Method for converting double-side-wall pilot tunnel method to single-side-wall pilot tunnel method for ultra-large-span multi-arch tunnel

By gradually shortening the excavation error distance, installing temporary arches and optimizing the construction sequence in the super-large span continuous arch tunnel, the transformation of the double-sided wall guide pit normal to single-sided wall guide pit method is achieved, and construction in the existing technology is solved The problems of single method and poor safety and economicality have improved construction efficiency and project quality.

CN119041918APending Publication Date: 2024-11-29YUEYANG TRAFFIC HIGHWAY ENG CONSTR CO LTD +4
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411395478.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-08
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

The lack of research on the conversion of the double-sided wall excavation method to single-sided wall excavation method of ultra-large span tunnels in the construction of existing double-continuous arch tunnels has resulted in a single construction method, poor safety and economicality, and it is difficult to follow the surrounding rock and geological conditions. Changes to adjust the working method.

Method used

A method for converting the double-sided wall guide pit method to the single-sided wall guide pit method of super-large span continuous arch tunnel is proposed. By gradually shortening the excavation error distance, installing temporary arches, and following the outside first and then the inside from top to bottom Principles, optimize construction sequence and steps, realize synchronous excavation of multiple sections, and reduce construction costs and environmental impact.

Benefits of technology

It improves the safety and economicality of construction, reduces material waste and unnecessary work, enhances tunnel stability, simplifies construction management, improves construction efficiency and project quality, and reduces the impact on the environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041918A_ABST
    Figure CN119041918A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of tunneling methods, and discloses a method for converting a double-side-wall pilot tunnel method to a single-side-wall pilot tunnel method for an ultra-large-span multi-arch tunnel. The method comprises the steps that when middle pilot tunnel construction exceeds an end section, when a first main tunnel is constructed to be close to an initial section, the excavation staggered distance is gradually shortened till the upper step sections of an outer pilot tunnel and an inner pilot tunnel of the first main tunnel coincide on the initial section, and the upper step section of a first middle pilot tunnel and the initial section keep a safe distance. And the upper and lower steps of the three pilot pits of the first main hole keep short step pitches. And a temporary inverted arch is additionally installed, and forward alternate excavation is conducted according to the sequence of the first left upper portion, the first left lower portion, the first right upper portion and the first right lower portion till the whole tunnel face is excavated to form an end section. The second main hole has an excavation staggered distance relative to the first main hole, construction method conversion lags behind the first main hole, but the conversion sequence and steps are the same. According to the method, multiple construction faces are allowed to be excavated synchronously, so that the construction period is shortened, and temporary supporting materials are saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel excavation methods, and in particular to a construction method for converting a double-side wall pilot tunnel method into a single-side wall pilot tunnel method for a super-large span multi-arch tunnel. Background Art

[0002] The characteristics of a multi-arch tunnel are that the tunnel has two parallel tunnels on the left and right, with a large excavation span, and most of them are super-large span tunnel structures. When the multi-arch tunnel is shallow and the surrounding rock conditions are poor, it should be designed more reasonably, and different construction methods should be adopted through step-by-step excavation to ensure construction safety while improving construction efficiency and economic benefits.

[0003] However, the conversion between different construction methods is still a challenge for engineers. Especially for the construction of ultra-large span multi-arch tunnels, there has been no relevant research on "converting from double-side wall excavation method to more economical single-side wall excavation method based on the premise of simultaneous construction of multiple sections of the main tunnel and the middle guide tunnel".

[0004] The prior art has the following defects or deficiencies:

[0005] 1. The existing double-arch tunnel construction mostly adopts the same excavation scheme for both the entrance and the tunnel body excavation, and fails to adopt a more suitable and economical construction method according to the changes in the surrounding rock and geological conditions.

[0006] 2. The existing tunnel construction conversion from complex construction methods to economical construction methods (such as double-side wall excavation method to single-side wall excavation method, double-side wall excavation method to step excavation method) is only applied to single-hole tunnels. There has been no research on the conversion of arch-type three-pilot tunnels to economical construction methods during the excavation process. Compared with single-hole tunnels, arch-type tunnels are more complicated in the conversion of construction methods, and additional consideration needs to be given to factors such as the construction sequence between pilot tunnels, the step distance of the pilot tunnel sections, and the step distance of the steps in the pilot tunnels. Summary of the invention

[0007] The present invention provides a method for converting a double-side wall pilot pit method to a single-side wall pilot pit method for a super-large span double-arch tunnel, which can realize simultaneous excavation of multiple construction surfaces, save a lot of time and material costs for subsequent construction, and solve the technical problems of the existing double-arch tunnel construction, single excavation scheme, poor safety and economy.

[0008] The present invention provides a method for converting a double-side-wall pilot tunnel method to a single-side-wall pilot tunnel method in a super-large-span multi-arch tunnel. The starting point of the conversion is an initial section, and the end point of the conversion is an ending section. The method comprises the following steps: S100, the middle pilot tunnel is constructed first and exceeds the ending section; S200, when the first main tunnel is constructed to the point close to the initial section, the excavation offset is gradually shortened, until the excavation sections of the upper step of the first outer pilot tunnel and the upper step of the first inner pilot tunnel overlap at the initial section, the upper step section of the first middle pilot tunnel approaches the initial section and maintains a safe distance from the initial section, and the upper steps of the first outer pilot tunnel, the first middle pilot tunnel and the first inner pilot tunnel of the first main tunnel are A short step distance is maintained with the lower step; S300, a temporary invert is installed, and based on the temporary invert, it is divided into the first upper left part away from the middle guide tunnel, the first lower left part away from the middle guide tunnel, the first upper right part close to the middle guide tunnel, and the first lower right part close to the middle guide tunnel; S400, following the principle of first outside and then inside and from top to bottom, the first upper left part, the first lower left part, the first upper right part and the first lower right part are excavated forward alternately in sequence until the entire heading face is excavated out of the ending section; S500, the second main tunnel has an excavation offset relative to the first main tunnel, and the construction method conversion of the second main tunnel lags behind that of the first main tunnel. The construction method conversion sequence and steps are the same as those of the first main tunnel.

