Subway section flood escape channel
By setting up a movable sinking passage in the subway area to connect the evacuation platform and the platform, the problem of difficulty in evacuation of passengers during floods is solved, evacuation efficiency and safety are improved, and passengers can escape safely.
Patent Information
- Application Number
- CN202411255343.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-09
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-09-09
AI Technical Summary
The existing subway area lacks targeted passenger evacuation methods in flooding situations, resulting in flooding of evacuation platforms and roadbeds, preventing passengers from escaping.
Design a flood escape passage between subway areas, including setting up a platform and evacuation platform in the tunnel, and connecting it through a movable sinking passage to cover the passage to the tunnel bed to ensure that passengers can pass safely during flooding.
It improves the safety and efficiency of passengers evacuation in flood situations, avoids the risk of tripping caused by water accumulation, and ensures that passengers can safely gather on the platform for evacuation.
Smart Images

Figure CN119062385A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of escape passages, and in particular to a flood escape passage in a subway section. Background Art
[0002] The subway is a common means of transportation and a type of urban rail transit line. The lines located in the central city are basically set up in underground tunnels. For safety reasons, when safety problems occur in subway tunnels, the passenger evacuation method is an extremely important part of the design content. It is a safety guarantee to ensure the safe escape of passengers. Floods are one of the disasters that affect passenger safety.
[0003] Under current circumstances, there is no targeted design for the passenger evacuation problem under flood conditions. Generally, when a flood occurs in a subway section, the fire evacuation method will be referred to, and passengers will be evacuated along the roadbed or evacuation platform. However, the roadbed will be quickly submerged by the flood during a flood, and the turbid water will make it difficult for passengers to identify the road and they may easily trip. A sunken walkway leading to the roadbed is set on the evacuation platform, and the height of some evacuation platforms is lowered by stairs, making it easy to be submerged by the flood during a flood, thereby hindering the evacuation of passengers. Therefore, an evacuation method for flood conditions is needed. Summary of the invention
[0004] The purpose of the present invention is to provide a subway section flood escape passage, which solves the problem that the existing subway passage has no passenger evacuation method under flood conditions.
[0005] In order to solve the above technical problems, the present invention specifically provides the following technical solutions:
[0006] A subway section flood escape passage comprises a platform arranged in a subway tunnel, and two evacuation platforms arranged on the side wall of the subway tunnel and located in the subway line section, the platform comprises a platform room and a platform corridor, and one of the evacuation platforms is connected to the platform corridor, a connecting passage is arranged at one end of the platform corridor, and the connecting passage is located at the end of the platform room and connected to another evacuation platform, each of the evacuation platforms is provided with a movable sunken passage, and the movable sunken passage is used to provide a passage for passengers to pass to the roadbed during fire evacuation, and to cover the passage leading to the roadbed in the event of a flood.
[0007] As a preferred solution of the present invention, the movable sunken passage includes an interrupted notch arranged on the evacuation platform, and the interrupted notch divides the evacuation platform into two sections, a downwardly extending sunken walkway is arranged at the interrupted notch, and a cover plate is arranged on the side wall of the subway tunnel by rotating through a hinge, and the length of the cover plate is greater than the length of the interrupted notch, and it is flipped to overlap the two sections of the evacuation platform when a flood occurs.
[0008] As a preferred solution of the present invention, a support frame is provided at the bottom of the cover plate, a plurality of support columns are rotatably connected to the support frame, and the support columns rotate due to gravity when the cover plate is turned over.
[0009] As a preferred solution of the present invention, the evacuation platform is connected to the platform corridor via a gentle slope.
[0010] As a preferred solution of the present invention, the gentle slope is an obstacle-free gentle slope with a slope of 1:8.
[0011] As a preferred solution of the present invention, a manned air defense door is provided at the connection point between the evacuation platform and the platform corridor.
[0012] As a preferred solution of the present invention, a fire door is provided in the connecting passage.
[0013] As a preferred solution of the present invention, a platform plate is provided on one side of the platform, and the platform plate is connected to two evacuation platforms. A stairwell is provided at the platform plate, and the stairwell is connected to a connecting passage and to the ground.
[0014] Compared with the prior art, the present invention has the following beneficial effects:
[0015] The present invention connects the evacuation platform with the platform corridor so that passengers can directly enter the platform for evacuation through the evacuation platform, and connects the evacuation platforms on both sides through a connecting passage so that passengers on the evacuation platforms on both sides can gather at the platform for evacuation, and provides a movable sunken passage to cover the passage leading to the track bed, so that passengers are convenient to transfer through the evacuation platform, thereby improving the safety and efficiency of passenger transfer when a flood occurs. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the implementation methods of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for the implementation methods or the description of the prior art. Obviously, the drawings in the following description are only exemplary, and for ordinary technicians in this field, other implementation drawings can be derived from the provided drawings without creative work.
