Fabricated steel structure platform canopy and mounting method
By adopting the installation method of prefabricated steel structure platform canopy and articulated structure, the problems of large welding volume and difficulty in positioning adjustment in the construction of existing platform canopy are solved, the construction efficiency and safety are improved, and the stable lifting of the main body of the steel frame is achieved and fixed.
Patent Information
- Application Number
- CN202411273429.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-12
- Publication Date
- 2024-12-03
AI Technical Summary
The on-site construction methods of existing platform awnings have problems such as large welding volume and uneven anti-corrosion coating quality of welds. Prefabricated parts need to be manually positioned and adjusted when hoisting, which affects construction safety and efficiency.
The prefabricated steel structure platform canopy and corresponding installation methods are adopted, including the steel frame main body, canopy board and anchor assembly, and the connecting structure and fastener are connected, and the steel frame main body is lifted and fixed by lifting equipment to reduce the positioning and adjustment steps. , improve construction efficiency and safety.
The safety and convenience of the steel frame body and construction efficiency are improved during the lifting process, ensuring the stability and safety of the structure, reducing material costs, and reducing construction risks.
Smart Images

Figure CN119062157A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of building structures, and in particular to an assembled steel structure platform canopy and an installation method thereof. Background Art
[0002] Awnings are common building facilities at bus stations and coach stations. Station awnings are generally constructed on-site. The existing platform awnings are mostly connected by full welding or welding combined with fasteners. The amount of on-site welding is large, and the welding quality and weld anti-corrosion coating quality are uneven, which affects the stress safety of the awning structure.
[0003] Compared with other buildings or structures, canopies are smaller in size and are suitable for installation by prefabricated parts. However, when prefabricated parts are hoisted for installation, it is still necessary to set up brackets for assembly and connection between different prefabricated parts. When connecting the prefabricated parts of the canopy, it is necessary to manually position and adjust the prefabricated parts hoisted later. The safety and efficiency of the construction process need to be improved. Summary of the invention
[0004] In order to improve the on-site construction and installation efficiency of the canopy, the present application provides a prefabricated steel structure platform canopy and an installation method.
[0005] The assembled steel structure platform canopy and installation method provided in this application adopt the following technical solutions: An assembled steel structure platform canopy comprises a steel frame body, a canopy board and an anchoring assembly, wherein the anchoring assembly is used to anchor the steel frame body to the concrete foundation of the platform, the steel frame body comprises a supporting structure, a ceiling mounting structure and a limiting member, the ceiling mounting structure comprises a first extension portion and a second extension portion, the first extension portion and the second extension portion are respectively located on both sides of the supporting structure, a hinge structure may be connected between the ceiling mounting structure and the supporting structure, and the hinge structure is a detachable structure; the limiting member is used to prevent the second extension portion from rotating downward, a first fastener is connected between the limiting member and the supporting structure; a second fastener is connected between the ceiling mounting structure and the supporting structure.
[0006] By adopting the above technical solution, before installing the assembled steel structure platform canopy on the platform, the supporting structure and the ceiling installation structure of the steel frame body are welded and prefabricated respectively, and then the supporting structure and the ceiling installation structure are connected by a hinge structure, and the canopy board is installed on the ceiling installation structure, and then the steel frame body is hoisted to the platform by hoisting equipment and fixed by anchoring components. In the process of hoisting the steel frame body, the side of the second extension part away from the first extension part is used as the hoisting connection point, so that the ceiling installation structure and the supporting structure are kept in a vertical downward state during the hoisting of the steel frame body, so that the space occupied by the steel frame body during the hoisting process is small, and the steel frame body can easily keep the center of gravity stable during the hoisting process, and is not easy to shake, so that the hoisting of the steel frame body is safer and more convenient. After the main body of the steel frame is anchored by the anchor assembly, the first extension part of the ceiling installation structure is lifted upward by the hoisting equipment until the limiter abuts against the supporting structure, and then the limiter and the installation structure are connected by the first fastener. After the first fastener is installed, the ceiling installation structure and the supporting structure are already in a mutually connected and fixed state. Then the hoisting equipment is removed, and then the second fastener is used to further connect and reinforce the ceiling installation structure and the supporting structure. In the process of connecting the ceiling installation structure and the supporting structure by the first fastener, the second extension part is difficult to rotate downward due to the limiting effect of the limiter between the ceiling installation structure and the supporting structure, so that the safety of the staff in the process of installing the first fastener can be guaranteed, and in this process, there is no need to perform positioning and adjustment actions between the supporting structure of the steel frame main body and the ceiling installation structure, which helps to improve construction efficiency and construction safety.
