Land high-strength batholith construction method under complex geological environment
Through segmented design and GPS-positioned sand-blown bag laying, the stability of the cofferdam is calculated, combined with the water stop treatment of high-pressure spin-spray piles and pine piles, the safety and stability of high-strength rock foundation construction in complex geological environments are solved. , improves project quality and construction efficiency.
Patent Information
- Application Number
- CN202411165956.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-23
- Publication Date
- 2024-11-29
AI Technical Summary
In complex geological environments, the existing technology is difficult to ensure the safety and stability of onshore high-strength rock foundation construction, and the cofferdam after construction has not been checked for relevant strength, resulting in doubt about its stability.
Using the sectional design and construction method, the cofferdam is divided into several sectional layers. Through GPS positioning and laying and drainage precipitation of sand blowing bags, the overall stability, anti-slip stability and seepage stability are calculated to ensure that each sectional layer meets the requirements. Design requirements, and water stop treatment is carried out through double rows of high-pressure rotary spray piles and pine piles.
The quality of the project is improved, the overall stability and anti-slip performance of the cofferdam are ensured, the quality and construction period requirements are met, and the safety and stability of high-strength rock foundation construction in complex geological environments are achieved.
Smart Images

Figure CN119041460A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of cofferdam construction, and in particular to an onshore high-strength rock foundation construction method under a complex geological environment. Background Art
[0002] In the prior art, only relevant designs were carried out during the excavation of the harbor foundation trench and the construction of the cofferdam. However, in the complex environment, it was difficult to ensure the safety of the entire rock foundation construction, and the cofferdam after construction was not verified for relevant strength, etc., which led to doubts about its stability. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a method for constructing high-strength rock foundation on land under complex geological environment.
[0004] In order to solve the above technical problems, the technical solutions provided by the present invention are as follows: A method for constructing high-strength rock foundation on land in a complex geological environment, in which the cofferdam is divided into several parts by separating weirs, and the construction is carried out in the order of taking sand points, from the shore side to the sea side, and from the sea side to the wharf cofferdam; The cofferdam construction includes the following steps: First locate the top edge of the sand blowing bag and the bottom edge of the filling bag, and then use GPS positioning to lay out the filling bag; Each cofferdam is divided into several sections, and each end surface layer is laid with filling bags, sand blown and drained. After the first layer of the first section is filled, the first layer of the second section is filled, and then the second layer of the first section is filled again; Take a typical section layer in each cofferdam and calculate the overall stability, anti-sliding stability and seepage stability of the typical section layer to determine whether it meets the requirements; It also includes the excavation of the harbor and foundation trench below the cofferdam before the cofferdam construction, specifically from top to bottom, layer by layer and section by section, excavating downwards along the slope line.
[0005] Furthermore, the sand bag blowing and filling adopts a high-pressure water pump to pump seawater nearby to flush the sand, and a mud pump to pump the sand. The filling process is carried out in the order of filling, slurry feeding, secondary filling, and the thickness of the sand body in the bag meets the design requirements.
[0006] Furthermore, the sandbag filling is specifically a step-by-step filling operation method, which is to fill the first layer of the previous section with sandbags, and then fill the first layer of the next section with sandbags, and then return to fill the second layer of the previous section with sandbags.
[0007] Furthermore, it also includes cofferdam water stopping, specifically, water stopping is achieved through the construction of double rows of high-pressure rotary jet piles and double rows of pine piles, wherein the diameter of the large end of the pine pile is greater than or equal to 10 cm, and the small end is a pointed shape with a length of not less than 30 cm.
[0008] Furthermore, the overall stability is calculated using Slide6.0 slope stability analysis software, and its safety factor is not less than 1.1, which meets the requirements.
[0009] Furthermore, the anti-sliding stability is calculated by the bearing capacity limit design expression, as shown in formula (1):
[0010] Where: c 0——Structural importance coefficient, take 1.0; cd ——Horizontal wave force partial coefficient, take 1.2; cE ——Earth pressure partial coefficient, take 1.35; γpw ——Residual water pressure partial coefficient, take 1.05; γG ——Deadweight partial coefficient, take 1.0; f ——The friction coefficient of the cofferdam bottom surface is taken as 0.3.
[0011] Furthermore, the seepage stability calculation includes a critical hydraulic gradient formula and a hydraulic slope, both of which meet the requirements at the same time.
[0012] Furthermore, the critical hydraulic gradient formula is specifically: i cr =(G s -1)*(1-n)=(G s -1) / (1+e) (2) Among them, G s is the specific gravity of the soil, n is the porosity, and e is the void ratio.
[0013] Furthermore, the calculation formula of the hydraulic gradient is: i=△h / L (3) i represents, △h is the water level difference in the cofferdam, and L represents the seepage diameter.
[0014] The present invention has the following beneficial effects: The present invention fully considers the segmented design and construction, and respectively uses the overall stability, anti-sliding stability and seepage stability to judge the strength of the cross-section layer, thus providing a basis for improving the quality of the project. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 A flow chart of the cofferdam construction process in the foundation trench excavation construction provided by the present invention; Figure 2The present invention provides a flow chart for the construction of a temporary cofferdam. DETAILED DESCRIPTION
[0016] The present invention is described in detail below in conjunction with the various embodiments shown in the accompanying drawings, but it should be noted that these embodiments are not limitations of the present invention, and any equivalent transformations or substitutions in functions, methods, or structures made by ordinary technicians in the field based on these embodiments are all within the scope of protection of the present invention.
