Embankment structure of cross-sea road and construction method

By using plastic drainage plates, immersed pipe sand piles and prefabricated pipe piles in the construction of cross-sea highways, combined with non-woven geotextiles and steel-plastic geogrids, construction problems under different geological environments are solved and the foundation is realized The improvement of stability and construction costs are suitable for cross-sea highway construction.

CN119061751APending Publication Date: 2024-12-03ZHEJIANG COMM CONSTR GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411469510.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-21
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

The construction difficulty and cost of uneven foundation settlement and different soil characteristics in the construction of cross-sea highways is problematic, and effective treatment methods are lacking to adapt to different geological environments.

Method used

Adopt foundation treatment structures such as plastic drainage plates, immersed pipe sand piles and prefabricated pipe piles, combined with non-woven geotextiles and steel-plastic geogrids, and different treatment methods are selected according to the geological environment, including blasting, silting, inserting and punching drainage plates, and immersing pipes. Construction methods such as sand piles and prefabricated pipe piles ensure the stability and safety of the embankment.

Benefits of technology

It realizes flexible treatment of different geological environments, reduces foundation disturbances and construction costs, improves the bearing capacity of the foundation and the overall stability of the embankment, and is suitable for the construction of cross-sea highways, with high cost-effectiveness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119061751A_ABST
    Figure CN119061751A_ABST
Patent Text Reader

Abstract

The invention discloses an embankment structure of a cross-sea road and a construction method. The embankment structure comprises a foundation treatment structure, and the foundation treatment structure comprises a plastic drainage plate treatment structure or a pipe sinking sand pile treatment structure or a prefabricated pipe pile treatment structure; the plastic drainage plate treatment structure comprises a plastic drainage plate, a non-woven geotextile, a first broken stone hardcore, a two-way steel-plastic geogrid, a second broken stone hardcore and a steel-plastic geogrid. The immersed tube sand pile processing structure comprises an immersed tube sand pile, non-woven geotextile, a first broken stone hardcore, a two-way steel-plastic geogrid, a second broken stone hardcore and a steel-plastic geogrid. The prefabricated pipe pile treatment structure comprises a prefabricated pipe pile, non-woven geotextile, a first broken stone hardcore, a bidirectional steel-plastic geogrid and a second broken stone hardcore.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of embankment engineering of a cross-sea highway, and in particular to an embankment structure and a construction method of a cross-sea highway. Background Art

[0002] With the booming economy of my country and the accelerated process of regional integration, small island cities in coastal areas are facing unique challenges brought by the marine environment. In order to break the geographical barriers and promote economic exchanges and personnel exchanges, cross-sea bridges and cross-sea tunnels have emerged as landmark projects, which have effectively alleviated the constraints of marine conditions on transportation to a certain extent. However, given the great difficulty and high cost of the construction of these super projects, the idea of ​​an economical cross-sea highway has become one of the ideas for connecting islands with the inland.

[0003] However, there are a large number of tidal flats, silt and silty clay along the cross-sea highway, and the soil properties are mostly characterized by high compressibility, high sensitivity, high water content, poor permeability, and weak foundation strength. During the construction process, it is easy to cause uneven foundation settlement, which poses a huge risk. In addition, the soil quality of different sections is also different, and different soil structures require different treatment methods. These problems have brought huge challenges to the construction of the cross-sea highway.

[0004] In view of the above problems, there is currently a lack of further specific research on the construction process of cross-sea highways under different geological environments, so it is urgent to design a structure and construction method for cross-sea highway embankments that can effectively solve the above problems. Summary of the invention

[0005] 1. Technical issues to be resolved

[0006] The technical problem to be solved by the present invention is to provide a cross-sea highway embankment structure and construction method, which is suitable for treating different soft foundations and can adopt different treatment methods for various complex geological environments, which is flexible and changeable.

[0007] (II) Technical solution

[0008] The solution adopted by the present invention to solve the above technical problems is a cross-sea highway embankment structure, including a foundation treatment structure, wherein the foundation treatment structure includes a plastic drainage board treatment structure or a pipe-sinking sand pile treatment structure or a prefabricated pipe pile treatment structure;

[0009] The plastic drain board treatment structure includes a plastic drain board, a non-woven geotextile, a first crushed stone cushion layer, a bidirectional steel-plastic geogrid, a second crushed stone cushion layer and a steel-plastic geogrid; the plastic drain boards are arranged at equal intervals below the main body of the embankment, and the top of the plastic drain board extends out of the first crushed stone cushion layer, and the bottom of the plastic drain board is lower than the bottom of the soft soil layer; the plastic drain boards are arranged in an equilateral triangle; the non-woven geotextile is arranged below the first crushed stone cushion layer, and on both sides of the first crushed stone cushion layer and the second crushed stone cushion layer; the first crushed stone cushion layer, the bidirectional steel-plastic geogrid and the second crushed stone cushion layer are arranged on the non-woven geotextile and are stacked tightly from bottom to top, and the first crushed stone cushion layer and the second crushed stone cushion layer both extend outward in the transverse direction of the roadbed. The steel-plastic geogrid is arranged at equal intervals on the second crushed stone cushion layer;

[0010] The pipe-sinking sand pile treatment structure comprises pipe-sinking sand piles, non-woven geotextile, a first crushed stone cushion layer, a bidirectional steel-plastic geogrid, a second crushed stone cushion layer and a steel-plastic geogrid; the pipe-sinking sand piles are arranged at equal intervals below the first crushed stone cushion layer, and the tops of the pipe-sinking sand piles are in contact with the bottoms of the first crushed stone cushion layer, and adjacent pipe-sinking sand piles are arranged in an equilateral triangle; the non-woven geotextile is arranged below the first crushed stone cushion layer, and on both sides of the first crushed stone cushion layer and the second crushed stone cushion layer; the first crushed stone cushion layer, the bidirectional steel-plastic geogrid and the second crushed stone cushion layer are arranged on the non-woven geotextile, and are stacked closely in sequence from bottom to top; the first crushed stone cushion layer and the second crushed stone cushion layer both extend outward in the transverse direction of the roadbed; the steel-plastic geogrid is arranged at equal intervals on the second crushed stone cushion layer;