[0007] Optionally, the hinge structure includes a hinge shaft, a first hinge plate and a second hinge plate, the hinge shaft is connected to the first hinge plate and the second hinge plate at the same time, there are multiple first hinge plates and multiple second hinge plates, and they are arranged alternately in sequence along the axial direction of the intersection shaft, the first hinge plate is fixedly installed on the ceiling mounting structure, and the second hinge plate is fixedly installed on the supporting structure, and the first hinge plate and the second hinge plate are arranged one by one.
[0008] By adopting the above technical solution, the gravity load is transmitted between the ceiling mounting structure and the supporting structure through the main hinge structure. The hinge shaft of the hinge structure is simultaneously connected in series with multiple first hinge plates and multiple second hinge plates, so that the load on the hinge structure is dispersed along the axial direction, making the hinge structure's support for the ceiling mounting structure more stable and reliable.
[0009] Optionally, the first hinge plate and the second hinge plate are both provided with a through hole for the second fastener to pass through, the first hinge plate is provided with a first positioning hole for passing the pin shaft, and the second hinge plate is provided with a second positioning hole for passing the pin shaft.
[0010] By adopting the above technical solution, in the process of fixing the first hinge plate to the ceiling mounting structure, the hinge shaft can be used to pass through each first hinge plate at the same time, and the pin shaft adapted to the first positioning hole can be used to pass through each first hinge plate at the same time, so that each first hinge plate can maintain a better relative position after being fixed to the ceiling mounting structure, so as to control the position of the through hole on the first hinge plate. The position of the through hole on the second hinge plate is controlled in a corresponding manner. When the first hinge plate and the second hinge plate are connected in series through the hinge shaft, the hinge shaft has a positioning effect on the first hinge plate and the second hinge plate, so that the through hole on the first hinge plate and the through hole on the second hinge plate are easier to align, so as to facilitate the installation of the second fastener.
[0011] Optionally, the hinge shaft includes a solid section and a hollow section, the diameter of the solid section is greater than or equal to the outer diameter of the hollow section, the solid section and the hollow section are alternately arranged along the axial direction, the length of the hollow section is greater than that of the solid section, and the hinge shaft is connected to the first hinge plate and the second hinge plate through the solid section.
[0012] By adopting the above technical solution, the hinge shaft is formed by alternating solid sections and hollow ends. The solid section plays a role in transmitting the load between the first hinge plate and the second hinge plate, so that the hinge shaft can reliably bear the ceiling installation structure; the hollow section plays a role in connecting two adjacent solid sections, so that each solid section and hollow section are connected as a whole, which is convenient for the installation of the hinge shaft. The weight of the hollow section is relatively low, which is conducive to reducing the weight of the steel frame body, saving material costs and reducing the load of the hoisting steel frame body.
[0013] Optionally, the articulated shaft is provided with at least two retaining springs, the retaining springs are located in the solid section, and the two retaining springs are used to jointly limit the axial movement of the articulated shaft.
[0014] By adopting the above technical solution, the retaining spring can limit the axial position of the hinge shaft after installation, so that the installation state of the hinge shaft on the steel frame body remains stable.
[0015] Optionally, the outward extension dimension of the first extension portion is larger than the outward extension dimension of the second extension portion, a diagonal support plate is provided in the angle region between the first extension portion and the supporting structure, an arc-shaped notch is provided on the side of the diagonal support plate close to the supporting structure, the arc-shaped notch is adapted to the solid section, the diameter of the solid section is larger than the outer diameter of the hollow section, the arc angle of the arc-shaped notch is larger than 180°, the opening width of the arc-shaped notch is larger than the outer diameter of the hollow section and smaller than the diameter of the solid section, and a wedge-shaped gasket is provided between the diagonal support plate and the second extension portion.
