Construction method of prefabricated reverse ridge
The prefabricated counter-sill construction method addresses positioning deviations and leakage issues by using prefabricated components and a trapezoidal groove structure for accurate installation, enhancing construction efficiency and reliability.
Patent Information
- Application Number
- CN202411371651.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-29
- Publication Date
- 2024-12-06
AI Technical Summary
Existing construction methods for counter-sills in building construction suffer from positioning deviations and leakage issues, leading to increased construction costs and extended periods due to rework.
A prefabricated counter-sill construction method involving prefabrication of the anti-ridge main body with positioning bars and a waterproof layer, using positioning ribs and a trapezoidal groove structure for accurate installation and connection with the building component.
This method reduces positioning deviations and ensures waterproof integrity, controlling construction costs and improving efficiency by avoiding rework and ensuring reliable installation.
Smart Images

Figure CN119083606A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a construction method of a prefabricated anti-ridge. Background Art
[0002] The counter-sill is a raised structure constructed on the roof and other building components, and its main function is waterproofing. In the process of counter-sill construction, there are currently two conventional construction methods: the first is to cast the main unit in one go; the second is to position and lay out the two structural units, then chisel and plant the reinforcement for casting. Among them, when the first construction method is adopted, it is often easy to produce positioning deviations during the construction process, resulting in rework in the later stage, extending the construction period, and increasing construction costs; when the second construction method is adopted, the requirements for the casting process are higher, otherwise the counter-sill is prone to leakage. Therefore, it is necessary to provide a construction method for a prefabricated counter-sill that can solve the problems of positioning deviations in the one-time casting of the counter-sill in the prior art and easy leakage of the counter-sill constructed by chiseling and casting. Summary of the invention
[0003] The purpose of the present invention is to provide a construction method for a prefabricated counter-sill, which can solve the problems in the prior art that a counter-sill cast in one go has positioning deviation and a counter-sill cast in roughening and casting construction is prone to leakage.
[0004] The present invention is achieved in that:
[0005] A construction method for a prefabricated anti-ridge comprises the following steps:
[0006] Step 1: Prefabricate and process the anti-ridge main body;
[0007] Step 2: Pre-embed a number of positioning bars at intervals in the anti-slope construction area;
[0008] Step 3: Construct a waterproof layer in the anti-slope construction area, and several positioning bars penetrate the waterproof layer;
[0009] Step 4: Place the bottom of the anti-ridge main body in the waterproof layer, and insert a number of positioning ribs into the positioning holes;
[0010] Step 5: Inject mortar into the anti-slope body to connect the anti-slope body and the waterproof layer with the building components to form a whole.
[0011] A grouting hole and a positioning hole are reserved in the anti-ridge main body. The positioning hole is located at the bottom of the anti-ridge main body and penetrates the anti-ridge downward. The bottom of the grouting hole is connected with the positioning hole, and the grouting hole penetrates the anti-ridge main body upward.
[0012] The lower end of the positioning rib is embedded and fixed in the anti-ridge construction area, the upper end of the positioning rib extends to the top of the anti-ridge construction area, and the arrangement space of a plurality of positioning ribs is smaller than the volume of the positioning hole.
[0013] The plurality of positioning ribs are arranged at intervals along the central axis of the anti-ridge construction area.
[0014] The anti-ridge construction area is formed on the building component in a concave structure, and the size of the anti-ridge construction area is larger than the bottom size of the anti-ridge main body.
[0015] A counter-embedded groove is formed on the top of the waterproof layer, and a plurality of positioning ribs penetrate through the counter-embedded groove.
[0016] The cross section of the anti-ridge embedding groove is a trapezoidal structure that is wide at the top and narrow at the bottom, and the cross section bottom of the anti-ridge main body is a trapezoidal structure that matches the anti-ridge embedding groove, so that the bottom of the anti-ridge main body is matched and embedded in the anti-ridge embedding groove.
[0017] Compared with the prior art, the present invention has the following beneficial effects:
[0018] 1. The present invention adopts an anti-ridge main body, which is prefabricated in the factory according to the design requirements of the anti-ridge and transported to the site for installation. There is no need to cast the anti-ridge at one time on the construction site, which avoids the problem of positioning deviation that is easy to occur during the casting and molding process of the anti-ridge, thereby reducing the phenomenon of rework in the later stage and is conducive to controlling the construction period and cost of the anti-ridge construction.
[0019] 2. The present invention adopts an anti-ridge main body, positioning ribs and a waterproof layer. The positioning ribs are pre-buried in the anti-ridge construction area of the building component. The waterproof layer is poured in the anti-ridge construction area by waterproof mortar to form a waterproof structure at the bottom of the anti-ridge main body. The anti-ridge main body is plugged into the positioning ribs through the positioning holes, and the anti-ridge main body is connected to the building component as a whole by grouting, thereby ensuring the construction reliability and anti-seepage performance of the anti-ridge main body, and the requirements for construction technology are relatively low.
