Early-dismantling-based beam-slab supporting system with multiple beam sections and slab height difference
By adopting a beam-slab support system with multi-beam cross-section and plate height drop in construction, combined with steel pipe fasteners and double joists, the problems of insufficient bearing capacity and cumbersome installation of traditional support poles are solved, and the construction is standardized and safe and high efficiency to achieve plaster-free concrete quality.
Patent Information
- Application Number
- CN202411320844.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-23
- Publication Date
- 2024-12-03
AI Technical Summary
In traditional construction, the bearing capacity of the supporting poles is insufficient, the installation and demolition are cumbersome and difficult to adjust, resulting in high construction difficulty, poor concrete forming quality, and high material usage, which affects construction efficiency and safety.
The beam and plate support system based on early disassembly and the height and drop of the plates is adopted. Combined with the advantages of steel pipe fasteners and double joists, a simple and flexible support structure is formed through the connection of bottom, low and high joists, which meets the needs of the horizontal pull rods. The support needs of different beams and slabs achieve mutual cooperation and overall support.
It improves the standardization and safety of construction, reduces the material usage and installation and removal difficulty, enhances construction efficiency, and achieves plaster-free concrete quality.
Smart Images

Figure CN119062099A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of support systems for transverse slab projects in building construction, and more specifically to a beam-slab support system based on early-dismantling multi-beam sections and slab height differences. Background Art
[0002] Before pouring beams and floors, it is necessary to first build a supporting structure for the beam and slab formwork that bears and supports concrete. The commonly used supporting poles are Ф48 steel pipes, wheel buckles, sleeve buckles, and disc buckles. The supporting structures required for beams of different positions, functions, and sizes and floor formworks of different height differences are also different. Therefore, it is necessary to build a beam and slab support system for the supporting structures of different supporting poles, which can not only ensure that different supporting structures can fulfill their own functions, but also enable different supporting structures to be connected and coordinated with each other. One way to realize the traditional wooden formwork is commonly known as the soft beam bottom. Most of them use Φ48 steel pipes and cross fasteners as the main beam keel. A long steel pipe is used parallel to the bottom of the beam and fixed to the plate support uprights on both sides of the bottom of the beam. Then the wooden secondary keel of the beam bottom is placed on the Φ48 steel pipe main keel on both sides, and then the beam bottom template is placed and fixed on the wooden secondary keel; the other method is commonly known as the hard beam bottom, which is to use a Φ48 steel pipe and cross fastener of about 1.3 meters on the site, and fix the vertical beam bottom to the plate support uprights on both sides of the beam bottom. Then the beam bottom template is connected to the wooden square of about 3 meters long with parallel iron nails, and then placed vertically on the Φ48 round tube main keel. Due to the limited bearing capacity of Φ48 round tubes, and the fact that most of the Φ48 round tubes currently in use have been used for more than 5 years, due to factors such as natural corrosion, the bearing capacity has been greatly reduced. As a result, many local governments now require that the spacing between support poles cannot exceed 900mm, which greatly increases the use of support poles and the labor costs for installation, removal and transportation, and also increases the difficulty of transporting materials for wall column construction. The biggest problem is that it is extremely difficult to fix the Φ48 round tubes at the same level with fasteners. It is common to have a height error of 3 to 5mm between fasteners. In order to ensure the fastener support, when the beam cross-section exceeds 0.1㎡, it is necessary to add anti-slip fasteners under each fixed fastener. As a result, during and after the concrete pouring process, the beam structure cannot be corrected and adjusted, which greatly increases the construction difficulty, and it is difficult for the formed concrete structure to achieve plaster-free quality.
[0003] In the construction of industrial plants, the traditional double-joist beam main keel structure is also used. According to the spacing between the disc buckle posts on both sides of the beam, a 1650mm or 1350mm long lower joist is selected. The lower joist is composed of two upper and lower horizontal pieces with a width of 30mm, a middle vertical piece with a thickness of about 5mm and a height of 80mm. It is connected and fixed with two sets of limit pipes and screw assemblies. Although its vertical bearing capacity is very good, its lateral bearing capacity and torsional force are poor; and because the lower joist is placed on the disc buckle posts supporting the plates on both sides of the beam, the lower joist will extend out of the supporting posts by 50 to 400mm from the disc buckle posts with a spacing of 400 to 900mm from the bottom of the beam, which will affect the main and secondary keels and other materials of the floor formwork when the floor formwork is dismantled. When falling, it is easy for them to collide and damage each other; the upper supporting beam is composed of 2 wooden squares or square tubes, and the two ends of the upper supporting beam are placed on the U-shaped top supports on both sides of the bottom of the beam, and the U-shaped top supports are inserted into the 350mm long disc buckle extension section of the lower supporting beam. The U-shaped top supports are adjusted to meet the beam elevation requirements of the upper supporting beam. If the beam cross-section is more than 0.16㎡, it is necessary to insert another 350mm disc buckle extension on the 350mm disc buckle extension section that is inserted into the lower end beam, and connect the top support extension section with a horizontal tie rod, and then insert the U-shaped top support to support and adjust the upper supporting beam; that is, although the traditional double supporting beam has sufficient supporting force, it uses more materials and has a total weight of 23 to 30kg, and the installation, removal and adjustment are cumbersome, labor-intensive, time-consuming and labor-intensive. Summary of the invention
[0004] In view of the deficiencies in the prior art, the present application provides a beam-slab support system with multiple beam sections and plate height differences based on early dismantling, which integrates the advantages of steel pipe fasteners and double support beams and has been upgraded and innovated. It has a simple structure, which can not only complete the support of all beams and plates during the building construction process, but also can simply cooperate with each other, so that all supporting structures can form a complete support system, and can better meet the non-early dismantling and early dismantling requirements of most formwork systems, which can effectively promote the standardization and safety of construction, and can also effectively improve the efficiency of construction and make it easier to achieve the quality of plastering-free.