[0016] By adopting the above technical solution, the inclined support plate can play the role of auxiliary support for the ceiling installation structure, making the ceiling installation structure more stable and reliable. When installing the inclined support plate, the arc-shaped notch of the inclined support plate and the hollow section of the hinge shaft are inserted radially. When the hollow section enters the inner side of the arc-shaped notch, the inclined support plate is moved horizontally to the solid section of the hinge shaft so that the arc-shaped notch is clamped in the solid section. Then, the wedge-shaped gasket is inserted between the inclined support plate and the ceiling installation structure so that the inclined support plate can provide reliable support for the ceiling installation structure.
[0017] Optionally, the wedge-shaped gasket is in the shape of an elongated strip, the length direction of the wedge-shaped gasket is perpendicular to the axial direction of the hinge structure, the thickness of the wedge-shaped gasket gradually decreases in the direction approaching the hinge axis, and the wedge-shaped gasket is provided with a guide groove along its own length direction, and the guide groove is used to avoid the upper edge of the diagonal support plate.
[0018] By adopting the above technical solution, during the process of inserting the wedge-shaped gasket into the inclined support plate and the ceiling mounting structure, the guide groove has a guiding effect on the insertion process of the wedge-shaped gasket, making the insertion process of the wedge-shaped gasket more convenient.
[0019] The installation method of the assembled steel structure platform canopy includes the following steps: pre-embed an anchor assembly on the platform, the anchor assembly including anchor bolts and nuts; assemble the ceiling installation structure of the steel frame body and the supporting structure by using a hinge shaft, and install the canopy board to the steel frame body; use a lifting device to lift the steel frame body to the platform, and use the anchor assembly to fix the installation of the steel frame body; use the lifting device to lift the first extension part of the steel frame body upward, so that the limit piece abuts the supporting structure, and use a raised object to support one end of the first extension part away from the second extension part; use a first fastener and a second fastener to connect the ceiling installation structure and the supporting structure.
[0020] By adopting the above technical solution, during the process of installing the platform canopy, after the hoisting equipment lifts the first extension part, the first extension part is supported by a raised object, so that the position of the roof mounting structure can be more stable before the first fastener is installed.
[0021] Optionally, the top of the anchor bolt is pre-drilled to form a first through hole and a second through hole for passing the rope, the first through hole is connected to the second through hole, the first through hole is opened on the outer peripheral surface of the anchor assembly, and the second through hole is opened on the top surface of the anchor assembly; when hoisting the steel frame body, the rope is passed through the anchor hole at the bottom of the steel frame body, and then through the first through hole and the second through hole on the corresponding anchor bolt, and then a limiting member for preventing the rope from escaping from the anchor hole is tied to the rope; in the process of hoisting the steel frame body, the steel frame body is guided by the rope so that the anchor hole at the lower end of the steel frame body is aligned with the anchor assembly.
[0022] By adopting the above technical solution, in the process of hoisting the steel frame body to the platform, the rope can play a guiding role in the process of aligning the anchor hole with the anchor bolt, making the process of aligning the anchor hole with the anchor bolt more convenient, and when the staff uses the rope to adjust the steel frame body, they can maintain a certain safety distance from the steel frame body, which is conducive to ensuring the safety of the staff. In the process of using the rope to guide the anchor hole, the limiting component can keep the rope on the steel frame body, and the staff only needs to pull one end of the rope to adjust the position of the steel frame body, which is more convenient. After the anchor bolt of the anchor assembly is inserted into the anchor hole, the rope is pulled out of the anchor hole of the steel frame body to facilitate the anchoring of the steel frame body.
[0023] In summary, the present application includes at least one of the following beneficial technical effects: 1. During the process of hoisting the steel frame body, the side of the second extension part away from the first extension part is used as the hoisting connection point, so that the ceiling installation structure and the supporting structure are kept in a vertical downward state during the hoisting of the steel frame body, which can make it easy for the steel frame body to maintain a stable center of gravity during the hoisting process, making the hoisting of the steel frame body safer and more convenient.
[0024] 2. During the installation of the platform canopy, after the hoisting equipment lifts the first extension part, the first extension part is supported by a raised object, so that the position of the canopy roof mounting structure can be more stable before the first fastener is installed. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a side view of the assembled steel structure platform canopy of this embodiment.
[0026] Figure 2 yes Figure 1 A magnified partial view of point A in the middle.
[0027] Figure 3 It is a front view of the assembled steel structure platform canopy of this embodiment.
