Decoration robot man-machine collaborative construction operation method

By constructing a collaborative construction method of human-machine robots, the problems of single function and immature human-machine cooperation mode in the application of decoration robots are solved, and the close cooperation between multiple decoration robots and traditional decoration teams is achieved, and the construction is improved. Efficiency and coverage reduce costs and provide support for the intelligent transformation of the construction and decoration industry.

CN119083686APending Publication Date: 2024-12-06CHINA CONSTR FOURTH ENG DIV CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411301753.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-18
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The application of decoration robots in China is still in its infancy, facing problems such as single function, immature human-machine collaboration model, and high initial investment costs, which makes it difficult to fully utilize the advantages of efficiency and achieve full automation of construction.

Method used

Provide a method of collaborative construction of decoration robots, and by building a collaborative interlude operation model system, it realizes the close cooperation between various decoration robots and traditional decoration teams, and scientific and reasonable collaborative operation processes to improve construction efficiency and expand operation coverage. and reduce overall costs.

Benefits of technology

Through a comprehensive and efficient collaborative interspersed operation model system, we can improve construction efficiency, expand operation coverage and reduce overall costs, providing support for the intelligent transformation of the construction and decoration industry.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083686A_ABST
    Figure CN119083686A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building decoration, in particular to a decoration robot man-machine collaborative construction operation method, which comprises the following steps: S1, repairing an Nth layer of a wall surface base layer, and transferring after the repairing treatment is completed; s2, the (N-1) th layer is installed by manually hanging internal and external corner strips and ceiling gypsum boards; s3, manually scraping putty for the first time on the (N-2) th layer to ensure that the base surface is flat; s4, the (N-3) th layer adopts the putty coating robot to conduct second putty construction on the construction condition area, and meanwhile the area which cannot be covered by the putty coating robot is manually repaired; s5, a putty polishing robot is adopted for construction on the (N-4) th layer, and manual auxiliary polishing is conducted on the area which cannot be covered by the putty polishing robot; s6, an indoor cleaning robot is adopted to clean the ground on the (N-5) th floor, and the cleaning robot is manually transferred and maintained between households; and S7, the (N-6) th layer is subjected to finish paint spraying on the wall surface ceiling through a finish paint spraying robot, and special parts are arranged to be subjected to edge closing treatment manually.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of building decoration, and in particular to a decoration robot human-machine collaborative construction operation method. Background Art

[0002] As the global wave of industrial automation continues to advance, the traditional construction industry faces the dual challenges of labor shortage and rising costs. In this context, the use of robotics to replace manual construction has become a key path to promote the transformation and upgrading of the construction industry and improve production efficiency.

[0003] In the field of decoration, putty and topcoat construction are important links in fine decoration projects. Their standardization and high repeatability make this field an ideal scenario for the application of construction robots. In recent years, a number of technologically mature decoration robots have emerged in China, such as putty coating robots, putty grinding robots, latex paint spraying robots, etc. These robots have shown significant advantages in improving construction efficiency and reducing labor costs, and have gradually been applied in multiple engineering projects. By continuously optimizing and iterating existing technologies, decoration robots have made great progress in adapting to complex construction environments and improving construction quality.

[0004] However, despite important technological breakthroughs in decoration robots, their application in my country is still in its infancy and faces many challenges. The primary problem is the single function. Most of the decoration robots on the market currently only have a single operating capability and lack effective linkage between robots, making it difficult to give full play to their efficiency advantages. Secondly, the human-machine collaboration model is not yet mature, and it is difficult for construction robots to achieve full automation in actual construction. Human assistance is still required, but the specific process, interface division and interspersed operation mechanism of human-machine collaboration have yet to be clarified and improved. In addition, the high initial investment cost is also one of the important factors restricting the widespread application of decoration robots, including the purchase of equipment, transformation of the construction environment, and construction organization planning, which are all relatively large in the early stages. Summary of the invention

[0005] In order to overcome the shortcomings of the existing technology, the present application provides a human-machine collaborative construction operation method for decoration robots, aiming to fill the technical gap between decoration robots and traditional manual collaboration modes, and achieve close cooperation between various decoration robots and traditional decoration teams by constructing a comprehensive and efficient collaborative interspersed operation model system. Through a scientific and reasonable collaborative operation process, the construction efficiency is improved, the operation coverage is expanded, and the overall cost is reduced, providing strong support for the intelligent transformation of the building decoration industry.