[0017] See attached Figure 1-2 As shown, the solution in the present invention is used in a local confidential project, which is mainly a fishing port project. It is necessary to form dry construction conditions to meet the requirement of a short project period. At this time, it is necessary to assist through the construction of a temporary cofferdam (i.e., the cofferdam in the present invention).
[0018] The following is an introduction based on the specific circumstances of the project. 1. Project Features
[0019] In this project, geological surveys show that the strength of medium-weathered rock is 40-90Mpa. At the same time, the water depth of this project is relatively shallow (average water depth of 1-2.5 meters), and ships and machinery cannot enter the undredged areas of the harbor for construction, which seriously restricts the construction of breakwaters and docks. At this time, a comparative analysis of underwater blasting by drilling and blasting ships, underwater blasting by carbon dioxide, underwater blasting by carbon dioxide, underwater blasting by underwater gunners, and dry construction of temporary cofferdams suitable for the construction of this project was conducted, and Table 1 was obtained.
[0020] Table 1 Comparison of rock foundation treatment construction technology
[0021] After comparison and comprehensive evaluation of various construction technologies, it was found that only by forming dry construction conditions can the construction period and quality requirements of this project be met in order to treat the weathered granite on the north side of the harbor, the breakwater and the wharf foundation trench. Therefore, temporary cofferdams were set up on the north side of the harbor (including the west breakwater XK0+700~XK0+826 and the north breakwater foundation trench) and outside the wharf foundation trench.
[0022] In this project, the cofferdam and excavation are arranged in two major areas: the cofferdam on the north side of the harbor and the temporary cofferdam on the dock; each area is divided into three small areas by two partition weirs. The cofferdam on the north side of the harbor is divided into areas one to three from east to west, and the dock cofferdam is divided into areas one to three from north to south.
[0023] The cofferdams are arranged along the periphery of the unexcavated areas of the harbor basin and foundation trench, covering the remaining water areas of the harbor basin that cannot be excavated and the foundation trench areas with rock foundation treatment. In order to speed up the construction of the harbor basin and foundation trench, two partition weirs are set up in each large area to divide it into three small areas, and the cofferdams are constructed continuously, that is, the cofferdam construction of one small area is completed during the construction, and the covering layer and rock foundation of one small area are treated.
[0024] The project has a total cofferdam length of 2507m, 336,000m³ of bagged sand, 483,000m³ of harbor and foundation trench excavation, 1.41 million㎡ of split-film yarn woven geotextile, and 180,000㎡ of two fabrics and one membrane. The construction period of this project is only within 140 days, and the exact time is 136 days.
[0025] In this project, the foundation trench excavation includes the north breakwater foundation trench excavation, the west breakwater foundation trench excavation, the wharf foundation trench excavation and the revetment foundation trench excavation. The north breakwater foundation trench excavation is BK0+000-BK0+380, the west breakwater foundation trench excavation is XK0+700-XK0+826, and the wharf foundation trench excavation is MK0+000-MK0+801.86. The bottom elevation of the harbor excavation is -3.5m and -4.5m. In order to facilitate construction, the cofferdam is arranged in an area that does not involve medium-weathered granite as much as possible, but there is a medium-weathered granite layer in some locations, especially under the weir, and the excavation of the rock layer below is particularly important. During construction, according to the actual situation on site, the adjacent partitions with excavation conditions will be merged, the weir will be removed, and the underlying cover layer and medium-weathered granite will be excavated. If the cofferdam cannot be constructed as described above, a temporary cofferdam shall be added to the excavated area, the original cofferdam shall be partially dismantled, and the covering layer and moderately weathered granite under the original cofferdam shall be processed.
[0026] According to the characteristics of this project, we selected construction equipment with high construction efficiency and did a good job in equipment maintenance. Three 220kw high-power mud pumps were used to fill sand bags and three 110kw mud pumps were used to pump water for cofferdam construction; 12 excavators, 4 loaders, 6 pickaxes, and 24 dump trucks were used for harbor and foundation trench excavation; and one 8m³ grab dredger and two 2000t flat barges were used for cofferdam removal. This ensured that harbor and foundation trench excavation was completed on time.
[0027] The construction of the cofferdam is divided into three lines, in the order of cofferdam area 1 on the north side of the harbor (cofferdam area 1 on the wharf) → cofferdam area 2 on the north side of the harbor (cofferdam area 2 on the wharf) → cofferdam area 3 on the north side of the harbor (cofferdam area 3 on the wharf). At this time, the construction is carried out starting from the sand taking point and in the order of from the shore to the sea side and / or from the sea side to the wharf cofferdam.
[0028] This project mainly includes cofferdam construction, harbor and foundation trench excavation and cofferdam removal. 2. Introduction of construction technology
[0029] 1. Temporary cofferdam construction In this embodiment, it is necessary to go through the steps of measurement and positioning, setting up sand delivery pipelines, processing and laying sandbags, blowing and filling sandbags, and draining and settling sandbags. In the processing and laying of sandbags, the bag body is protected by an outer geotextile during transportation to prevent damage or aging. If damage occurs, take measures to fill the bag in time. When processing sandbags, cuffs and reserved pipes are arranged at intervals of 4m. When blowing and filling sandbags, the bag bodies are laid in layers parallel to the axis of the cofferdam, stacked neatly, and the upper and lower bag bodies are laid with staggered seams, and the bags on the same layer squeeze each other. The bag body is raised layer by layer to prevent the local embankment section from being raised by two layers at a time. The sandbags are blown and filled using a step-by-step sand blowing operation method: after the first layer is blown and filled in the first section, the first layer of the second section is blown and filled, and then the second layer of the first section is blown and filled again, and so on, and the construction is carried out in a cycle.