[0005] The beam-slab support system based on early-demolition multi-beam cross-section and slab height difference includes any one or more of the following structural systems: edge beam support structure system, middle beam support mode 1 structure system, middle beam support mode 2 structure system, middle beam support mode 3 structure system, bathroom / high-low span intersection beam support structure system, and post-cast strip slab support structure system; different structural systems are connected to each other by a number of bottom-position transverse tie rods, a number of low-position transverse tie rods and a number of high-position transverse tie rods.
[0006] Preferably, the side beam support structure system is composed of a number of side beam support structures which are arranged side by side and connected in sequence by bottom-position transverse tie rods, low-position transverse tie rods and high-position transverse tie rods; the side beam support structure is composed of a vertically arranged side support upright, a U-shaped top support at the upper end of the side support upright, a type of support upright which is a vertically arranged upper-stage threaded rod 600mm away from the side support upright, a plate top head arranged at the upper end of the threaded rod, a disc buckle tray and an inner threaded disc buckle tray arranged on the threaded rod, a U-shaped top support fixed in the middle at the upper end of the side support upright, one end fixed to the disc buckle tray in the middle of the threaded rod, and the other end connected by a screw thread. The oblique support rod is fixed to the beam supporting the main keel on the side support upright, and is composed of a bottom transverse tie rod at both ends respectively arranged on the side support upright and the type-one support upright, and a low transverse tie rod at both ends respectively arranged on the side support upright and the type-one support upright; the two adjacent side beam support structures are connected by a bottom transverse tie rod arranged on the two side support uprights, a low transverse tie rod arranged on the two side support uprights, a bottom transverse tie rod arranged on the two type-one support uprights, a low transverse tie rod arranged on the two type-one support uprights, and a high transverse tie rod arranged on the inner threaded disc buckle of the two threaded rods.
[0007] Preferably, the intermediate beam support mode 1 structural system is composed of a plurality of intermediate beam support mode 1 structures which are arranged side by side and connected in sequence by a bottom transverse tie rod, a low transverse tie rod and a high transverse tie rod; the intermediate beam support mode 1 structure is composed of two type 1 support uprights which are vertically arranged with a spacing of 1200mm and an upper-level threaded rod, a plate top head which is respectively arranged at the upper ends of the two threaded rods, a disc buckle tray and an inner threaded disc buckle tray which are respectively arranged in the middle of the two threaded rods, a type 2 support upright which is arranged at the center position of the two type 1 support uprights and is 600mm away from the two type 1 support uprights, a U-shaped top bracket which is arranged at the upper end of the type 2 support upright, and a U-shaped top bracket which is fixed in the middle at the upper end of the type 2 support upright. The main keel is supported by a beam fixed on a disc tray at both ends in the middle of the two threaded rods, and the two ends are respectively arranged between the two type one support uprights and the type two support uprights, and the two ends are respectively arranged between the two type one support uprights and the type two support uprights. The two adjacent intermediate beam support mode one structures are connected by the bottom transverse tie rods arranged on the two type two support uprights, the low transverse tie rods arranged on the two type two support uprights, the bottom transverse tie rods arranged on the two adjacent type one support uprights, the low transverse tie rods arranged on the two adjacent type one support uprights, and the high transverse tie rods arranged on the inner thread disc of the two adjacent threaded rods.
[0008] Preferably, the intermediate beam support mode two structural system is composed of a number of intermediate beam support mode two structures which are arranged side by side and connected in sequence by bottom transverse tie rods, low transverse tie rods and high transverse tie rods; the intermediate beam support mode two structure is composed of two three-type support uprights which are vertically arranged with a spacing of 1200mm and an upper-level threaded rod, respectively arranged at the top of the plate at the upper end of the two threaded rods, respectively arranged at the disc-buckle trays on the two threaded rods, a beam supporting main keel whose two ends are respectively fixed on the disc-buckle trays of the two threaded rods, respectively arranged at two bottom transverse tie rods on the two three-type support uprights, and respectively arranged at two low transverse tie rods on the two three-type support uprights; two adjacent intermediate beam support mode two structures are connected by a bottom transverse tie rod and a low transverse tie rod arranged on two adjacent three-type support uprights, and a high transverse tie rod arranged on two adjacent three-type support uprights.
