Bridge steel-concrete combined section structure with steel shell and using method of bridge steel-concrete combined section structure
By designing the steel-concrete section structure of the bridge with steel shell, the problems of long construction time and low safety in traditional construction methods are solved, and the construction process is simplified and the load sharing capacity is improved, which significantly shortens the construction cycle and improves construction safety. sex.
Patent Information
- Application Number
- CN202411352891.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-26
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2044-09-26
AI Technical Summary
In the construction of bridge steel-concrete sections, traditional methods require the installation of lifting beams and hanging baskets to bear the load of the concrete in the wet joint section, resulting in a long and complex construction time, and the lifting beams need to be anchored and removed, affecting construction efficiency and safety.
Design a steel-concrete section structure of a bridge with steel shell. An opening is set on the top of the steel shell. The longitudinal length is greater than the length of the wet joint section. The two ends are fixedly connected to the cantilever concrete beam and the steel beam respectively, as the outer formwork and bearing of the concrete in the wet joint section. The structure is hoisted to the designed height by hanging basket and poured into concrete after welding.
The construction process is simplified, the erection and demolition of tower formwork is eliminated, the construction cycle is shortened, and the load sharing capacity and construction safety are improved.
Smart Images

Figure CN119041285A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of bridge engineering construction, and in particular relates to a bridge steel-concrete combined section structure with a steel shell and a use method thereof. Background Art
[0002] A hybrid beam bridge is a beam bridge in which a steel beam and a reinforced concrete beam are combined together through a joint in the longitudinal direction of the bridge to bear the force together. The steel-concrete joint section is an important component that connects the concrete beam section and the steel beam section in a steel-concrete hybrid beam bridge. The steel beam of the steel-concrete joint section is hoisted to the designed height on the cantilever concrete beam using a hanging basket or a bridge crane, and then the wet joint section concrete between the concrete beam and the steel beam is poured. In this way, the internal force of the steel-concrete hybrid beam bridge can be smoothly transmitted between the steel beam and the concrete beam through the steel-concrete joint section to avoid sudden changes in stiffness. Usually, the weight of the wet joint section concrete is relatively large, and the weight of the wet joint section concrete cannot be borne by the hanging basket alone. Temporary fixing devices need to be added when pouring the wet joint section concrete.
[0003] Taking the hanging basket hoisting as an example, first lift the hanging basket's hanger to the designed position, make sure the steel beam is directly below the designed position, then lower the hanger, connect the hanger to the steel beam's lifting lug, and when ready, lift the steel beam to the designed height, install the cantilever beam as a temporary fixing device for the steel beam, and finally set up the wet joint formwork to pour the wet joint concrete. In order to pour the heavy wet joint concrete, the cantilever beam often uses a steel beam with a larger cross-section to share the load when pouring the wet joint concrete.
[0004] At present, during the construction of the steel-concrete joint section, before pouring the heavy wet joint concrete, a cantilever beam is installed as a temporary fixing device for the steel-concrete joint section, and the cantilever beam and hanging basket are used to bear the load during the pouring of the wet joint concrete. The cantilever beam needs to be anchored on the cantilever concrete beam and the steel beam respectively, and after pouring the wet joint concrete, the cantilever beam needs to be removed for the convenience of the next section construction. The whole process takes up a lot of construction time. Summary of the invention
[0005] The purpose of the present invention is to provide a bridge steel-concrete combined section structure with a steel shell and a method of using the same, so as to solve the above-mentioned problems and achieve the purpose of reducing construction difficulty, shortening construction period and improving construction safety.
[0006] To achieve the above object, the present invention provides the following solution: a steel-concrete combined section structure of a bridge with a steel shell, comprising:
[0007] A steel shell, wherein the top of the steel shell is provided with an opening, and the longitudinal length of the steel shell is greater than the length of the wet joint section;
[0008] The inner contour of one end of the steel shell is the same as the outer contour of the cantilever concrete beam, and the inner wall of one end of the steel shell is fixedly connected to the outer wall of one end of the cantilever concrete beam close to the wet joint section;
[0009] The outer contour of the other end of the steel shell is similar to the outer contour of the steel beam, and the other end of the steel shell is fixedly connected to the end surface of one end of the steel beam close to the wet joint section.
[0010] Preferably, the steel shell comprises a flat bottom plate, two sides of the flat bottom plate are respectively vertically fixedly connected to the bottom ends of the vertical webs, and the tops of the two groups of vertical webs are respectively fixedly connected to the inclined bottom plates.
