems is mostly differential protection. Differential protection is based on the principle of current differential. In power systems, under normal circumstances, the current should be balanced between various components. When a fault occurs, the distribution of current will lose balance. At this time, differential protection can determine whether there is a fault by measuring the current difference between components, and quickly remove the fault point to protect the safe operation of the system.

[0003] In the current acceptance of new investment and protection transformation, differential protection verification is required when performing differential protection to ensure that the differential protection circuit is correctly connected. The differential protection verification of the secondary circuit is mainly achieved by adding quantity test on the relevant secondary circuit. The differential protection verification of the primary circuit can usually only be achieved by point polarity or CT (current transformer) test. These methods cannot intuitively check whether the polarity and transformation ratio of the primary original CT related to the differential protection are correct. If the CT polarity is not matched correctly, it may cause protection misoperation. In order to intuitively check whether the polarity and transformation ratio of the primary original CT (that is, the ratio of the primary and secondary currents of the CT) are correct and avoid protection misoperation, it is necessary to observe the correctness of the differential related current circuit by switching on and off the load during actual power transmission, but it is difficult to verify the correctness of the circuit when the power is off. This verification method has the following problems:

[0004] 1) When the load current is insufficient, the phase measurement is not accurate enough to verify the circuit;

[0005] 2) The switching operation takes a long time and the work efficiency is low;

[0006] 3) It is found that the problem is complex to deal with, which may easily cause false protection and pose a threat to personal safety. Summary of the invention

[0007] In order to solve the deficiencies existing in the prior art, the purpose of the present invention is to provide a differential protection overall loop inspection device and method. By installing a device composed of a time synchronization module, an MCU controller, a large current generator, a current sampling unit, a liquid crystal display and a key knob at both ends of the line, a power frequency sinusoidal current with a unified reference can be generated at each end of the differential protection without being restricted by distance; the overall function of the differential protection can be effectively verified, and the primary side wiring of the current loop, the secondary wiring and the overall coordination of the protection device setting can be checked to prevent the occurrence of polarity errors; the quality and efficiency of the overall acceptance of the differential protection when the substation is newly put into use or renovated are improved, which is conducive to smooth power transmission and effectively solves the above-mentioned problems existing in the background technology.

[0008] The present invention adopts the following technical solution.

[0009] According to the first aspect of the present invention, a differential protection overall loop inspection device is provided. The device comprises:

[0010] The time synchronization module is used to decode the received satellite timing signal to obtain the pulse-per-second timing signal;

[0011] A controller connected to the output end of the time synchronization module to obtain the second pulse timing signal, and to generate a control signal according to a set initial phase and amplitude with the second pulse timing signal as a reference;

[0012] A high current generator, connected to the controller, for generating a power frequency sinusoidal current according to the control signal to provide it to the load;

[0013] A current sampling unit is connected to the high current generator and is used to sample the industrial frequency sinusoidal current and feed back the sampling result to the controller so that the controller adjusts the control signal according to the sampling result.

[0014] Preferably, the device also includes a liquid crystal display and a key knob.

[0015] Preferably, the industrial frequency sinusoidal current is connected to the load through the L terminal and the N terminal.

[0016] Preferably, the satellite timing signal is a Beidou or GPS satellite timing signal.

[0017] Preferably, the control signal can control the phase amplitude of the industrial frequency sinusoidal current.

[0018] Preferably, the controller is an MCU controller.

[0019] Preferably, the controller adjusts the control signal according to the sampling result in the following manner:

[0020] Assume that the target generates a power frequency sinusoidal current for:

[0021]

[0022] in, I and f are the current effective value and frequency of the timing pulse signal, respectively. Φ is the set initial phase. t is the time and the offset time.

[0023] Assuming that the actual generated power frequency sinusoidal current for:

[0024]

[0025] The controller sets the amplitude adjustment threshold to ε and the phase adjustment threshold to θ; if |A'-A|>ε, the control signal is adjusted so that the adjustment amount of the power frequency sinusoidal current amplitude output by the large current generator is ΔA=α(A-A'), where α is the amplitude adjustment coefficient; if |Φ'-Φ|>θ, the control signal is adjusted so that the secondary time offset of the power frequency sinusoidal current phase output by the large current generator is β is the phase adjustment coefficient.

