Full-section tunnel boring machine with local pressure at front end

By using pressure-limited soil and water tanks, main drainage pipes and backup drainage pipes in a full-section tunnel boring machine, combining electromagnetic detection and drilling detection, monitoring and rapid discharge of groundwater, the construction of TBM equipment under water-rich and high water pressure conditions is solved. Safety issues have improved the safety of tunnel construction and the stability of equipment.

CN119041925APending Publication Date: 2024-11-29SICHUAN COMM SURVEYING & DESIGN INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411323617.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-23
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

In water-rich and high-hydraulic hard rock formations, TBM equipment is difficult to adapt to complex geological conditions, causing groundwater to pour into the equipment, causing poor construction environment and safety hazards. In addition, the shield machine also has the risk of equipment damage under high water pressure. .

Method used

A full-section tunnel boring machine with local pressure at the front end is designed, using pressure-limited soil and water tanks, main drainage pipes and spare drainage pipes. The groundwater situation is monitored through electromagnetic detection and drilling detection equipment, and the main drainage pipes and spare drainage pipes are used to quickly use the main drainage pipes and spare drainage pipes. Discharge groundwater, limit water pressure, prevent excessive water pressure, and set up a mobile water barrier device and water pressure gauge to ensure the safety of the equipment.

Benefits of technology

Effectively discharge groundwater, prevent excessive water pressure, avoid tunnel burial and equipment damage, improve the safety and environment of tunnel construction, and ensure construction stability and equipment safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041925A_ABST
    Figure CN119041925A_ABST
Patent Text Reader

Abstract

The invention discloses a full-section tunnel boring machine with a local front end under pressure, which comprises a tunneling cutterhead, a pressure-limiting water and soil cabin, a main drainage pipeline and a standby drainage pipeline, and is characterized in that the tunneling cutterhead is used for tunneling; the pressure-limiting water and soil cabin is arranged behind the tunneling cutterhead; the main drainage pipeline is communicated with the pressure-limiting water-soil cabin, and a water inlet of the main drainage pipeline is formed in the lower half part of the pressure-limiting water-soil cabin; a water inlet of the standby drainage pipeline is formed in the upper half part of the pressure-limiting water-soil cabin to limit the pressure in the pressure-limiting water-soil cabin. The pressure-limiting water and soil cabin is used for storing underground water in a centralized mode, the main drainage pipeline is used for undertaking a main drainage task, the standby drainage pipeline is used for auxiliary drainage, and meanwhile the standby drainage pipeline can avoid the situation that the water yield and the pressure in the pressure-limiting water and soil cabin are too large; underground water can be quickly and effectively discharged to prevent overhigh water pressure, so that structural equipment of the tunnel boring machine is prevented from being damaged, and the safety of tunnel construction is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel boring construction equipment, and in particular to a full-section tunnel boring machine with local pressure at the front end. Background Art

[0002] Full-section tunnel boring machines (TBMs, shield machines) are commonly used equipment in tunnel construction and are widely used in municipal, railway, highway, water conservancy and other fields. In soft surrounding rock formations, shield machines are generally used; in hard rock formations with good face stability, TBMs (full-section rock tunnel boring machines) are generally used. Due to the complexity of geological conditions, in recent years, a tunnel has both soft surrounding rock sections and hard rock sections. Therefore, in recent years, dual-mode or triple-mode shield machines with TBM-earth pressure balance-mud balance have been developed, so that shield machine mode can be used in sections with poor surrounding rock, and TBM construction mode can be used in hard rock sections. However, it still does not have good adaptability in water-rich, high-water-pressure hard rock formations.

[0003] TBM equipment is increasingly used in complex mountain tunnels, and the geological conditions of mountain tunnels are becoming more and more complex. However, given the complexity of the geological conditions of mountain tunnels, there may be sections in mountain tunnels with extremely abundant groundwater and high water pressure, which greatly restricts the use of TBM (shield machine). With conventional shield TBMs, since the front of the face is not closed, groundwater will directly enter the TBM equipment. When the groundwater is extremely abundant, the water level in the TBM equipment is high and the lower part of the equipment is flooded. The workers who assemble the pipe segments and construct the internal structure at the lower part of the equipment face the problems of poor construction environment and difficult construction operations. When a sudden high-pressure water surge occurs in front of the face, the workers at the lower part of the equipment may even face life-threatening situations. If a shield machine is used, whether it is a slurry shield machine or an earth pressure balance shield machine, since the front of the cutterhead is fully closed, excessive water pressure (the current water pressure in mountain tunnels reaches 5-6MPa, and the maximum water pressure in tunnels constructed by shield machines is only about 1MPa) may cause the slurry compartment and slurry pipe to burst (for slurry shield machines) or a high-pressure surge from the tail of the screw conveyor (for earth pressure balance shield machines). There is still a great risk. Summary of the invention