[0011] The prefabricated pipe pile processing structure includes prefabricated pipe piles, non-woven geotextile, a first crushed stone cushion layer, a bidirectional steel-plastic geogrid and a second crushed stone cushion layer; the top of the pile cap of the prefabricated pipe pile is flush with the top of the first crushed stone cushion layer, the bottom of the pile cap of the prefabricated pipe pile is flush with the bottom of the first crushed stone cushion layer, adjacent prefabricated pipe piles are arranged in a square shape on the plane, and the prefabricated pipe piles are arranged at equal intervals; the non-woven geotextile is arranged below the first crushed stone cushion layer, and on both sides of the first crushed stone cushion layer and the second crushed stone cushion layer; the first crushed stone cushion layer, the bidirectional steel-plastic geogrid and the second crushed stone cushion layer are arranged on the non-woven geotextile, and are stacked tightly in sequence from bottom to top; the first crushed stone cushion layer and the second crushed stone cushion layer both extend outward in the transverse direction of the roadbed.

[0012] In some embodiments, different foundation treatment structures are selected for different geological environments of cross-sea embankments; for sections with deep silt and silty soil, a plastic drainage board treatment structure is used; for sections with shallow silt, plain fill and clay soil, a sunken pipe sand pile treatment structure is used; for bridgehead sections, higher fill sections and sections with deep soft foundations with complex geology, a prefabricated pipe pile treatment structure is used.

[0013] In some embodiments, the non-woven geotextile is made of 100% polyester filament needle-punched non-woven material with a unit mass ≥300g / m2; the bidirectional steel-plastic geogrid is a mesh structure and can be stretched in the transverse and longitudinal directions simultaneously; the longitudinal and transverse breaking elongation of the steel-plastic geogrid and the bidirectional steel-plastic geogrid is ≤3%, the longitudinal and transverse tensile strength is ≥100kN / m2, the friction coefficient is ≥0.6, the width is ≥4m, the node peeling force is ≥300N, and the overlap width is greater than 20cm; the pile body of the sunken pipe sand pile is made of medium-coarse sand or gravel or stone chips, with a maximum particle size of ≤20mm and a mud content of ≤5%; the prefabricated pipe pile is a prestressed concrete pipe pile, the pipe pile of the prefabricated pipe pile is made of C70 concrete, and the pile cap of the prefabricated pipe pile is made of C30 concrete.

[0014] In some embodiments, it also includes a circular culvert arranged on the foundation treatment structure; the foundation of the circular culvert is arranged above the second gravel cushion layer, and the pipe section of the circular culvert is arranged above the foundation of the circular culvert.

[0015] The above solution can ensure that the seawater on both sides of the cross-sea highway is interconnected, reducing damage to the environment.

[0016] In some embodiments, expansion joints are provided between the foundations of the circular culvert and between the pipe sections of the circular culvert.

[0017] By adopting the above scheme, the impact of cracking or damage of the circular culvert caused by changes in temperature and humidity can be reduced, thereby improving the safety and stability of the circular culvert structure.

[0018] The solution adopted by the present invention to solve the above technical problems is a construction method of an embankment structure of a cross-sea highway, comprising the following steps:

[0019] (1) For sections of silt and silty soil, blasting and squeezing of silt are first required. The specific steps are as follows: first, survey and lay out the lines, and fill the embankment according to the parameters. Next, explosive packs are placed on both sides of the road section for blasting. The detonation will generate huge pressure to form a cavity in the silt, destroying and squeezing out the silt. The riprap body, with its own gravity, slides into the cavity after being vibrated to form a new stone tongue, achieving the purpose of replacing the silt. This cycle promotes the work.

[0020] (2) For sections with deep silt and silty soil, a plastic drainage board treatment structure is used for soft foundation treatment. The specific steps are as follows: first, a layer of non-woven geotextile is laid on the ground, and then the first crushed stone cushion layer is filled and compacted on top of the non-woven geotextile. The positioning unit is assembled on top of the first crushed stone cushion layer, and the plastic drainage board is inserted. When it is inserted to the designed depth, the plastic drainage board is cut off and replaced to the next point. The cycle is repeated until the construction of all points is completed. After the construction is completed, a bidirectional steel-plastic geogrid is laid on top of the first crushed stone cushion layer, and the second crushed stone cushion layer is filled and compacted on the bidirectional steel-plastic geogrid. The second crushed stone cushion layer should extend a certain length from the slope foot in the transverse direction of the roadbed, and the specific length should meet the design requirements. Then, the two ends of the non-woven geotextile under the first crushed stone cushion layer are reversed upward as the edge protection of the first crushed stone cushion layer and the second crushed stone cushion layer. Finally, steel-plastic geogrids are added at a certain interval on the second crushed stone cushion layer, and the spacing is determined according to the design requirements.

