Reinforcing structure for power transmission tower and reinforcing method of reinforcing structure

The reinforcement structure for transmission towers addresses flexibility issues by using a cement seat with corner and tensioning components, enabling adjustable telescopic rods and V-shaped plates, enhancing adjustability and stability.

CN119062147APending Publication Date: 2024-12-03ECONOMIC RES INST OF STATE GRID GANSU ELECTRIC POWER
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411464689.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-21
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

Existing reinforcement structures for transmission towers lack flexibility, making it inconvenient to adjust the towers after installation, thereby affecting their practicality and convenience.

Method used

A reinforcement structure comprising a cement seat with corner reinforcement components, tensioning components, inner support components, and adjustable telescopic rods, along with V-shaped reinforcement plates, allowing for flexible adjustment and support.

Benefits of technology

Enhances the flexibility and adjustability of transmission towers, improving their bearing capacity, ensuring power supply safety, and reducing the risk of damage from natural environments, while reducing project costs and enhancing reliability and stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119062147A_ABST
    Figure CN119062147A_ABST
Patent Text Reader

Abstract

The invention discloses a reinforcing structure for a power transmission tower and a reinforcing method of the reinforcing structure, and relates to the technical field of reinforcing structures of the power transmission tower. The reinforcing structure comprises a cement base, corner reinforcing assemblies are arranged on the periphery of the upper surface of the cement base, and the power transmission tower is installed on the corner reinforcing assemblies; tensioning assemblies are arranged on the two sides of the upper surface of the cement base correspondingly, an inner supporting assembly is arranged on the upper surface of the cement base, pouring bases are arranged on the two sides of the lower surface of the cement base correspondingly, the number of the pouring bases is four, reinforcing plates are arranged on the two sides of each pouring base correspondingly, and the reinforcing plates are in a V shape. According to the scheme, the problems that in the prior art, a reinforcing structure of a power transmission tower is poor in flexibility in use, so that the power transmission tower is inconvenient to adjust after being installed, and the practicability and convenience of the power transmission tower are affected are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of reinforcement structures of power transmission towers, and in particular to a reinforcement structure for power transmission towers and a reinforcement method thereof. Background Art

[0002] The transmission tower is the supporting point of the overhead line. If one circuit is erected on the transmission tower, it is a single-circuit transmission tower. If two circuits are erected on the transmission tower, it is a double-circuit transmission tower. A single circuit refers to a circuit with one power supply for one load; a double circuit refers to a circuit with two power supplies for one load. It needs to be reinforced during installation to ensure its stability.

[0003] For example, the Chinese authorized patent with announcement number CN206346216U (a reinforcement structure for the foundation of a power transmission line tower): comprises a ring beam cast at the lower end of the power transmission line tower, the ring beam is fixed to the ground, a concrete foundation is arranged at the upper end of the ring beam, the concrete foundation is cast on the foundation legs of the power transmission line tower, a plurality of sleeves are fixedly arranged in the vertical direction on the concrete foundation, a steel column is arranged in the vertical direction in each sleeve, the steel column is rotatably connected to the sleeve, the steel column is supported on the ring beam, the steel column drives the sleeve, the concrete foundation and the foundation legs to rise and fall vertically by rotation, the concrete foundation is a cross beam cast on the four foundation legs of the power transmission line tower, and the four cross intersections of the cross beam are respectively located at the four foundation legs. A ring beam is cast at the lower end of the transmission line tower, the ring beam is fixed to the ground, a concrete foundation is arranged on the upper end of the ring beam, and the concrete foundation is cast on the foundation legs of the transmission line tower, so that the four foundation legs at the lower end of the transmission line tower become a whole on a reinforced foundation, and the bottom of the transmission line tower is reinforced as a whole. A sleeve is fixed on the concrete foundation, a steel column is arranged in the sleeve, the steel column is rotatably connected to the sleeve, and the steel column is supported on the ring beam. When the transmission line tower tilts, the sleeve and the concrete foundation are driven to lift the foundation legs of the tilted transmission line tower by rotating the steel column at the corresponding position, so that the four foundation legs are on the same horizontal plane, thereby realizing the correction of the transmission line tower.