[0004] The object of the present invention is to provide a full-section tunnel boring machine with local pressure at the front end, which can quickly and effectively discharge groundwater to prevent excessive water pressure, thereby avoiding high-pressure sudden water inrush in the front from burying the tunnel, avoiding damage to the tunnel boring machine structure and equipment, and thus improving the safety of tunnel construction.

[0005] The present invention is achieved through the following technical solutions:

[0006] A full-face tunnel boring machine with local pressure at the front end comprises a tunneling cutter disc, a pressure-limited water and soil compartment, a main drainage pipe and a spare drainage pipe, wherein the tunneling cutter disc is used for tunneling; the pressure-limited water and soil compartment is arranged behind the tunneling cutter disc, and the pressure-limited water and soil compartment is used for collecting groundwater and debris generated by tunneling; the main drainage pipe is communicated with the pressure-limited water and soil compartment, and the water inlet of the main drainage pipe is arranged in the lower half of the pressure-limited water and soil compartment, and the main drainage pipe is used for discharging groundwater in the pressure-limited water and soil compartment; the spare drainage pipe is communicated with the pressure-limited water and soil compartment, and the water inlet of the spare drainage pipe is arranged in the upper half of the pressure-limited water and soil compartment, and the spare drainage pipe is used for assisting in discharging groundwater in the pressure-limited water and soil compartment and limiting the pressure in the pressure-limited water and soil compartment. In order to solve the above technical problems and achieve the corresponding technical effects, the present invention uses a pressure-limited water-soil chamber to realize centralized storage of groundwater, takes the main drainage responsibility through the main drainage pipe, and uses a spare drainage pipe for auxiliary drainage, which can avoid the situation where the water output in the pressure-limited water-soil chamber is too large and the pressure is too high; it can quickly and effectively drain the groundwater to prevent the water pressure from being too high, thereby avoiding large-scale sudden water inrush in the tunnel that causes the tunnel to be buried, avoiding damage to the structural equipment of the tunnel boring machine, and thus improving the safety of tunnel construction.

[0007] Further technical solutions:

[0008] The main drainage pipe is arranged at the bottom of the pressure-limiting water and soil tank;

[0009] Furthermore, the backup drainage pipe is arranged at the middle position of the upper half of the pressure-limiting water and soil tank, and when the water level in the pressure-limiting water and soil tank reaches the outlet of the backup drainage pipe, the pressure in the pressure-limiting water and soil tank reaches a preset pressure value.

[0010] Furthermore: an electromagnetic detection device is also provided in the pressure-limited water-soil chamber, and the electromagnetic detection device is used to detect the underground water content in front of the tunnel face;

[0011] Furthermore: the detection range of the electromagnetic detection equipment is 50m to 100m.

[0012] Furthermore: a drilling detection platform is also provided in the pressure-limited water and soil chamber, and a drilling device is configured on the drilling detection platform. When the electromagnetic detection device detects that the underground water content in front of the heading face is higher than the preset water content, the drilling device configured on the drilling detection platform is used to perform drilling verification on the underground water content in front of the heading face.

[0013] Further: the outlet of the main drainage pipe extends to the rear of the tunnel boring machine and extends into the fully constructed lower structure;

[0014] Furthermore, the water outlet of the backup drainage pipe extends to the rear of the tunnel boring machine, and the water outlet of the backup drainage pipe is connected to the main drainage pipe.

[0015] Furthermore: a movable water retaining device is arranged in the lower structure, and the movable water retaining device moves forward synchronously with the tunnel boring machine;

[0016] Furthermore: the water outlet of the main drainage pipe extends to the rear of the movable water retaining device.

