The application discloses a kind of
artificial reef concrete preparation methods, comprising: preparation steel
slag fine aggregate, preparation steel
slag base coarse aggregate, preparation
artificial reef concrete;Specifically including the steel
slag that meets the condition is screened, obtains two different particle sizes steel slag particles, carries out stabilization, screening and
grinding, washing treatment, then the steel slag
powder obtained is two-step
granulation and two-step maintenance, obtains steel slag base coarse aggregate;Finally steel slag fine aggregate, coarse aggregate, cementing material, water and admixture are mixed uniformly according to preset proportion after forming maintenance, preparation adult
artificial reef concrete.The steel slag content of the present application is not less than 55%, the 28-day
compressive strength of concrete is higher than 38MPa, the strength
retention rate is not less than 95% after
seawater immersion for 360 days, pH is stabilized at 8.39~8.46, close to natural
seawater pH value 8.2.Using steel slag for artificial
reef concrete can realize large-scale, high-value utilization of steel slag, adapt to the current situation of large demand for artificial
reef, and also can greatly reduce the production cost of artificial
reef.