[0009] Preferably, the three-structure system of the intermediate beam support mode is composed of a plurality of intermediate beam support mode three structures which are arranged side by side and connected in sequence by a bottom-position transverse tie rod, a low-position transverse tie rod and a high-position transverse tie rod; the three-structure system of the intermediate beam support mode is composed of two type-one support uprights which are vertically arranged with a spacing of 1200mm and an upper-stage threaded rod, respectively arranged at the top of the plate at the upper ends of the two threaded rods, respectively arranged at the disc buckle tray and the inner threaded disc buckle tray in the middle of the two threaded rods, and respectively fixed at both ends of the beam supporting the main keel on the disc buckle tray in the middle of the two threaded rods. The three structures of the middle beam support mode are connected by a bottom horizontal tie rod whose two ends are respectively arranged on the two adjacent type one support uprights, a low horizontal tie rod whose two ends are respectively arranged on the two adjacent type one support uprights, and a high horizontal tie rod which is arranged on the inner threaded disc buckle of two adjacent threaded rods.
[0010] Preferably, the bathroom / high-low span boundary beam support structure system is composed of a plurality of bathroom / high-low span boundary beam support structures arranged side by side and connected in sequence by a bottom horizontal tie rod, a low horizontal tie rod and a high horizontal tie rod; the bathroom / high-low span boundary beam support structure is composed of a three-type support upright pole which is vertically arranged and the upper section is a threaded rod, a four-type support upright pole which is vertically arranged and the spacing between it and the three-type support upright pole is 600mm and the upper section is a threaded rod, a four-type support upright pole which is vertically arranged and the spacing between it and the three-type support upright pole is 1200mm and the upper section is a threaded rod. The spacing between the four-type support uprights is 600mm and the upper section is a threaded rod. The plate top head is respectively set on the three-type support upright and the upper end of the threaded rod of the four-type support upright that is 1200mm away from the three-type support upright. The U-shaped top bracket is set on the upper end of the threaded rod of the four-type support upright that is 1200mm away from the three-type support upright. The disc buckle tray is set on the threaded rod on the three-type support upright, and the inner threaded disc buckle tray is respectively set on the threaded rods on the two four-type support uprights, and one end is fixed to the three-type support. A plate-buckle tray on the support pole, a U-shaped top bracket fixed in the middle section on the four-type support pole, and a beam supporting the main keel located between the two four-type support poles at the other end, a bottom horizontal tie rod set between the three-type support pole and the four-type support pole, a low-position horizontal tie rod set between the three-type support pole and the four-type support pole, a bottom horizontal tie rod set between two four-type support poles, a low-position horizontal tie rod set between the two four-type support poles, and an inner thread plate of a threaded rod set on two four-type support poles. The two adjacent toilet / high-low span boundary beam support structures are connected by a bottom horizontal tie rod arranged on two three-type support uprights, a low horizontal tie rod arranged on two three-type support uprights, a high horizontal tie rod arranged on two three-type support uprights, a bottom horizontal tie rod arranged on two adjacent four-type support uprights, a low horizontal tie rod arranged on two adjacent four-type support uprights, and a high horizontal tie rod arranged on the inner threaded disc buckle of the threaded rod on two adjacent four-type support uprights.
[0011] Preferably, the post-cast strip slab support structure system is composed of a number of post-cast strip slab support structures which are arranged side by side and connected in sequence by bottom-position transverse tie rods, low-position transverse tie rods and high-position transverse tie rods; the post-cast strip slab support structure is composed of three-type support uprights which are vertically arranged and have upper-stage threaded rods, and side beam top supports which are arranged at the upper ends of the threaded rods; two adjacent post-cast strip slab support structures are connected by bottom-position transverse tie rods arranged on the two three-type support uprights, low-position transverse tie rods arranged on the two three-type support uprights, and high-position transverse tie rods arranged on the two three-type support uprights.
[0012] In addition, all the bottom tie rods are arranged on the same horizontal plane; all the low-position tie rods are arranged on the same horizontal plane; and all the high-position tie rods are arranged on the same horizontal plane.
[0013] Compared with the prior art, the embodiments of the present application have the following beneficial effects:
[0014] The present invention integrates the advantages of steel pipe fasteners and double joists and has been upgraded and innovated. It has a simple structure and can not only complete the support of all beams and plates during the construction process of the building, but also can simply cooperate with each other, so that all supporting structures can form a complete supporting system, and can better meet the non-early removal and early removal requirements of most formwork systems, effectively promoting the standardization and safety of construction, and can also effectively improve the efficiency of construction and make it easier to achieve the quality of plastering-free. .
[0015] Some additional features of the present application may be explained in the following description. Some additional features of the present application will be apparent to those skilled in the art by inspection of the following description and corresponding drawings or understanding of the production or operation of the embodiments. The features disclosed in the present application may be realized and achieved by practice or use of various methods, means and combinations of the specific embodiments described below. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The exemplary embodiments of the present application and their descriptions are used to explain the present application and do not constitute a limitation of the present application. In each figure, the same reference numeral represents the same component.
[0017] Figure 1 It is a schematic diagram of the overall framework structure of the present invention.