[0017] Further: it also includes a slag discharge device, the feed port of the slag discharge device is arranged in the pressure-limiting water and soil chamber, and the feed port of the slag discharge device is arranged at a height higher than the water inlet of the standby drainage pipe;

[0018] Furthermore: the slag discharge device extends to the rear of the tunnel boring machine.

[0019] Furthermore: it also includes a water pressure gauge, which is arranged at the bottom of the pressure-limiting water and soil tank, and the water pressure gauge is used to monitor the pressure value in the pressure-limiting water and soil tank.

[0020] Further: when the water pressure gauge monitors that the pressure value in the pressure-limiting water and soil chamber is higher than the preset pressure value or the water level in the pressure-limiting water and soil chamber is higher than the setting height of the water inlet of the backup drainage pipe, the excavation cutter head is in a shutdown state and water is discharged to the outside through the main drainage pipe and the backup drainage pipe.

[0021] Furthermore: the water inlet of the main drainage pipe and the water inlet of the backup drainage pipe are both provided with a filter.

[0022] Compared with the prior art, the present invention has the following advantages and beneficial effects:

[0023] 1. The present invention provides a full-section tunnel boring machine with local pressure at the front end, which uses a pressure-limited water-soil chamber to realize centralized storage of groundwater, takes the main drainage responsibility through a main drainage pipe, and uses a spare drainage pipe for auxiliary drainage, which can avoid the situation where the water output in the pressure-limited water-soil chamber is too large and the pressure is too high; it can quickly and effectively discharge groundwater to prevent the water pressure from being too high, thereby avoiding the occurrence of high-pressure sudden water inrush in front of the tunnel to bury the tunnel, avoiding damage to the structural equipment of the tunnel boring machine, and thus improving the safety of tunnel construction.

[0024] 2. The present invention is a full-section tunnel boring machine with local pressure at the front end. It detects the water and soil conditions in front of the heading face through electromagnetic detection equipment, and uses drilling detection equipment to perform drilling detection when abundant groundwater is found, so as to clarify the water and soil conditions in front and then provide feedback on the tunnel excavation work.

[0025] 3. The full-section tunnel boring machine with partial pressure at the front end of the present invention, the arrangement of the pressure-limiting water and soil chamber, the main drainage pipe, the spare drainage pipe, and the mobile water retaining device can effectively prevent groundwater from flowing through the pipe segment assembly and internal structure construction work area, thereby avoiding the influence of groundwater on the pipe segment splicing and internal structure assembly work in the tunnel, and improving the construction safety and construction environment in the tunnel.

[0026] In order to more clearly illustrate the technical solutions of the exemplary embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments. It should be understood that the following drawings only illustrate certain embodiments of the present invention and should not be regarded as limiting the scope. For those of ordinary skill in the art, other relevant drawings can be obtained based on these drawings without creative work. In the drawings:

[0027] Figure 1 It is a schematic diagram of the longitudinal section structure of the present invention;

[0028] Figure 2 for Figure 1 Section 2-2;

[0029] Figure 3 for Figure 1 Section 3-3;

[0030] Figure 4 for Figure 1 Section 4-4;

[0031] Figure 5 for Figure 1 Section 5-5.

[0032] Marks and corresponding parts names in the attached drawings:

[0033] 1-excavation cutterhead, 2-pressure-limiting water and soil chamber, 3-main drainage pipe, 4-backup drainage pipe, 5-electromagnetic detection equipment, 6-drilling detection platform, 7-lower structure, 8-mobile water retaining device, 9-slag discharge device, 10-water pressure gauge. DETAILED DESCRIPTION

[0034] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with embodiments and drawings. The exemplary embodiments of the present invention and their description are only used to explain the present invention and are not intended to limit the present invention.

[0035] In the following description, a large number of specific details are set forth in order to provide a thorough understanding of the present invention. However, it is apparent to one of ordinary skill in the art that these specific details are not necessarily employed to practice the present invention. In other embodiments, in order to avoid obscuring the present invention, well-known structures, circuits, materials, or methods are not specifically described.