[0009] Further, step S200 is specifically as follows: S201, when the construction of the first main tunnel is close to the initial section, the excavation offset of the first outer guide pit, the first inner guide pit and the first middle guide pit is gradually shortened; S202, the construction of the first main tunnel continues, and the excavation sections of the upper step of the first outer guide pit and the upper step of the first inner guide pit are made to overlap at the initial section; S203, the upper step section of the first middle guide pit approaches the initial section and maintains a safe distance from the initial section, and the safety distance range belongs to the preparation section for the conversion of the construction method.

[0010] Further, step S300 is specifically as follows: S301, installing a temporary invert in the first middle guide pit to improve the safety of the construction method conversion; S302, on the cross-section of the first main tunnel, with the midpoint of the temporary invert as the center, it is divided longitudinally and transversely into a first upper left part away from the middle guide tunnel, a first lower left part away from the middle guide tunnel, a first upper right part close to the middle guide tunnel, and a first lower right part close to the middle guide tunnel.

[0011] Further, step S400 includes: S401, the first upper left part includes the first part of the upper step area of ​​the first middle guide pit and the upper step area of ​​the first outer guide pit, the first upper left part is excavated forward to the end section and forms the first upper left step area, and then the initial support is carried out in time, and a temporary invert arch and a vertical steel arch frame are erected to close the first upper left part.

[0012] Further, step S400 includes: S402, the first lower left part includes the first part of the lower step area of ​​the first middle guide pit and the lower step area of ​​the first outer guide pit, the first part of the lower step area of ​​the first middle guide pit is excavated forward to the initial section, and forms the lower step area of ​​the first lower left part with the lower step area of ​​the first outer guide pit, and then initial support is carried out, and a vertical steel arch frame is erected at the initial section to form a temporary middle partition wall, thereby completing the bottoming of the middle partition wall.

[0013] Further, step S400 includes: S403, the first upper right part includes the second part of the upper step area of ​​the first middle guide pit and the upper step area of ​​the first inner guide pit, the first upper right part is excavated forward to the end section to form the upper step area of ​​the first upper right part, and then the initial support is carried out in time, and a temporary invert arch is erected under the upper step area of ​​the first upper right part, thereby closing the first upper right part.

[0014] Further, step S400 includes: S404, the first lower right part includes the second part of the lower step area of ​​the first middle guide pit and the lower step area of ​​the first inner guide pit, the second part of the lower step area of ​​the first middle guide pit is excavated forward to the initial section, and forms the lower step area of ​​the first lower right part with the lower step area of ​​the first inner guide pit, and then the initial support is carried out in time to complete the closure of the first lower right part and temporarily form the construction section of the CD method.

[0015] Further, step S400 includes: S405, dismantling the temporary invert from the initial section to the end section, and completing the conversion from the double-side wall pilot pit method to the single-side wall pilot pit method of the first main tunnel.

[0016] Furthermore, after the face construction exceeds the end section, no temporary invert will be constructed.

[0017] Furthermore, in the double-side wall pilot tunnel method, the first main tunnel and the second main tunnel are excavated with staggered distances, and the excavation staggered distance between the first main tunnel and the second main tunnel is greater than twice the tunnel diameter; in view of the fact that the excavation staggered distance between the first main tunnel and the second main tunnel is greater than twice the tunnel diameter, the construction method conversion of the second main tunnel will lag behind that of the first main tunnel, but the order and steps of the construction method conversion of the second main tunnel are the same as those of the first main tunnel, following the principle of outside first, inside later, and from top to bottom.

[0018] The present invention has the following beneficial effects:

[0019] The method for converting the double-side wall pilot pit method to the single-side wall pilot pit method of a super-large span multi-arch tunnel of the present invention ensures that the first outer pilot pit and the first middle pilot pit overlap at the initial section by gradually shortening the excavation offset, while maintaining a safe distance, thereby reducing potential safety hazards during construction; installing a temporary invert (preparation section) provides additional support for construction and enhances the stability of the tunnel during construction; by optimizing the construction sequence and steps, material waste and unnecessary additional work are reduced, thereby reducing engineering costs. For example, the construction of the second main tunnel lags behind the construction of the first main tunnel, but the construction method conversion sequence is the same. This coordinated construction sequence can improve resource utilization efficiency and realize multi-section synchronous construction; by accurately controlling the excavation steps and sequence, the disturbance to the surrounding rock is reduced, thereby reducing the impact of the construction on the surrounding environment; by following the principle of first outside and then inside and from top to bottom, excavation is carried out in an orderly manner, thereby reducing confusion and delays during construction and improving construction efficiency; by clarifying the construction steps and sequence, construction management is simplified, making the construction process more orderly and convenient for monitoring and adjustment. The method of the present invention provides a systematic solution to the technical difficulties in the construction of super-large span multi-arch tunnels, which not only improves the safety and economy of construction, but also helps to improve the quality of the project, reduce the impact on the environment, and improve construction efficiency; these effects are particularly important in the construction of mountain multi-arch tunnels.