[0028] Figure 4 It is a schematic diagram of the present embodiment for illustrating the connection relationship between the diagonal support plate and the hinge shaft.
[0029] Figure 5 It is a flow chart of the installation method of the assembled steel structure platform canopy of this embodiment.
[0030] Figure 6 It is a schematic diagram of the present embodiment for reflecting the state in which the rope plays a guiding role.
[0031] Description of reference numerals: 1. Steel frame body; 11. Support structure; 12. Ceiling installation structure; 121. First extension; 122. Second extension; 13. Hinge structure; 131. Hinge shaft; 1311. Solid section; 1312. Hollow section; 1313. Positioning protrusion; 1314. Retaining spring groove; 1315. Retaining spring; 132. First hinge plate; 1322. First positioning hole; 133. Second hinge plate; 1332. Second positioning hole; 14. Limiting member; 15. First fastener; 16. Second fastener; 17. Diagonal support plate; 171. Arc notch; 18. Wedge-shaped gasket; 181. Guide groove; 2. Canopy board; 3. Anchor assembly; 31. Anchor bolt; 311. First through hole; 312. Second through hole; 32. Nut; 4. Rope; 5. Limiting member. DETAILED DESCRIPTION
[0032] The following is combined with Figure 1-6 This application is described in further detail.
[0033] The present application discloses an assembled steel structure platform canopy and an installation method. Figure 1 The assembled steel structure platform canopy and installation method include a steel frame body, a canopy board and an anchor assembly, the anchor assembly includes an anchor bolt and a nut, the anchor bolt is pre-buried and fixed in the concrete foundation of the platform, and the anchor assembly is used to anchor the steel frame body to the concrete foundation of the platform. The steel frame body includes a support structure and a ceiling installation structure, the ceiling installation structure includes a first extension part and a second extension part, the outward extension size of the first extension part is larger than the outward extension size of the second extension part, and the first extension part and the second extension part are respectively located on both sides of the support structure.
[0034] Reference Figure 1 and Figure 2 A hinge structure is connected between the ceiling mounting structure and the supporting structure. The ceiling mounting structure is provided with a limit piece. The limit piece is a long rectangular steel plate welded and fixed to the ceiling mounting structure. The length direction of the limit piece is along the axial direction of the hinge structure, and the width direction of the limit piece is vertically arranged. The limit piece abuts against a side of the supporting structure away from the first extension portion. A first fastener is connected between the limit piece and the supporting structure. The first fastener is a bolt. The first fastener is connected to the limit piece through a thread and is threadedly connected to the supporting structure.
[0035] During the installation of the assembled steel structure platform canopy, the ceiling installation structure of the steel frame body is first hinged to the support structure using a hinge structure, and then the steel frame body is hoisted to the concrete foundation of the platform, anchored using an anchor assembly, and then the ceiling installation structure is connected and fixed to the support structure using a first fastener. During the hoisting of the steel frame body, the hoisting position of the steel frame body is set at the middle part of the side of the second extension away from the first extension, so that both the ceiling installation structure and the support structure can be kept in a drooping state, so as to reduce the space occupied by the steel frame body, and at the same time, the center of gravity of the steel frame body can be more stable.
[0036] It is worth mentioning that the limiting member can also be arranged on the supporting structure. In this case, the first fastener needs to be threadedly connected to the ceiling mounting structure.
[0037] Reference Figure 2 and Figure 3 The hinge structure includes a hinge shaft, a first hinge plate and a second hinge plate. The first hinge plate and the second hinge plate are provided in plurality and are arranged alternately in sequence along the axial direction of the intersection shaft. The hinge shaft is connected with the first hinge plate and the second hinge plate at the same time. The first hinge plate is welded and fixedly installed on the ceiling installation structure, and the second hinge plate is welded and fixedly installed on the support structure. The first hinge plate and the second hinge plate are arranged one by one. The first hinge plate and the corresponding second hinge plate are attached to each other. The first hinge plate and the corresponding second hinge plate are connected by a second fastener, which is a bolt and nut assembly. The first hinge plate and the second hinge plate are provided with a through hole for the second fastener to pass through. The first hinge plate is provided with a first positioning hole for passing a pin shaft, and the second hinge plate is provided with a second positioning hole for passing a pin shaft.