[0026] According to a second aspect of the present invention, a differential protection overall loop inspection system is provided. The system comprises:

[0027] Substation A and substation B are connected through a line, and each includes: a bus, a phase A differential protection CT, a circuit breaker, a bus-side disconnector, and a line-side disconnector; the bus-side port of the phase A differential protection CT is connected to the bus via the bus-side disconnector; the line-side port of the phase A differential protection CT is connected to the line via the circuit breaker and the line-side disconnector;

[0028] Device 1 and device 2 are respectively arranged in the substation A and substation B; wherein, the device 1 and device 2 adopt the differential protection overall circuit detection device according to the first aspect of the present invention; the bus side port and line side port of the A-phase differential protection CT of the substation A are respectively connected to the L terminal and N terminal of the large current generator of the device 1; the bus side port and line side port of the A-phase differential protection CT of the substation B are respectively connected to the N terminal and L terminal of the large current generator of the device 2.

[0029] According to a third aspect of the present invention, a method for verifying a differential protection overall loop is provided. The method comprises the following steps:

[0030] (1) A device 1 provided at substation A and a device 2 provided at substation B are provided; wherein both the device 1 and the device 2 adopt the differential protection overall circuit detection device according to the first aspect of the present invention; the substation A and the substation B are connected through a line, and each comprises: a bus, a differential protection CT of each phase ABC, a circuit breaker, a bus-side disconnector, and a line-side disconnector; the bus-side port of the differential protection CT of each phase ABC is connected to the bus via the bus-side disconnector; the line-side port of the differential protection CT of each phase ABC is connected to the line via the circuit breaker and the line-side disconnector;

[0031] (2) connecting the bus side port and line side port of the A-phase differential protection CT of the substation A to the L terminal and N terminal of the large current generator of the device 1 respectively; connecting the bus side port and line side port of the A-phase differential protection CT of the substation B to the N terminal and L terminal of the large current generator of the device 2 respectively;

[0032] (3) The reference time and amplitude of the industrial frequency sinusoidal current generated by the large current generators in the device 1 and the device 2 are set to be consistent through the controllers in the device 1 and the device 2, and the angles of the industrial frequency sinusoidal currents corresponding to the device 1 and the device 2 are set to be 0° and 180° respectively, and the difference between the device 1 and the device 2 is observed to be correct;

[0033] (4) Repeat steps 2 and 3 for phase B and phase C respectively.

[0034] Furthermore, the method also includes: before executing step (2), the circuit breakers, bus-side disconnectors and line-side disconnectors of the substation A and substation B are placed in an open state.

[0035] Furthermore, in step (3), observing whether the differential current between device 1 and device 2 is correct includes:

[0036] When the angles of the industrial frequency sinusoidal currents corresponding to device 1 and device 2 differ by 0°, if the differential current between device 1 and device 2 is 0, then the differential current between device 1 and device 2 is correct;

[0037] When the angles of the industrial frequency sinusoidal currents corresponding to device one and device two differ by 180°, if there is a differential current between device one and device two, then the differential current between device one and device two is correct.

[0038] The beneficial effect of the present invention is that, compared with the prior art, a time synchronization module, a controller, a large current generator, and a current sampling unit are provided, and the controller generates a control signal according to the second pulse timing signal obtained from the time synchronization module and the set initial phase and amplitude, so that the large current generator generates a corresponding industrial frequency sinusoidal current based on the control signal. Through the above-mentioned setting, multi-channel amplitude and phase controllable sinusoidal industrial frequency currents with the same reference can be generated at any position. Further, by respectively setting the differential protection overall loop inspection device of the present invention at each end of the differential protection, an industrial frequency sinusoidal current with a unified reference can be generated at each end of the differential protection. In this way, the primary current with a unified time reference at each end of the differential protection during power transmission can be simulated in the case of power failure, thereby effectively verifying the overall function of the differential protection from the root, checking the primary wiring, secondary wiring and overall coordination of the protection device setting of the current loop, preventing the occurrence of polarity errors, and avoiding repeated switching operations. Due to the early verification, the possibility of problems occurring during power transmission is further reduced, and the quality and efficiency of the overall acceptance of differential protection during new commissioning and renovation of substations are improved, which helps to smoothly transmit power. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] Figure 1 It is a structural schematic diagram of the present invention;

[0040] Figure 2 It is a schematic diagram of the method of using the present invention;

[0041] In the figure: 1 is a time synchronization module, 2 is a controller, 3 is a large current generator, 4 is a current sampling unit, 5 is a liquid crystal display, 6 is a key knob, 7 is a load, 11 is a substation A, 12 is a bus, 13 is a bus side disconnector, 14 is a differential protection CT, 15 is a circuit breaker, 16 is a device 1, 17 is a line side disconnector, 18 is a line, 19 is a substation B, and 20 is a device 2. DETAILED DESCRIPTION

[0042] In order to make the purpose, technical scheme and advantages of the present invention clearer, the technical scheme of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. The embodiments described in this application are only part of the embodiments of the present invention, not all of them. Based on the spirit of the present invention, other embodiments obtained by ordinary technicians in this field without creative work are all within the scope of protection of the present invention.