[0018] Figure 2 It is a structural schematic diagram of the side beam support structure of the present invention.
[0019] Figure 3 It is a structural schematic diagram of the first mode of the intermediate beam support structure of the present invention.
[0020] Figure 4 It is a structural schematic diagram of the second mode of the intermediate beam support structure of the present invention.
[0021] Figure 5 It is a structural schematic diagram of the third mode of the intermediate beam support structure of the present invention.
[0022] Figure 6 It is a structural schematic diagram of the bathroom / high-low span boundary beam support structure of the present invention.
[0023] Figure 7 It is a structural schematic diagram of the post-cast strip slab support structure of the present invention.
[0024] Explanation of the reference numerals in the accompanying drawings: 1. Side beam support structure; 2. Middle beam support mode 1 structure; 3. Middle beam support mode 2 structure; 4. Middle beam support mode 3 structure; 5. Bathroom / high-low span boundary beam support structure; 6. Post-cast strip slab support structure; 7. Bottom horizontal tie rod; 8. Low horizontal tie rod; 9. High horizontal tie rod; 10. Beam support main keel; 11. Oblique support rod; 12. Beam auxiliary support structure; 13. Side support vertical rod; 14. Type 1 support vertical rod; 15. Type 2 support vertical rod; 16. Type 3 support vertical rod; 17. Type 4 support vertical rod; 18. Plate top head; 19. Side beam top support; 20. Disc tray; 21. Inner thread disc tray; 22. U-shaped top support. DETAILED DESCRIPTION
[0025] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.
[0026] It should be noted that if the description and claims of the present application and the above-mentioned drawings relate to the terms "first", "second", etc., they are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present application described here. In addition, if the terms "including" and "having" and any of their variations are involved, it is intended to cover non-exclusive inclusions, for example, the process, method, system, product or equipment that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or equipment.
[0027] In this application, if the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", "inside", "outside", "middle", "vertical", "horizontal", "lateral", "longitudinal", etc. are involved, the orientation or position relationship indicated is based on the orientation or position relationship shown in the drawings. These terms are mainly used to better describe the present application and its embodiments, and are not used to limit the indicated devices, elements or components to have a specific orientation, or to be constructed and operated in a specific orientation.
[0028] In addition, some of the above terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those of ordinary skill in the art, the specific meanings of these terms in this application can be understood according to specific circumstances.
[0029] In addition, in this application, the terms "installed", "set", "provided with", "connected", "connected", "socketed" and the like should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be an internal connection between two devices, elements or components. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to the specific circumstances.
[0030] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0031] Example
[0032] like Figure 1 As shown, the beam-slab support system based on early-demolition multi-beam cross-section and slab height difference includes any one or more of the following structural systems: edge beam support structure system, middle beam support mode one structure system, middle beam support mode two structure system, middle beam support mode three structure system, bathroom / high-low span intersection beam support structure system, and post-cast strip slab support structure system; different structural systems are interconnected by a number of bottom-position transverse tie rods 7, a number of low-position transverse tie rods 8, and a number of high-position transverse tie rods 9.
[0033] like Figure 2As shown, the side beam support structure system is composed of a plurality of side beam support structures 1 arranged side by side and connected in sequence by a bottom transverse tie rod 7, a low transverse tie rod 8 and a high transverse tie rod 9; the side beam support structure 1 is composed of a vertically arranged side support upright 13, a U-shaped top bracket 22 at the upper end of the side support upright 13, a type of support upright 14 of an upper segment threaded rod vertically arranged and 600 mm away from the side support upright, a plate top head 18 arranged at the upper end of the threaded rod, a disc buckle tray 20 and an inner threaded disc buckle tray 21 arranged on the threaded rod, a U-shaped top bracket 22 fixed in the middle at the upper end of the side support upright 13, one end fixed to the disc buckle tray 20 in the middle of the threaded rod, and the other end connected by an oblique support rod 1. The beam supporting main keel 10 fixed on the side support upright 13 is composed of a bottom horizontal tie rod 7 with two ends respectively arranged on the side support upright 13 and the first-type support upright 14, and a low horizontal tie rod 8 with two ends respectively arranged on the side support upright 13 and the first-type support upright 14; two adjacent side beam supporting structures 1 are connected by the bottom horizontal tie rod 7 arranged on the two side support uprights 13, the low horizontal tie rod 8 arranged on the two side support uprights 13, the bottom horizontal tie rod 7 arranged on the two first-type support uprights 14, the low horizontal tie rod 8 arranged on the two first-type support uprights 14, and the high horizontal tie rod 9 arranged on the inner threaded disc buckle disc 21 of the two threaded rods.
[0034] The side beam supported by the side beam support structure system has a beam width of 100-400mm, a beam height of 500-1200mm, and a beam cross-section of less than 0.48m 2 .