[0038] In the process of welding the first hinge plate to the ceiling mounting structure, the hinge shaft can be used to pass through each first hinge plate at the same time, and the pin shaft adapted to the first positioning hole can be used to pass through each first hinge plate at the same time, so that each first hinge plate can maintain a better relative position after being fixed to the ceiling mounting structure, so as to control the position of the through hole on the first hinge plate. The position of the through hole on the second hinge plate is controlled in the same way, so that the through hole on the second hinge plate can be more easily aligned with the through hole on the first hinge plate.
[0039] Reference Figure 3 and Figure 4The articulated shaft includes a solid section and a hollow section. The diameter of the solid section is larger than the outer diameter of the hollow section, the length of the hollow section is larger than the solid section, the solid section and the hollow section are alternately arranged along the axial direction, and a positioning protrusion is provided on the end surface of the solid section close to the hollow section, and the positioning protrusion is interference fit with the inner hole of the hollow section. The articulated shaft is connected to the first articulated plate and the second articulated plate through the solid section, so that the articulated shaft can bear the load between the ceiling mounting structure and the supporting structure more reliably. The role of the hollow section is to connect the solid sections in series, which can reduce the weight of the articulated shaft while ensuring the bearing capacity of the articulated shaft.
[0040] Reference Figure 2 and Figure 3 Both ends of the hinge shaft are solid sections, and the solid sections at both ends of the hinge shaft are respectively provided with retaining spring grooves. The hinge shaft is clamped with retaining springs through the retaining spring grooves. The two retaining springs are located between the two first hinge plates at both ends. At the same time, the two retaining springs are located between the two second hinge plates at both ends. The retaining spring can play a limiting role on the hinge shaft to limit the axial movement of the hinge shaft.
[0041] Reference Figure 4 A plurality of diagonal brace plates are provided in the angle region between the first extension portion and the supporting structure, and the plurality of diagonal brace plates are equidistantly arranged along the axial direction of the hinge shaft. An arc-shaped notch is provided on the side of the diagonal brace plate close to the supporting structure, and the arc-shaped notch is adapted to the solid section, and the diameter of the solid section is larger than the outer diameter of the hollow section. The arc angle of the arc-shaped notch is larger than 180°, and the opening width of the arc-shaped notch is larger than the outer diameter of the hollow section and smaller than the diameter of the solid section.
[0042] A wedge-shaped gasket is provided between the diagonal support plate and the second extension portion. The wedge-shaped gasket is in the shape of an elongated strip. The length direction of the wedge-shaped gasket is perpendicular to the axial direction of the hinge structure. The thickness of the wedge-shaped gasket gradually decreases in the direction approaching the hinge axis. The wedge-shaped gasket is provided with a guide groove along its own length direction. The two ends of the guide groove are through-set. The guide groove is used to avoid the upper edge of the diagonal support plate.
[0043] When installing the diagonal support plate, the arc-shaped notch of the diagonal support plate is inserted radially into the hollow section of the hinge shaft. When the hollow section enters the inner side of the arc-shaped notch, the diagonal support plate is laterally moved to the solid section of the hinge shaft so that the arc-shaped notch is clamped in the solid section. Then the wedge-shaped gasket is inserted between the diagonal support plate and the ceiling mounting structure so that the diagonal support plate can provide reliable support for the ceiling mounting structure. In order to keep the position of the wedge-shaped gasket stable, the wedge-shaped gasket and the diagonal support plate can be welded and fixed.