[0006] The technical means adopted by the present invention to solve the technical problem is: a decoration robot human-machine collaborative construction operation method, the improvement of which is that the method includes: S1: repairing the wall base layer of the Nth layer and handing it over after completion; S2: manually hanging the yin and yang corner strips and installing the ceiling gypsum board on the N-1th layer; S3: manually scraping the first coat of putty on the N-2nd layer to ensure that the base surface is flat to meet the construction requirements of the putty coating robot; S4: the N-3rd layer uses the putty coating robot to carry out the second coat on the construction condition area Putty construction, and manual repairs are performed on areas that the putty coating robot cannot cover; S5: The N-4th floor is constructed using a putty polishing robot, and the wall and ceiling areas that have been puttyed twice are polished, and manual assisted polishing is performed on areas that the putty polishing robot cannot cover; S6: The N-5th floor uses an indoor cleaning robot to clean the floor, and the cleaning robot is manually transferred and maintained between households; S7: The N-6th floor uses a paint spraying robot to spray the walls and ceilings with paint, and manual finishing is arranged for special parts.

[0007] Step S1 described in the above technical solution includes: measuring the flatness and verticality of the walls and ceilings. If the concrete base does not meet the corresponding national standards, the labor team will be arranged to repair and smooth it in time.

[0008] Step S2 described in the above technical solution includes: hanging corner strips in advance in the inner and outer corners of the wall, installing the keel according to the elastic line position, the keel must be installed firmly and evenly spaced, fixing the cut gypsum board on the keel, and using seam tape and gypsum putty to cover the seams of the gypsum board and polish and level them.

[0009] Step S3 described in the above technical solution includes: mixing putty powder and clean water in a suitable proportion, and stirring thoroughly with a stirrer to ensure that there are no particles; using a scraper to evenly scrape the putty on the wall ceiling from top to bottom or from left to right, and the thickness is controlled between 1-2mm; after the putty is applied, it is naturally dried for 24 hours.

[0010] Step S4 described in the above technical solution includes: before work, set the starting height, ending height, running speed, robot movement speed and other parameters in the robot APP, and then click to start work; when polishing the ceiling, the height of the robot arm needs to be readjusted, and the joints of each putty need to be greater than 20cm; after the putty coating robot completes the construction work of a single household, it adopts the transfer mode to move to the next household, and special parts are manually trimmed. After the single layer of putty is applied, it is naturally dried in the shade for 24 hours.

[0011] In the above technical solution, before working, set the starting height, ending height, running speed, robot movement speed and other parameters in the robot APP, and then click to start work; the joint of each putty is greater than 10cm; the height of the robot arm needs to be readjusted when grinding the ceiling; the edges of the wall within 30cm from the ground, near the pipeline box, the entrance corridor and narrow space areas are manually finished with a handheld grinder or sandpaper.

[0012] Step S6 described in the above technical solution includes: before the cleaning robot starts working, manually clean up large debris, long steel wires, and large concrete stones in the house; lightly press the power button to start cleaning. After starting, the cleaning robot will autonomously plan the cleaning route according to the map generated by the scan, and clean each partition one by one by first cleaning along the wall and then filling in a "Z" shape; the terrain is relatively complex, and the space is narrow. The area is cleaned manually with a broom; after the cleaning robot has worked for a long time, the dust box needs to be cleaned in time; open the upper cover of the cleaning robot, press the dust box buckle to take out the dust box upwards, and pour the garbage in the box into the trash can; after injecting clean water into the dust box, close the dust box cover, shake it left and right, and pour out the dirty water; remove the filter, rinse it with water, and repeatedly rinse and pat the filter frame to knock out the dirt until it is clean, wipe the filter dry and put it back for continued use.

[0013] Step S7 described in the above technical solution includes: before work, set the starting height, ending height, running speed, robot moving speed and other parameters in the robot APP, and click to start work; when grinding the ceiling, the height of the robot arm needs to be readjusted, and each joint needs to be greater than 20cm. After the topcoat spraying robot completes the construction work of a single household, it moves to the next household in a transfer mode, and special parts are manually trimmed. After the putty coating and topcoat spraying robots complete their daily tasks, they need to be cleaned and maintained in time.