[0030] In this embodiment, the specific cofferdam construction process is as follows: 1.1 Construction Preparation (1) Prepare a detailed construction plan and provide safety and technical briefings to on-site construction personnel to ensure that personnel, materials, and construction machinery are in place in a timely manner.
[0031] (2) Inspect and dredge the seabed in the area where the filling bags are to be laid, and clean up any corrosive debris or debris that may easily scratch the filling bags.
[0032] 1.2 Measurement and positioning (1) Before filling construction, the top edge line of the filling bag and the bottom edge line of the filling bag should be located first, and the number of layers of the filling bags should be controlled according to the seabed elevation. The number of stacking layers of filling bags varies at different water depths, and the filling height of the bagged sand should be adjusted accordingly.
[0033] (2) The laying of the filling bags is positioned by GPS. The underwater sandbag cofferdam is fixed with steel pipes, with a pile spacing of 10 meters, arranged along both sides of the filling bags. The steel pipes are positioned by GPS and manually injected. After the filling bags are spread on the water, the two sides of the filling bags are tied to the steel pipes with ropes to fix them; after the filling bags on the water are processed, they are manually transported to the site for laying, and GPS is used to locate them based on the actual situation.
[0034] 1.3 Sand transport pipeline installation The sand conveying pipe is gradually advanced along the direction of the cofferdam and is installed on the filled sand bags.
[0035] (1) When laying sand transport pipelines, try to make them smooth and straight, and avoid dead bends, so as to minimize the resistance head loss along the pipeline and the local resistance head loss, and reduce the dynamic load. Geotextiles should be laid under the pipeline to prevent damage to the sand bags that have been blown.
[0036] (2) The sand delivery pipe opening is connected to the sand bag reserved pipe. The interface should be firm to prevent it from falling off.
[0037] 1.4 Sandbag processing and laying (1) Sand bag processing The processing of sandbags uses split film silk woven geotextiles with appropriate width. The width direction is perpendicular to the axis of the cofferdam. The splicing seams are nylon threads. The seams are folded into three layers, with a seam width of 5cm and three seams (first sew one, then fold and then sew two). The strength after sewing is not less than 70% of the strength of the original geotextile. After the sandbags are processed, their filled dimensions meet the design requirements. The width, height and longitudinal length of each layer of the filling bag are calculated in longitudinal sections according to the measured mud surface elevation. Geotextiles are sewn on the top and bottom surfaces of each layer of filling bags. Each geotextile is 500mm long, 50mm wide, and 3m apart in the longitudinal direction. The bag body is protected by an outer geotextile during transportation to prevent damage or aging. If damage occurs, take measures to fill the bag in time. When processing sandbags, cuffs and reserved pipes are arranged at intervals of 4m.
[0038] (2) Laying of filling bags Before laying the bottom layer of filling bags, lay two layers of two cloths and one film at the bottom of the cofferdam according to the design drawings.
[0039] When laying underwater filling bags, two rows of DN40 steel pipes are placed at about 5m from the bag body along both sides of the center of the cofferdam as positioning markers. Each pile is 8m long and is fixed by a manual sledgehammer. The depth of the pile is about 2m, and the longitudinal spacing is 10m, which is about 1 / 3 of the length of the filling bag. The head, middle and tail of the filling bag are fixed to the positioning piles with nylon ropes. The water filling bags are laid manually. (3) The laying of filling bags must meet the following requirements: 1) The filling bags are laid along the axis of the cofferdam and are a whole in the horizontal direction. The staggered length of the upper and lower bags is not less than 2m.
[0040] 2) There should be no gap between the two bags after filling.
[0041] 3) The laying of filling bags should be controlled according to the designed slope ratio.
[0042] 4) To prevent the occurrence of through gaps, the filling bags constructed later should be dragged about 2m toward the front section at the contact surface with the front section so that they can be better connected with the front section during filling.
[0043] 1.5 Blown sand bags The length and width of each filling bag are set according to the construction requirements: the filling port is arranged on the surface of the bag body, and one filling port is arranged every 4m, the pipe port diameter is 15cm, and each filling port is set with a cuff, the cuff length is 1m, and the cuff is connected to a 3~5mφ150 reserved pipe (the reserved pipe is a rubber pipe, and the length is arranged according to the water depth). The reserved pipe is fixed with a small float. 50% of the reserved pipe is an overflow pipe, which is used for drainage and to detect whether the sandbag is filled. After filling, the bag mouth must be tied tightly.
[0044] High-pressure water pumps are used to pump seawater nearby to flush sand, and mud pumps are used to pump sand. The filling process is carried out in the order of filling, slurry feeding, secondary filling, and the thickness of the sand body in the bag meets the design requirements. The bag filling fullness is controlled at 70%, and the filling thickness does not exceed 0.5m. The sand filling is guaranteed to be flat and solid, and the height is increased layer by layer; the bags are laid in layers parallel to the axis of the cofferdam, stacked neatly, and the upper and lower bags are laid with staggered seams, and the bags on the same layer squeeze each other. The bags are raised layer by layer to prevent the local embankment section from being raised by two layers at one time.