[0004] However, the reinforcement structure of the transmission tower in the above-mentioned prior art has poor flexibility when in use, so it is inconvenient to adjust the transmission tower after installation, which affects its practicality and convenience; therefore, it does not meet the existing needs. In this regard, we propose a reinforcement structure for a transmission tower and a reinforcement method thereof. Summary of the invention

[0005] The object of the present invention is to provide a reinforcement structure for a transmission tower and a reinforcement method thereof, so as to solve the problem that the reinforcement structure of the transmission tower in the prior art proposed in the above background technology has poor flexibility when in use, making it inconvenient to adjust the transmission tower after installation, thus affecting its practicability and convenience.

[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a reinforcement structure for a transmission tower, comprising a cement seat, corner reinforcement components are arranged around the upper surface of the cement seat, a transmission tower is installed on the corner reinforcement components, tensioning components are arranged on both sides of the upper surface of the cement seat, an inner support component is arranged on the upper surface of the cement seat, casting seats are arranged on both sides of the lower surface of the cement seat, four casting seats are arranged, and reinforcement plates are arranged on both sides of the casting seat, and the reinforcement plates are V-shaped.

[0007] Preferably, a first support seat is provided at the bottom of the edge and corner reinforcement assembly, a support column is provided on the upper surface of the first support seat, a support plate is provided on the top of the support column, fixing bolts are installed around the upper surface of the support plate, and a fixing nut is provided at the bottom of the fixing bolt.

[0008] Preferably, a limiting plate is provided on the upper surface of the support plate, a spacer plate is provided on one side of the limiting plate, limiting grooves are provided on both sides of the spacer plate, and fixing holes are provided on both the support plate and the spacer plate.

[0009] Preferably, a second support seat is provided at the bottom of the tensioning assembly, a cable box is provided on the upper surface of the second support seat, and cables are provided inside the cable box.

[0010] Preferably, a motor is installed on the front end surface of the cable box, and a rope pulling tube is provided on the upper surface of the cable box.

[0011] Preferably, a third support seat is provided at the bottom of the inner support assembly, a drive seat is installed on the upper surface of the third support seat, a support rod is installed above the drive seat, a telescopic rod is installed inside the support rod, and the telescopic rod is plug-connected with the inside of the support rod.

[0012] Preferably, a support assembly is installed on the support rod, connecting sleeves are provided on both sides of the support assembly, the connecting sleeves are arc-shaped, and fixing plates are provided on the front and rear end surfaces of the connecting sleeves, and connecting screws are installed on the fixing plates.

[0013] Preferably, a mounting plate is provided on one end face of the connecting sleeve, mounting grooves are provided on one side of the front and rear end faces of the mounting plate, a connecting rod is installed in the mounting groove, and a connecting plate is provided on one side of the connecting rod.

[0014] Preferably, the reinforcement method for a reinforcement structure of a transmission tower comprises the following steps:

[0015] Step 1: First, place the four corners of the transmission tower in the limiting grooves of the corner reinforcement components, and then use screws to pass through the fixing holes to reinforce and fix them;

[0016] Step 2: After the corners are fixed, pull out the top rope tube of the tensioning assembly, and then connect and fix it to the poles on the outside of the two ends of the transmission tower;

[0017] Step 3: After the drive seat drives the telescopic rod to extend to the fixed position, the support assembly is fixed on the telescopic rod and the support rod through the connecting sleeve and the fixing plate:

[0018] Step 4: Finally, fix the connecting rod to the mounting groove of the mounting plate with screws, and then make the connecting plate contact and lock with the inner rod of the transmission tower.

[0019] Compared with the prior art, the present invention has the following beneficial effects:

[0020] 1. The present invention provides a corner fixing assembly, a tensioning assembly and a supporting assembly. First, the four corners of the transmission tower are placed inside the limiting grooves of the corner reinforcement assembly, and then screws are used to pass through the fixing holes for reinforcement and fixing. After the corners are fixed, the pull rope tube at the top of the tensioning assembly is pulled out, and then it is connected and fixed to the poles on the outside of the two ends of the transmission tower. After the driving seat drives the telescopic rod to extend to a fixed position, the supporting assembly is installed and fixed on the telescopic rod and the supporting rod through a connecting sleeve and a fixing plate. Finally, the connecting rod is fixed to the mounting groove of the mounting plate by screws, and then the connecting plate is contacted and locked with the inner rod of the transmission tower. The telescopic extension between the telescopic rod and the supporting rod can be adjusted according to the height that the tower body needs to support. At the same time, the connecting rod installed on one side of the mounting plate can be installed in different sizes according to the spacing, which is convenient for adjustment. This solves the problem that the reinforcement structure of the transmission iron tower in the prior art is poor in flexibility when in use, so that it is inconvenient to adjust the transmission tower after installation, thereby affecting its practicality and convenience.