[0014] The timely cleaning and maintenance of the robot described in the above technical scheme includes: after the remaining putty and topcoat are discharged and recovered, an appropriate amount of clean water is injected, the reflux pipe of the putty coating robot or the topcoat spraying robot is placed in a waste barrel, and the reflux valve is opened for reflux until clean water flows back; the reflux valve is closed, the nozzle is aimed at the waste barrel, the spray gun is turned on to start circulating cleaning of the pipeline, and the hydraulic system pressure is gradually increased until clean water is sprayed out and the pipeline cleaning is completed; the spray gun filter and nozzle are removed, rinsed, and then installed back; finally, the entire machine and each laser ranging sensor are wiped to keep them clean. Then the robotic arm returns to zero and returns to the center, and the cleaning and maintenance are completed; the putty grinding robot needs to transfer the dust in its dust storage bag to the waste area, and then the entire machine is cleaned, the robotic arm returns to zero and returns to the center, and the maintenance is completed; after the construction of the indoor cleaning robot is completed, wipe the host body and mobile base with a soft dry cloth; transfer the robots to a dedicated charging area, turn off the power, and connect the power supply for charging in preparation for the next use; among them, before charging the indoor cleaning robot, the excess wires need to be put into the wire trough, and the charging base must be placed against the wall on a horizontal ground, the power supply must be connected, and there must be more than 0.5 meters on both sides of the charging base and more than 1 meter in front; press and hold the power button to start the charging base, and after the power indicator light is on, place the host on the charging base for charging.

[0015] Before step S1 described in the above technical solution, the method also includes: conducting construction planning briefings for the robot operation team and the robot team before construction, clarifying the responsibilities of each person, the robot operation path, safety precautions, etc.; placing the required putty powder, topcoat and other materials on the floor in advance, and ensuring normal water and power supply; using a construction elevator to transport the robot to the operating floor. The construction elevator must have a load-bearing capacity greater than 1000kg, a door opening height greater than 1.8m, and a door opening width greater than 1.2m to meet the robot's passage needs.

[0016] The beneficial effects of the present invention are: by constructing a comprehensive and efficient collaborative and interspersed operation model system, close cooperation between various decoration robots and traditional decoration teams is achieved, and through a scientific and reasonable collaborative operation process, construction efficiency is improved, operation coverage is expanded, and overall costs are reduced, providing strong support for the intelligent transformation of the building decoration industry. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 The present invention is a flowchart of a decoration robot human-machine collaborative construction method shown in an embodiment of the present invention. DETAILED DESCRIPTION

[0018] The present invention is further described below in conjunction with the accompanying drawings and embodiments.

[0019] The following will clearly and completely describe the concept, specific structure and technical effects of the present invention in combination with the embodiments and drawings, so as to fully understand the purpose, characteristics and effects of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, other embodiments obtained by technicians in this field without creative work are all within the scope of protection of the present invention. In addition, all the connection / connection relationships involved in the patent do not refer to the direct connection of components, but refer to the formation of a better connection structure by adding or reducing connection accessories according to the specific implementation situation. The various technical features in the invention can be combined interchangeably without conflicting with each other.

[0020] like Figure 1 As shown, the present application provides a decoration robot human-machine collaborative construction operation method, the method comprising:

[0021] S1: Repair the wall base of the Nth layer and hand it over after completion.

[0022] S2: The N-1th floor is manually hung with corner strips and installation of ceiling gypsum boards.

[0023] S3: The first coat of putty is manually scraped for the N-2 layer to ensure that the base surface is flat to meet the construction requirements of the putty coating robot.

[0024] S4: For the N-3 layer, a putty coating robot is used to apply a second coat of putty to the construction condition area, and at the same time, manual repairs are performed on the areas that cannot be covered by the putty coating robot.

[0025] S5: The N-4 layer is constructed using a putty grinding robot to grind the wall and ceiling areas that have been puttyed twice, and manual assisted grinding is performed on areas that cannot be covered by the putty grinding robot.

[0026] S6: The N-5th floor uses indoor cleaning robots to clean the floor, and manual cleaning robots are transferred and maintained between households.

[0027] S7: On the N-6th floor, a paint spraying robot is used to spray the walls and ceilings with paint, and manual finishing is arranged for special parts.