[0011] Preferably, the wall thickness of the flat bottom plate, the vertical web plate and the inclined bottom plate is the same as the wall thickness of the steel beam.
[0012] Preferably, a plurality of welding studs are fixedly connected to the inner wall of one end of the flat bottom plate and the vertical web plate close to the cantilever concrete beam, and the plurality of welding studs are respectively fixedly connected to the cantilever concrete beam.
[0013] Preferably, the diameter of the welding nail is 22 mm, the length is 20 mm, and the spacing between two adjacent welding nails is 200 mm.
[0014] Preferably, a plurality of stiffening ribs are fixedly connected to the inner sides of the flat bottom plate and the vertical web along the longitudinal direction, and the stiffening ribs are I-shaped ribs.
[0015] Preferably, the stiffening rib has a rib height of 150 mm and a thickness of 12 mm.
[0016] Preferably, the plurality of stiffening ribs on the vertical web are arranged in an unequal spacing manner, and the spacing between two adjacent stiffening ribs decreases gradually from top to bottom;
[0017] The plurality of stiffening ribs on the flat bottom plate are arranged at equal intervals, and the interval between two adjacent stiffening ribs is 300 mm.
[0018] A method for using a steel-concrete combined section structure of a bridge with a steel shell, the operation steps comprising:
[0019] The steel shell is assembled on the ground;
[0020] Before pouring the cantilever concrete beam, after setting up the outer formwork of the cantilever concrete beam, use the hanging basket to hoist the steel shell to the designed height so that the outer side of one end of the steel shell is close to the outer formwork;
[0021] After the steel beam is lifted to the designed height, the other end of the steel shell is butt-welded to the steel beam;
[0022] Concrete is poured into the steel shell and cured.
[0023] Compared with the prior art, the present invention has the following advantages and technical effects:
[0024] 1. The construction of the steel shell is relatively simple. It can be assembled on the ground and then hoisted up by a hanging basket. Compared with the traditional construction method, it greatly reduces the construction difficulty and construction period.
[0025] 2. The steel shell can be directly used as the outer formwork of the wet joint concrete, eliminating the process of tower formwork in the wet joint and further shortening the construction period.
[0026] 3. The two ends of the steel shell are fixedly connected to the steel beam and the cantilever concrete beam respectively, which can reliably share the load during the pouring of wet joint concrete and improve the safety of construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0028] Figure 1 This is the elevation view of the steel-concrete combined section of the present invention;
[0029] Figure 2 It is a schematic diagram of the cross section of the steel beam of the present invention;
[0030] Figure 3 It is a schematic diagram of a segment cross section of the steel shell outside the cantilever concrete beam of the present invention;
[0031] Figure 4 It is a schematic diagram of a segment cross section of a steel shell in a cantilever concrete beam of the present invention;
[0032] Among them, 1. Steel shell; 2. Flat bottom plate; 3. Vertical web; 4. Inclined bottom plate; 5. Welding nails; 6. Stiffening ribs; 7. Wet joint; 8. Cantilever concrete beam; 9. Steel beam. DETAILED DESCRIPTION
[0033] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0034] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.
[0035] Reference Figure 1-Figure 4The present invention provides a steel-concrete combined section structure of a bridge with a steel shell, comprising:
[0036] A steel shell 1, wherein the top of the steel shell 1 is provided with an opening, and the longitudinal length of the steel shell 1 is greater than the length of the wet joint section 7;
[0037] The inner contour of one end of the steel shell 1 is the same as the outer contour of the cantilever concrete beam 8, and the inner wall of one end of the steel shell 1 is fixedly connected to the outer wall of one end of the cantilever concrete beam 8 close to the wet joint 7;
[0038] The outer contour of the other end of the steel shell 1 is similar to the outer contour of the steel beam 9 , and the other end of the steel shell 1 is fixedly connected to the end surface of one end of the steel beam 9 close to the wet joint section 7 .
[0039] The upper part of the steel shell 1 is open to facilitate pouring concrete therein; the length of the steel shell 1 is greater than the length of the wet joint, so that one end of the steel shell 1 can be welded to the steel beam 9, and the other end can be wrapped around the outside of the suspended concrete beam to play the role of formwork and load-bearing. Overall, the steel shell of the present invention is relatively simple to construct. It can be assembled on the ground and then hoisted up by a hanging basket. Secondly, the steel shell can be directly used as the outer formwork of the wet joint concrete, which greatly shortens the construction period. Finally, the steel shell can reliably share the load during the pouring of the wet joint concrete, improving the safety of the construction.