[0036] Throughout the specification, references to "one embodiment," "an embodiment," "an example," or "an example" mean that a particular feature, structure, or characteristic described in conjunction with the embodiment or example is included in at least one embodiment of the present invention. Therefore, the phrases "one embodiment," "an embodiment," "an example," or "an example" appearing in various places throughout the specification do not necessarily all refer to the same embodiment or example. In addition, particular features, structures, or characteristics may be combined in one or more embodiments or examples in any suitable combination and / or sub-combination. In addition, it will be appreciated by those of ordinary skill in the art that the figures provided herein are for illustrative purposes and that the figures are not necessarily drawn to scale. The term "and / or" as used herein includes any and all combinations of one or more of the associated listed items.

[0037] In the description of the present invention, the directions or positional relationships indicated by terms such as “front”, “rear”, “left”, “right”, “up”, “down”, “vertical”, “horizontal”, “high”, “low”, “inside” and “outside” are based on the directions or positional relationships shown in the accompanying drawings and are only for the convenience of describing the present invention and simplifying the description. They do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they should not be understood as limiting the scope of protection of the present invention.

[0038] Example:

[0039] like Figure 1 to Figure 5As shown, the present invention is a full-section tunnel boring machine with local pressure at the front end, comprising a tunneling cutterhead 1, a pressure-limited water and soil compartment 2, a main drainage pipe 3 and a backup drainage pipe 4, wherein the tunneling cutterhead 1 is used for tunneling; the pressure-limited water and soil compartment 2 is arranged behind the tunneling cutterhead 1, and the pressure-limited water and soil compartment 2 is used to collect groundwater and debris generated by tunneling; the main drainage pipe 3 is communicated with the pressure-limited water and soil compartment 2, and the water inlet of the main drainage pipe 3 is arranged in the lower half of the pressure-limited water and soil compartment 2, and the main drainage pipe 3 is used to discharge the groundwater in the pressure-limited water and soil compartment 2; the backup drainage pipe 4 is communicated with the pressure-limited water and soil compartment 2, and the water inlet of the backup drainage pipe 4 is arranged in the upper half of the pressure-limited water and soil compartment 2, and the backup drainage pipe 4 is used to assist in discharging the groundwater in the pressure-limited water and soil compartment 2 and limit the pressure in the pressure-limited water and soil compartment 2. In this embodiment, the slag and groundwater excavated by the excavation cutter head 1 are first concentrated in the pressure-limited water and soil compartment 2, and the groundwater is quickly discharged to the rear through the main drainage pipe 3 and the backup drainage pipe 4, wherein the main drainage pipe 3 plays a major drainage role, and then the backup drainage pipe 4 plays an auxiliary drainage role. Specifically, when the amount of water in the pressure-limited water and soil compartment 2 is not large, the groundwater is discharged from the main drainage pipe 3. When the amount of groundwater is large and the main drainage pipe 3 cannot meet the drainage demand, the water level in the pressure-limited water and soil compartment 2 rises, and the backup drainage pipe 4 starts to drain water, so that the backup drainage pipe 4 can effectively avoid the situation where the water level in the pressure-limited water and soil compartment 2 is too high and the pressure is too high, thereby avoiding the occurrence of high-pressure sudden water in the front of the tunnel to bury the tunnel, avoiding damage to the structure and equipment of the tunnel boring machine, and thus improving the safety of tunnel construction. Specifically, the main drainage pipe 3 is arranged at the bottom of the pressure-limited water and soil tank 2; the backup drainage pipe 4 is arranged at the middle position of the upper half of the pressure-limited water and soil tank 2, and when the water level in the pressure-limited water and soil tank 2 reaches the outlet of the backup drainage pipe 4, the pressure in the pressure-limited water and soil tank 2 reaches a preset pressure value. The preset pressure value is less than the maximum pressure that the pressure-limited water and soil tank 2 can bear, so as to effectively avoid the excessive pressure in the pressure-limited water and soil tank 2 from causing damage to the equipment structure.