[0020] In addition to the above-described objects, features and advantages, the present invention has other objects, features and advantages. The present invention will be further described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the accompanying drawings:

[0022] Figure 1 It is a schematic diagram of the construction of a double-side wall pilot tunnel method for a super-large span multi-arch tunnel according to a preferred embodiment of the present invention;

[0023] Figure 2 It is a schematic diagram of the construction phase of a method for converting a double-sidewall pilot pit method to a single-sidewall pilot pit method for a super-large-span multi-arch tunnel according to a preferred embodiment of the present invention;

[0024] Figure 3 is a cross-sectional schematic diagram of a first main hole preparation section of a preferred embodiment of the present invention;

[0025] Figure 4 It is a schematic diagram of the conversion of the first main tunnel construction method of the preferred embodiment of the present invention.

[0026] Legend:

[0027] 1. Middle guide tunnel; 101. Middle partition wall; 102. Lateral temporary support; 103. Left wall of middle guide tunnel; 104. Right wall of middle guide tunnel; 2. First main tunnel; 201. Outer temporary support; 202. Inner temporary support; 3. Second main tunnel; 4. Initial section; 5. End section; 6. Temporary invert (preparation section); 7. Temporary invert (construction method conversion section); 8. Vertical steel arch frame; 9. Middle partition wall. DETAILED DESCRIPTION

[0028] The embodiments of the present invention are described in detail below with reference to the accompanying drawings. However, the present invention can be implemented in many different ways as defined and covered below.

[0029] Figure 1 It is a schematic diagram of the construction of a double-side wall pilot tunnel method for a super-large span multi-arch tunnel according to a preferred embodiment of the present invention; Figure 2 It is a schematic diagram of the construction phase of a method for converting a double-sidewall pilot pit method to a single-sidewall pilot pit method for a super-large-span multi-arch tunnel according to a preferred embodiment of the present invention; Figure 3 is a cross-sectional schematic diagram of a first main hole preparation section of a preferred embodiment of the present invention; Figure 4 It is a schematic diagram of the conversion of the first main tunnel construction method of the preferred embodiment of the present invention.

[0030] like Figure 1 and Figure 2As shown, the method for converting the double-side wall pilot tunnel method of the super-large span multi-arch tunnel of this embodiment to the single-side wall pilot tunnel method, the starting point of the conversion is the initial section 4, and the end point of the conversion is the end section 5, and the method comprises the following steps: S100, the middle pilot tunnel 1 is constructed first to exceed the end section 5; S200, when the first main tunnel 2 is constructed to the vicinity of the initial section 4, the excavation offset is gradually shortened, until the excavation sections of the upper step of the first outer pilot tunnel (L1 area) and the upper step of the first inner pilot tunnel (L2 area) coincide with the initial section 4, the upper step section of the first middle pilot tunnel (L3 area) approaches the initial section 4 and maintains a safe distance from the initial section 4, and the upper steps and lower steps of the first outer pilot tunnel, the first middle pilot tunnel and the first inner pilot tunnel of the first main tunnel 2 all maintain Short step distance; S300, install a temporary invert (preparation section) 6, and based on the temporary invert (preparation section) 6, divide it into the first upper left part (A1 area) away from the middle guide tunnel 1, the first lower left part (B1 area) away from the middle guide tunnel 1, the first upper right part (A2 area) close to the middle guide tunnel 1 and the first lower right part (B2 area) close to the middle guide tunnel 1; S400, follow the principle of first outside and then inside and from top to bottom, the first upper left part, the first lower left part, the first upper right part and the first lower right part are excavated forward alternately in sequence until the entire tunnel face is excavated out of the end section 5; S500, the second main tunnel 3 has an excavation offset relative to the first main tunnel 2, and the construction method conversion of the second main tunnel 3 lags behind that of the first main tunnel 2, and the construction method conversion sequence and steps are the same as those of the first main tunnel 2. The method for converting the double-side wall pilot method to the single-side wall pilot method of a super-large span multi-arch tunnel of the present invention ensures that the excavation sections of the upper step of the first outer pilot pit and the upper step of the first inner pilot pit overlap at the initial section 4 by gradually shortening the excavation offset, and at the same time, the lower step of the first inner and outer pilot pits also maintains a short step distance with the upper step thereof (the short step distance is 3m to 5m), thereby reducing the potential safety hazards during the construction process; the temporary invert (preparation section) 6 is added to provide additional support for the construction, thereby enhancing the stability of the tunnel during the construction process; and the waste of materials and unnecessary additional work are reduced by optimizing the construction sequence and steps. The construction cost is reduced by coordinating the construction steps and sequence, for example, the construction of the second main tunnel 3 lags behind that of the first main tunnel 2, but the order of the construction method conversion is the same. This coordinated construction sequence can improve resource utilization efficiency and realize multi-section synchronous construction; by accurately controlling the excavation steps and sequence, the disturbance to the surrounding rock is reduced, thereby reducing the impact of the construction on the surrounding environment; by following the principle of first outside and then inside and from top to bottom, the excavation is carried out in an orderly manner, which reduces the confusion and delays in the construction and improves the construction efficiency; by clarifying the construction steps and sequence, the construction management is simplified, making the construction process more orderly and easy to monitor and adjust. The method of the present invention provides a systematic solution to the technical difficulties in the construction of super-large span multi-arch tunnels, which not only improves the safety and economy of the construction, but also helps to improve the quality of the project, reduce the impact on the environment, and improve the construction efficiency; these effects are particularly important in the construction of mountain multi-arch tunnels.