[0017] Figure 1 A schematic diagram of the structural layout of a flood escape passage in a subway section is provided for an embodiment of the present invention;
[0018] Figure 2 A schematic diagram of a station structure layout with wiring is provided for an embodiment of the present invention;
[0019] Figure 3 A structural schematic diagram of a movable sinking channel is provided for an embodiment of the present invention.
[0020] The numbers in the figure represent the following:
[0021] 1. Evacuation platform; 2. Platform room; 3. Platform corridor; 4. Connecting passage; 5. Movable sunken passage; 6. Stairwell;
[0022] 501. sunken walkway; 502. cover plate; 503. support frame; 504. support column; 505. hinge. DETAILED DESCRIPTION
[0023] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0024] like Figures 1 to 3 As shown, the present invention provides a subway section flood escape passage, including a platform arranged in a subway tunnel, and two evacuation platforms 1 arranged on the side wall of the subway tunnel and located in the subway line section, the platform includes a platform room 2 and a platform corridor 3, and one of the evacuation platforms 1 is connected to the platform corridor 3, a connecting passage 4 is arranged at one end of the platform corridor 3, and the connecting passage 4 is located at the end of the platform room 2 and connected to another evacuation platform 1, each evacuation platform 1 is provided with a movable sunken passage 5, and the movable sunken passage 5 is used to provide a passage for passengers to pass to the roadbed during fire evacuation, and cover the passage leading to the roadbed in the event of a flood.
[0025] The present application is aimed at the problem of how to safely evacuate passengers in a subway tunnel under flooding conditions. In the solution of the present application, by connecting the evacuation platform 1 with the platform corridor 3, passengers in the subway line section can directly reach the platform through the evacuation platform 1 after getting off the train, gather at the platform, and evacuate safely. Compared with the existing method of entering the roadbed through the down-track stairs at the adjacent platform via the evacuation platform 1 and then entering the platform via the stairs, the present application improves the safety and efficiency of the evacuation process.
[0026] In order to save space, a platform corridor 3 is generally only set on one side of the platform. Therefore, by setting a connecting passage 4, passengers on the evacuation platform 1 on one side of the subway line section can directly reach the platform corridor 3, and passengers on the evacuation platform 1 on the other side can reach the platform corridor 3 through the connecting passage 4, so that passengers evacuating through the evacuation platform 1 can all reach the platform corridor 3 for evacuation, thereby improving the evacuation efficiency.
[0027] Furthermore, if platform corridors 3 are provided on both sides of the platform, the two platform corridors 3 are respectively connected to the two evacuation platforms 1, so that passengers evacuating on the two evacuation platforms 1 can quickly reach the platform corridors 3 for safe evacuation.
[0028] In order to ensure the safety of fire evacuation, a movable sunken passage 5 is arranged on the evacuation platform 1, so that passengers can evacuate through the passage on the movable sunken passage 5 to the roadbed. However, in the event of a flood, the road is difficult to identify due to water accumulation on the roadbed, and passengers are prone to tripping and falling when evacuating from the roadbed. At this time, the movable sunken passage 5 covers the passage to close it, so that passengers can directly enter the platform corridor 3 through the evacuation platform 1 for safe evacuation, thereby improving the evacuation efficiency and ensuring the safe evacuation of passengers.
[0029] In this embodiment, the two evacuation platforms 1 only refer to the number within a subway line section, and this part is taken as an example, and all subway areas are designed and constructed according to the example of this part.
[0030] The movable sunken passage 5 includes an interrupted gap arranged on the evacuation platform 1, and the interrupted gap divides the evacuation platform 1 into two sections. A downwardly extending sunken walkway 501 is arranged at the interrupted gap. A cover plate 502 is rotatably arranged on the side wall of the subway tunnel through a hinge 505, and the length of the cover plate 502 is greater than the length of the interrupted gap. When a flood occurs, it is flipped to overlap the two sections of the evacuation platform 1.
[0031] A sunken walkway 501 is provided at the interruption gap so that in case of fire evacuation, passengers on the evacuation platform 1 can reach the roadbed for evacuation through the sunken walkway 501. In the present embodiment, the sunken walkway 501 is a staircase, and there are two of them, so that passengers on the evacuation platforms 1 on both sides of the interruption gap can evacuate to the roadbed through the sunken walkway.
[0032] When a flood occurs, passengers or staff members flip the cover plate 502 so that the two ends of the cover plate 502 are respectively overlapped on the evacuation platforms 1 at both ends. At this time, the evacuation platforms 1 provide support for the cover plate 502, and the passengers on the evacuation platform 1 can directly reach the platform corridor 3 through the cover plate 502, so that the passengers do not have to walk through the roadbed to the evacuation platform 1, avoiding the problem of passengers being tripped and injured by accumulated water on the roadbed.