[0028] In a possible implementation, before step S1, the method further includes:

[0029] Before construction, the robot operation team and robot team will be briefed on the construction plan to clarify the responsibilities of each person, the robot operation path, safety precautions, etc.;

[0030] Place the required putty powder, topcoat and other materials on the floor in advance, and ensure normal water and power supply;

[0031] Use a construction elevator to transport the robot to the working floor. The construction elevator must have a load-bearing capacity greater than 1000kg, a door opening height greater than 1.8m, and a door opening width greater than 1.2m to meet the robot's passage needs.

[0032] Through detailed explanations to the robot operation team and construction personnel before construction, it is ensured that each participant is clear about their responsibilities, the robot's operation path and safety regulations. This clear division of labor and planning helps reduce communication barriers and errors during the construction process, thereby improving construction efficiency and ensuring the accuracy of robot operations.

[0033] In a possible implementation, step S1 includes:

[0034] The flatness and verticality of the walls and ceilings should be measured on the spot. If the concrete base does not meet the relevant national standards, the labor team should be arranged in time to repair and smooth it.

[0035] In a possible implementation, step S2 includes:

[0036] Hang corner strips in advance at the inner and outer corners of the wall, install the keel according to the elastic line position. The keel must be installed firmly and evenly spaced. Fix the cut gypsum board on the keel, use joint tape and gypsum putty to cover the joints of the gypsum board and grind and level them.

[0037] In a possible implementation, step S3 includes:

[0038] Mix putty powder and clean water in a suitable proportion and stir thoroughly with a blender to ensure that there are no particles. Use a scraper to apply the putty evenly on the wall and ceiling from top to bottom or from left to right. The thickness should be controlled between 1-2mm. After the putty is applied, let it dry naturally for 24 hours.

[0039] It is worth mentioning that steps S4-S6 are robot-constructed, so manual preparation is required before construction. Specifically, the preparation work includes:

[0040] 1) Turn on and connect to the APP: Turn on the robot's power button to power on the robot, use the tablet to connect to the robot's Wi-Fi, then open the robot APP, enter the connection interface, and set the connection parameters.

[0041] 2) Pre-operation inspection: After the equipment is successfully connected, check whether the robot equipment moves normally, whether the robot arm operates normally, and whether the nozzle and filter are blocked.

[0042] 3) Pressure test: Use clean water to test whether the robot is normal in a non-construction site, and turn on the hydraulic switch to pressurize the robot; if no water is sprayed out during the pressurization process, the hydraulic pipeline may be blocked, and the circuit needs to be checked to eliminate the fault.

[0043] 4) Material preparation: Mix putty powder and water in appropriate proportions and stir thoroughly with a stirrer. To prevent large particles in putty powder from clogging the nozzle, pour the mixed putty into a putty grinder and grind it thoroughly before putting it in a bucket for later use.

[0044] 5) Loading: Open the discharge valve to drain excess water, pour in putty, aim the nozzle at the waste bucket, turn on the nozzle switch until the putty is evenly sprayed out, turn off the nozzle switch, and the loading is completed.

[0045] 6) Adjust the robotic arm: operate the putty coating robot to move to the construction work surface, and adjust the distance between the putty coating robot and the work surface according to the laser positioning function of the putty robot so that the robotic arm can stretch freely to work.

[0046] At the same time, in order to cope with different work scenarios, the putty coating robot has three different working modes. When coating large surfaces, the automatic mode is adopted, which can enable the robot to automatically coat and move; the inching mode can be adopted in special areas, and manual control is performed by humans; when the robot is transferred between households, the transfer mode is adopted.

[0047] In a possible implementation, step S4 includes:

[0048] Before work, set the starting height, ending height, running speed, robot movement speed and other parameters in the robot APP, and click to start work; when polishing the ceiling, the height of the robot arm needs to be readjusted, and the joint of each putty needs to be greater than 20cm.

[0049] After the putty coating robot completes the construction work of a single household, it moves to the next household in transfer mode. Special parts are finished manually. After the single layer of putty is applied, it is naturally dried in the shade for 24 hours.

[0050] In a possible implementation, step S5 includes:

[0051] Before work, set the starting height, ending height, running speed, robot moving speed and other parameters in the robot APP, and click to start work; the joint of each putty is greater than 10cm; the height of the robot arm needs to be readjusted when polishing the ceiling;

[0052] Edge finishing is done manually using a hand-held grinder or sandpaper within 30 cm from the ground on the wall, near pipe boxes, in entrance hallways, and in narrow areas.