[0031] like Figure 2 and Figure 3 As shown, in this embodiment, step S200 is specifically as follows: S201, when the first main tunnel 2 is constructed to the vicinity of the initial section 4, the excavation offset of the first outer pilot pit, the first inner pilot pit and the first central pilot pit is gradually shortened; S202, the first main tunnel 2 continues to be constructed, and the excavation sections of the upper step of the first outer pilot pit and the upper step of the first inner pilot pit are made to overlap at the initial section 4; S203, the upper step section of the first inner pilot pit approaches the initial section 4 and maintains a safe distance from the initial section 4, and the safety distance range belongs to the preparation section for the conversion of the construction method. By gradually shortening the excavation offset of the first outer pilot pit, the first inner pilot pit and the first central pilot pit, the excavation sections of the upper step of the first outer pilot pit and the upper step of the first inner pilot pit are made to overlap at the initial section 4, and the lower step of the first inner and outer pilot pits also maintains a short step distance with its upper step, the stability during the construction process can be effectively controlled to reduce the risk of collapse caused by improper excavation. At the same time, the upper step section of the first middle pilot tunnel maintains a safe distance from the initial section 4. This safety distance serves as a preparatory section for the method conversion, providing additional safety guarantees for the construction. Step S200 improves construction efficiency by designing the construction sequence, so that the excavation and support of each pilot tunnel can be carried out in an orderly manner. This orderly construction sequence helps to reduce confusion and potential safety risks in construction. In step S203, by carrying out preparatory work for the method conversion within the safety distance, it can be ensured that the stability of the tunnel structure is strengthened during the construction process. By optimizing the construction steps and sequence, it helps to reduce material waste and improve resource utilization efficiency, thereby reducing project costs. At the same time, reducing potential risks in construction also means reducing additional costs caused by accidents.

[0032] like Figure 3 and Figure 4As shown, in this embodiment, step S300 is specifically as follows: S301, a temporary invert (preparation section) 6 is installed in the first middle guide pit to improve the safety of the construction method conversion; S302, on the cross section of the first main tunnel 2, with the midpoint of the temporary invert as the center, it is divided into a first upper left part away from the middle guide tunnel 1, a first lower left part away from the middle guide tunnel 1, a first upper right part close to the middle guide tunnel 1 and a first lower right part close to the middle guide tunnel 1 along the longitudinal and transverse directions. By installing a temporary invert (preparation section) 6 in the first middle pilot tunnel, such a structural design helps to improve the safety of the construction method conversion process, and can better withstand the surrounding rock pressure and transfer the load to the foundation, thereby enhancing the overall stability of the tunnel structure; on the cross section of the first main tunnel 2, with the midpoint of the temporary invert as the center, it is divided into four parts along the longitudinal and transverse directions. This division helps to optimize the construction layout, making the construction operation surface clearer, facilitating the construction organization and the operation of construction machinery, and improving the construction efficiency; the setting of the temporary invert helps to control the deformation of the surrounding rock around the tunnel, reduce the stress redistribution and deformation of the surrounding rock caused by excavation, thereby reducing the safety risk in the tunnel construction process; the temporary invert, as a reverse arch structure, can evenly distribute the upper load to the entire structure, avoid local stress concentration, and reduce the risk of structural damage. ; By reasonably setting the temporary invert, the construction conditions can be improved, providing a safer working environment for construction personnel, and also helping to improve the construction quality; the setting of the temporary invert can form a closed support ring, increase the integrity and stability of the tunnel structure, and provide protection for subsequent construction method conversion.

[0033] like Figure 4 As shown in (a), in this embodiment, step S400 includes: S401, the first upper left part includes the first part of the upper step area of ​​the first middle guide pit (the left half of the L3a area) and the upper step area of ​​the first outer guide pit (the L1a area), the first upper left part is excavated forward to the end section 5 and forms the first upper left step area, and then the initial support is carried out in time, and a temporary invert arch (construction method conversion section) 7 and a vertical steel arch frame 8 are erected, thereby closing the first upper left part. By timely carrying out initial support at the first upper left part and erecting a temporary invert (construction method conversion section) 7 and a vertical steel arch frame 8, the stability of the initial support can be effectively enhanced, thereby improving the overall stability of the tunnel structure; during tunnel excavation, initial support is an important means to control surrounding rock deformation; timely support and erection can reduce the stress redistribution and deformation of the surrounding rock caused by excavation, thereby reducing the safety risks during tunnel construction; the erection of temporary inverts and vertical steel arch frames 8 can provide a stable working environment for face excavation and secondary lining construction, and provide additional safety guarantees for construction personnel; the timely closure of the first upper left step area helps to effectively control the deformation of the surrounding rock and prevent landslides, thereby reducing the safety risks during construction. .