[0044] This embodiment also discloses the installation method of the above-mentioned assembled steel structure platform canopy, referring to Figure 5-6 , including the following steps: Step 1: pre-embed and install the anchor assembly on the platform so that the nut of the anchor assembly is kept separate from the anchor bolt; The top of the anchor bolt is pre-drilled to form a first through hole and a second through hole for passing the rope, the first through hole is connected to the second through hole, the center line of the first through hole forms an obtuse angle with the center line of the second through hole, the first through hole is opened on the outer peripheral surface of the anchor assembly, and the second through hole is opened on the top surface of the anchor assembly; Step 2, assemble the ceiling installation structure and the support structure of the steel frame body using a hinged shaft, and install the canopy board to the steel frame body; Step 3, hoist the steel frame body to the platform using hoisting equipment, and fix the installation of the steel frame body using anchoring components; When hoisting the main body of the steel frame, the rope is passed through the anchor hole at the bottom of the main body of the steel frame, and then through the first and second holes on the corresponding anchor bolts, and then the limiting member used to prevent the rope from slipping out of the anchor hole is tied to the rope; in the process of hoisting the main body of the steel frame, the main body of the steel frame is guided by the rope so that the anchor hole at the lower end of the main body of the steel frame is aligned with the anchor assembly; when each anchor bolt is inserted into the anchor hole and the main body of the steel frame has not yet landed, the rope is pulled out so that the nut can be installed on the anchor bolt after the steel structure is hoisted in place; In this embodiment, the rope used to guide the steel frame body can be a steel rope, steel wire, nylon monofilament, etc., and the number of ropes is at least two, and the ropes and anchor holes are arranged one by one; the limiting member used to tie to the rope can be a wire rope clamp or a rod-shaped object; it should be noted that when the staff uses the rope to guide the steel frame body, it is necessary to use tools such as pliers to indirectly pull the rope to prevent the rope from causing damage to the hands of the staff; Step 4, after the steel frame body is installed in place, the first extension part of the steel frame body is lifted upward by the lifting equipment, so that the limiter abuts against the supporting structure, and a cushioning object is used to support one end of the first extension part away from the second extension part; the cushioning object can be an object that can be easily stacked, such as a sandbag, a wooden box, etc., or a lifting platform or a manual stacker can be used as a cushioning object; Step 5: Use a first fastener to connect the limiter and the support structure, and use a second fastener to connect the first hinge plate and the second hinge plate.
[0045] Step 6, install the inclined support plate to the solid section of the hinge shaft so that the inclined support plate abuts the first intersection plate or the second hinge plate, then insert the wedge-shaped gasket between the inclined support plate and the ceiling mounting structure, and spot weld the wedge-shaped gasket to the inclined support plate.
[0046] During the installation of the assembled steel structure platform canopy, the support structure and the ceiling installation structure are connected through a hinged structure. During the process of hoisting the steel frame body, the side of the second extension away from the first extension is used as the hoisting connection point, so that the ceiling installation structure and the support structure can both remain in a vertical downward drooping state during the hoisting of the steel frame body, which is conducive to making the steel frame body easy to maintain a stable center of gravity during the hoisting process, and is conducive to making the hoisting of the steel frame body safer and more convenient. After the steel frame body is anchored by the anchor assembly, the first extension of the ceiling installation structure is lifted upward, and the first extension is supported by a padding object. When the ceiling installation structure and the support structure are limited by the limiter, the second extension is difficult to rotate downward, so that the staff can safely install the first fastener on the steel frame body.
[0047] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. Prefabricated steel structure platform canopy, Features: The invention comprises a steel frame body (1), a canopy plate (2) and an anchoring assembly (3), wherein the anchoring assembly (3) is used to anchor the steel frame body (1) to a concrete foundation of a platform, wherein the steel frame body (1) comprises a supporting structure (11), a ceiling mounting structure (12) and a stopper (14), wherein the ceiling mounting structure (12) comprises a first extension portion (121) and a second extension portion (122), wherein the first extension portion (121) and the second extension portion (122) are respectively located on two sides of the supporting structure (11), wherein a hinged structure (13) may be connected between the ceiling mounting structure (12) and the supporting structure (11), wherein the hinged structure (13) is a detachable structure; wherein the stopper (14) is used to prevent the second extension portion (122) from rotating downward, wherein a first fastener (15) is connected between the stopper (14) and the supporting structure (11); and wherein a second fastener (16) is connected between the ceiling mounting structure (12) and the supporting structure (11).
2. The assembled steel structure platform canopy according to claim 1, Features: The hinge structure (13) comprises a hinge shaft (131), a first hinge plate (132) and a second hinge plate (133); the hinge shaft (131) is connected to the first hinge plate (132) and the second hinge plate (133); a plurality of the first hinge plates (132) and the second hinge plates (133) are provided, and the first hinge plates (132) and the second hinge plates (133) are arranged alternately in sequence along the axial direction of the intersection shaft; the first hinge plate (132) is fixedly mounted on the ceiling mounting structure (12), and the second hinge plate (133) is fixedly mounted on the supporting structure (11); the first hinge plates (132) and the second hinge plates (133) are arranged in a one-to-one correspondence.