[0045] 1.6 Sand bag drainage sedimentation (1) After the sand is transported into the filling bag through the sand delivery pipeline, the filling bag is filled with sand and drained at the same time. The filling speed should not be too fast. When the filling bag sinks, a special person must be assigned to control the speed and position of the filling bag, and constantly adjust the sinking position during the sinking process.
[0046] (2) The sandbags are blown in a step-by-step manner: after the first layer of the first section is blown, the first layer of the second section is blown, and then the second layer of the first section is blown back, and so on, in a circular manner. The first layer of sandbags above the water surface is closed at low tide.
[0047] (3) Before laying the sandbags, lay two layers of two-sheets and one membrane at the bottom of the cofferdam according to the design drawings. During the subsequent cofferdam construction, the two-sheets and one membrane on the outside of the cofferdam are laid one section after the cofferdam is formed, and the sandbags are exposed to the sun as much as possible to avoid damage to the sandbags.
[0048] 2. Water stop of cofferdam Specifically, it includes the construction of double-row high-pressure rotary jet piles and double-row pine wood piles.
[0049] The implementation of double-row jet grouting piles is determined based on the actual thickness of the sand layer on site. If the thickness of the sand layer is less than 0.3m, it can be cancelled. The implementation of double-row wooden piles is determined based on the actual thickness of the sand layer on site. If the thickness of the sand layer is less than 0.3m, it can be cancelled.
[0050] 3. Excavation of harbor basin and foundation trench After the cofferdam is formed, according to the actual area and pumping capacity of the site, one 110KW water pump is configured in each of the two large areas on the dock and the north side of the harbor to pump water (which can be used to fill the cofferdam with water). At the same time, two 7.5KW water pumps are configured in each area to maintain pumping water in each area and maintain dry construction conditions.
[0051] After the pumping is completed, the floating mud in the harbor and foundation trench within the enclosure is blown into the land sedimentation tank through a 22kw mud pump.
[0052] In order to protect the temporary cofferdam, 5m (excavation slope not less than 1:2) is reserved at the foot of the temporary cofferdam during excavation and no excavation is carried out first. The excavation will be carried out together with the cofferdam when it is dismantled.
[0053] (1) Construction sequence The order of excavation of the harbor basin and foundation trench is the same as the order of cofferdam construction. For example, after the first area of the cofferdam on the north side of the harbor basin (the first area of the dock cofferdam) is formed, the first area of the cofferdam on the north side of the harbor basin (the first area of the dock cofferdam) will be immediately pumped out to form dry construction conditions. Backhoes, pickaxes, and dump trucks will enter the construction site. The construction is divided into two lines: ① From east to west: cofferdam area 1 on the north side of the harbor → the first barrier weir → cofferdam area 2 on the north side of the harbor → the second barrier weir → cofferdam area 3 on the north side of the harbor; ② From north to south: wharf cofferdam area 1 → first barrier weir → wharf cofferdam area 2 → second barrier weir → wharf cofferdam area 3.
[0054] (2) Determination of excavation scope and slope According to the construction drawings, the original mud surface elevation within the cofferdam range is -0.5m~-1.5m, and the port basin is excavated to -3.5m (-4.5m); the wharf foundation trench needs to be excavated to -5.5m~-11.1m according to the foundation trench section, and the foundation trench slope excavation is controlled according to the actual situation. The slope ratio of the rock foundation part is 1:1, and the slope ratio of the soil foundation part is 1:2.5. When excavating the overburden layer, for the rock foundation that cannot be excavated to the design elevation, the rock surface is cleared as much as possible during the construction process, and the supervision engineer will measure and confirm on site.
[0055] (3) Excavation of overburden and strongly weathered layers 1) When excavating, first measure and locate, level and lay out, determine the excavation width, and dig the soil in blocks (sections) and layers according to the laid out lines. According to the soil quality and hydrological conditions, slope excavation is adopted to ensure the safety of construction operations.
[0056] 2) Set up a survey control network in the construction area, including control baselines, axis lines and horizontal reference points; do a good job of checking the axis control measurement. The control network should avoid buildings, structures, earth-moving machinery operations and transportation routes, and have protection signs; set up a 10×10m grid for site leveling, make control stakes at each grid point, and measure the natural terrain and elevation at each stake as the basis for calculating the excavation volume and construction control.
[0057] 3) Excavate evenly in sections and layers.
[0058] 4) When using an excavator to excavate the foundation trench and harbor basin, dig in layers and sections from top to bottom and dig downward along the slope line. It is strictly forbidden to work at a height exceeding 3m or under unstable soil. However, the center of each layer should be slightly higher than the two sides to prevent water accumulation.
[0059] 5) When soft soil or quicksand is found on the excavation slope, or cracks appear on the ground surface, stop excavation and take appropriate remedial measures in time to prevent soil collapse and sliding.
[0060] 6) When excavating with a backhoe, the following two construction methods are used: End excavation method: The excavator excavates from the end of the harbor or foundation trench by driving backward, and dump trucks are placed on both sides of the excavator to transport soil.
[0061] Lateral excavation method: The excavator moves along one side of the harbor or foundation trench, and the dump truck loads soil on the other side.
[0062] 7) For earth that cannot be dug by machines, manual excavation will be carried out and the earth will be transported to places where machines can dig so that it can be dug away in time.