[0033] When not in use, the cover plate 502 is flipped and leaned against the wall of the subway tunnel. It can also be fixed by corresponding locks, for example, by setting hooks on the side walls of the subway tunnel to hook the cover plate 502.
[0034] Furthermore, the cover plate 502 may also be rotatably connected to the inner wall of the subway tunnel in other ways, such as by a hinge connection.
[0035] A support frame 503 is disposed at the bottom of the cover plate 502 , and a plurality of support columns 504 are rotatably connected to the support frame 503 , and the support columns 504 rotate due to gravity when the cover plate 502 is turned over.
[0036] When the cover plate 502 is flipped over to overlap with the evacuation platform 1, the support column 504 is flipped over to contact with the ground under the action of gravity. The cover plate 502 is supported by multiple support columns 504, thereby improving the safety of the cover plate 502 when passengers pass through. When the cover plate 502 is folded up, the support column 504 automatically rotates to contact with the support frame 503 due to the action of gravity, and then automatically folds up, avoiding interference with the area of the sunken walkway 501, so that passengers can pass through the sunken walkway 501 normally.
[0037] The evacuation platform 1 is connected to the platform corridor 3 through a gentle slope.
[0038] The gentle slope is barrier-free and has a slope of 1:8.
[0039] There is a height difference between the evacuation platform 1 and the platform corridor 3, so a gentle slope is set to ensure the safe passage of passengers.
[0040] In this embodiment, the gradient of the gentle slope is 1:8, and it may also be other gradients, which can be adjusted according to actual engineering design.
[0041] A manned air defense door is provided at the connection point between the evacuation platform 1 and the platform corridor 3.
[0042] When a section civil defense door is set at one end of the platform, the evacuation path of the subway line section is blocked by the section civil defense door under flood conditions, and the evacuation passage through the roadbed is also blocked at this time. Therefore, a civil defense door is set at the connection between the evacuation platform 1 and the platform corridor 3 to connect the evacuation platform 1 and the platform corridor 3 to ensure that passengers have a safe evacuation path.
[0043] Furthermore, relevant lines should be laid above the civil defense doors to avoid the evacuation routes.
[0044] A fire door is provided in the connecting passage 4 to block wind pressure and smoke.
[0045] A platform plate is provided on one side of the platform, and the platform plate is connected with two evacuation platforms 1 , a stairwell 6 is provided at the platform plate, and the stairwell 6 is connected with the connecting passage 4 and the ground.
[0046] Due to driving needs, some platforms are equipped with various wiring such as single crossovers, return lines, and stop lines. These wiring blocks the evacuation path of the platform corridor 3 and increases the evacuation distance. Taking the single crossover as an example, the platform is divided into two parts. If there is a platform room 2 at the end of the platform, the area will form an island. Therefore, a stairwell 6 is set at one end of the platform to connect to the passage 4 to facilitate the evacuation of staff and passengers to the ground, and the evacuation platform 1 is connected through the platform plate, so that the evacuation platform 1 is in a connected state with the platform corridor 3.
[0047] Furthermore, in order to facilitate the entry and exit of the staff, the station hall where the stairwell 6 is located is generally a piston passage, which is arranged along the air duct direction of the subway tunnel to reduce the occupation of the air duct.
[0048] Furthermore, if the side platform station is blocked by the main line between the subway section evacuation platform 1 and the platform, this method can also be used to increase the safety of passenger evacuation under flood conditions.
[0049] In actual projects, it is recommended that the evacuation platform 1 on both sides of the station wiring be extended as much as possible and close to the wiring under the premise of meeting the limit, and the blocking distance be controlled within the train length. Under flood conditions, the empty train closest to the area can be dispatched and parked here, and the side doors at both ends of the train are connected to the evacuation platform 1 respectively, and the long passenger compartment inside the train is used as a temporary evacuation connection channel, crossing the wiring area for emergency evacuation of passengers in the section.
[0050] In this embodiment, the general construction method is:
[0051] Civil engineering projects such as platforms and section tunnels are the basic projects for the implementation of escape routes, and civil engineering projects are implemented first. Stations generally adopt the open-cut method, and implement the main structure, platform slabs, evacuation stairwells and other secondary structures in turn, and finally install civil defense doors. Section tunnels are generally implemented using the shield method.
[0052] After the civil construction of the platform and section tunnel is completed, the decoration project of the corresponding escape passage will be implemented simultaneously in the platform and section tunnel. The platform part will lay anti-slip floor tiles on the platform board escape passage and stairwell 6 to maintain the flatness of the ground of the entire escape path. During the implementation process, special attention should be paid to ensure that no obstacles protruding from the ground affect the safety of escape.