[0021] For sections with shallow silt, plain fill and clay soil, the soft foundation treatment structure is carried out by using a pipe-sinking sand pile treatment structure. The specific steps are as follows: first, lay a layer of non-woven geotextile on the ground, and then fill the first crushed stone cushion layer on top of the non-woven geotextile and compact it; then install a pile driver on top of the first crushed stone cushion layer, insert the pipe-sinking sand pile into the soil to the specified elevation and start filling with sand, use the pipe mouth flushing and vibration to sink the sand and repeatedly lift and lower the pressure to pull the column pipe until the pipe-sinking sand pile is lifted to the hole mouth, and then replace it to the next point, and repeat the cycle until all points are completed. After the construction is completed, a bidirectional steel-plastic geogrid is laid on the top of the first crushed stone cushion layer, and the second crushed stone cushion layer is filled and compacted on the bidirectional steel-plastic geogrid. The second crushed stone cushion layer should extend a certain length from the slope foot along the transverse direction of the roadbed, and the specific length should meet the design requirements; then the two ends of the non-woven geotextile under the first crushed stone cushion layer are reversed upward as the edge protection of the first crushed stone cushion layer and the second crushed stone cushion layer; finally, steel-plastic geogrids are added on the second crushed stone cushion layer at a certain interval, and the spacing is determined according to the design requirements;

[0022] For the bridgehead section, the higher fill section and the deep soft foundation section with complex geology, the prefabricated pipe pile treatment structure is used for soft foundation treatment. The specific steps are as follows: first, a layer of non-woven geotextile is laid on the ground, and then the first crushed stone cushion layer is filled and compacted on the non-woven geotextile; then, a pile driver is installed on the first crushed stone cushion layer, and the prefabricated pipe piles are vertically pressed into the soil through the hydraulic system, and the pile positions are moved in sequence to press the piles; after the construction is completed, the pile cap soil needs to be excavated, and the steel bars are tied and poured with concrete for maintenance; finally, a bidirectional steel-plastic geogrid is laid on the first crushed stone cushion layer, and the second crushed stone cushion layer is filled and compacted on the bidirectional steel-plastic geogrid. The second crushed stone cushion layer should extend a certain length from the slope foot along the transverse direction of the roadbed, and the specific length should meet the design requirements; the two ends of the non-woven geotextile under the first crushed stone cushion layer are reversed upward as the edge protection of the first crushed stone cushion layer and the second crushed stone cushion layer;

[0023] (3) Next, the roadbed is processed, mainly including filling and excavation. The specific steps are as follows: When filling, firstly, the construction is set out, and horizontal segmentation and layering are adopted. After paving with a bulldozer, it is pre-compacted and leveled with a bulldozer or a roller, and finally vibrated and compacted with a roller; when excavating, the rocks with larger diameters are mainly crushed, and hydraulic breakers are used to crush the rock mass;

[0024] (4) For the coastal section, a circular culvert needs to be set up on the roadbed. The specific steps are as follows: first, survey and lay out the lines and excavate the foundation pit. Then, use C20 concrete to construct the culvert bottom foundation. Use a hoist and a forklift to install the pipe section of the circular culvert. Finally, backfill the foundation pit at the top of the circular culvert and compact it with a compactor.

[0025] (5) After the roadbed is built, the embankment pavement needs to be constructed. The specific steps are as follows: the pavement from bottom to top is graded crushed stone cushion layer, cement stabilized crushed stone base layer, and concrete pavement; first, the graded crushed stone is mixed, spread on the roadbed with a mixture transport vehicle, and rolled with a roller in a direction parallel to the center of the road; then, the cement stabilized crushed stone is mixed, spread on the roadbed with a mixture transport vehicle, and rolled with a roller in a direction parallel to the center of the road. After the construction is completed, the geotextile is laid and water is sprinkled for maintenance for seven days; finally, the cement soil pavement is poured, and the concrete mixture is transported to the paving site by a concrete transport vehicle for paving, vibration, and surface preparation, then smoothed with a disc trowel, roughened with an embossing machine, sprinkled with water, and covered with old sacks for maintenance for 14 to 21 days.

[0026] In some embodiments, the blasting to squeeze out silt needs to determine the height of the embankment fill based on geotechnical calculation principles and the designed height of the embankment; the width of the embankment fill needs to be determined based on the fill height and the designed section of the embankment; the fill stone is the embankment core stone, and after the blasting is completed, the bottom elevation of the embankment core stone foundation should meet the design requirements.

[0027] In some embodiments, the gaps between the pipe sections of the circular culvert are filled with asphalt hemp, and the outside is wrapped with three layers of oil felt coated with hot asphalt for waterproofing.

[0028] (III) Beneficial effects

[0029] Compared with the prior art, the present invention designs an embankment structure and construction method for a cross-sea highway.

[0030] (1) When treating a deep soft foundation with high moisture content, high compressibility and poor water permeability, the present invention adopts a plastic drainage board for foundation treatment. This method has the characteristics of good drainage performance, low cost, little disturbance to the foundation and ensuring the integrity of the foundation;

[0031] (2) The present invention uses pipe-sinking sand piles for foundation treatment when treating shallow silt, plain fill, and clay foundations with insufficient foundation bearing capacity or poor geological conditions. This method has good drainage and consolidation performance and can improve soil strength through compaction replacement.

[0032] (3) The present invention uses prefabricated pipe piles for foundation treatment when treating bridgehead sections, high fill sections, and deep soft foundations with complex geology. This method has the characteristics of strong bearing capacity and efficient construction.

[0033] (4) The present invention is applicable to treating different soft foundations, and can adopt different treatment methods for various complex geological environments, which is flexible and changeable;

[0034] (5) The present invention can also be applied to the construction of cross-sea highway sections. On the basis of the above, by adding a circular culvert in the roadbed, the construction of the cross-sea highway embankment can be realized. Compared with bridges and tunnels, the construction of cross-sea highways has a higher cost-effectiveness. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0036] Figure 1 It is a schematic diagram of three structures of the foundation treatment structure of the embankment structure of a cross-sea highway;

[0037] Figure 2 This is a cross-sectional view of the plastic drainage board treatment structure;

[0038] Figure 3 This is a cross-sectional view of the pipe-sinking sand pile treatment structure;

[0039] Figure 4This is a cross-sectional view of the prefabricated pipe pile treatment structure;

[0040] Figure 5 It is the cross-section diagram of the circular culvert;

[0041] Figure 6 This is a schematic diagram of the side opening of a circular culvert;

[0042] Figure 7 The present invention is a construction process flow chart of a construction method of an embankment structure of a cross-sea highway.