[0034] like Figure 4 (b) As shown, in this embodiment, step S400 includes: S402, the first lower left part includes the first part of the lower step area of ​​the first middle guide pit (the left half of the L3b area) and the lower step area of ​​the first outer guide pit (the L1b area), the first part of the lower step area of ​​the first middle guide pit is excavated forward to the initial section 4, and forms the first lower left lower step area with the lower step area of ​​the first outer guide pit, and then initial support is carried out, and a vertical steel arch frame 8 is erected on the initial section 4 to form a temporary middle partition wall 9, thereby completing the bottoming of the middle partition wall 9. By excavating the first lower left part and carrying out initial support in time, the stability of the excavation surface in the left half area divided by the center line of the first main tunnel is improved and the safety of the construction workers is guaranteed; the vertical steel arch frame 8 is erected at the initial section 4 to form a temporary middle partition wall 9, which helps to improve the overall stability of the tunnel structure. The steel arch frame can withstand the stratum pressure and resist the reaction force, reducing tunnel deformation; through step-by-step excavation and support, the construction process is made more reasonable, which is convenient for construction organization and management and improves construction efficiency; the completion of the middle partition wall 9 provides a stable construction environment for further excavation of the tunnel, conversion of construction methods and secondary lining construction.

[0035] like Figure 4 As shown in (c), in this embodiment, step S400 includes: S403, the first upper right part includes the second part of the upper step area of ​​the first middle pilot pit (another part of the L3a area) and the upper step area of ​​the first inner pilot pit (the L2a area), the first upper right part is excavated forward to the end section 5, the upper step area of ​​the first upper right part is formed, and then the initial support is carried out in time, and a temporary invert (construction method conversion section) 7 is erected below the upper step area of ​​the first upper right part, so as to close the first upper right part. By excavating forward in the first upper right part and carrying out the initial support in time, the temporary support erection of the construction conversion section has been completed; the temporary invert (construction method conversion section) 7 is erected below the upper step area of ​​the first upper right part, which helps to improve the integrity and stability of the construction conversion section; closing the first upper right part and completing the temporary support frame of the construction conversion section provide a more stable structural foundation for the tunnel.

[0036] like Figure 4(d) As shown, in this embodiment, step S400 includes: S404, the first lower right part includes the second part of the lower step area of ​​the first middle pilot pit (another part of the L3b area) and the lower step area of ​​the first inner pilot pit (the L2b area), the second part of the lower step area of ​​the first middle pilot pit is excavated forward to the initial section 4, and forms the lower step area of ​​the first lower right part with the lower step area of ​​the first inner pilot pit, and then the initial support is carried out in time to complete the closure of the first lower right part, and the construction section of the CD method is temporarily formed. After the lower step area of ​​the first lower right part is formed, the initial support is carried out in time to complete the closure of the first lower right part, and the construction section of the CD method is temporarily formed. By forming the construction section of the CD method, a sufficiently stable working surface is provided for the construction conversion section, which is helpful for the subsequent safe construction of the second lining and the finishing work of the conversion of the construction method.

[0037] like Figure 4 As shown, in this embodiment, step S400 includes: S405, dismantling the temporary invert (preparation section) 6 and the temporary invert (construction method conversion section) 7 from the initial section 4 to the end section 5, and completing the conversion of the double-side wall pilot pit method to the single-side wall pilot pit method of the first main tunnel 2. The removal of the temporary invert marks the completion of the conversion from the double-sidewall pilot tunnel method to the single-sidewall pilot tunnel method, providing conditions for the subsequent stages of tunnel construction; the temporary invert plays a supporting and protective role in the construction process, and their removal means that the initial support of the tunnel is stable enough to withstand the pressure of the surrounding rock, thereby ensuring the safety of the structure; after the temporary structure is removed, the final lining of the tunnel and other subsequent work can be carried out more smoothly, which improves construction efficiency, reduces the occupation of the internal space of the tunnel, provides more space for other construction operations, reduces construction interference, and can carry out the final lining of the tunnel and other subsequent work more quickly, thereby speeding up the construction progress. Necessary adjustments can be made according to the actual conditions of the surrounding rock to adapt to changes in geological conditions, ensure the smooth progress of construction, ensure that the quality meets the design requirements, and provide protection for the long-term use of the tunnel; the removal and recycling of temporary structures can reduce material waste and reduce construction costs.

[0038] In this embodiment, after the face construction exceeds the end section 5, the temporary invert (construction method conversion section) 7 is no longer constructed. Stopping the construction of the temporary invert means that the construction has been converted from the double-side wall pilot method to the single-side wall pilot method, in order to improve construction efficiency and adapt to the needs of subsequent construction stages; the temporary invert provides additional support and stability during the construction process. Once the face exceeds a specific section, it indicates that the subsequent construction no longer requires such additional support because the other parts of the tunnel are stable enough to withstand the pressure of the surrounding rock; no longer needing the temporary invert can reduce the use of materials and labor, thereby reducing construction costs; after the face exceeds the end section 5, the construction personnel can focus on the subsequent secondary lining construction and forward excavation with the single-side wall pilot method; in tunnel construction, different geological conditions may require different construction methods and support structures. Stopping the construction of the temporary invert may be an adaptation to the current geological conditions to ensure that the construction method matches the geological conditions; removing or no longer constructing the temporary invert can reduce the occupation of the internal space of the tunnel, provide more space for other construction operations, and reduce construction interference. To ensure the smooth progress of construction, multiple factors such as efficiency, cost, safety and geological conditions were taken into consideration.