[0035] like Figure 3As shown, the intermediate beam support mode one structural system is composed of a plurality of intermediate beam support mode one structures 2 which are arranged side by side and connected in sequence by a bottom transverse tie rod 7, a low transverse tie rod 8 and a high transverse tie rod 9; the intermediate beam support mode one structure 2 is composed of two type one support uprights 14 which are vertically arranged with a spacing of 1200mm and upper segment threaded rods, plate tops 18 respectively arranged at the upper ends of the two threaded rods, disc buckle trays 20 and inner threaded disc buckle trays 21 respectively arranged in the middle of the two threaded rods, type two support uprights 15 which are arranged at the center position of the two type one support uprights 14 and are 14600mm away from the two type one support uprights, a U-shaped top support 22 arranged at the upper end of the type two support uprights 15, and a middle part fixed on the U-shaped top support 22 at the upper end of the type two support uprights 15. , a beam supporting main keel 10 whose two ends are respectively fixed on a disc tray 20 in the middle of two threaded rods, a bottom transverse tie rod 7 whose two ends are respectively arranged between two type-1 support uprights 14 and type-2 support uprights 15, and a low transverse tie rod 8 whose two ends are respectively arranged between two type-1 support uprights 14 and type-2 support uprights 15; the two adjacent intermediate beam supporting mode one structures 2 are connected by a bottom transverse tie rod 7 arranged on two type-2 support uprights 15, a low transverse tie rod 8 arranged on two type-2 support uprights 15, a bottom transverse tie rod 7 arranged on two adjacent type-1 support uprights 14, a low transverse tie rod 8 arranged on two adjacent type-1 support uprights 14, and a high transverse tie rod 9 arranged on the inner thread disc 21 of two adjacent threaded rods.
[0036] The middle beam supported by the structural system has a beam width of 200-600mm, a beam height of 800-1200mm, and a beam cross-section greater than or equal to 0.24m 2 .
[0037] like Figure 4 As shown, the intermediate beam support mode II structural system is composed of a number of intermediate beam support mode II structures 3 which are arranged side by side and connected in sequence by bottom transverse tie rods 7, low transverse tie rods 8 and high transverse tie rods 9; the intermediate beam support mode II structure 3 is composed of two three-type support uprights 16 which are vertically arranged with a spacing of 1200mm and upper-level threaded rods, plate tops 18 respectively arranged at the upper ends of the two threaded rods, disc-shaped disc trays 20 respectively arranged on the two threaded rods, a beam support main keel 10 whose two ends are respectively fixed on the disc-shaped disc trays 20 of the two threaded rods, bottom transverse tie rods 7 respectively arranged at two ends on the two three-type support uprights 16, and low transverse tie rods 8 respectively arranged at two ends on the two three-type support uprights 16; two adjacent intermediate beam support mode II structures 3 are connected by bottom transverse tie rods 7 and low transverse tie rods 8 arranged on two adjacent three-type support uprights 16, and high transverse tie rods 9 arranged on two adjacent three-type support uprights 16.
[0038] The middle beam supported by the second structural system has a beam width of 100-400mm, a beam height of less than 500mm, and a beam cross-section of less than 0.18m 2 .
[0039] like Figure 5 As shown, the intermediate beam support mode three-structure system is composed of a plurality of intermediate beam support mode three-structures 4 which are arranged side by side and connected in sequence by a bottom horizontal tie rod 7, a low horizontal tie rod 8 and a high horizontal tie rod 9; the intermediate beam support mode three-structure 4 is composed of two one-type support uprights 14 of upper segment threaded rods which are arranged vertically and spaced at a distance of 1200mm, respectively arranged at the top heads 18 of the two threaded rods, respectively arranged at the upper ends of the two threaded rods, respectively arranged at the middle parts of the two threaded rods, respectively arranged at the disc buckle tray 20 and the inner threaded disc buckle tray 21, respectively fixed at both ends of the beam supporting main keel 10 on the disc buckle tray 20 in the middle parts of the two threaded rods, and respectively fixed at both ends on the two one-type support uprights 14 of the upper segment threaded rods. The three structures of the middle beam support mode 4 are connected by a bottom transverse tie rod 7 whose two ends are respectively arranged on two adjacent type one support uprights 14, a low transverse tie rod 8 whose two ends are respectively arranged on two adjacent type one support uprights 14, and a high transverse tie rod 9 which is arranged on the inner threaded disc 21 of two adjacent threaded rods.
[0040] The width of the middle beam supported by the three structural systems is 200-600mm, the height is 500-800mm, and the cross section is greater than or equal to 0.18m 2 Less than 0.24m 2 .