[0043] The names of the components corresponding to the various figure marks in the figure are: 1. Plastic drainage board treatment structure; 1-1. Plastic drainage board; 1-2. Non-woven geotextile; 1-3. First crushed stone cushion layer; 1-4. Bidirectional steel-plastic geogrid; 1-5. Second crushed stone cushion layer; 1-6. Steel-plastic geogrid; 2. Sinking tube sand pile treatment structure; 2-1. Sinking tube sand pile; 3. Prefabricated pipe pile treatment structure; 3-1. Prefabricated pipe pile; 4. Embankment core stone; 5. Circular culvert. DETAILED DESCRIPTION

[0044] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

[0045] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0046] The following describes the implementation methods of the present application through specific examples, and those skilled in the art can easily understand other advantages and effects of the present application from the contents disclosed in this specification. Obviously, the described embodiments are only a part of the embodiments of the present application, rather than all the embodiments. The present application can also be implemented or applied through other different specific implementation methods, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present application. It should be noted that, in the absence of conflict, the following embodiments and the features in the embodiments can be combined with each other. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without making creative work belong to the scope of protection of the present application.

[0047] It should be noted that various aspects of the embodiments within the scope of the appended claims are described below. It should be apparent that the aspects described herein can be embodied in a wide variety of forms, and any specific structure and / or function described herein is merely illustrative. Based on the present application, it should be understood by those skilled in the art that an aspect described herein can be implemented independently of any other aspect, and two or more of these aspects can be combined in various ways. For example, any number and aspect described herein can be used to implement the device and / or practice the method. In addition, other structures and / or functionalities other than one or more of the aspects described herein can be used to implement this device and / or practice this method.

[0048] It should also be noted that the illustrations provided in the following embodiments are only schematic illustrations of the basic concept of the present application. The drawings only show components related to the present application rather than being drawn according to the number, shape and size of components in actual implementation. In actual implementation, the type, quantity and proportion of each component may be changed arbitrarily, and the component layout may also be more complicated.

[0049] Additionally, in the following description, specific details are provided to facilitate a thorough understanding of the examples. However, it will be understood by those skilled in the art that the examples can be practiced without these specific details.

[0050] The technical solutions provided by various embodiments of the present application are described below in conjunction with the accompanying drawings.

[0051] like Figure 1 As shown, the present invention provides an embankment structure for a cross-sea highway, wherein the foundation treatment structure includes a plastic drainage board treatment structure 1 or a pipe-sunken sand pile treatment structure 2 or a prefabricated pipe pile treatment structure 3.

[0052] like Figure 2As shown, the plastic drain board treatment structure 1 includes a plastic drain board 1-1, a non-woven geotextile 1-2, a first crushed stone cushion layer 1-3, a bidirectional steel-plastic geogrid 1-4, a second crushed stone cushion layer 1-5 and a steel-plastic geogrid 1-6; the plastic drain boards 1-1 are arranged at equal intervals below the main body of the embankment, and the top of the plastic drain board 1-1 extends out of the first crushed stone cushion layer 1-3, and the bottom of the plastic drain board 1-1 is lower than the bottom of the soft soil layer; the plastic drain boards 1-1 are arranged in an equilateral triangle; the non-woven geotextile 1-2 is arranged below the first crushed stone cushion layer 1-3, and on both sides of the first crushed stone cushion layer 1-3 and the second crushed stone cushion layer 1-5; the first crushed stone cushion layer 1-3, the bidirectional steel-plastic geogrid 1-4 and the second crushed stone cushion layer 1-5 are arranged on the non-woven geotextile 1-2, and are stacked tightly from bottom to top, and the first crushed stone cushion layer 1-3 and the second crushed stone cushion layer 1-5 both extend outward in the transverse direction of the roadbed. The steel-plastic geogrids 1-6 are arranged on the second crushed stone cushion layer 1-5 at equal intervals;

[0053] like Figure 3 As shown, the pipe-sinking sand pile treatment structure 2 includes a pipe-sinking sand pile 2-1, a non-woven geotextile 1-2, a first crushed stone cushion layer 1-3, a bidirectional steel-plastic geogrid 1-4, a second crushed stone cushion layer 1-5 and a steel-plastic geogrid 1-6; the pipe-sinking sand piles 2-1 are arranged at equal intervals below the first crushed stone cushion layer 1-3, and the top of the pipe-sinking sand pile 2-1 is in contact with the bottom of the first crushed stone cushion layer 1-3, and adjacent pipe-sinking sand piles 2-1 are arranged in an equilateral triangle; the non-woven geotextile 1- 2 is arranged below the first crushed stone cushion layer 1-3, and on both sides of the first crushed stone cushion layer 1-3 and the second crushed stone cushion layer 1-5; the first crushed stone cushion layer 1-3, the bidirectional steel-plastic geogrid 1-4 and the second crushed stone cushion layer 1-5 are arranged on the non-woven geotextile 1-2, and are stacked closely from bottom to top; the first crushed stone cushion layer 1-3 and the second crushed stone cushion layer 1-5 both extend outward in the transverse direction of the roadbed; the steel-plastic geogrid 1-6 is arranged on the second crushed stone cushion layer 1-5 at equal intervals;

[0054] like Figure 4As shown, the prefabricated pipe pile treatment structure 3 includes a prefabricated pipe pile 3-1, a non-woven geotextile 1-2, a first crushed stone cushion layer 1-3, a bidirectional steel-plastic geogrid 1-4 and a second crushed stone cushion layer 1-5; the top of the pile cap of the prefabricated pipe pile 3-1 is flush with the top of the first crushed stone cushion layer 1-3, the bottom of the pile cap of the prefabricated pipe pile 3-1 is flush with the bottom of the first crushed stone cushion layer 1-3, and adjacent prefabricated pipe piles 3-1 are arranged in a square shape on the plane, and the prefabricated pipe piles 3-1 are arranged at equal intervals; the non-woven geotextile 1-2 is arranged below the first crushed stone cushion layer 1-3, and on both sides of the first crushed stone cushion layer 1-3 and the second crushed stone cushion layer 1-5; the first crushed stone cushion layer 1-3, the bidirectional steel-plastic geogrid 1-4 and the second crushed stone cushion layer 1-5 are arranged on the non-woven geotextile 1-2, and are stacked tightly in sequence from bottom to top; the first crushed stone cushion layer 1-3 and the second crushed stone cushion layer 1-5 both extend outward along the transverse direction of the roadbed.