[0053] The evacuation platform 1 and the sunken walkway 501 of the interval part adopt a steel structure system. First, the load-bearing steel beam structure support part of the evacuation platform 1 and the sunken walkway 501 is implemented, and the transverse steel beams are fixed on the tunnel structure segments. The spacing between the steel beams is 1.2 meters, which is consistent with the width of the segments.
[0054] After the steel beam load-bearing structure is completed, the evacuation flat pedal is laid on top. The step plate is connected to the steel support with hooks. There must be no less than 2 hooks on each steel beam. The platform pedal surface is in the form of a non-grid flat panel to prevent walking obstacles caused by special heels.
[0055] Finally, the handrail and the foldable cover 502 at the sunken walkway 501 are implemented. The cover 502 can be prefabricated in advance and assembled on site. The cover 502, the support frame 503 and the support column 504 can be prefabricated and fixed in advance. The number of support columns 504 is determined by the load-bearing structural steel beams at the bottom of the site, and the positions correspond to the steel beams. Each support column 504 consists of two supporting rigid columns, which match the height of the sunken walkway 501 and the overall force balance. After the cover 502 is turned down, the support column 504 is loaded The force is unfolded and falls on the steel beam to provide reverse supporting force. The cover plate 502 is fixed on the shield tunnel segment by hinges 505. It has the function of flipping up and down and can prevent wind pressure from falling and affecting driving safety. The number of hinges 505 is determined according to actual conditions. Generally, a group of hinges 505 is set on each of the evacuation platforms 1 and support columns 504 on both sides. Finally, conventional measures such as chains are used to temporarily fix the flipped cover plate 502 panel to the lateral segment, which does not affect the normal maintenance and traffic function. In case of floods, the chain is manually loosened to drop the cover plate 502.
[0056] The above embodiments are only exemplary embodiments of the present application and are not intended to limit the present application. The protection scope of the present application is defined by the claims. Those skilled in the art may make various modifications or equivalent substitutions to the present application within the essence and protection scope of the present application, and such modifications or equivalent substitutions shall also be deemed to fall within the protection scope of the present application.
Claims
1. A subway section flood escape passage, It is characterized in that The invention comprises a platform arranged in a subway tunnel, and two evacuation platforms (1) arranged on the side wall of the subway tunnel and located in the subway line section, wherein the platform comprises a platform room (2) and a platform corridor (3), and one of the evacuation platforms (1) is connected to the platform corridor (3), and a connecting passage (4) is arranged at one end of the platform corridor (3), and the connecting passage (4) is located at the end of the platform room (2) and connected to the other evacuation platform (1), and each of the evacuation platforms (1) is provided with a movable sunken passage (5), and the movable sunken passage (5) is used to provide a passage for passengers to pass to the roadbed during fire evacuation, and to cover the passage leading to the roadbed in the event of a flood.
2. A subway section flood escape passage according to claim 1, It is characterized in that The movable sunken passage (5) comprises an interruption notch arranged on the evacuation platform (1), and the interruption notch divides the evacuation platform (1) into two sections, and a downwardly extending sunken walkway (501) is arranged at the interruption notch, and a cover plate (502) is rotatably arranged on the side wall of the subway tunnel through a hinge (505), and the length of the cover plate (502) is greater than the length of the interruption notch, and when a flood occurs, it is turned over to overlap the two sections of the evacuation platform (1).
3. A subway section flood escape passage according to claim 2, It is characterized in that A support frame (503) is provided at the bottom of the cover plate (502), and a plurality of support columns (504) are rotatably connected to the support frame (503), and the support columns (504) rotate due to gravity when the cover plate (502) is turned over.
4. A subway section flood escape passage according to claim 1, It is characterized in that The evacuation platform (1) is connected to the platform corridor (3) via a gentle slope.
5. A subway section flood escape passage according to claim 4, It is characterized in that The gentle slope is an obstacle-free gentle slope with a slope of 1:
8.
6. A subway section flood escape passage according to claim 1, It is characterized in that A man-air defense door is provided at the connection point between the evacuation platform (1) and the platform corridor (3).
7. A subway section flood escape passage according to claim 1, It is characterized in that A fireproof door is arranged in the connecting passage (4).
8. A subway section flood escape passage according to claim 1, It is characterized in that A platform plate is provided on one side of the platform, and the platform plate is connected to two evacuation platforms (1); a stairwell (6) is provided at the platform plate, and the stairwell (6) is connected to a connecting passage (4) and to the ground.
Citation Information
Patent Citations
Escape way for emergency evacuation
CN102381317A
Intercity railway underground station integrally developed above track area
CN110700318A
In-subway evacuation structure
CN112539080A
Subway interval tunnel escape channel
CN115898519A
Semiconductor device
KR1020230160579A