[0039] In this embodiment, the double-sidewall pilot tunnel method is used, and the first main tunnel 2 and the second main tunnel 3 are excavated with staggered distances, and the excavation staggered distance between the first main tunnel 2 and the second main tunnel 3 is greater than twice the tunnel diameter; in view of the fact that the excavation staggered distance between the first main tunnel 2 and the second main tunnel 3 is greater than twice the tunnel diameter, the construction method conversion of the second main tunnel 3 lags behind the first main tunnel 2, but the order and steps of the construction method conversion of the second main tunnel 3 are the same as those of the first main tunnel 2, following the principle of first outside, then inside, and from top to bottom. The middle pilot tunnel 1 is excavated 50m ahead, and the first main tunnel 2 and the second main tunnel 3 are excavated with staggered distances greater than twice the tunnel diameter, which weakens the mutual influence caused by the construction of the first main tunnel 2 (the first main tunnel), the middle pilot tunnel 1 and the second main tunnel 3 (the second main tunnel) during the construction method conversion process, so that other tunnels can be allowed to be constructed synchronously when the construction method of the first main tunnel 2 (the first main tunnel) is converted.

[0040] Compared with the single double-side wall pilot method for the entire tunnel section, the conversion of the construction method has obvious economic benefits. The main tunnels of the first main tunnel 2 and the second main tunnel 3 are constructed using the single side wall method, which changes from the three construction surfaces of the inner, middle and outer walls to the double construction surfaces of the inner and outer walls. On the one hand, it reduces the cost of building materials for two vertical temporary supports. On the other hand, it optimizes the complicated construction process, helps improve construction efficiency and saves labor costs.

[0041] During implementation, a construction method for converting the double-side wall pilot pit method to the single-side wall pilot pit method for an ultra-large span multi-arch tunnel is provided, which can realize simultaneous excavation of multiple construction surfaces and save a lot of time and material costs for subsequent construction.

[0042] The construction method of the present invention is based on the actual excavation process of the tunnel project. The maximum burial depth of the tunnel is about 55m, the length of the open tunnel is 25m, and the length of the dark tunnel is 250m. The surrounding rock is V-grade. The cross-sectional width and height of a main tunnel are 15.75m and 10.55m respectively, and the cross-sectional height of the middle guide tunnel 1 is 7.36m and the width is 7.92m. The excavation design of the main tunnel 40m into the cave adopts the double-side wall pilot method for construction. The surrounding rock stability of the tunnel body is better than that of the entrance and exit. The double-side wall pilot method is changed to the single-side wall pilot method to reduce the degree of construction disturbance and ensure the stability of the surrounding rock.

[0043] The construction steps of the double side wall pilot pit method are as follows:

[0044] S1: Advanced support.

[0045] First, the pipe shed is used to support the middle guide tunnel 1. Then, the pipe shed is used to support the first main tunnel 2 and the second main tunnel 3. In the surrounding rock section where there is no long pipe shed support in the tunnel, the hot-rolled seamless steel pipe with an outer diameter of φ50×4mm is used for advance small guide pipe support.

[0046] S2: Construction of middle guide tunnel 1.

[0047] S21, excavation of middle guide tunnel 1. The upper and lower steps method is used for excavation, with a penetration of about 1 meter per cycle. The excavation reserves deformation, mainly mechanical excavation, local drilling and blasting excavation, and timely support. When constructing the steel frame of the upper step, measures such as expanding the arch foot or applying locking foot anchors are adopted. The lower step is excavated when the sprayed concrete of the upper step reaches more than 70% of the design strength. Repeat the above construction steps to excavate the middle guide tunnel 1 forward 50m.

[0048] S22, construction of the middle partition wall 101. The arch tunnel has high requirements for the foundation bearing capacity of the middle partition wall 101. Before the construction of the middle partition wall 101, the design adopts a φ42×3.5mm small grouting pipe with a length of 3.5m, a longitudinal and transverse spacing of 50×100cm, and a plum blossom arrangement to reinforce the foundation in the middle partition wall 101 area; to ensure the compactness of the top of the middle partition wall 101, the design embeds a φ42 grouting pipe every 3m, and the grouting is cement mortar, and the pressure shall not exceed 1.0MPa; the corner of the middle partition wall 101 is embedded with a full-length 32×1.5mm steel plate, which will be connected to the active permanent support I-beam later. The lining steel bars of the middle partition wall 101 are tied on site, with a segment length of 5 to 6m. After the tying is completed, the middle partition wall template is placed in the designed position using a trolley, and then the concrete is poured.

[0049] S3: Single-side main tunnel construction.

[0050] S31, according to the engineering geological conditions, determine the construction sequence of the first main tunnel 2 and the second main tunnel 3, taking the construction of the first main tunnel 2 (the first main tunnel) as an example. In order to reduce the construction excavation span, the first main tunnel 2 (the first main tunnel) and the second main tunnel 3 (the second main tunnel) are excavated at staggered distances, and the staggered distance between the left and right tunnels is greater than twice the tunnel diameter. The outer pilot pit of the first main tunnel 2 needs to wait until the concrete strength of the middle partition wall 101 reaches 75% before it can be excavated, and the construction of the outer pilot pit and the middle partition wall 101 can be carried out simultaneously. Figure 1 As shown, before the excavation of the first main tunnel 2, a lateral temporary support 102 is set on the right side of the middle partition wall 101. The temporary support can be made of concrete or I-beams as needed. A 1.2 mm thick EVA waterproof membrane is laid between the temporary support and the middle partition wall 101 to facilitate the removal of the temporary support during the construction of the right tunnel.

[0051] S32, the outer pilot pit L1 area is excavated by the up-and-down step method, and the initial support and outer temporary support 201 are carried out immediately after excavation.