[0063] 8) Clear the bottom. Draw a horizontal line 300mm from the actual elevation of the trench bottom, drive in small wooden stakes, and then manually dig away the temporary soil layer.
[0064] 9) When excavating the harbor basin and foundation trench, leave enough good soil for backfilling if conditions permit; the excess soil should be transported away at once to avoid secondary transportation.
[0065] (4) Excavation of moderately weathered granite 1) The excavation of medium-weathered granite is carried out in layers from top to bottom. During the construction, the rock layer is first crushed in layers using an onshore pickaxe, and the excavator is equipped with a dump truck to remove the rock blocks. The crushing is carried out according to the designed slope gradient and the elevation of the harbor or foundation trench. When the crushing reaches the designed slope or elevation, the crushing is stopped and the slope or base is repaired using an excavator.
[0066] 2) Based on the precisely measured excavation contour of the foundation trench or harbor basin, since the excavation and crushing method is layered excavation from top to bottom, the first-level construction platform is first built according to the actual terrain to facilitate the placement of the pickaxe machine and backhoe excavator.
[0067] 3) Arrange construction workers on site to divide the area according to the actual terrain, and the pickaxe machine will crush the rock according to the arranged area divisions. When the pickaxe machine is crushing, the drill rod of the pickaxe machine is pressed on the rock, and after maintaining a certain pressure, the pickaxe machine is started to use the impact force of the pickaxe to crush the rock.
[0068] 4) When the pickaxe machine breaks the rock mass, it must be broken strictly according to the slope ratio. It is not allowed to have a slope deficit or a slope ratio that is too large. After the rock layer on the first-level construction platform is broken into place and the slope is corrected and leveled with an excavator, the rock breaking construction of the next construction platform can be carried out.
[0069] 5) When the pickaxe machine is breaking, the backhoe excavator cooperates to remove the broken rock and load the broken rock onto a truck. The transportation vehicle is a dump truck and transports it to the designated location until the slope of the harbor or foundation trench is formed and the elevation of the harbor or foundation trench meets the design requirements.
[0070] (5) Construction access road layout During construction, the soil is turned on site, and the cover layer, strongly weathered granite and moderately weathered granite below the access road are constructed first. After the construction is completed, the construction access road is paved with the cover layer soil and stones of the harbor. The construction access road has a pavement width of 8m, and a layer of rocks and gravel dug out of the harbor or foundation trench is added to the pavement, with a slope of 1:1.5 on both sides. After the construction of the harbor and foundation trench is completed, the retreat method is used to excavate the construction access road.
[0071] 4. Cofferdam removal After the treatment of the medium-weathered granite in the cofferdam area is completed, the temporary cofferdam is removed. Before the cofferdam is removed, water is pumped into the cofferdam with a pump. When the water level in the cofferdam is not lower than the water level outside, the removal begins away from the foundation trench to prevent damage to the excavated harbor and foundation trench due to excessive water level difference. A grab dredger is equipped with two flat barges to remove the cofferdam in sections. The sand is transported by the flat barge to the temporary loading platform and then transported to the designated location by a dump truck.
[0072] After part of the cofferdam is removed, the installation of caissons in relevant areas will begin while ensuring safety and quality.
[0073] The order of dismantling the cofferdam on the north side of the harbor basin: after the construction of the barrier weir is completed in each area, the covering layer and medium-weathered granite under the cofferdam are dismantled and processed. After the covering layer and medium-weathered granite of the outermost cofferdam in the entire area are processed, the cofferdam on the south side (from east to west) is processed first to meet the conditions for installing caissons. The cofferdam on the north side is dismantled using onshore equipment and is carried out simultaneously with the installation of caissons. The dismantling of the wharf cofferdam is the same as the cofferdam on the north side of the harbor basin, and the dismantling direction is from north to south.
[0074] The cofferdam is arranged as a whole in the excavated area of the original harbor basin. The bottom of the cofferdam involves the covering layer and the medium-weathered granite area. Before demolition, a cofferdam is added to the excavated area on the periphery, and then the cofferdam and excavated covering layer and medium-weathered granite are demolished.
[0075] In this embodiment, in order to ensure the safety and stability of construction, each cofferdam is then divided into several cross-section layers. Before construction, the typical cross-section layer can be selected based on various parameters such as water depth, and then the overall stability, anti-sliding stability, and seepage stability of the typical cross-section layer can be calculated to determine whether the requirements are met.
[0076] 5. Requirements for harbor basin and foundation trench excavation operations (1) When the excavator is operating, the end digging method or the side digging method is adopted. The dump truck is arranged in front of or on the side of the excavator to reduce the rotation angle and improve productivity.
[0077] (2) The number of dump trucks should be based on the size of the excavator, productivity and construction period requirements to ensure continuous operation of the excavator.
[0078] (3) In the corners of the harbor basin and foundation trench where mechanical excavation is not possible, a small amount of manual labor is used to clear the slope and move the loose soil within the operating radius of the machine before it is transported away by the machine.
[0079] (4) When excavators and dump trucks enter and exit construction access roads, they should try to use the adjacent areas on one or both sides of the foundation that need to be excavated later, so that they can be connected to each other as driveways, or use the areas where the earth has been excavated in advance as construction access roads for several adjacent areas to reduce the amount of excavation.
[0080] 6. Contents of foundation pit excavation.
[0081] (1) When the foundation pit is excavated to the design elevation, the soil quality should be checked. The soil quality at the bottom of the pit should meet the design requirements.