[0040] According to a further optimized solution, the steel shell 1 comprises a flat bottom plate 2, two sides of the flat bottom plate 2 are respectively vertically fixedly connected to the bottom ends of the vertical webs 3, and the tops of the two groups of vertical webs 3 are respectively fixedly connected to the inclined bottom plates 4.
[0041] like Figure 3 As shown, the flat bottom plate 2 and the vertical web plate 3 form an outer formwork for pouring concrete, and the inclined bottom plate 4 is used to provide a pouring formwork for the cantilever structure at the edge of the bridge.
[0042] According to a further optimization scheme, the wall thickness of the flat bottom plate 2 , the vertical web plate 3 and the inclined bottom plate 4 is the same as the wall thickness of the steel beam 9 .
[0043] By setting the wall thickness of the flat bottom plate 2, the vertical web plate 3 and the inclined bottom plate 4 to be the same as the plate thickness of the corresponding part of the steel beam 9, the continuity of the overall structure of the bridge is improved.
[0044] According to a further optimized solution, a plurality of welding nails 5 are fixedly connected to the inner wall of the flat bottom plate 2 and the vertical web plate 3 at one end close to the cantilever concrete beam 8, and the plurality of welding nails 5 are fixedly connected to the cantilever concrete beam 8 respectively.
[0045] According to a further optimized solution, the diameter of the welding nail 5 is 22 mm, the length is 120 mm, and the spacing between two adjacent welding nails 5 is 200 mm.
[0046] like Figure 4As shown, in order to strengthen the connection between the steel shell 1 and the cantilever concrete beam 8, welding nails 5 are arranged at equal intervals on the segment flat bottom plate 2 and the vertical web plate 3 of the steel shell 1 in the cantilever concrete beam 8. After pouring concrete, the connection performance between the steel shell 1 and the cantilever concrete beam 8 is improved by extending the welding nails 5 into the cantilever concrete beam 8.
[0047] According to a further optimized solution, a plurality of stiffening ribs 6 are fixedly connected to the inner sides of the flat bottom plate 2 and the vertical web plate 3 along the longitudinal direction, and the stiffening ribs 6 are I-shaped ribs.
[0048] like Figure 3 As shown, the main function of the stiffening ribs 6 is to improve the bearing capacity of the flat bottom plate 2 and the vertical web 3 so as to better bear the load during the pouring of the wet joint concrete.
[0049] According to the further optimization scheme, the rib height of the stiffening rib 6 is 150 mm and the thickness is 12 mm.
[0050] To further optimize the solution, the plurality of stiffening ribs 6 on the vertical web 3 are arranged in an unequal spacing manner, and the spacing between two adjacent stiffening ribs 6 gradually decreases from top to bottom;
[0051] The plurality of stiffening ribs 6 on the flat bottom plate 2 are arranged at equal intervals, and the interval between two adjacent stiffening ribs 6 is 300 mm.
[0052] like Figure 3 As shown, in the vertical direction, the pressure exerted by the concrete on the lower part of the vertical web 3 is greater than the pressure on the upper part. Therefore, the stiffening ribs 6 on the vertical web 3 are arranged to be distributed more and more densely from top to bottom, which can effectively improve the bearing capacity of the vertical web 3 and make the distribution number of the stiffening ribs 6 reasonable.
[0053] A method for using a steel-concrete combined section structure of a bridge with a steel shell, the operation steps comprising:
[0054] The steel shell 1 is assembled on the ground;
[0055] Before pouring the cantilever concrete beam 8, after the outer formwork of the cantilever concrete beam 8 is erected, the steel shell 1 is hoisted to the designed height using a hanging basket so that the outer side of one end of the steel shell 1 is closely attached to the outer formwork;
[0056] After the outer formwork of the cantilever concrete beam 8 is built, the steel shell 1 is lifted to the designed height using a hanging basket, and it is ensured that the steel shell 1 fits closely with the inner side of the outer formwork. When pouring the cantilever concrete beam 8, the end of the steel shell 1 and the welding nails 5 can be directly in contact with the concrete, and finally the steel shell 1 and the cantilever concrete beam 8 are in a connected state. After the outer formwork is removed, the steel shell 1 can be used as a permanent device to wrap the concrete, further improving the connection performance.