[0020] 3. Since the present invention constructs an anti-hump construction area whose size is larger than the anti-hump main body and an anti-hump embedding groove that matches and plugs with the anti-hump main body, it can adapt to the installation positioning error of the anti-hump main body through the anti-hump construction area, and further adapt to the installation positioning error of the anti-hump main body by reserving a positioning hole in the anti-hump main body that is larger than the space required for the arrangement of the positioning ribs. At the same time, it can also accurately and quickly locate the installation position of the anti-hump main body through the anti-hump embedding groove, thereby ensuring the construction quality and construction efficiency of the anti-hump. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a construction schematic diagram of step 1 and step 2 in the construction method of the prefabricated anti-ridge of the present invention;
[0022] Figure 2 It is a construction schematic diagram of step 3 in the construction method of the prefabricated anti-ridge of the present invention;
[0023] Figure 3It is a construction schematic diagram of step 4 in the construction method of the prefabricated anti-ridge of the present invention;
[0024] Figure 4 It is a construction schematic diagram of step 5 in the construction method of prefabricated anti-ridge of the present invention.
[0025] In the figure, 1c, 101 grouting hole, 102 positioning hole, 2 positioning rib, 3 anti-ridge construction area, 4 waterproof layer, 401 anti-ridge embedded groove. DETAILED DESCRIPTION
[0026] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
[0027] A construction method for a prefabricated anti-ridge comprises the following steps:
[0028] Please see attached Figure 1 , step 1: prefabricate and process the anti-ridge main body 1.
[0029] The anti-ridge main body 1 is provided with a grouting hole 101 and a positioning hole 102. The positioning hole 102 is located at the bottom of the anti-ridge main body 1 and penetrates downwardly through the anti-ridge 1. The bottom of the grouting hole 101 is connected to the positioning hole 102, and the grouting hole 101 penetrates upwardly through the anti-ridge main body 1.
[0030] The anti-ridge main body 1 can be prefabricated in the factory according to the design requirements of the building structure and transported to the site for installation, without the need for one-time pouring on site, thus avoiding the positioning deviation problem caused by one-time pouring, reducing the problem of rework in the later stage, and being beneficial to the control of construction period and cost.
[0031] The sizes of the grouting hole 101 and the positioning hole 102 can be adaptively reserved and formed in the anti-ridge main body 1 according to the size of the anti-ridge main body 1 and actual use requirements.
[0032] Please see attached Figure 1 , Step 2: Pre-embed a number of positioning bars 2 at intervals in the anti-slope construction area 3.
[0033] The lower end of the positioning rib 2 is embedded and fixed in the anti-ridge construction area 3 , the upper end of the positioning rib 2 extends above the anti-ridge construction area 3 , and the arrangement space of several positioning ribs 2 is smaller than the volume of the positioning hole 102 .
[0034] Preferably, the positioning ribs 2 can be made of steel bars. The positioning ribs 2 can be pre-buried simultaneously according to the design position of the counter-slope during the concrete pouring construction in the counter-slope construction area 3. The positioning ribs 2 can be used to fix the counter-slope main body 1 in the counter-slope construction area 3 and fasten it to the building components without the need for on-site roughening and pouring, which reduces the requirements for construction technology and can also reduce the problem of counter-slope leakage in the later stage.
[0035] The arrangement space of the plurality of positioning ribs 2 is smaller than the volume of the positioning hole 102 , so that a certain adjustment space can be provided when installing the anti-slope main body 1 , thereby avoiding the construction position deviation of the anti-slope main body 1 .
[0036] The plurality of positioning ribs 2 are arranged at intervals along the central axis of the anti-ridge construction area 3 .
[0037] Preferably, a plurality of positioning ribs 2 can be arranged in two parallel rows and symmetrically disposed on both sides of the central axis of the anti-slope construction area 3. The number and spacing of the positioning ribs 2 can be adjusted according to the size of the anti-slope body 1 to ensure that the anti-slope body 1 can be reliably tied and fixed to the building components through the positioning ribs 2.
[0038] The anti-ridge construction area 3 is a concave structure formed on a building component such as a roof, and the size of the anti-ridge construction area 3 is larger than the bottom size of the anti-ridge main body 1.
[0039] When constructing a building component such as a roof that needs to be constructed with a counter-bump, a counter-bump construction area 3 with a concave structure is formed on the building component to facilitate positioning and installing the counter-bump body 1. The counter-bump construction area 3 is larger than the bottom size of the counter-bump body 1, so that there is a certain adjustment space when the counter-bump body 1 is installed, which can further avoid the deviation of the construction position of the counter-bump body 1.
[0040] Please see attached Figure 2 , step 3: construct a waterproof layer 4 in the anti-ridge construction area 3, and a plurality of positioning ribs 2 penetrate the waterproof layer 4.