[0040] The pressure-limited water and soil chamber 2 is also provided with an electromagnetic detection device 5, which is used to detect the underground water content in front of the face. In this embodiment, the electromagnetic detection device 5 is used to detect the underground water content in front of the face, and the detection results are used to provide feedback and guidance for the tunnel excavation construction work. If a water-rich water bag is detected in front, a prompt is first given, and the cutterhead can be automatically stopped. The next step of construction is carried out after the situation in front is clearly investigated. Preferably, the detection range of the electromagnetic detection device 5 is 50m to 100m, which has the effect of advanced detection. Furthermore, a drilling detection platform 6 is also provided in the pressure-limited water and soil chamber 2. When the electromagnetic detection device 5 detects that the underground water content in front of the face is higher than the preset water content, a drilling detection device is configured on the drilling detection platform 6, and drilling verification is performed on the underground water content in front of the face. When the electromagnetic detection device 5 detects the presence of water-rich water bags ahead, a drilling detection device is configured on the drilling detection platform 6, and the groundwater content ahead of the face is detected using the drilling detection device to clarify the status of the groundwater content ahead and provide data feedback.

[0041] The outlet of the main drainage pipe 3 extends to the rear of the tunnel boring machine and extends to the lower structure 7 that has been completely constructed; in this embodiment, the main drainage pipe 3 can effectively drain groundwater to the completed section to avoid affecting the splicing work of the internal structure. Furthermore, the outlet of the backup drainage pipe 4 extends to the rear of the tunnel boring machine, and the outlet of the backup drainage pipe 4 is connected to the main drainage pipe 3, and the water in the backup drainage pipe 4 is merged into the main drainage pipe 3 for unified discharge, which can reduce the setting of pipes and reduce costs; of course, if the main drainage pipe 3 cannot effectively discharge the water in the two pipes, the backup drainage pipe 4 can be set up separately to drain the water to the completed section.

[0042] A mobile water retaining device 8 is provided in the lower structure 7, and the mobile water retaining device 8 moves forward synchronously with the tunnel boring machine; the outlet of the main drainage pipe 3 extends to the rear of the mobile water retaining device 8. In this embodiment, the provision of the mobile water retaining device 8 can effectively prevent water from flowing back to the section where the internal structure construction is not completed, thereby avoiding the water flow from affecting the normal construction of the internal structure. At the same time, the movable characteristic of the mobile water retaining device 8 can facilitate its movement effect in the tunnel, so that it can be accurately and effectively moved into place to achieve the effect of blocking the water flow.

[0043] It also includes a slag discharge device 9, the feed port of which is arranged in the pressure-limited water and soil chamber 2, and the slag discharge device 9 extends to the rear of the tunnel boring machine. In this embodiment, the slag discharge device 9 is used to bring out the slag excavated by the tunneling cutter head 1 in the pressure-limited water and soil chamber 2, so as to prevent the excessive amount of slag in the pressure-limited water and soil chamber 2 from affecting the normal operation of the tunneling cutter head 1. At the same time, in order to prevent groundwater from entering the slag discharge device 9 and causing damage to its structure, as well as polluting the equipment, the feed port of the slag discharge device 9 is set at a height higher than the water inlet setting height of the backup drainage pipe 4.

[0044] In this embodiment, in order to monitor the pressure value in the pressure-limited water and soil compartment 2 in real time and avoid damage to the equipment structure due to excessive pressure, the tunnel boring machine further includes a water pressure gauge 10. Specifically, the water pressure gauge 10 is arranged at the bottom of the pressure-limited water and soil compartment 2, which can effectively monitor the pressure value in the pressure-limited water and soil compartment 2. And specifically, when the pressure value in the pressure-limited water and soil compartment 2 monitored by the water pressure gauge 10 is higher than the preset pressure value or the water level in the pressure-limited water and soil compartment 2 is higher than the water inlet setting height of the backup drainage pipe 4, the tunnel boring cutter head 1 is in a shutdown state, and water is discharged to the outside through the main drainage pipe 3 and the backup drainage pipe 4. In this process, for example, the openings opened at the electromagnetic detection equipment 5 and the drilling detection platform 6 need to be blocked to prevent groundwater from entering the equipment and causing damage to it.

[0045] The water inlet of the main drainage pipe 3 and the water inlet of the backup drainage pipe 4 are both provided with a filter screen. In this embodiment, the provision of the filter screen can prevent debris from entering the main drainage pipe 3 and the backup drainage pipe 4, causing pipe blockage and thus affecting the normal drainage effect.