[0055] Specifically, different foundation treatment structures are selected for different geological environments of cross-sea embankments; for sections with deep silt and silty soil, plastic drainage board treatment structure 1 is adopted; for shallow silt, plain fill and clay soil sections, pipe-sunken sand pile treatment structure 2 is adopted; for bridgehead sections, higher fill sections and deep soft foundation sections with complex geology, prefabricated pipe pile treatment structure 3 is adopted.

[0056] In some embodiments, the non-woven geotextile 1-2 is made of 100% polyester filament needle-punched non-woven material with a unit mass ≥300g / m2; the bidirectional steel-plastic geogrid 1-4 is a mesh structure and can be stretched in the transverse and longitudinal directions simultaneously; the longitudinal and transverse breaking elongation of the steel-plastic geogrid 1-6 and the bidirectional steel-plastic geogrid 1-4 is ≤3%, the longitudinal and transverse tensile strength is ≥100kN / m2, the friction coefficient is ≥0.6, the width is ≥4m, the node peeling force is ≥300N, and the overlap width is greater than 20cm; the pile body aggregate of the sunken pipe sand pile 2-1 is made of medium-coarse sand or gravel or stone chips, with a maximum particle size of ≤20mm and a mud content of ≤5%; the prefabricated pipe pile 3-1 is a prestressed concrete pipe pile, the pipe pile of the prefabricated pipe pile 3-1 is made of C70 concrete, and the pile cap of the prefabricated pipe pile 3-1 is made of C30 concrete.

[0057] In some embodiments, Figure 5-Figure 6 , and also includes a circular culvert 5 arranged on the foundation treatment structure; the foundation of the circular culvert 5 is arranged above the second gravel cushion layer 1-5, and the pipe section of the circular culvert 5 is arranged above the foundation of the circular culvert 5. The above scheme can ensure that the seawater on both sides of the cross-sea highway is connected to each other, reducing damage to the environment.

[0058] In some embodiments, expansion joints are provided between the foundations of the circular culvert 5 and between the pipe sections of the circular culvert 5. The above scheme can reduce the impact of cracking or damage of the circular culvert 5 caused by changes in temperature and humidity, thereby improving the safety and stability of the circular culvert 5 structure.

[0059] like Figure 7 As shown, the present invention also provides a construction method for an embankment structure of a cross-sea highway, comprising the following steps:

[0060] (1) For sections of silt and silty soil, blasting and squeezing of silt are first required. The specific steps are as follows: first, survey and lay out the lines, and fill the embankment according to the parameters. Next, explosive packs are placed on both sides of the road section for blasting. At the moment of detonation, huge pressure will be generated to form a cavity in the silt, destroying and squeezing out the silt. The riprap body, with the help of its own gravity, slides into the cavity after being vibrated to form a new stone tongue, achieving the purpose of replacing the silt. This cycle promotes the work;

[0061] (2) For sections with deep silt and silty soil, a plastic drainage board treatment structure 1 is used for soft foundation treatment. The specific steps are as follows: first, a layer of non-woven geotextile 1-2 is laid on the ground, and then a first crushed stone cushion layer 1-3 is filled on top of the non-woven geotextile 1-2 and compacted. A positioning unit is assembled on top of the first crushed stone cushion layer 1-3, and the plastic drainage board 1-1 is inserted and inserted. When it is inserted to the designed depth, the plastic drainage board 1-1 is cut off and replaced to the next point, and the cycle is repeated until the construction of all points is completed; after the construction is completed, the first crushed stone cushion layer 1-3 is filled with a first crushed stone cushion layer 1-3. A bidirectional steel-plastic geogrid 1-4 is laid on the top, and a second crushed stone cushion layer 1-5 is filled and compacted on the bidirectional steel-plastic geogrid 1-4. The second crushed stone cushion layer 1-5 should extend a certain length from the slope foot along the transverse direction of the roadbed, and the specific length should meet the design requirements; then, both ends of the non-woven geotextile 1-2 below the first crushed stone cushion layer 1-3 are turned up to serve as the edge protection of the first crushed stone cushion layer 1-3 and the second crushed stone cushion layer 1-5; finally, steel-plastic geogrids 1-6 are added on the second crushed stone cushion layer 1-5 at a certain interval, and the interval distance is determined according to the design requirements;

[0062] For sections of shallow silt, plain fill and clay soil, a pipe-sinking sand pile treatment structure 2 is used for soft foundation treatment. The specific steps are as follows: first, a layer of non-woven geotextile 1-2 is laid on the ground, and then a first crushed stone cushion layer 1-3 is filled on the non-woven geotextile 1-2 and compacted; then, a pile driver is installed on the first crushed stone cushion layer 1-3, and the pipe-sinking sand pile 2-1 is inserted into the soil to a specified elevation and then sand is poured. The sand is deposited by flushing water and vibrating the pipe mouth, and the pressure is repeatedly raised and lowered to pull the column pipe until the pipe-sinking sand pile 2-1 is lifted to the hole mouth, and then replaced to the next point, and the cycle is repeated until the construction of all points is completed; construction After completion, a bidirectional steel-plastic geogrid 1-4 is laid on the first crushed stone cushion layer 1-3, and a second crushed stone cushion layer 1-5 is filled and compacted on the bidirectional steel-plastic geogrid 1-4. The second crushed stone cushion layer 1-5 should extend a certain length from the slope foot in the transverse direction of the roadbed, and the specific length should meet the design requirements; then, both ends of the non-woven geotextile 1-2 under the first crushed stone cushion layer 1-3 are reversed upward as the edge protection of the first crushed stone cushion layer 1-3 and the second crushed stone cushion layer 1-5; finally, steel-plastic geogrids 1-6 are added on the second crushed stone cushion layer 1-5 at a certain interval, and the spacing distance is determined according to the design requirements;