[0082] Number of inspections: The construction unit, supervision unit and design unit shall conduct a complete inspection according to the construction section.
[0083] Inspection method: Check construction records and conduct observation inspection.
[0084] (2) The plane position of the foundation pit excavation meets the design requirements and the cross-sectional dimensions are not less than those specified in the design.
[0085] Number of inspections: All inspections must be carried out by the construction unit and the supervision unit.
[0086] Inspection method: Check cross-sectional measurement data.
[0087] (3) The allowable deviation, inspection quantity and inspection method of underwater foundation trench excavation shall comply with the requirements of Table 4.3.2.3-1 and Table 4.3.2.3-2 of the Quality Inspection Standard for Water Transport Engineering (JTS257-2008). 3: In this embodiment, the cofferdam structure calculation sheet
[0088] 1. Standards and specifications adopted
[0089] (1) Code for Design of Foundations for Water Transport Engineering (JTS 147-2017); (2) "Design Specifications for Dredging and Filling Projects" (JTS 181-5-2012); (3) Hydrographic Specifications for Ports and Waterways (JTS145-2015); (4) Code for Design of Breakwaters and Bank Protection (JTS154-1-2018); Other current national, industry and local standards, specifications and regulations. 2. Calculation content
[0090] The main calculation contents of temporary bagged sand cofferdam are as follows: (1) Overall stability; (2) Anti-slip stability; (3) Calculation of foundation settlement; (4) Calculation of seepage stability. 3. Calculation method and results
[0091] 1) Overall stability calculation Slide6.0 slope stability analysis software is used to calculate the overall stability of a typical section of a temporary cofferdam. This process includes an introduction to residual soil, sandy soil-like strong weathering, fragmented strong weathering, and moderate weathering.
[0092] In this embodiment, the calculation table of the overall stability of the cofferdam for a typical cross-section layer is shown in Table 2.
[0093]
[0094] According to empirical calculations, the overall stability safety factor of temporary cofferdams is greater than 1.1, meeting the relevant requirements of the "Code for Design of Foundations for Water Transport Engineering" (JTS 147-2017). 2) Stability calculation of temporary cofferdam 2-2 section
[0095] Specifically, it includes the calculation of strong weathering and moderate weathering of sandy soil on the cross section.
[0096] According to the Code for Design of Wharf Structures (JTS 167-2018), the design expression of the bearing capacity limit of the anti-sliding stability of temporary cofferdam is as follows:
[0097] Where: c 0——Structural importance coefficient, take 1.0; cd ——Horizontal wave force partial coefficient, take 1.2; cE ——Earth pressure partial coefficient, take 1.35; γpw ——Residual water pressure partial coefficient, take 1.05; γG ——Deadweight partial coefficient, take 1.0; f ——The friction coefficient of the cofferdam bottom surface is taken as 0.3.
[0098] The calculation table of the anti-sliding stability of the cofferdam for a typical section layer of a certain part of the classic interface is shown in Table 3.
[0099] Table 3 Calculation table of anti-sliding stability of temporary cofferdam
[0100] 3) Calculation of foundation settlement According to the "Water Transport Engineering Foundation Design Code" (JTS147-2017), the final settlement is calculated using the layered summation method: Where: S ∞ ——final settlement (m); h i ——thickness of the i-th soil layer (m); 1i 、e 2i ——are the average self-weight pressure of the i-th layer of soil (б si ) and the average final pressure (б si +б zi ) porosity ratio when compression is stable; m s ——Empirical correction coefficient, take 1.1.
[0101] Calculations show that the total foundation settlement is approximately 0.05~0.15m.
[0102] 4) Seepage stability calculation According to the critical hydraulic gradient formula: i cr =(G s -1)*(1-n)=(G s -1) / (1+e) (2) Among them, G s is the specific gravity of the soil, n is the porosity, and e is the void ratio.
[0103] Calculate the critical hydraulic gradient of each typical section, see formula: i=△h / L (3) i represents, △h is the water level difference in the cofferdam, and L represents the seepage diameter.
[0104] The calculation table of critical hydraulic steps for a typical section layer of a certain part of the classic interface is shown in Table 4.
[0105] Table 4 Calculation table of critical hydraulic gradient of each section of temporary cofferdam.
[0106]
[0107] The hydraulic gradient can be calculated based on the water level difference △h (design high water level) inside and outside the cofferdam: i=△h / L The calculation results are shown in Table 5 below.
[0108] Table 5 Temporary cofferdam anti-seepage calculation table
[0109] Calculation conclusion After calculation, the overall stability, anti-sliding stability and seepage stability of the temporary cofferdam meet the requirements.
[0110] 4. Other construction
[0111] In this embodiment, the excavation of the harbor basin and foundation trench is also included.
[0112] After the cofferdam is formed, according to the actual area and pumping capacity of the site, one 110KW water pump is configured in each of the two large areas on the dock and the north side of the harbor to pump water (which can be used to fill the cofferdam with water). At the same time, two 7.5KW water pumps are configured in each area to maintain pumping water in each area and maintain dry construction conditions.
[0113] After the pumping is completed, the floating mud in the harbor and foundation trench within the enclosure is blown into the land sedimentation tank through a 22kw mud pump.
[0114] In order to protect the temporary cofferdam, 5m (excavation slope not less than 1:2) is reserved at the foot of the temporary cofferdam during excavation and no excavation is carried out first. The excavation will be carried out together with the cofferdam when it is dismantled.