[0052] S33, excavate the inner pilot tunnel L2 area, and immediately carry out initial support and temporary support after excavation. After the initial support of the main tunnel is stable, demolish the left wall 103 of the middle pilot tunnel.

[0053] S34, the middle L3 area is excavated using the up-and-down step method, and initial support and inner temporary support 202 are immediately carried out after excavation.

[0054] S35: After the deformation of the surrounding rock in the closed loop area of ​​the primary support is basically stable, the temporary support in the area is removed, and then the invert is constructed and backfilled. Subsequently, the drainage arrangement and the second lining casting are carried out.

[0055] S4: Construction of main tunnels on both sides.

[0056] This stage enters the simultaneous construction of multiple sections, with the middle guide tunnel 1 being constructed first, followed by the first main tunnel 2 using double side walls, and then the second main tunnel 3 being formally excavated. First, the outer guide pit R1 area is excavated using the up and down step method. Then, the inner guide pit R2 area is excavated, and after the initial support of the second main tunnel 3 is stable, the right side wall 104 of the middle guide tunnel and the lateral temporary support 102 are removed. Finally, the same steps as the fourth S34 and the fifth S35 in S3 are taken to construct the right tunnel (for example, excavating the middle L3 area corresponds to excavating the middle R3 area).

[0057] The construction steps for converting the double-side wall pilot pit method to the single-side wall pilot pit method are as follows:

[0058] S5: Construction method conversion.

[0059] like Figure 2As shown in the figure, the starting point of the construction method conversion section is the initial section 4, and the end point is the end section 5. When the double-side wall pilot tunnel method of S1 to S4 is used, the middle pilot tunnel 1 needs to be constructed to exceed the end section 5 first, and when the first main tunnel 2 is constructed to the initial section 4, the offset distance of the L1 to L3 area needs to be gradually reduced. Figure 3 As shown, the L1-L3 area is divided into two parts, a and b, according to the positions of the upper and lower steps. The excavated sections of the L1a area and the L2a area overlap at the initial section 4, and the section of L3a maintains a safety distance l from the initial section 4. The safety distance range belongs to the preparation section for the construction method conversion, and a temporary invert 6 needs to be installed in the L3 area to improve the safety of the construction method conversion process.

[0060] S51, the left half of L1a and L3a is excavated forward to the end section 5, forming the upper step area A1 of the upper left branch of the first main tunnel 2, and then the initial support is carried out in time, and the temporary invert (construction method conversion section) 7 and the vertical steel arch 8 are erected to close the upper left branch, such as Figure 4 As shown in a.

[0061] S52, the left half of L3b and L1b are excavated forward to the initial section 4 to form the lower step area B1 of the left lower division, and then the initial support is carried out in time, and a vertical steel arch frame 8 is erected at the initial section 4 to form the lower half of the temporary middle partition wall 9, thereby completing the bottoming of the middle partition wall 9, such as Figure 4 As shown in b.

[0062] S53, excavate the right half of L2a and L3a forward to the end section 5, forming the upper step area A2 of the upper right branch of the first main tunnel 2, and then carry out the initial support in time, and set up a temporary invert (construction method conversion section) 7 under the A2 area, so as to close the upper right branch. Figure 4 As shown in c.

[0063] S54, the right half of L3b and L2b are excavated forward to the initial section 4 to form the lower step area B2 of the right lower section, and then the initial support is carried out in time to complete the closure of the right lower section and temporarily form the construction section of the CD method, such as Figure 4 As shown in d.

[0064] S55, such as Figure 2 and Figure 4 As shown in d, the A1, B1, A2, and B2 areas are excavated forward alternately in sequence until the entire tunnel face is excavated out of the end section 5. After the tunnel face construction exceeds the end section 5, the temporary invert (construction method conversion section) 7 is no longer constructed.

[0065] S56, dismantle the temporary invert (preparation section) 6 and the temporary invert (construction method conversion section) 7 from the initial section 4 to the end section 5, and complete the conversion of the double-side wall pilot pit method to the single-side wall pilot pit method of the first main tunnel 2, such as Figure 4e. Considering that the excavation offset between the first main tunnel 2 and the second main tunnel 3 is twice the tunnel diameter, the construction method conversion of the second main tunnel 3 lags behind that of the first main tunnel 2. However, the order and steps of the construction method conversion of the second main tunnel 3 are the same as those of the first main tunnel 2, following the principle of "outside first, inside later, from top to bottom".

[0066] Matters not covered by the present invention are known technologies.

[0067] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0068] The above-mentioned embodiments only express several implementation modes of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the invention. It should be pointed out that, for a person of ordinary skill in the art, several modifications and improvements can be made without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the attached claims.

[0069] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A method for converting a double-sidewall pilot pit method to a single-sidewall pilot pit method for a super-large-span multi-arch tunnel, characterized in that: The starting point of the conversion is the initial section, and the end point of the conversion is the ending section. The method comprises the following steps: S100, the middle pilot tunnel is constructed first and exceeds the end section; S200, when the first main tunnel is under construction and approaches the initial section, the excavation offset is gradually shortened until the excavation sections of the upper step of the first outer pilot pit and the upper step of the first inner pilot pit coincide with the initial section, the upper step section of the first middle pilot pit approaches the initial section and maintains a safe distance from the initial section, and the upper and lower steps of the first outer pilot pit, the first middle pilot pit and the first inner pilot pit all maintain a short step distance; S300, installing a temporary invert, and based on the temporary invert, dividing the first invert into a first upper left portion away from the middle guide tunnel, a first lower left portion away from the middle guide tunnel, a first upper right portion close to the middle guide tunnel, and a first lower right portion close to the middle guide tunnel; S400, following the principle of first outside and then inside and from top to bottom, the first upper left part, the first lower left part, the first upper right part and the first lower right part are excavated forward alternately in sequence until the entire tunnel face is excavated out of the end section; S500. The second main tunnel has an excavation offset relative to the first main tunnel. The construction method conversion of the second main tunnel lags behind that of the first main tunnel. The construction method conversion sequence and steps are the same as those of the first main tunnel.