[0063] For the bridgehead section, the higher fill section and the deep soft foundation section with complex geology, the prefabricated pipe pile treatment structure 3 is used for soft foundation treatment. The specific steps are as follows: first, a layer of non-woven geotextile 1-2 is laid on the ground, and then the first crushed stone cushion layer 1-3 is filled on the non-woven geotextile 1-2 and compacted; then, a pile driver is installed on the first crushed stone cushion layer 1-3, and the prefabricated pipe pile 3-1 is vertically pressed into the soil through the hydraulic system, and the pile position is moved to press the pile in turn; after the construction is completed, the soil of the pile cap needs to be excavated and the steel is tied. The reinforcement is poured and cured with concrete; finally, a bidirectional steel-plastic geogrid 1-4 is laid on the first crushed stone cushion layer 1-3, and a second crushed stone cushion layer 1-5 is filled and compacted on the bidirectional steel-plastic geogrid 1-4. The second crushed stone cushion layer 1-5 should extend a certain length from the slope foot in the transverse direction of the roadbed, and the specific length should meet the design requirements; both ends of the non-woven geotextile 1-2 under the first crushed stone cushion layer 1-3 are reversed upward as the edge protection of the first crushed stone cushion layer 1-3 and the second crushed stone cushion layer 1-5;

[0064] (3) Next, the roadbed is processed, mainly including filling and excavation. The specific steps are as follows: When filling, firstly, the construction is set out, and horizontal segmentation and layering are adopted. After paving with a bulldozer, it is pre-compacted and leveled with a bulldozer or a roller, and finally vibrated and compacted with a roller; when excavating, the rocks with larger diameters are mainly crushed, and hydraulic breakers are used to crush the rock mass;

[0065] (4) For the coastal section, a circular culvert 5 needs to be set up on the roadbed. The specific steps are as follows: first, survey and lay out and excavate the foundation pit, then use C20 concrete to construct the culvert bottom foundation, and use a hoist and a forklift to install the pipe section of the circular culvert 5; finally, backfill the foundation pit of the pipe top of the circular culvert 5 and compact it with a compactor;

[0066] (5) After the roadbed is built, the embankment pavement needs to be constructed. The specific steps are as follows: the pavement from bottom to top is graded crushed stone cushion layer, cement stabilized crushed stone base layer, and concrete pavement; first, the graded crushed stone is mixed, spread on the roadbed with a mixture transport vehicle, and rolled with a roller in a direction parallel to the center of the road; then, the cement stabilized crushed stone is mixed, spread on the roadbed with a mixture transport vehicle, and rolled with a roller in a direction parallel to the center of the road. After the construction is completed, the geotextile is laid and water is sprinkled for maintenance for seven days; finally, the cement soil pavement is poured, and the concrete mixture is transported to the paving site by a concrete transport vehicle for paving, vibration, and surface preparation, then smoothed with a disc trowel, roughened with an embossing machine, sprinkled with water, and covered with old sacks for maintenance for 14 to 21 days.

[0067] In some embodiments, the blasting and squeezing of silt needs to determine the height of the embankment fill based on geotechnical calculation principles and the designed height of the embankment; the width of the embankment fill needs to be determined based on the fill height and the designed section of the embankment; the fill stone is the embankment core stone 4, and after the blasting is completed, the bottom elevation of the foundation of the embankment core stone 4 should meet the design requirements.

[0068] In some embodiments, the gaps between the pipe sections of the circular culvert 5 are filled with asphalt hemp, and the outside is wrapped with three layers of oil felt coated with hot asphalt for waterproofing.

[0069] The same and similar parts between the various embodiments in this specification can be referenced to each other, and each embodiment focuses on the differences from other embodiments.

[0070] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed in the present application should be included in the protection scope of the present application. Therefore, the protection scope of the present application shall be based on the protection scope of the claims.