[0021] 2. By setting the cable inside the cable box of the tensioning assembly, using the rope tube to pull one end of the cable to the required fixed height, and after connecting and fixing it with the rod body on the outer end face of the tower body, the motor is used to drive the cable to rotate inward, thereby tightening the cable, thereby pulling and fixing the outer end faces on both sides of the tower body, and the tensioning assembly and the inner support assembly play the role of simultaneous internal and external support.

[0022] 3. Casting seats are set around the bottom of the cement seat, and reinforcement plates are set on both side ends of the casting seat. The reinforcement plates are V-shaped to ensure its overall grip, foundation bearing strength and support stability. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a schematic overall plan view of the reinforcement structure of the power transmission tower of the present invention;

[0024] Figure 2 It is an enlarged schematic diagram of the reinforcement component structure of the present invention;

[0025] Figure 3 It is an enlarged schematic diagram of the structure of the corner reinforcement assembly of the present invention;

[0026] Figure 4 It is an enlarged schematic diagram of the tensioning assembly structure of the present invention;

[0027] Figure 5 It is an enlarged schematic diagram of the inner support assembly structure of the present invention;

[0028] Figure 6 It is an enlarged schematic diagram of the support assembly structure of the present invention;

[0029] In the figure: 1. cement seat; 2. transmission tower; 3. casting seat; 4. reinforcement plate; 5. edge and corner reinforcement assembly; 6. tensioning assembly; 7. inner support assembly; 8. support column; 9. support plate; 10. fixing nut; 11. fixing bolt; 12. limit plate; 13. spacer; 14. limit groove; 15. fixing hole; 16. first support seat; 17. second support seat; 18. cable box; 19. motor; 20. rope tube; 21. third support seat; 22. drive seat; 23. support rod; 24. telescopic rod; 25. support assembly; 26. connecting sleeve; 27. fixing plate; 28. connecting screw; 29. ​​mounting plate; 30. mounting groove; 31. connecting rod; 32. connecting plate. DETAILED DESCRIPTION

[0030] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0031] See also Figure 1-6, an embodiment provided by the present invention: a reinforcement structure for a transmission tower, comprising a cement seat 1, corner reinforcement components 5 are arranged around the upper surface of the cement seat 1, a transmission tower 2 is installed on the corner reinforcement components 5, tensioning components 6 are arranged on both sides of the upper surface of the cement seat 1, an inner support component 7 is arranged on the upper surface of the cement seat 1, casting seats 3 are arranged on both sides of the lower surface of the cement seat 1, four casting seats 3 are arranged, and reinforcement plates 4 are arranged on both sides of the casting seats 3, and the reinforcement plates 4 are V-shaped. First, the four corners of the transmission tower 2 are placed inside the limiting grooves 14 of the corner reinforcement components 5, and then screws are used to pass through the fixing holes 15 for reinforcement and fixation; after the corners are fixed, the top pull rope tube 20 of the tensioning component 6 is pulled out, and then it is connected and fixed to the poles on the outer sides of the two ends of the transmission tower 2;After the driving seat 22 drives the telescopic rod 24 to extend to a fixed position, the support assembly 25 is fixed to the telescopic rod 24 and the support rod 23 through the connecting sleeve 26 and the fixing plate 27: finally, the connecting rod 31 is fixed to the mounting groove 30 of the mounting plate 29 by screws, and then the connecting plate 32 is contacted and locked with the inner rod of the transmission tower 2. The extension and retraction between the telescopic rod 24 and the support rod 23 can be adjusted according to the height of the tower body to be supported. At the same time, the connecting rod 31 installed on one side of the mounting plate 29 can be installed in different sizes according to the spacing, which is convenient for adjustment, solving the transmission problem in the prior art. The reinforcement structure of the iron tower is less flexible when in use, so it is inconvenient to adjust the transmission tower 2 after installation, which affects its practicality and convenience. By arranging a cable inside the cable box 18 of the tensioning assembly 6, using the pull rope tube 20 to pull one end of the cable to the required fixed height, and after connecting and fixing it with the rod body on the outer end face of the tower body, the motor 19 is used to drive the cable to rotate inward, thereby tightening the cable, thereby pulling and fixing the outer end faces on both sides of the tower body, and the tensioning assembly 6 and the inner support assembly 7 play the role of supporting both inside and outside. Casting seats 3 are arranged around the top, and reinforcement plates 4 are arranged on both side end faces of the casting seats 3. The reinforcement plates 4 are V-shaped to ensure its overall grip, foundation bearing strength and support stability. The reinforcement of the transmission tower improves the bearing capacity of the transmission tower 2, ensures power supply safety, protects the transmission line from damage by the natural environment, and improves the reliability and stability of power supply. The transmission tower is the supporting point of the overhead line, and its stability and safety are crucial to the normal operation of the power system. Under extreme weather conditions, such as strong winds, ice covering, etc., the main material of the tower body often becomes the weak link in the structural stress. Solidification treatment can improve the carrying capacity of the tower without interrupting power supply, thereby ensuring that the transmission line can operate safely and stably under various environmental conditions. This not only reduces the project cost, but also brings significant economic and social benefits. In addition, the reinforcement of the transmission tower can also prevent damage to the natural environment, such as long-term scouring and erosion by river water. Through measures such as strengthening the foundation, the power supply safety of the transmission line can be protected. When extreme weather or natural disasters occur, the reinforced transmission tower can better withstand external pressure, reduce the possibility of power outages, and ensure the continuity and stability of power supply. ;