[0057] After the steel beam 9 is lifted to the designed height, the other end of the steel shell 1 is butt-welded to the steel beam 9;
[0058] By welding the steel beam 9 to the steel shell 1, the steel shell 1 can be used not only as an outer formwork for the concrete of the wet joint section 7, but also as a load-bearing member for supporting the weight of the steel beam 9 segment and concrete during the construction of the steel-concrete joint section.
[0059] Concrete is poured into the steel shell 1 and cured.
[0060] In the description of the present invention, it should be understood that the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0061] The embodiments described above are only descriptions of the preferred modes of the present invention, and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.
Claims
1. A steel-concrete combined section structure of a bridge with a steel shell, characterized in that: include: A steel shell (1), wherein the top of the steel shell (1) is provided with an opening, and the longitudinal length of the steel shell (1) is greater than the length of the wet joint section (7); The inner contour of one end of the steel shell (1) is the same as the outer contour of the cantilever concrete beam (8), and the inner wall of one end of the steel shell (1) is fixedly connected to the outer wall of one end of the cantilever concrete beam (8) close to the wet joint section (7); The outer contour of the other end of the steel shell (1) is similar to the outer contour of the steel beam (9), and the other end of the steel shell (1) is fixedly connected to the end surface of one end of the steel beam (9) close to the wet joint section (7).
2. The steel-concrete combined section structure of a bridge with a steel shell according to claim 1, characterized in that: The steel shell (1) comprises a flat bottom plate (2), the two sides of which are respectively vertically fixedly connected to the bottom ends of vertical webs (3), and the tops of the two groups of vertical webs (3) are respectively fixedly connected to inclined bottom plates (4).
3. The steel-concrete combined section structure of a bridge with a steel shell according to claim 2, characterized in that: The wall thickness of the flat bottom plate (2), the vertical web plate (3) and the inclined bottom plate (4) is the same as the wall thickness of the steel beam (9).
4. The steel-concrete combined section structure of a bridge with a steel shell according to claim 2, characterized in that: A plurality of welding nails (5) are fixedly connected to the inner wall of one end of the flat bottom plate (2) and the vertical web plate (3) close to the cantilever concrete beam (8), and the plurality of welding nails (5) are respectively fixedly connected to the cantilever concrete beam (8).
5. The steel-concrete combined section structure of a bridge with a steel shell according to claim 4, characterized in that: The diameter of the welding nail (5) is 22 mm, the length is 120 mm, and the spacing between two adjacent welding nails (5) is 200 mm.
6. The steel-concrete combined section structure of a bridge with a steel shell according to claim 2, characterized in that: A plurality of stiffening ribs (6) are fixedly connected along the longitudinal direction to the inner sides of the flat bottom plate (2) and the vertical web plate (3), and the stiffening ribs (6) are I-shaped ribs.
7. The steel-concrete combined section structure of a bridge with a steel shell according to claim 6, characterized in that: The stiffening rib (6) has a rib height of 150 mm and a thickness of 12 mm.
8. The steel-concrete combined section structure of a bridge with a steel shell according to claim 6, characterized in that: The plurality of stiffening ribs (6) on the vertical web (3) are arranged in an unequal spacing manner, and the spacing between two adjacent stiffening ribs (6) gradually decreases from top to bottom; The plurality of stiffening ribs (6) on the flat bottom plate (2) are arranged at equal intervals, and the interval between two adjacent stiffening ribs (6) is 300 mm.
9. A method for using a steel-concrete combined section structure of a bridge with a steel shell, characterized in that: Based on the steel-concrete combined section structure of a bridge with a steel shell according to claim 1, the operation steps include: The steel shell (1) is assembled on the ground; Before pouring the cantilever concrete beam (8), after the outer formwork of the cantilever concrete beam (8) is erected, the steel shell (1) is hoisted to the designed height using a hanging basket so that the outer side of one end of the steel shell (1) is closely attached to the outer formwork; After the steel beam (9) is lifted to the designed height, the other end of the steel shell (1) is butt-welded to the steel beam (9); Concrete is poured into the steel shell (1) and cured.
Citation Information
Patent Citations
Composite beam for cable-stayed bridge
CN106812057A
Fabricated steel-concrete composite bridge superstructure and construction process thereof
CN114592440A
Steel-concrete hybrid beam continuous rigid frame bridge suspension casting and hoisting construction method
CN115341483A
Fabricated steel-concrete composite beam and construction method thereof
CN117626786A
A composite beam for cable -stay bridge
CN206591418U