3. The assembled steel structure platform canopy according to claim 1, Features: The first hinge plate (132) and the second hinge plate (133) are both provided with a through hole for the second fastener (16) to pass through, the first hinge plate (132) is provided with a first positioning hole (1322) for passing a pin shaft through, and the second hinge plate (133) is provided with a second positioning hole (1332) for passing a pin shaft through.
4. The assembled steel structure platform canopy according to claim 1, Features: The hinge shaft (131) comprises a solid section (1311) and a hollow section (1312); the diameter of the solid section (1311) is greater than or equal to the outer diameter of the hollow section (1312); the solid section (1311) and the hollow section (1312) are alternately arranged along the axial direction; the length of the hollow section (1312) is greater than that of the solid section (1311); and the hinge shaft (131) is connected to the first hinge plate (132) and the second hinge plate (133) via the solid section (1311).
5. The assembled steel structure platform canopy according to claim 1, Features: The hinge shaft (131) is provided with at least two retaining springs (1315), wherein the retaining springs (1315) are located in the solid section (1311), and the two retaining springs (1315) are used to jointly limit the axial movement of the hinge shaft (131).
6. The assembled steel structure platform canopy according to claim 1, Features: The outward extension dimension of the first extension portion (121) is greater than the outward extension dimension of the second extension portion (122); a diagonal support plate (17) is provided in the angle region between the first extension portion (121) and the support structure (11); a side of the diagonal support plate (17) close to the support structure (11) is provided with an arc-shaped notch (171); the arc-shaped notch (171) is adapted to the solid section (1311); the diameter of the solid section (1311) is greater than the outer diameter of the hollow section (1312); the arc angle of the arc-shaped notch (171) is greater than 180°; the opening width of the arc-shaped notch (171) is greater than the outer diameter of the hollow section (1312) and smaller than the diameter of the solid section (1311); and a wedge-shaped gasket (18) is provided between the diagonal support plate (17) and the second extension portion (122).
7. The assembled steel structure platform canopy according to claim 1, Features: The wedge-shaped gasket (18) is in the shape of an elongated strip, the length direction of the wedge-shaped gasket (18) is perpendicular to the axial direction of the hinge structure (13), the thickness of the wedge-shaped gasket (18) gradually decreases in a direction approaching the hinge shaft (131), and the wedge-shaped gasket (18) is provided with a guide groove (181) along its length direction, and the guide groove (181) is used to avoid the upper edge of the diagonal support plate (17).
8. The method for installing the assembled steel structure platform canopy according to any one of claims 1 to 7, It is characterized in that The steps include: An anchor assembly (3) is pre-buried and installed on the platform, wherein the anchor assembly (3) comprises an anchor bolt (31) and a nut (32); Assembling the ceiling mounting structure (12) and the supporting structure (11) of the steel frame body (1) using a hinge shaft (131), and mounting the canopy board (2) on the steel frame body (1); Using lifting equipment to lift the steel frame body (1) onto the platform, and using anchoring components (3) to secure the steel frame body (1); Using a lifting device to lift the first extension portion (121) of the steel frame body (1) upwards, so that the limiting member (14) abuts against the supporting structure (11), and using a raised object to support one end of the first extension portion (121) away from the second extension portion (122); The ceiling mounting structure (12) and the supporting structure (11) are connected by using a first fastener (15) and a second fastener.
9. The method for installing the assembled steel structure platform canopy according to claim 8, It is characterized in that The top of the anchor bolt (31) is pre-drilled to form a first penetration hole (311) and a second penetration hole (312) for passing the rope (4); the first penetration hole (311) is connected to the second penetration hole (312); the first penetration hole (311) is opened on the outer peripheral surface of the anchor assembly (3); and the second penetration hole (312) is opened on the top surface of the anchor assembly (3); when the steel frame body (1) is hoisted, the rope (4) is passed through the anchor bolt (31) hole at the bottom of the steel frame body (1), and then passed through the first penetration hole (311) and the second penetration hole (312) on the corresponding anchor bolt (31); then, a limiting member (5) is tied to the rope (4) to prevent the rope (4) from slipping out of the anchor bolt (31) hole; in the process of hoisting the steel frame body (1), the rope (4) is used to guide the steel frame body (1) so that the anchor bolt (31) hole at the lower end of the steel frame body (1) is aligned with the anchor assembly (3).