[0115] (1) Construction sequence The order of excavation of the harbor basin and foundation trench is the same as the order of cofferdam construction. For example, after the first area of the cofferdam on the north side of the harbor basin (the first area of the dock cofferdam) is formed, the first area of the cofferdam on the north side of the harbor basin (the first area of the dock cofferdam) will be immediately pumped out to form dry construction conditions. Backhoes, pickaxes, and dump trucks will enter the construction site. The construction is divided into two lines: ① From east to west: cofferdam area 1 on the north side of the harbor → the first barrier weir → cofferdam area 2 on the north side of the harbor → the second barrier weir → cofferdam area 3 on the north side of the harbor; ② From north to south: wharf cofferdam area 1 → first barrier weir → wharf cofferdam area 2 → second barrier weir → wharf cofferdam area 3.
[0116] (2) Determination of excavation scope and slope According to the construction drawings, the original mud surface elevation within the cofferdam range is -0.5m~-1.5m, and the port basin is excavated to -3.5m (-4.5m); the wharf foundation trench needs to be excavated to -5.5m~-11.1m according to the foundation trench section, and the foundation trench slope excavation is controlled according to the actual situation. The slope ratio of the rock foundation part is 1:1, and the slope ratio of the soil foundation part is 1:2.5. When excavating the overburden layer, for the rock foundation that cannot be excavated to the design elevation, the rock surface is cleared as much as possible during the construction process, and the supervision engineer will measure and confirm on site.
[0117] (3) Excavation of overburden and strongly weathered layers 1) When excavating, first measure and locate, level and lay out, determine the excavation width, and dig the soil in blocks (sections) and layers according to the laid out lines. According to the soil quality and hydrological conditions, slope excavation is adopted to ensure the safety of construction operations.
[0118] 2) Set up a survey control network in the construction area, including control baselines, axis lines and horizontal reference points; do a good job of checking the axis control measurement. The control network should avoid buildings, structures, earth-moving machinery operations and transportation routes, and have protection signs; set up a 10×10m grid for site leveling, make control stakes at each grid point, and measure the natural terrain and elevation at each stake as the basis for calculating the excavation volume and construction control.
[0119] 3) Excavate evenly in sections and layers.
[0120] 4) When using an excavator to excavate the foundation trench and harbor basin, dig in layers and sections from top to bottom and dig downward along the slope line. It is strictly forbidden to work at a height exceeding 3m or under unstable soil. However, the center of each layer should be slightly higher than the two sides to prevent water accumulation.
[0121] 5) When soft soil or quicksand is found on the excavation slope, or cracks appear on the ground surface, stop excavation and take appropriate remedial measures in time to prevent soil collapse and sliding.
[0122] 6) When excavating with a backhoe, the following two construction methods are used: End excavation method: The excavator excavates from the end of the harbor or foundation trench by driving backward, and dump trucks are placed on both sides of the excavator to transport soil.
[0123] Lateral excavation method: The excavator moves along one side of the harbor or foundation trench, and the dump truck loads soil on the other side.
[0124] 7) For earth that cannot be dug by machines, manual excavation will be carried out and the earth will be transported to places where machines can dig so that it can be dug away in time.
[0125] 8) Clear the bottom. Draw a horizontal line 300mm from the actual elevation of the trench bottom, drive in small wooden stakes, and then manually dig away the temporary soil layer.
[0126] 9) When excavating the harbor basin and foundation trench, leave enough good soil for backfilling if conditions permit; the excess soil should be transported away at once to avoid secondary transportation.
[0127] (4) Excavation of moderately weathered granite 1) The excavation of medium-weathered granite is carried out in layers from top to bottom. During the construction, the rock layer is first crushed in layers using an onshore pickaxe, and the excavator is equipped with a dump truck to remove the rock blocks. The crushing is carried out according to the designed slope gradient and the elevation of the harbor or foundation trench. When the crushing reaches the designed slope or elevation, the crushing is stopped and the slope or base is repaired using an excavator.
[0128] 2) Based on the precisely measured excavation contour of the foundation trench or harbor basin, since the excavation and crushing method is layered excavation from top to bottom, the first-level construction platform is first built according to the actual terrain to facilitate the placement of the pickaxe machine and backhoe excavator.
[0129] 3) Arrange construction workers on site to divide the area according to the actual terrain, and the pickaxe machine will crush the rock according to the arranged area divisions. When the pickaxe machine is crushing, the drill rod of the pickaxe machine is pressed on the rock, and after maintaining a certain pressure, the pickaxe machine is started to use the impact force of the pickaxe to crush the rock.
[0130] 4) When the pickaxe machine breaks the rock mass, it must be broken strictly according to the slope ratio. It is not allowed to have a slope deficit or a slope ratio that is too large. After the rock layer on the first-level construction platform is broken into place and the slope is corrected and leveled with an excavator, the rock breaking construction of the next construction platform can be carried out.
[0131] 5) When the pickaxe machine is breaking, the backhoe excavator cooperates to remove the broken rock and load the broken rock onto a truck. The transportation vehicle is a dump truck and transports it to the designated location until the slope of the harbor or foundation trench is formed and the elevation of the harbor or foundation trench meets the design requirements.