[0032] See also Figure 1-Figure 6 A first support seat 16 is provided at the bottom of the edge and corner reinforcement component 5, a support column 8 is provided on the upper surface of the first support seat 16, a support plate 9 is provided on the top of the support column 8, fixing bolts 11 are installed around the upper surface of the support plate 9, and a fixing nut 10 is provided at the bottom of the fixing bolt 11.

[0033] See also Figure 1-Figure 6A limit plate 12 is arranged on the upper surface of the support plate 9, a spacer plate 13 is arranged on one side of the limit plate 12, and limit grooves 14 are arranged on both sides of the spacer plate 13. Fixing holes 15 are arranged on the support plate 9 and the spacer plate 13. First, the four corners of the transmission tower 2 are placed inside the limit grooves 14 of the corner reinforcement component 5, and then the screws are passed through the fixing holes 15 for reinforcement and fixation; after the corners are fixed, the top pull rope tube 20 of the tensioning component 6 is pulled out, and then it is connected and fixed to the poles on the outside of the two ends of the transmission tower 2; the driving seat 22 drives the telescopic rod 24 to extend to After the position is fixed, the support assembly 25 is installed and fixed on the telescopic rod 24 and the support rod 23 through the connecting sleeve 26 and the fixing plate 27: finally, the connecting rod 31 is fixed to the mounting groove 30 of the mounting plate 29 by screws, and then the connecting plate 32 is contacted and locked with the inner rod of the transmission tower 2. The telescopic relationship between the telescopic rod 24 and the support rod 23 can be adjusted according to the height of the tower body to be supported. At the same time, the connecting rod 31 installed on one side of the mounting plate 29 can be installed in different sizes according to the spacing, which is convenient for adjustment, and solves the reinforcement structure of the transmission tower in the prior art. The flexibility is poor during use, so it is inconvenient to adjust the transmission tower 2 after installation, which affects its practicality and convenience. The reinforcement of the transmission tower improves the bearing capacity of the transmission tower 2, ensures power supply safety, protects the transmission line from damage by the natural environment, and improves the reliability and stability of power supply. As the supporting point of the overhead line, the stability and safety of the transmission tower are crucial to the normal operation of the power system. Under extreme weather conditions, such as strong winds, ice, etc., the main material of the tower body often becomes a weak link in the structural stress. Through reinforcement treatment, the bearing capacity of the tower can be improved without interrupting the power supply, thereby ensuring that the transmission line can operate safely and stably under various environmental conditions. This not only reduces the project cost, but also brings significant economic and social benefits. In addition, the reinforcement of the transmission tower can also prevent damage to the natural environment, such as long-term scouring and erosion by river water. Through measures such as strengthening the foundation, the power supply safety of the transmission line can be protected. When extreme weather or natural disasters occur, the reinforced transmission tower can better resist external pressure, reduce the possibility of power outages, and ensure the continuity and stability of power supply.