[0046] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A full-face tunnel boring machine with partial pressure at the front end, characterized in that: It comprises a tunneling cutterhead (1), a pressure-limiting water-soil chamber (2), a main drainage pipeline (3) and a backup drainage pipeline (4), wherein the tunneling cutterhead (1) is used for tunneling; The pressure-limiting water-soil chamber (2) is arranged behind the excavation cutterhead (1), and the pressure-limiting water-soil chamber (2) is used to collect groundwater and debris generated by excavation; The main drainage pipe (3) is in communication with the pressure-limiting water and soil tank (2), and a water inlet of the main drainage pipe (3) is arranged in the lower half of the pressure-limiting water and soil tank (2). The main drainage pipe (3) is used to discharge groundwater in the pressure-limiting water and soil tank (2); The standby drainage pipe (4) is in communication with the pressure-limiting water and soil tank (2), and a water inlet of the standby drainage pipe (4) is arranged in the upper half of the pressure-limiting water and soil tank (2). The standby drainage pipe (4) is used to assist in discharging groundwater in the pressure-limiting water and soil tank (2) and to limit the pressure in the pressure-limiting water and soil tank (2).

2. A full-face tunnel boring machine with partial pressure at the front end according to claim 1, characterized in that: The main drainage pipe (3) is arranged at the bottom of the pressure-limiting water and soil tank (2); The standby drainage pipe (4) is arranged at the middle position of the upper half of the pressure-limiting water and soil tank (2), and when the water level in the pressure-limiting water and soil tank (2) reaches the water outlet of the standby drainage pipe (4), the pressure in the pressure-limiting water and soil tank (2) reaches a preset pressure value.

3. A full-face tunnel boring machine with partial pressure at the front end according to claim 1, characterized in that: The pressure-limited water-soil chamber (2) is also provided with an electromagnetic detection device (5), and the electromagnetic detection device (5) is used to detect the underground water-rich situation in front of the tunnel face; The detection range of the electromagnetic detection equipment (5) is 50m to 100m.

4. A full-face tunnel boring machine with partial pressure at the front end according to claim 3, characterized in that: A drilling detection platform (6) is also provided in the pressure-limited water-soil chamber (2), and a drilling device is arranged on the drilling detection platform (6). When the electromagnetic detection device (5) detects that the underground water content in front of the face is higher than a preset water content, the drilling device arranged on the drilling detection platform (6) is used to perform drilling verification on the underground water content in front of the face.

5. A full-face tunnel boring machine with local pressure at the front end according to claim 1, characterized in that: The outlet of the main drainage pipe (3) extends to the rear of the tunnel boring machine and extends into the lower structure (7) which has been completely constructed; The water outlet of the backup drainage pipe (4) extends toward the rear of the tunnel boring machine, and the water outlet of the backup drainage pipe (4) is connected to the main drainage pipe (3).

6. A full-face tunnel boring machine with partial pressure at the front end according to claim 5, characterized in that: A movable water retaining device (8) is arranged in the lower structure (7), and the movable water retaining device (8) moves forward synchronously with the tunnel boring machine; The water outlet of the main drainage pipe (3) extends to the rear of the movable water retaining device (8).

7. A full-face tunnel boring machine with partial pressure at the front end according to claim 1, characterized in that: It also comprises a slag discharge device (9), wherein the feed port of the slag discharge device (9) is arranged in the pressure-limiting water and soil chamber (2), and the feed port of the slag discharge device (9) is arranged at a height higher than the water inlet of the standby drainage pipe (4); The slag discharge device (9) extends toward the rear of the tunnel boring machine.

8. A full-face tunnel boring machine with local pressure at the front end according to claim 2, characterized in that: It also comprises a water pressure gauge (10), which is arranged at the bottom of the pressure-limiting water and soil chamber (2), and is used to monitor the pressure value in the pressure-limiting water and soil chamber (2).

9. A full-face tunnel boring machine with partial pressure at the front end according to claim 8, characterized in that: When the pressure value in the pressure-limiting water and soil compartment (2) monitored by the water pressure gauge (10) is higher than a preset pressure value or the water level in the pressure-limiting water and soil compartment (2) is higher than the set height of the water inlet of the backup drainage pipe (4), the excavation cutterhead (1) is in a shutdown state, and water is discharged to the outside through the main drainage pipe (3) and the backup drainage pipe (4).

10. A full-face tunnel boring machine with partial pressure at the front end according to claim 1, characterized in that: The water inlet of the main drainage pipe (3) and the water inlet of the backup drainage pipe (4) are both provided with filter screens.