[0043] According to a first aspect of the present invention, a differential protection overall loop inspection device is provided.

[0044] like Figure 1As shown, in one embodiment, the differential protection overall loop inspection device of the present invention comprises a time synchronization module 1, a controller 2, a large current generator 3 and a current sampling unit 4.

[0045] The time synchronization module 1 is used to decode the received satellite timing signal into a pulse-second timing signal. Preferably, the satellite timing signal received by the time synchronization module 1 is a Beidou or GPS satellite timing signal. Specifically, taking the GPS satellite timing signal as an example, the time synchronization module 1 first receives a signal from a GPS satellite through a GPS antenna. These signals usually contain the satellite's position information, time information, and a pulse-second signal for synchronization. Then, the GPS receiving chip inside the time synchronization module 1 decodes and processes the received signal. The decoding process includes extracting the navigation message (including satellite ephemeris, clock error, etc.) and the pulse-second signal sent by the satellite. Subsequently, the time synchronization module 1 compares the decoded satellite clock information with the local clock, calculates the time difference between the two, and adjusts the local clock according to the time difference to synchronize it with the time of the GPS system. This synchronization process is usually achieved by adding or subtracting a time offset from the local clock. Once the local clock is synchronized with the time of the GPS system, the time synchronization module 1 can output an accurate pulse-second signal (1PPS). This pulse-second signal has very high accuracy and stability and can be used as a time reference for various systems. In addition, due to factors such as signal propagation delay, multipath effect and hardware error, the received GPS time may have certain errors. In order to reduce these errors, the time synchronization device 1 also uses some error correction technologies, such as differential positioning technology, Kalman filtering algorithm, etc. to correct the second pulse signal.

[0046] The controller 2 is connected to the output end of the time synchronization module 1 to obtain the second pulse timing signal, and uses the second pulse timing signal as a reference to generate a control signal according to the set initial phase and amplitude. Preferably, the controller 2 is an MCU (Microcontroller Unit) controller. In other embodiments, other types of controllers, dedicated or general integrated circuits, etc. can also be selected according to actual conditions.

[0047] The high current generator 3 is connected to the controller 2, and is used to generate an industrial frequency sinusoidal current according to the control signal to provide it to the load 7. Since the control signal generated by the controller 2 is based on the pulse-per-second timing signal, the industrial frequency sinusoidal current generated by the high current generator 3 is an industrial frequency sinusoidal current with a reference time as a reference and controllable phase and amplitude. Specifically, the high current generator 3 may include an adjustable oscillator, such as a voltage-controlled oscillator.

[0048] The current sampling unit 4 is connected to the high current generator 3 and is used for sampling the industrial frequency sinusoidal current and feeding back the sampling result to the controller 2 so that the controller 2 adjusts the control signal according to the sampling result.

[0049] Furthermore, the differential protection overall circuit inspection device also includes a liquid crystal display screen 5 and a key knob 6. The output end of the controller 2 is respectively connected to the liquid crystal display screen 5 and the key knob 6. The device can be controlled by the key knob 6, and the operation interface is displayed by the liquid crystal display screen 5. Through the operation interface or the key knob, the reference time, the current second pulse timing signal, and the initial phase and amplitude of the generated power frequency sinusoidal current can be set.

[0050] Furthermore, the industrial frequency sinusoidal current generated by the large current generator 3 is connected to the load 7 through the L terminal and the N terminal to provide power to the load 7 .

[0051] Preferably, the satellite timing signal received by the time synchronization module 1 is a Beidou or GPS satellite timing signal.

[0052] In practical applications, the time synchronization module 1 can receive the satellite timing signal of Beidou or GPS, and send the second pulse timing signal to the controller 2. The controller 2 is respectively connected to the liquid crystal display 5 and the key knob 6. The device can be controlled by the key knob 6, and the operation interface can be displayed through the liquid crystal display 5.