Claims

1. A cross-sea highway embankment structure, characterized in that: It comprises a foundation treatment structure, wherein the foundation treatment structure comprises a plastic drainage board treatment structure (1) or a pipe-sinking sand pile treatment structure (2) or a prefabricated pipe pile treatment structure (3); The plastic drainage board treatment structure (1) comprises a plastic drainage board (1-1), a non-woven geotextile (1-2), a first crushed stone cushion layer (1-3), a bidirectional steel-plastic geogrid (1-4), a second crushed stone cushion layer (1-5) and a steel-plastic geogrid (1-6); the plastic drainage boards (1-1) are arranged at equal intervals below the main body of the embankment, and the top of the plastic drainage board (1-1) extends out of the first crushed stone cushion layer (1-3), and the bottom of the plastic drainage board (1-1) is lower than the bottom of the soft soil layer; the plastic drainage boards (1-1) are arranged in an equilateral triangle; The non-woven geotextile (1-2) is arranged below the first crushed stone cushion layer (1-3) and on both sides of the first crushed stone cushion layer (1-3) and the second crushed stone cushion layer (1-5); the first crushed stone cushion layer (1-3), the bidirectional steel-plastic geogrid (1-4) and the second crushed stone cushion layer (1-5) are arranged on the non-woven geotextile (1-2) and are stacked closely in sequence from bottom to top, and the first crushed stone cushion layer (1-3) and the second crushed stone cushion layer (1-5) both extend outwards in the transverse direction of the roadbed; the steel-plastic geogrid (1-6) is arranged on the second crushed stone cushion layer (1-5) at equal intervals; The pipe-sinking sand pile treatment structure (2) comprises a pipe-sinking sand pile (2-1), a non-woven geotextile (1-2), a first crushed stone cushion layer (1-3), a bidirectional steel-plastic geogrid (1-4), a second crushed stone cushion layer (1-5) and a steel-plastic geogrid (1-6); the pipe-sinking sand piles (2-1) are arranged at equal intervals below the first crushed stone cushion layer (1-3), and the top of the pipe-sinking sand pile (2-1) is in contact with the bottom of the first crushed stone cushion layer (1-3), and adjacent pipe-sinking sand piles (2-1) are arranged in an equilateral triangle; the non-woven geotextile (1-2 ) are arranged below the first crushed stone cushion layer (1-3), and on both sides of the first crushed stone cushion layer (1-3) and the second crushed stone cushion layer (1-5); the first crushed stone cushion layer (1-3), the bidirectional steel-plastic geogrid (1-4) and the second crushed stone cushion layer (1-5) are arranged on the non-woven geotextile (1-2), and are stacked closely in sequence from bottom to top; the first crushed stone cushion layer (1-3) and the second crushed stone cushion layer (1-5) both extend outwards in the transverse direction of the roadbed; the steel-plastic geogrid (1-6) is arranged on the second crushed stone cushion layer (1-5) at equal intervals; The prefabricated pipe pile treatment structure (3) comprises a prefabricated pipe pile (3-1), a non-woven geotextile (1-2), a first crushed stone cushion layer (1-3), a bidirectional steel-plastic geogrid (1-4) and a second crushed stone cushion layer (1-5); the top of the pile cap of the prefabricated pipe pile (3-1) is flush with the top of the first crushed stone cushion layer (1-3), the bottom of the pile cap of the prefabricated pipe pile (3-1) is flush with the bottom of the first crushed stone cushion layer (1-3), adjacent prefabricated pipe piles (3-1) are arranged in a square shape on a plane, and the prefabricated pipe piles (3-1) are arranged in a square shape on a plane. -1) are arranged at equal intervals; the non-woven geotextile (1-2) is arranged below the first crushed stone cushion layer (1-3), and on both sides of the first crushed stone cushion layer (1-3) and the second crushed stone cushion layer (1-5); the first crushed stone cushion layer (1-3), the bidirectional steel-plastic geogrid (1-4) and the second crushed stone cushion layer (1-5) are arranged on the non-woven geotextile (1-2), and are stacked closely in sequence from bottom to top; the first crushed stone cushion layer (1-3) and the second crushed stone cushion layer (1-5) both extend outwards in the transverse direction of the roadbed.

2. The embankment structure of the cross-sea highway according to claim 1 is characterized in that: Different foundation treatment structures are selected for different geological environments of cross-sea embankments; for sections with deep silt and silty soil, a plastic drainage board treatment structure (1) is used; for sections with shallow silt, plain fill and clay soil, a pipe-sunken sand pile treatment structure (2) is used; for bridgehead sections, higher fill sections and sections with deep soft foundations with complex geology, a prefabricated pipe pile treatment structure (3) is used.

3. The embankment structure of the cross-sea highway according to claim 1 is characterized in that: The non-woven geotextile (1-2) is made of 100% polyester filament needle-punched non-woven material with a unit mass of ≥300g / m2; the bidirectional steel-plastic geogrid (1-4) is a mesh structure and can be stretched in the transverse and longitudinal directions simultaneously; the longitudinal and transverse breaking elongation of the steel-plastic geogrid (1-6) and the bidirectional steel-plastic geogrid (1-4) is ≤3%, the longitudinal and transverse tensile strength is ≥100kN / m2, the friction coefficient is ≥0.6, the width is ≥4m, the node peeling force is ≥300N, and the overlap width is greater than 20cm; the pile body granular material of the sunken pipe sand pile (2-1) is made of medium-coarse sand or gravel or stone chips, the maximum particle size is ≤20mm, and the mud content is ≤5%; the prefabricated pipe pile (3-1) is a prestressed concrete pipe pile, the pipe pile of the prefabricated pipe pile (3-1) is made of C70 concrete, and the pile cap of the prefabricated pipe pile (3-1) is made of C30 concrete.

4. The embankment structure of the cross-sea highway according to claim 1 is characterized in that: It also comprises a circular culvert (5) arranged on the foundation treatment structure; the foundation of the circular culvert (5) is arranged above the second gravel cushion layer (1-5), and the pipe sections of the circular culvert (5) are arranged above the foundation of the circular culvert (5).

5. The embankment structure of the cross-sea highway according to claim 4 is characterized in that: Expansion joints are provided between the foundations of the circular culvert (5) and between the pipe sections of the circular culvert (5).