[0041] like Figure 6As shown, the bathroom / high-low span boundary beam support structure system is composed of a plurality of bathroom / high-low span boundary beam support structures 5 arranged side by side and connected in sequence by a bottom horizontal tie rod 7, a low horizontal tie rod 8 and a high horizontal tie rod 9; the bathroom / high-low span boundary beam support structure 5 is composed of a three-type support upright 16 which is vertically arranged and the upper section is a threaded rod, a four-type support upright 17 which is vertically arranged and the spacing between it and the three-type support upright 16 is 600mm and the upper section is a threaded rod, and a four-type support upright 17 which is vertically arranged and the spacing between it and the three-type support upright 16 is 1200mm and the spacing between it and the upper four-type support upright 17 is 1200mm. Another four-type support upright 17 with a length of 600mm and an upper section being a threaded rod, a plate top head 18 respectively arranged on the three-type support upright 16 and the upper end of the threaded rod of the four-type support upright 17 with a distance of 1200mm from the three-type support upright 16, a U-shaped top support 22 arranged on the upper end of the threaded rod of the four-type support upright 17 with a distance of 1200mm from the three-type support upright 16, a disc buckle tray 20 arranged on the threaded rod on the three-type support upright 16, inner threaded disc buckle trays 21 respectively arranged on the threaded rods on the two four-type support uprights 17, and a disc buckle tray fixed at one end on the three-type support upright 16 The upper and middle sections of the tray 20 are fixed on the U-shaped top bracket 22 on the four-type support uprights 17, and the other end of the beam supporting the main keel 10 is located between the two four-type support uprights 17, the bottom horizontal tie rod 7 is set between the three-type support uprights 16 and the four-type support uprights 17, the bottom horizontal tie rod 7 is set between the three-type support uprights 16 and the four-type support uprights 17, the low horizontal tie rod 8 is set between the two four-type support uprights 17, the low horizontal tie rod 8 of the bottom horizontal tie rod 7 is set between the two four-type support uprights 17, and the inner threaded buckle of the threaded rod set on the two four-type support uprights 17 The two adjacent toilet / high-low span boundary beam support structures 5 are connected by a bottom horizontal tie rod 7 arranged on two three-type support uprights 16, a low horizontal tie rod 8 arranged on two three-type support uprights 16, a high horizontal tie rod 9 arranged on two three-type support uprights 16, a bottom horizontal tie rod 7 arranged on two adjacent four-type support uprights 17, a low horizontal tie rod 8 arranged on two adjacent four-type support uprights 17, and a high horizontal tie rod 9 arranged on the inner threaded disc buckle disc 21 of the threaded rod on two adjacent four-type support uprights 17.
[0042] The supported bathroom / high-low span boundary beam has a beam width of 100-400mm, a beam height of 100-1200mm, and a beam cross-section of less than 0.48m 2 .
[0043] like Figure 7As shown, the post-cast strip slab support structure system is composed of a plurality of post-cast strip slab support structures 6 which are arranged side by side and connected in sequence by bottom-position transverse tie rods 7, low-position transverse tie rods 8 and high-position transverse tie rods 9; the post-cast strip slab support structure 6 is composed of three-type support uprights 16 which are vertically arranged and upper-stage threaded rods, and side beam top supports 19 arranged at the upper ends of the threaded rods; two adjacent post-cast strip slab support structures 6 are connected by bottom-position transverse tie rods 7 arranged on two three-type support uprights 16, low-position transverse tie rods 8 arranged on two three-type support uprights 16, and high-position transverse tie rods 9 arranged on two three-type support uprights 16.
[0044] The function of the post-cast strip slab support structure system is to support the floor formwork below the post-cast strip. When setting it up, it can be connected to any adjacent structure system through low-position cross-bars and high-position cross-bars. Among them, the side beam top support is an existing technology, and its top is against the bottom of the floor formwork to complete the support of the floor formwork.
[0045] All the bottom tie rods 7 are arranged on the same horizontal plane; all the low-position tie rods 8 are arranged on the same horizontal plane; all the high-position tie rods 9 are arranged on the same horizontal plane.
[0046] Controlling the setting height of the low-position transverse tie rod and the high-position transverse tie rod can effectively ensure the overall firmness and passability of the overall supporting upright frame after construction, avoid the unbalanced force on the supporting upright frame caused by inconsistent height settings of the low-position transverse tie rod and the high-position transverse tie rod, and also effectively avoid the increased difficulty of construction workers' activities caused by inconsistent height settings of the transverse tie rod and the high-position transverse tie rod, thereby better protecting the construction safety of construction workers.
[0047] During the specific construction, the corresponding structural system is selected from the above-mentioned structural systems according to the actual size of the beams to be cast, and the different structural systems can be connected without obstacles.
[0048] It should be noted that all features disclosed in this specification, or steps in all methods or processes disclosed, except for mutually exclusive features and / or steps, can be combined in any manner.
[0049] In addition, the above specific embodiments are exemplary, and those skilled in the art can come up with various solutions inspired by the disclosure of the present invention, and these solutions also belong to the disclosure scope of the present invention and fall within the protection scope of the present invention. Those skilled in the art should understand that the present invention description and its drawings are illustrative and do not constitute a limitation of the claims. The protection scope of the present invention is defined by the claims and their equivalents.
Claims
1. A beam-slab support system based on early-dismantling multi-beam sections and slab height differences, characterized in that: It comprises any one or more structural systems selected from the group consisting of a side beam support structural system, a middle beam support mode 1 structural system, a middle beam support mode 2 structural system, a middle beam support mode 3 structural system, a bathroom / high-low span boundary beam support structural system, and a post-cast strip slab support structural system; the different structural systems are interconnected via a plurality of bottom-position transverse tie rods (7), a plurality of low-position transverse tie rods (8), and a plurality of high-position transverse tie rods (9).