[0053] The differential protection overall loop inspection device of the present invention is described below through a specific example.

[0054] It is assumed that the reference initial time of the timing second pulse signal obtained by the time synchronization device 1 after decoding the satellite timing signal is t0, the effective value of the current is I, and the frequency f=50 Hz.

[0055] At the same time, assuming that the initial phase set received by controller 2 is Φ, controller 2 uses the received timing second pulse signal as the reference benchmark, and the target generates the industrial frequency sinusoidal current for:

[0056]

[0057] in, Offset time

[0058] Controller 2 according to A control signal is generated to control the large current generator 3 to generate an initial industrial frequency sinusoidal current with an amplitude of A and a phase of Φ. The generated industrial frequency sinusoidal current is connected to the load 7 through the L terminal and the N terminal. At the same time, the generated industrial frequency sinusoidal current is sampled by the current sampling unit 4, and the current sampling result is sent to the controller 2 through analog-to-digital conversion. The controller 2 compares the sampling result with the second pulse timing signal to calculate the amplitude A' and phase Φ' of the actual generated current.

[0059] Assume that the actual generated current waveform for:

[0060]

[0061] Then the controller 2 sets the amplitude adjustment threshold to ε. If |A'-A|>ε, the control signal is adjusted to control the large current generator 3 to adjust the output current amplitude. The adjustment amount is ΔA=α(A-A'), where α is the amplitude adjustment coefficient. At the same time, the controller 2 sets the phase adjustment threshold to θ. If |Φ'-Φ|>θ, the control signal is adjusted to control the large current generator to adjust the output current phase. The secondary time offset is β is the phase adjustment coefficient, which shifts the current waveform as a whole and adjusts the current phase. The output current is feedback-corrected in the above manner to reduce the amplitude and phase errors.

[0062] It can be seen that in this embodiment, a time synchronization module, a controller, a large current generator, and a current sampling unit are provided, and the controller generates a control signal according to the second pulse timing signal obtained from the time synchronization module and the set initial phase and amplitude, so that the large current generator generates a corresponding industrial frequency sinusoidal current based on the control signal. Through the above settings, multi-channel amplitude and phase controllable sinusoidal industrial frequency currents with the same reference can be generated at any position, so that industrial frequency sinusoidal currents with a unified reference can be generated at each end of the differential protection, so that the above device of the present invention can be used to simulate the primary current during power transmission.

[0063] According to a second aspect of the present invention, a differential protection overall loop inspection system is provided.

[0064] like Figure 2 In one embodiment, the differential protection overall loop inspection system includes: substation A 11, substation B 19, device 1 16 and device 2 20.

[0065] Substation A 11 and substation B 19 are connected through a line 18, and each includes: a bus 12, differential protection CT 14 of each phase of ABC, a circuit breaker 15, a bus-side disconnector 13, and a line-side disconnector 17. The bus-side port of the differential protection CT 14 is connected to the bus 12 via the bus-side disconnector 13; the line-side port of the differential protection CT 14 is connected to the line 18 via the circuit breaker 15 and the line-side disconnector 17.

[0066] Device 1 16 and device 2 20 are respectively arranged in the substation A 11 and substation B 19. Among them, the device 1 16 and device 2 20 adopt the differential protection overall loop detection device described in the first aspect of the present invention. The bus side port and line side port of the differential protection CT 14 of each phase ABC of the substation A 11 are respectively connected to the L terminal and N terminal of the large current generator of the device 1 16; the bus side port and line side port of the differential protection CT 14 of each phase ABC of the substation B 19 are respectively connected to the N terminal and L terminal of the large current generator of the device 2 20.

[0067] In this embodiment, through the above-mentioned settings, a power frequency sinusoidal current with a unified reference can be generated at each end of the differential protection without being restricted by distance. This current can replace the load current during actual power transmission and be applied to the differential protection CT, avoiding the situation where the loop cannot be verified due to inaccurate phase measurement when the load current is insufficient. At the same time, the present invention can effectively verify the overall function of the differential protection from the source by simulating the primary current during power transmission, check the overall coordination of the primary wiring, secondary wiring and protection device settings of the current loop, and prevent the occurrence of polarity errors. In this way, due to the verification in advance, the possibility of problems during power transmission is further reduced, and the quality and efficiency of the overall acceptance of differential protection when the substation is newly put into use or renovated is improved, which is conducive to smooth power transmission.