2. The method for converting the double-sidewall pilot method to the single-sidewall pilot method of a super-large-span multi-arch tunnel according to claim 1 is characterized in that: Step S200 is specifically as follows: S201, when the first main tunnel is constructed close to the initial section, the excavation offset of the first outer pilot pit, the first inner pilot pit and the first middle pilot pit is gradually shortened; S202, the first main tunnel continues to be constructed, and the excavation sections of the upper step of the first outer pilot pit and the upper step of the first inner pilot pit are made to overlap at the initial section; S203, the upper step section of the first middle pilot tunnel is close to the initial section and maintains a safe distance from the initial section. The area within the safe distance belongs to the preparation section for the conversion of the construction method.

3. The method for converting the double-sidewall pilot method to the single-sidewall pilot method of a super-large-span multi-arch tunnel according to claim 2 is characterized in that: Step S300 is specifically as follows: S301, install a temporary invert in the first middle pilot pit to improve the safety of the construction method conversion; S302. On the cross section of the first main tunnel, with the midpoint of the temporary invert as the center, it is divided longitudinally and transversely into a first upper left part away from the middle guide tunnel, a first lower left part away from the middle guide tunnel, a first upper right part close to the middle guide tunnel, and a first lower right part close to the middle guide tunnel.

4. The method for converting the double-sidewall pilot method to the single-sidewall pilot method of a super-large-span multi-arch tunnel according to claim 3 is characterized in that: Step S400 includes: S401, the first upper left part includes the first part of the upper step area of ​​the first middle pilot pit and the upper step area of ​​the first outer pilot pit. The first upper left part is excavated forward to the end section and forms the first upper left step area. Subsequently, initial support is carried out in time, and a temporary invert arch and a vertical steel arch frame are erected to close the first upper left part.

5. The method for converting the double-sidewall pilot method to the single-sidewall pilot method of a super-large-span multi-arch tunnel according to claim 4 is characterized in that: Step S400 includes: S402, the first lower left part includes the first part of the lower step area of ​​the first middle guide pit and the lower step area of ​​the first outer guide pit. The first part of the lower step area of ​​the first middle guide pit is excavated forward to the initial section, and forms the lower step area of ​​the first lower left part together with the lower step area of ​​the first outer guide pit. Subsequently, initial support is carried out, and a vertical steel arch frame is erected at the initial section to form a temporary middle partition wall, thereby completing the bottoming of the middle partition wall.

6. The method for converting the double-sidewall pilot method to the single-sidewall pilot method of a super-large-span multi-arch tunnel according to claim 5 is characterized in that: Step S400 includes: S403, the first upper right part includes the second part of the upper step area of ​​the first middle guide pit and the upper step area of ​​the first inner guide pit. The first upper right part is excavated forward to the end section to form the upper step area of ​​the first upper right part, and then the initial support is carried out in time, and a temporary invert is erected under the upper step area of ​​the first upper right part, thereby closing the first upper right part.

7. The method for converting the double-sidewall pilot method to the single-sidewall pilot method of a super-large-span multi-arch tunnel according to claim 6 is characterized in that: Step S400 includes: S404, the first lower right part includes the second part of the lower step area of ​​the first middle pilot pit and the lower step area of ​​the first inner pilot pit. The second part of the lower step area of ​​the first middle pilot pit is excavated forward to the initial section, and forms the lower step area of ​​the first lower right part with the lower step area of ​​the first inner pilot pit. Subsequently, initial support is carried out in time to complete the closure of the first lower right part and temporarily form the construction section of the CD method.

8. The method for converting the double-sidewall pilot method to the single-sidewall pilot method of a super-large-span multi-arch tunnel according to claim 7 is characterized in that: Step S400 includes: S405. Remove the temporary invert from the initial section to the final section to complete the conversion from the double-side wall pilot tunnel method to the single-side wall pilot tunnel method for the first main tunnel.

9. The method for converting the double-sidewall pilot method to the single-sidewall pilot method of a super-large-span multi-arch tunnel according to any one of claims 1 to 8, characterized in that: After the face construction exceeds the end section, no temporary invert will be constructed.

10. The method for converting the double-sidewall pilot method to the single-sidewall pilot method of a super-large-span multi-arch tunnel according to any one of claims 1 to 8, characterized in that: Double sidewall pilot tunnel method, the first main tunnel and the second main tunnel are excavated at a staggered distance, and the excavation staggered distance between the first main tunnel and the second main tunnel is greater than twice the tunnel diameter; Considering that the excavation offset between the first and second main tunnels is greater than twice the tunnel diameter, the construction method conversion of the second main tunnel will lag behind that of the first main tunnel. However, the order and steps of the construction method conversion of the second main tunnel are the same as those of the first main tunnel, following the principle of outside first, inside later and from top to bottom.