2. The beam-slab support system based on early dismantling of multiple beam sections and slab height difference according to claim 1 is characterized in that: The side beam support structure system is composed of a plurality of side beam support structures (1) arranged side by side and connected in sequence by a bottom transverse tie rod (7), a low transverse tie rod (8) and a high transverse tie rod (9); the side beam support structure (1) is composed of a vertically arranged side support upright (13), a U-shaped top bracket (22) at the upper end of the side support upright (13), a type of support upright (14) of an upper threaded rod arranged vertically and 600 mm away from the side support upright (13), a plate top head (18) arranged at the upper end of the threaded rod, a buckle tray (20) and an inner threaded buckle tray (21) arranged on the threaded rod, a middle part fixed to the U-shaped top bracket (22) at the upper end of the side support upright (13), one end fixed to the buckle tray (20) at the middle of the threaded rod, and the other end fixed by an oblique support rod (11). The beam supporting main keel (10) fixed on the side support upright (13) is composed of a bottom transverse tie rod (7) whose two ends are respectively arranged on the side support upright (13) and the first-type support upright (14), and a low transverse tie rod (8) whose two ends are respectively arranged on the side support upright (13) and the first-type support upright (14); two adjacent side beam supporting structures (1) are connected by a bottom transverse tie rod (7) arranged on the two side support uprights (13), a low transverse tie rod (8) arranged on the two side support uprights (13), a bottom transverse tie rod (7) arranged on the two first-type support uprights (14), a low transverse tie rod (8) arranged on the two first-type support uprights (14), and a high transverse tie rod (9) arranged on the inner threaded disc buckle disc (21) of two threaded rods.
3. The beam-slab support system based on early dismantling of multiple beam sections and slab height difference according to claim 1 is characterized in that: The intermediate beam support mode one structural system is composed of a plurality of intermediate beam support mode one structures (2) arranged side by side and connected in sequence by a bottom transverse tie rod (7), a low transverse tie rod (8) and a high transverse tie rod (9); the intermediate beam support mode one structure (2) is composed of two type one support uprights (14) arranged vertically and spaced 1200 mm apart and upper segment threaded rods, plate tops (18) respectively arranged at the upper ends of the two threaded rods, buckle trays (20) and inner thread buckle trays (21) respectively arranged in the middle of the two threaded rods, type two support uprights (15) arranged at the center of the two type one support uprights (14) and 600 mm away from the two type one support uprights (14), a U-shaped top bracket (22) arranged at the upper end of the type two support uprights (15), a middle portion fixed to the U-shaped top bracket (22) at the upper end of the type two support uprights (15), and two ends respectively fixed to the U-shaped top bracket (22) at the upper end of the type two support uprights (15). The beam supporting main keel (10) is fixed on the disc tray (20) in the middle of the two threaded rods, and is composed of a bottom horizontal tie rod (7) whose two ends are respectively arranged between the two type one support uprights (14) and the type two support uprights (15), and a low horizontal tie rod (8) whose two ends are respectively arranged between the two type one support uprights (14) and the type two support uprights (15); two adjacent intermediate beam supporting mode one structures (2) are connected by a bottom horizontal tie rod (7) arranged on the two type two support uprights (15), a low horizontal tie rod (8) arranged on the two type two support uprights (15), a bottom horizontal tie rod (7) arranged on two adjacent type one support uprights (14), a low horizontal tie rod (8) arranged on two adjacent type one support uprights (14), and a high horizontal tie rod (9) arranged on the inner threaded disc tray (21) of two adjacent threaded rods.
4. The beam-slab support system based on early dismantling of multiple beam sections and slab height difference according to claim 1 is characterized in that: The intermediate beam support mode II structural system is composed of a plurality of intermediate beam support mode II structures (3) arranged side by side and connected in sequence by a bottom transverse tie rod (7), a low transverse tie rod (8) and a high transverse tie rod (9); the intermediate beam support mode II structure (3) is composed of two three-type support uprights (16) arranged vertically and spaced 1200 mm apart and upper threaded rods, plate tops (18) respectively arranged at the upper ends of the two threaded rods, and disc trays (20) respectively arranged on the two threaded rods, and the two ends are respectively fixed to the two threaded rods. The beam supporting main keel (10) on the disc-locking tray (20) is composed of a bottom transverse tie rod (7) with two ends respectively arranged on two three-type support uprights (16), and a low transverse tie rod (8) with two ends respectively arranged on two three-type support uprights (16); two adjacent intermediate beam support mode two structures (3) are connected by a bottom transverse tie rod (7) and a low transverse tie rod (8) arranged on two adjacent three-type support uprights (16), and a high transverse tie rod (9) arranged on two adjacent three-type support uprights (16).