[0034] See also Figure 1-Figure 6 A second support seat 17 is provided at the bottom of the tensioning assembly 6, a cable box 18 is provided on the upper surface of the second support seat 17, and cables are provided inside the cable box 18.

[0035] See also Figure 1-Figure 6A motor 19 is installed on the front end face of the cable box 18, and a rope pulling tube 20 is arranged on the upper surface of the cable box 18. By arranging a cable inside the cable box 18 of the tensioning assembly 6, the rope pulling tube 20 is used to pull one top end of the cable to the required fixed height, and after being connected and fixed with the rod body on the outer end face of the tower body, the motor 19 is used to drive the cable to rotate inward, so as to tighten the cable, thereby pulling and fixing the outer end faces on both sides of the tower body. The tensioning assembly 6 and the inner support assembly 7 play the role of simultaneous internal and external support. The reinforcement of the transmission tower plays an important role in improving power supply reliability, ensuring the safe operation of the power system, and reducing the impact of natural disasters on power facilities.

[0036] See also Figure 1-Figure 6 A third support seat 21 is provided at the bottom of the inner support assembly 7, a driving seat 22 is installed on the upper surface of the third support seat 21, a support rod 23 is installed above the driving seat 22, a telescopic rod 24 is installed inside the support rod 23, and the telescopic rod 24 is plugged and connected to the inside of the support rod 23.

[0037] See also Figure 1-Figure 6 A support assembly 25 is installed on the support rod 23, and connecting sleeves 26 are arranged on both sides of the support assembly 25, and the connecting sleeves 26 are in an arc shape.

[0038] See also Figure 1-Figure 6 The front and rear end surfaces of the connecting sleeve 26 are both provided with fixing plates 27, and connecting screws 28 are installed on the fixing plates 27. The reinforcement of the transmission tower plays an important role in improving power supply reliability, ensuring the safe operation of the power system, and reducing the impact of natural disasters on power facilities.

[0039] See also Figure 1-Figure 6 A mounting plate 29 is provided on one end face of the connecting sleeve 26 , and mounting grooves 30 are provided on one side of the front and rear end faces of the mounting plate 29 . A connecting rod 31 is installed in the mounting groove 30 , and a connecting plate 32 is provided on one side of the connecting rod 31 .

[0040] See also Figure 1-Figure 6 A reinforcement method for a reinforcement structure of a transmission tower, comprising the following steps:

[0041] Step 1: First, place the four corners of the transmission tower 2 inside the limiting grooves 14 of the corner reinforcement assembly 5, and then use screws to pass through the fixing holes 15 to reinforce and fix them;

[0042] Step 2: After the corners are fixed, pull out the top rope tube 20 of the tensioning assembly 6, and then connect and fix it to the poles on the outside of the two ends of the transmission tower 2;

[0043] Step 3: After the driving seat 22 drives the telescopic rod 24 to extend to a fixed position, the support assembly 25 is fixed to the telescopic rod 24 and the support rod 23 through the connecting sleeve 26 and the fixing plate 27:

[0044] Step 4: Finally, fix the connecting rod 31 to the mounting groove 30 of the mounting plate 29 with screws, and then contact and lock the connecting plate 32 with the inner rod of the transmission tower 2. The reinforcement of the transmission tower improves the bearing capacity of the transmission tower 2, ensures power supply safety, protects the transmission line from damage by the natural environment, and improves the reliability and stability of power supply. The stability and safety of the transmission tower as the supporting point of the overhead line are crucial to the normal operation of the power system. Under extreme weather conditions, such as strong winds, icing, etc., the main material of the tower body often becomes a weak link in the structural stress. Through reinforcement treatment, the bearing capacity of the tower can be improved without interrupting power supply, thereby ensuring that the transmission line can operate safely and stably under various environmental conditions. This not only reduces the project cost, but also brings significant economic and social benefits. In addition, the reinforcement of transmission towers can also prevent damage to the natural environment, such as long-term scouring and erosion by river water. By strengthening the foundation and other measures, the power supply safety of the transmission lines can be protected. When extreme weather or natural disasters occur, the reinforced transmission towers can better withstand external pressure, reduce the possibility of power outages, and ensure the continuity and stability of power supply.