[0068] According to a third aspect of the present invention, a differential protection overall loop inspection method is provided.

[0069] In one embodiment, the differential protection overall loop inspection method comprises the following steps:

[0070] Step 1, providing device 1 installed in substation A and device 2 installed in substation B; wherein, both device 1 and device 2 adopt the differential protection overall circuit detection device according to the first aspect of the present invention; substation A and substation B are connected through lines, and each includes: a bus, differential protection CT of each phase ABC, a circuit breaker, a bus-side disconnector, and a line-side disconnector; the bus-side port of the differential protection CT of each phase ABC is connected to the bus via the bus-side disconnector; the line-side port of the differential protection CT of each phase ABC is connected to the line via the circuit breaker and the line-side disconnector.

[0071] Step 2: Connect the bus side port and line side port of the A-phase differential protection CT of the substation A to the L terminal and N terminal of the large current generator of the device one, respectively; connect the bus side port and line side port of the A-phase differential protection CT of the substation B to the N terminal and L terminal of the large current generator of the device two, respectively.

[0072] Step three, through the controllers in device one and device two, set the reference time and amplitude of the industrial frequency sinusoidal current generated by the large current generators in device one and device two to be consistent, and set the angles of the industrial frequency sinusoidal current corresponding to device one and device two to be 0° and 180° respectively, and observe whether the differential current between device one and device two is correct.

[0073] Step 4: Repeat steps 2 and 3 for phase B and phase C respectively.

[0074] Among them, repeatedly executing step 2 and step 3 for phase B and phase C means: first replace the phase A differential protection CT in step 2 with the phase B differential protection CT, and execute the replaced steps 2 and 3; then replace the phase A differential protection CT in step 2 with the phase C differential protection CT, and execute the replaced steps 2 and 3.

[0075] Furthermore, the method also includes: before executing step 2, the circuit breakers, bus-side disconnectors and line-side disconnectors of the substation A and substation B are placed in an open state.

[0076] Furthermore, in step 3, observing whether the differential current between device 1 and device 2 is correct includes:

[0077] When the angles of the industrial frequency sinusoidal currents corresponding to device 1 and device 2 differ by 0°, if the differential current between device 1 and device 2 is 0, then the differential current between device 1 and device 2 is correct;

[0078] When the angles of the industrial frequency sinusoidal currents corresponding to device one and device two differ by 180°, if there is a differential current between device one and device two, then the differential current between device one and device two is correct.

[0079] The beneficial effect of the present invention is that, compared with the prior art, a time synchronization module, a controller, a large current generator, and a current sampling unit are provided, and the controller generates a control signal according to the second pulse timing signal obtained from the time synchronization module and the set initial phase and amplitude, so that the large current generator generates a corresponding power frequency sinusoidal current based on the control signal. Through the above-mentioned setting, a multi-channel amplitude and phase-controllable sinusoidal power frequency current with the same reference can be generated at any position. Further, by respectively providing the differential protection overall circuit inspection device of the present invention at each end of the differential protection, a power frequency sinusoidal current with a unified reference can be generated at each end of the differential protection. In this way, the primary current with a unified time reference at each end of the differential protection during power transmission can be simulated under power failure conditions, thereby effectively verifying the overall function of the differential protection from the root, checking the overall coordination of the primary wiring, secondary wiring and protection device settings of the current circuit, preventing the occurrence of polarity errors, and avoiding repeated switching operations. Due to the verification in advance, the possibility of problems during power transmission is further reduced, and the quality and efficiency of the overall acceptance of differential protection during new investment and transformation of substations are improved, which is conducive to smooth power transmission. .

[0080] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present invention can still be modified or replaced by equivalents, and any modifications or equivalent replacements that do not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.

Claims

1. A differential protection overall loop inspection device, characterized in that: include: A time synchronization module (1) is used to decode the received satellite timing signal to obtain a second pulse timing signal; A controller (2) is connected to the output end of the time synchronization module (1) to obtain the second pulse timing signal, and uses the second pulse timing signal as a reference to generate a control signal according to a set initial phase and amplitude; A high current generator (3), connected to the controller (2), for generating a power frequency sinusoidal current according to the control signal, so as to provide the current to the load (7); A current sampling unit (4) is connected to the high current generator (3) and is used to sample the industrial frequency sinusoidal current and feed back the sampling result to the controller (2) so that the controller (2) adjusts the control signal according to the sampling result.