5. The beam-slab support system based on early dismantling of multiple beam sections and slab height difference according to claim 1 is characterized in that: The intermediate beam support mode three-structure system is composed of a plurality of intermediate beam support mode three-structures (4) arranged side by side and connected in sequence by a bottom transverse tie rod (7), a low transverse tie rod (8) and a high transverse tie rod (9); the intermediate beam support mode three-structure (4) is composed of two type I support uprights (14) arranged vertically and spaced 1200 mm apart and upper segment threaded rods, plate tops (18) respectively arranged at the upper ends of the two threaded rods, buckle trays (20) and inner threaded buckle trays (21) respectively arranged in the middle of the two threaded rods, beam support main keels (10) respectively fixed at both ends on the buckle trays (20) in the middle of the two threaded rods, and beam support main keels (10) respectively fixed at both ends on the two type I support uprights. The invention relates to a beam supporting main keel (10) on a plurality of intermediate beam supporting modes (14), a beam auxiliary supporting structure (12) located between the two beam supporting main keels (10) and having two ends respectively fixed to the middle of the two beam supporting main keels (10), and a bottom transverse tie rod (7) having two ends respectively arranged on two type I supporting uprights (14); two adjacent intermediate beam supporting mode three structures (4) are connected by a bottom transverse tie rod (7) having two ends respectively arranged on two adjacent type I supporting uprights (14), a low transverse tie rod (8) having two ends respectively arranged on two adjacent type I supporting uprights (14), and a high transverse tie rod (9) arranged on the inner threaded buckle plate (21) of two adjacent threaded rods.
6. The beam-slab support system based on early dismantling of multiple beam sections and slab height difference according to claim 1 is characterized in that: The toilet / high-low span boundary beam support structure system is composed of a plurality of toilet / high-low span boundary beam support structures (5) arranged side by side and connected in sequence by a bottom horizontal tie rod (7), a low horizontal tie rod (8) and a high horizontal tie rod (9); the toilet / high-low span boundary beam support structure (5) is composed of a three-type support upright pole (16) arranged vertically and having an upper section as a threaded rod, a four-type support upright pole (17) arranged vertically and having a spacing of 600 mm between the three-type support upright pole (16) and having an upper section as a threaded rod, a three-type support upright pole (17) arranged vertically and having a spacing of 1200 mm between the three-type support upright pole (16) and having a spacing of 600 mm between the previous four-type support upright pole (17) and having an upper section as a threaded rod. Another four-type support vertical rod (17) of the threaded rod, a plate top head (18) respectively arranged on the three-type support vertical rod (16) and the upper end of the threaded rod of the four-type support vertical rod (17) with a distance of 1200mm from the three-type support vertical rod (16), a U-shaped top support (22) arranged on the upper end of the threaded rod of the four-type support vertical rod (17) with a distance of 1200mm from the three-type support vertical rod (16), a disc buckle tray (20) arranged on the threaded rod on the three-type support vertical rod (16), inner threaded disc buckle trays (21) respectively arranged on the threaded rods on the two four-type support vertical rods (17), one end fixed on the disc buckle tray (20) on the three-type support vertical rod (16), and the middle section fixed A beam supporting main keel (10) is provided on a U-shaped top support (22) on a four-type support upright (17), the other end of which is located between two four-type support uprights (17); a bottom horizontal tie rod (7) is provided between a three-type support upright (16) and a four-type support upright (17); a low horizontal tie rod (8) of the bottom horizontal tie rod (7) is provided between the three-type support upright (16) and the four-type support upright (17); a bottom horizontal tie rod (7) is provided between two four-type support uprights (17); a low horizontal tie rod (8) of the bottom horizontal tie rod (7) is provided between two four-type support uprights (17); and an inner threaded disc buckle disc (21) of a threaded rod provided on two four-type support uprights (17). ) between the two adjacent toilet / high-low span boundary beam support structures (5); the two adjacent toilet / high-low span boundary beam support structures (5) are connected by a bottom cross-tie rod (7) arranged on two three-type support uprights (16), a low cross-tie rod (8) arranged on two three-type support uprights (16), a high cross-tie rod (9) arranged on two three-type support uprights (16), a bottom cross-tie rod (7) arranged on two adjacent four-type support uprights (17), a low cross-tie rod (8) arranged on two adjacent four-type support uprights (17), and a high cross-tie rod (9) arranged on the inner threaded disc buckle disc (21) of the threaded rod on the two adjacent four-type support uprights (17).
7. The beam-slab support system based on early dismantling of multiple beam sections and slab height difference according to claim 1 is characterized in that: The post-cast strip slab support structure system is composed of a plurality of post-cast strip slab support structures (6) arranged side by side and connected in sequence by a bottom cross tie rod (7), a low cross tie rod (8) and a high cross tie rod (9); the post-cast strip slab support structure (6) is composed of a three-type support upright (16) of a vertically arranged upper-stage threaded rod, and a side beam top support (19) arranged at the upper end of the threaded rod; two adjacent post-cast strip slab support structures (6) are connected by a bottom cross tie rod (7) arranged on two three-type support uprights (16), a low cross tie rod (8) arranged on two three-type support uprights (16), and a high cross tie rod (9) arranged on two three-type support uprights (16).
8. The beam-slab support system based on early dismantling of multiple beam sections and slab height difference according to claim 6 is characterized in that: All the bottom tie rods (7) are arranged on the same horizontal plane; all the low-position tie rods (8) are arranged on the same horizontal plane; and all the high-position tie rods (9) are arranged on the same horizontal plane.