[0132] (5) Construction access road layout During construction, the soil is turned on site, and the cover layer, strongly weathered granite and moderately weathered granite below the access road are constructed first. After the construction is completed, the construction access road is paved with the cover layer soil and stones of the harbor. The construction access road has a pavement width of 8m, and a layer of rocks and gravel dug out of the harbor or foundation trench is added to the pavement, with a slope of 1:1.5 on both sides. After the construction of the harbor and foundation trench is completed, the retreat method is used to excavate the construction access road.
[0133] 5. Cofferdam removal
[0134] After the treatment of the medium-weathered granite in the cofferdam area is completed, the temporary cofferdam is removed. Before the cofferdam is removed, water is pumped into the cofferdam with a pump. When the water level in the cofferdam is not lower than the water level outside, the removal begins away from the foundation trench to prevent damage to the excavated harbor and foundation trench due to excessive water level difference. A grab dredger is equipped with two flat barges to remove the cofferdam in sections. The sand is transported by the flat barge to the temporary loading platform and then transported to the designated location by a dump truck.
[0135] After a part of the cofferdam is removed, the installation of caissons in the relevant areas will begin under the premise of ensuring safety and quality. The order of dismantling the cofferdam on the north side of the harbor is as follows: After the construction of the barrier weir is completed in each area, the covering layer and medium-weathered granite under the cofferdam are removed and processed. After the covering layer and medium-weathered granite of the outermost cofferdam in the entire area are processed, the cofferdam on the south side (from east to west) is processed first to meet the conditions for installing caissons. The cofferdam on the north side is dismantled by land equipment and is carried out simultaneously with the installation of caissons. The dismantling of the wharf cofferdam is the same as the cofferdam on the north side of the harbor, and the dismantling direction is from north to south.
[0136] The cofferdam is arranged as a whole in the excavated area of the original harbor basin. The bottom of the cofferdam involves the covering layer and the medium-weathered granite area. Before demolition, a cofferdam is added to the excavated area on the periphery, and then the cofferdam and excavated covering layer and medium-weathered granite are demolished.
[0137] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
[0138] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A method for constructing high-strength rock foundation on land in a complex geological environment, characterized in that: The cofferdam is divided into several parts by separating weirs. The construction is carried out starting from the sand taking point, from the shore side to the sea side, and from the sea side to the wharf cofferdam in the order of following the sand taking point; The cofferdam construction includes the following steps: First locate the top edge of the sand blowing bag and the bottom edge of the filling bag, and then use GPS positioning to lay out the filling bag; Each cofferdam is divided into several sections, and each end surface layer is laid with filling bags, sand blown and drained. After the first layer of the first section is filled, the first layer of the second section is filled, and then the second layer of the first section is filled again; Take a typical section layer in each cofferdam and calculate the overall stability, anti-sliding stability and seepage stability of the typical section layer to determine whether it meets the requirements; It also includes the excavation of the harbor and foundation trench below the cofferdam before the cofferdam construction, specifically from top to bottom, layer by layer and section by section, excavating downwards along the slope line.
2. The method for constructing high-strength rock foundation on land in a complex geological environment according to claim 1, characterized in that: The sand bag blowing and filling adopts a high-pressure water pump to pump seawater nearby to flush the sand, and a mud pump to pump the sand. The filling process is carried out in the order of filling, slurry feeding, secondary filling, and the thickness of the sand body in the bag meets the design requirements.
3. The method for constructing high-strength rock foundation on land in a complex geological environment according to claim 1, characterized in that: The sandbag filling is specifically a step-by-step filling operation method, in which after the first layer of the previous section is filled, the first layer of the next section is filled, and then the second layer of the previous section is filled again.
4. The method for constructing high-strength rock foundation on land in a complex geological environment according to claim 1, characterized in that: It also includes cofferdam water stopping, which is achieved through the construction of double rows of high-pressure rotary jet piles and double rows of pine wood piles. The diameter of the large end of the pine wood pile is greater than or equal to 10 cm, and the small end is a pointed shape with a length of not less than 30 cm.
5. The method for constructing high-strength rock foundation on land in a complex geological environment according to claim 1, characterized in that: The overall stability is calculated using Slide 6.0 slope stability analysis software, and if the safety factor is not less than 1.1, the requirements are met.
6. The onshore high-strength rock foundation construction method in a complex geological environment according to claim 1, characterized in that: The anti-sliding stability is calculated by the bearing capacity limit design expression, as shown in formula (1): Where: γ 0——Structural importance coefficient, take 1.0; γd ——Horizontal wave force partial coefficient, take 1.2; γE ——Earth pressure partial coefficient, take 1.35; γpw ——Residual water pressure partial coefficient, take 1.05; γG ——Deadweight partial coefficient, take 1.0; f ——The friction coefficient of the cofferdam bottom surface is taken as 0.
3.
7. The method for constructing high-strength rock foundation on land in a complex geological environment according to claim 1, characterized in that: The seepage stability calculation includes the critical hydraulic gradient formula and the hydraulic slope, both of which meet the requirements at the same time.
8. The method for constructing high-strength rock foundation on land in a complex geological environment according to claim 7, characterized in that: The critical hydraulic gradient formula is specifically: i cr =(G s -1)*(1-n)=(G s -1) / (1+e) (2) Among them, G s is the specific gravity of the soil, n is the porosity, and e is the void ratio.
9. The method for constructing high-strength rock foundation on land in a complex geological environment according to claim 71, characterized in that: The calculation formula of the hydraulic gradient is: i=△h / L (3) i represents, △h is the water level difference in the cofferdam, and L represents the seepage diameter.