2. The differential protection overall circuit detection device according to claim 1, characterized in that: It also includes a liquid crystal display screen (5) and a key knob (6).

3. The differential protection overall circuit inspection device according to claim 1, characterized in that: The industrial frequency sinusoidal current is connected to the load (7) through the L terminal and the N terminal.

4. The differential protection overall loop inspection device according to claim 1, characterized in that: The satellite timing signal is a Beidou or GPS satellite timing signal; the controller (2) is an MCU controller.

5. The differential protection overall loop inspection device according to claim 1, characterized in that: The control signal can control the phase amplitude of the industrial frequency sinusoidal current.

6. The differential protection overall circuit detection device according to claim 1, characterized in that: The controller (2) adjusts the control signal according to the sampling result in the following manner: Assume that the target generates a power frequency sinusoidal current for: in, I and f are the current effective value and frequency of the timing pulse signal, respectively. Φ is the set initial phase. t is the time and the offset time. Assuming that the actual generated power frequency sinusoidal current for: The controller (2) sets the amplitude adjustment threshold value to ε and sets the phase adjustment threshold value to θ; if |A'-A|>ε, the control signal is adjusted so that the adjustment amount of the amplitude of the industrial frequency sinusoidal current output by the large current generator (3) is ΔA=α(A-A'), where α is the amplitude adjustment coefficient; if |Φ'-Φ|>θ, the control signal is adjusted so that the secondary time offset of the phase of the industrial frequency sinusoidal current output by the large current generator (3) is β is the phase adjustment coefficient.

7. A differential protection overall loop inspection system, characterized in that: include: Substation A and substation B are connected through a line, and each includes: a bus, a phase A differential protection CT, a circuit breaker, a bus-side disconnector, and a line-side disconnector; the bus-side port of the phase A differential protection CT is connected to the bus via the bus-side disconnector; the line-side port of the phase A differential protection CT is connected to the line via the circuit breaker and the line-side disconnector; Device 1 and device 2 are respectively arranged in the substation A and substation B; wherein, the device 1 and device 2 adopt the differential protection overall circuit detection device according to any one of claims 1 to 6; the bus side port and line side port of the A-phase differential protection CT of the substation A are respectively connected to the L terminal and N terminal of the large current generator of the device 1; the bus side port and line side port of the A-phase differential protection CT of the substation B are respectively connected to the N terminal and L terminal of the large current generator of the device 2.

8. A differential protection overall loop inspection method, characterized in that: The following steps are involved: (1) A device 1 provided at substation A and a device 2 provided at substation B are provided; wherein both the device 1 and the device 2 adopt the differential protection overall circuit detection device according to any one of claims 1 to 6; the substation A and the substation B are connected through a line, and each comprises: a bus, a differential protection CT of each phase ABC, a circuit breaker, a bus-side disconnector, and a line-side disconnector; the bus-side port of the differential protection CT of each phase ABC is connected to the bus via the bus-side disconnector; the line-side port of the differential protection CT of each phase ABC is connected to the line via the circuit breaker and the line-side disconnector; (2) connecting the bus side port and line side port of the A-phase differential protection CT of the substation A to the L terminal and N terminal of the large current generator of the device 1 respectively; connecting the bus side port and line side port of the A-phase differential protection CT of the substation B to the N terminal and L terminal of the large current generator of the device 2 respectively; (3) The reference time and amplitude of the industrial frequency sinusoidal current generated by the large current generators in the device 1 and the device 2 are set to be consistent through the controllers in the device 1 and the device 2, and the angles of the industrial frequency sinusoidal currents corresponding to the device 1 and the device 2 are set to be 0° and 180° respectively, and the difference between the device 1 and the device 2 is observed to be correct; (4) Repeat steps 2 and 3 for phase B and phase C respectively.

9. A differential protection overall circuit inspection method according to claim 8, characterized in that: Before executing step (2), the circuit breakers, bus-side disconnectors and line-side disconnectors of the substation A and substation B are placed in an open state.

10. A differential protection overall circuit inspection method according to claim 8, characterized in that: In step (3), observing whether the differential current between device 1 and device 2 is correct includes: When the angles of the industrial frequency sinusoidal currents corresponding to device 1 and device 2 differ by 0°, if the differential current between device 1 and device 2 is 0, then the differential current between device 1 and device 2 is correct; When the angles of the industrial frequency sinusoidal currents corresponding to device one and device two differ by 180°, if there is a differential current between device one and device two, then the differential current between device one and device two is correct.