[0041] Preferably, the waterproof layer 4 can be formed by pouring waterproof mortar, which is used to fill the gap between the anti-ridge construction area 3 and the waterproof layer 4, and plays an effective waterproof role at the construction position of the anti-ridge main body 1.
[0042] A counter-embedded groove 401 is formed on the top of the waterproof layer 4 , and a plurality of positioning ribs 2 pass through the counter-embedded groove 401 .
[0043] The position and size of the anti-ridge embedding groove 401 are determined according to the design requirements of the anti-ridge. Through the setting of the anti-ridge embedding groove 401, the anti-ridge body 1 can be accurately positioned and installed.
[0044] Please see attached Figure 3 Step 4: Place the bottom of the anti-ridge main body 1 in the anti-ridge embedding groove 401 of the waterproof layer 4, and insert a plurality of positioning ribs 2 into the positioning holes 102.
[0045] The cross section of the anti-ridge embedding groove 401 is a trapezoidal structure that is wide at the top and narrow at the bottom. The cross section bottom of the anti-ridge body 1 is a trapezoidal structure that matches the anti-ridge embedding groove 401 , so that the bottom of the anti-ridge body 1 is matched and embedded in the anti-ridge embedding groove 401 .
[0046] By using the matching connection between the trapezoidal structure of the anti-slope embedding groove 401 and the bottom of the anti-slope main body 1, the anti-slope main body 1 can be quickly and accurately positioned and installed to avoid the construction position deviation of the anti-slope main body 1. At the same time, the concave groove structure of the anti-slope embedding groove 401 can improve the installation stability and reliability of the prefabricated anti-slope main body 1.
[0047] Please see attached Figure 4 Step 5: inject mortar into the anti-ridge main body 1, so that the mortar fills the gaps between the grouting holes 101 and the positioning holes 102 and the plurality of positioning ribs 2, and connects the anti-ridge main body 1 and the waterproof layer 4 with the building components to form a whole.
[0048] The mortar is injected from the grouting hole 101 on the top of the anti-slope main body 1 and flows downward into the positioning hole 102. After the mortar fills the gap between the positioning hole 102 and the positioning rib 2 and solidifies into shape, the anti-slope main body 1 is connected to the building component to form a whole, ensuring that the prefabricated anti-slope main body 1 is firmly installed on the building component.
[0049] The above are only preferred embodiments of the present invention and are not intended to limit the scope of protection of the invention. Therefore, any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A construction method for a prefabricated anti-ridge, characterized by: The following steps are involved: Step 1: Prefabricate and process the anti-ridge main body (1); Step 2: pre-embed a plurality of positioning bars (2) at intervals in the anti-slope construction area (3); Step 3: constructing a waterproof layer (4) in the anti-ridge construction area (3), and a plurality of positioning ribs (2) penetrate the waterproof layer (4); Step 4: placing the bottom of the anti-ridge main body (1) in the waterproof layer (4), and inserting a plurality of positioning ribs (2) into the positioning holes (102); Step 5: inject mortar into the anti-ridge main body (1) so that the anti-ridge main body (1) and the waterproof layer (4) are connected with the building components to form a whole.
2. The construction method of the prefabricated anti-ridge according to claim 1 is characterized in that: A grouting hole (101) and a positioning hole (102) are reserved in the anti-ridge main body (1); the positioning hole (102) is located at the bottom of the anti-ridge main body (1) and penetrates the anti-ridge (1) downward; the bottom of the grouting hole (101) is connected to the positioning hole (102); and the grouting hole (101) penetrates the anti-ridge main body (1) upward.
3. The construction method of the prefabricated anti-ridge according to claim 1 is characterized in that: The lower end of the positioning rib (2) is pre-buried and fixed in the anti-ridge construction area (3), the upper end of the positioning rib (2) extends above the anti-ridge construction area (3), and the arrangement space of a plurality of positioning ribs (2) is smaller than the volume of the positioning hole (102).
4. The construction method of the prefabricated anti-ridge according to claim 1 or 3 is characterized in that: The plurality of positioning ribs (2) are arranged at intervals along the central axis of the anti-ridge construction area (3).
5. The construction method of the prefabricated anti-ridge according to claim 4 is characterized in that: The anti-ridge construction area (3) is formed on the building component in a concave structure, and the size of the anti-ridge construction area (3) is larger than the bottom size of the anti-ridge main body (1).
6. The construction method of the prefabricated anti-ridge according to claim 1 is characterized by: A reverse ridge embedding groove (401) is formed on the top of the waterproof layer (4), and a plurality of positioning ribs (2) penetrate the reverse ridge embedding groove (401).
7. The construction method of the prefabricated anti-ridge according to claim 6 is characterized by: The cross section of the anti-ridge embedding groove (401) is a trapezoidal structure that is wide at the top and narrow at the bottom, and the cross section bottom of the anti-ridge main body (1) is a trapezoidal structure that matches the anti-ridge embedding groove (401), so that the bottom of the anti-ridge main body (1) is matched and embedded in the anti-ridge embedding groove (401).