6. A construction method for an embankment structure of a cross-sea highway, characterized in that: The following steps are involved: (1) For sections of silt and silty soil, blasting and squeezing of silt are first required. The specific steps are as follows: first, survey and lay out the lines, and fill the embankment according to the parameters. Next, explosive packs are placed on both sides of the road section for blasting. The detonation will generate huge pressure to form a cavity in the silt, destroying and squeezing out the silt. The riprap body, with its own gravity, slides into the cavity after being vibrated to form a new stone tongue, achieving the purpose of replacing the silt. This cycle promotes the work. (2) For sections of road with deep silt and silty soil, a plastic drainage board treatment structure (1) is used for soft foundation treatment. The specific steps are as follows: first, a layer of non-woven geotextile (1-2) is laid on the ground, and then a first crushed stone cushion layer (1-3) is filled on top of the non-woven geotextile (1-2) and compacted. A positioning unit is assembled on top of the first crushed stone cushion layer (1-3), and the plastic drainage board (1-1) is inserted. When the plastic drainage board (1-1) is inserted to the designed depth, the plastic drainage board (1-1) is cut off and replaced to the next point, and the cycle is repeated until the construction of all points is completed; after the construction is completed, a first crushed stone cushion layer (1-3) is placed on top of the first crushed stone cushion layer (1-3). Laying a bidirectional steel-plastic geogrid (1-4), filling a second crushed stone cushion layer (1-5) on the bidirectional steel-plastic geogrid (1-4) and compacting it, the second crushed stone cushion layer (1-5) should extend a certain length from the slope foot along the transverse direction of the roadbed, and the specific length should meet the design requirements; then, the two ends of the non-woven geotextile (1-2) below the first crushed stone cushion layer (1-3) are turned up to serve as the edge protection of the first crushed stone cushion layer (1-3) and the second crushed stone cushion layer (1-5); finally, adding steel-plastic geogrids (1-6) at a certain interval on the second crushed stone cushion layer (1-5), and the interval distance is determined according to the design requirements; For sections of shallow silt, plain fill and clay soil, a pipe-sinking sand pile treatment structure (2) is used to treat the soft foundation. The specific steps are as follows: first, a layer of non-woven geotextile (1-2) is laid on the ground, and then a first crushed stone cushion layer (1-3) is filled on the non-woven geotextile (1-2) and compacted; then, a pile driver is installed on the first crushed stone cushion layer (1-3), and the pipe-sinking sand pile (2-1) is inserted into the soil to a specified elevation and then sand is poured. The sand is deposited by flushing water and vibrating the pipe mouth, and the pressure is repeatedly raised and lowered to pull the column pipe until the pipe-sinking sand pile (2-1) is lifted to the hole mouth, and then replaced to the next point, and the cycle is repeated until the construction of all points is completed; after the construction is completed, A bidirectional steel-plastic geogrid (1-4) is laid on the first crushed stone cushion layer (1-3), and a second crushed stone cushion layer (1-5) is filled and compacted on the bidirectional steel-plastic geogrid (1-4). The second crushed stone cushion layer (1-5) should extend a certain length from the slope foot in the transverse direction of the roadbed, and the specific length should meet the design requirements; then, both ends of the non-woven geotextile (1-2) below the first crushed stone cushion layer (1-3) are turned up to serve as the edge protection of the first crushed stone cushion layer (1-3) and the second crushed stone cushion layer (1-5); finally, steel-plastic geogrids (1-6) are added on the second crushed stone cushion layer (1-5) at a certain interval, and the interval distance is determined according to the design requirements; For bridgehead sections, high fill sections, and deep soft foundation sections with complex geology, a prefabricated pipe pile treatment structure (3) is used to treat the soft foundation. The specific steps are as follows: first, a layer of non-woven geotextile (1-2) is laid on the ground, and then a first crushed stone cushion layer (1-3) is filled on the non-woven geotextile (1-2) and compacted; then, a pile driver is installed on the first crushed stone cushion layer (1-3), and the prefabricated pipe pile (3-1) is vertically pressed into the soil through a hydraulic system, and the pile position is moved to press the piles in turn; after the construction is completed, the soil of the pile cap needs to be excavated, and the steel bars are tied with concrete. Finally, a bidirectional steel-plastic geogrid (1-4) is laid on the first crushed stone cushion layer (1-3), and a second crushed stone cushion layer (1-5) is filled on the bidirectional steel-plastic geogrid (1-4) and compacted. The second crushed stone cushion layer (1-5) should extend a certain length from the slope foot in the transverse direction of the roadbed, and the specific length should meet the design requirements; both ends of the non-woven geotextile (1-2) below the first crushed stone cushion layer (1-3) are reversed upwards to serve as the edge protection of the first crushed stone cushion layer (1-3) and the second crushed stone cushion layer (1-5); (3) Next, the roadbed is processed, mainly including filling and excavation. The specific steps are as follows: When filling, firstly, the construction is set out, and horizontal segmentation and layering are adopted. After paving with a bulldozer, it is pre-compacted and leveled with a bulldozer or a roller, and finally vibrated and compacted with a roller; when excavating, the rocks with larger diameters are mainly crushed, and hydraulic breakers are used to crush the rock mass; (4) For the coastal road section, a circular culvert (5) needs to be set up on the roadbed; the specific steps are as follows: first, survey and lay out and excavate the foundation pit, then use C20 concrete to construct the culvert bottom foundation, and use a hoist and a forklift to install the pipe section of the circular culvert (5); finally, backfill the foundation pit of the pipe top of the circular culvert (5) and compact it with a compactor; (5) After the roadbed is built, the embankment pavement needs to be constructed. The specific steps are as follows: the pavement from bottom to top is graded crushed stone cushion layer, cement stabilized crushed stone base layer, and concrete pavement; first, the graded crushed stone is mixed, spread on the roadbed with a mixture transport vehicle, and rolled with a roller in a direction parallel to the center of the road; then, the cement stabilized crushed stone is mixed, spread on the roadbed with a mixture transport vehicle, and rolled with a roller in a direction parallel to the center of the road. After the construction is completed, the geotextile is laid and water is sprinkled for maintenance for seven days; finally, the cement soil pavement is poured, and the concrete mixture is transported to the paving site by a concrete transport vehicle for paving, vibration, and surface preparation, then smoothed with a disc trowel, roughened with an embossing machine, sprinkled with water, and covered with old sacks for maintenance for 14 to 21 days.

7. The construction method of the embankment structure of the cross-sea highway according to claim 6 is characterized by: The blasting to squeeze out silt needs to determine the height of the embankment according to the geotechnical calculation principle and the designed height of the embankment; the width of the embankment needs to be determined according to the height of the embankment and the designed section of the embankment; the embankment core stone (4) is the embankment core stone (4), and after the blasting is completed, the bottom elevation of the foundation of the embankment core stone (4) should meet the design requirements.

8. The construction method of the embankment structure of the cross-sea highway according to claim 6 is characterized by: The gaps between the pipe sections of the circular pipe culvert (5) are filled with asphalt hemp wool, and the outside is wrapped with three layers of oil felt coated with hot asphalt for waterproofing.