[0045] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.

Claims

1. A reinforcement structure for a power transmission tower, comprising a cement seat (1), characterized in that: Corner reinforcement components (5) are arranged around the upper surface of the cement seat (1), and a transmission tower (2) is installed on the corner reinforcement components (5). Tensioning components (6) are arranged on both sides of the upper surface of the cement seat (1). An inner support component (7) is arranged on the upper surface of the cement seat (1). Casting seats (3) are arranged on both sides of the lower surface of the cement seat (1), and four casting seats (3) are arranged. Reinforcement plates (4) are arranged on both sides of the casting seat (3), and the reinforcement plates (4) are V-shaped.

2. A reinforcement structure for a power transmission tower according to claim 1, characterized in that: A first support seat (16) is arranged at the bottom of the edge and corner reinforcement component (5); a support column (8) is arranged on the upper surface of the first support seat (16); a support plate (9) is arranged on the top of the support column (8); fixing bolts (11) are installed around the upper surface of the support plate (9); and fixing nuts (10) are arranged at the bottom of the fixing bolts (11).

3. A reinforcement structure for a power transmission tower according to claim 2, characterized in that: A limiting plate (12) is arranged on the upper surface of the support plate (9), a spacer plate (13) is arranged on one side of the limiting plate (12), limiting grooves (14) are arranged on both sides of the spacer plate (13), and fixing holes (15) are arranged on both the support plate (9) and the spacer plate (13).

4. A reinforcement structure for a power transmission tower according to claim 3, characterized in that: A second support seat (17) is provided at the bottom of the tensioning assembly (6), a cable box (18) is provided on the upper surface of the second support seat (17), and cables are provided inside the cable box (18).

5. A reinforcement structure for a power transmission tower according to claim 4, characterized in that: A motor (19) is installed on the front end surface of the cable box (18), and a rope pulling tube (20) is arranged on the upper surface of the cable box (18).

6. A reinforcement structure for a power transmission tower according to claim 5, characterized in that: A third support seat (21) is arranged at the bottom of the inner support assembly (7), a driving seat (22) is installed on the upper surface of the third support seat (21), a support rod (23) is installed above the driving seat (22), a telescopic rod (24) is installed inside the support rod (23), and the telescopic rod (24) is plug-connected with the inside of the support rod (23).

7. A reinforcement structure for a power transmission tower according to claim 6, characterized in that: A support assembly (25) is installed on the support rod (23), and connecting sleeves (26) are arranged on both sides of the support assembly (25), and the connecting sleeves (26) are in an arc shape.

8. A reinforcement structure for a power transmission tower according to claim 7, characterized in that: The front and rear end surfaces of the connecting sleeve (26) are both provided with fixing plates (27), and the fixing plates (27) are provided with connecting screws (28).

9. A reinforcement structure for a power transmission tower according to claim 8, characterized in that: A mounting plate (29) is provided on one end face of the connecting sleeve (26), mounting grooves (30) are provided on one side of the front and rear end faces of the mounting plate (29), a connecting rod (31) is installed in the mounting groove (30), and a connecting plate (32) is provided on one side of the connecting rod (31).

10. A reinforcement structure for a power transmission tower and a reinforcement method thereof are implemented based on any one of the reinforcement devices of claims 1 to 9, characterized in that: The following steps are involved: Step 1: First, place the four corners of the transmission tower (2) inside the limiting grooves (14) of the corner reinforcement assembly (5), and then use screws to pass through the fixing holes (15) to reinforce and fix them; Step 2: After the corners are fixed, pull out the top rope tube (20) of the tensioning assembly (6), and then connect and fix it to the poles on the outside of both ends of the transmission tower (2); Step 3: After the driving seat (22) drives the telescopic rod (24) to extend to a fixed position, the support assembly (25) is fixed to the telescopic rod (24) and the support rod (23) through the connecting sleeve (26) and the fixing plate (27): Step 4: Finally, the connecting rod (31) is fixed to the mounting groove (30) of the mounting plate (29) by means of screws, and then the connecting plate (32) is contacted and locked with the inner rod of the transmission tower (2).