[0053] In a possible implementation, step S6 includes:

[0054] Before the cleaning robot starts working, the large debris, long steel bars and wires, and large concrete stones in the house should be cleaned up manually in advance;

[0055] Press the power button to start cleaning. After starting, the robot vacuum cleaner will autonomously plan the cleaning route according to the map generated by scanning. It will clean each partition one by one by first cleaning along the wall and then filling in a "Z" shape.

[0056] The terrain is relatively complex, and the narrow space area is cleaned manually with a broom;

[0057] After the cleaning robot has been working for a long time, the dust box needs to be cleaned in time; open the upper cover of the cleaning robot, press the dust box buckle to take out the dust box upwards, and pour the garbage in the box into the trash can; after injecting clean water into the dust box, close the dust box cover, shake it left and right, and pour out the dirty water; remove the filter, rinse it with water, and repeatedly rinse and tap the filter frame to knock out the dirt until it is clean, wipe the filter dry and put it back for continued use.

[0058] In a possible implementation, step S7 includes:

[0059] Before work, set the starting height, ending height, running speed, robot movement speed and other parameters in the robot APP, and click to start work; when grinding the ceiling, the height of the robot arm needs to be readjusted, and each joint must be greater than 20cm.

[0060] After the topcoat spraying robot completes the construction work of a single household, it moves to the next household in transfer mode, and special parts are finished manually.

[0061] After the putty coating and topcoat spraying robots complete their daily tasks, they need to be cleaned and maintained in a timely manner.

[0062] Optionally, the timely cleaning and maintenance of the robot includes:

[0063] After the remaining putty and topcoat are discharged and recovered, inject an appropriate amount of clean water, place the reflux pipe of the putty coating robot or topcoat spraying robot in the waste bucket, open the reflux valve for reflux, and reflux until clean water flows out;

[0064] Close the return valve, aim the nozzle at the waste barrel, open the spray gun and start circulating the cleaning pipeline, gradually increase the hydraulic system pressure until clear water is sprayed out, and the pipeline cleaning is completed;

[0065] Remove the spray gun filter and nozzle, rinse them, and then install them back;

[0066] Finally, wipe the whole machine and each laser distance sensor to keep them clean. Then return the robot arm to zero and the cleaning and maintenance is complete;

[0067] The putty grinding robot needs to transfer the dust in its dust storage bag to the waste area, then clean the whole machine, return the robot arm to zero and return to the normal position, and the maintenance is completed;

[0068] After the indoor cleaning robot is finished, use a soft dry cloth to wipe the main body and mobile base;

[0069] Move the robots to a dedicated charging area, turn off the power, and connect them to a power source for charging in preparation for next use. For indoor cleaning robots, put excess wires into the wire trough before charging, place the charging base against the wall on a horizontal surface, connect the power source, and ensure that there is more than 0.5 meters of space on both sides of the charging base and more than 1 meter of space in front. Press and hold the power button to start the charging base, and after the power indicator light is on, place the main unit on the charging base for charging.

[0070] This application builds a comprehensive and efficient collaborative and interspersed operation model system to achieve close cooperation between various decoration robots and traditional decoration teams. Through a scientific and reasonable collaborative operation process, it improves construction efficiency, expands operation coverage and reduces overall costs, providing strong support for the intelligent transformation of the building decoration industry.

[0071] The above is a specific description of the preferred implementation of the present invention, but the invention is not limited to the embodiments. Those skilled in the art can make various equivalent modifications or substitutions without violating the spirit of the present invention. These equivalent modifications or substitutions are all included in the scope defined by the claims of this application.

Claims

1. A decoration robot human-machine collaborative construction method, characterized in that: The method comprises: S1: Repair the wall base of the Nth layer and hand it over after completion; S2: The N-1 layer is manually hung with corner strips and ceiling gypsum board installation; S3: The N-2 layer is manually puttyed for the first time to ensure that the base surface is flat to meet the construction requirements of the putty coating robot; S4: The N-3 layer uses a putty coating robot to apply a second coat of putty to the construction condition area, and at the same time, the area that the putty coating robot cannot cover is repaired manually; S5: The N-4 layer is constructed using a putty grinding robot to grind the wall and ceiling areas that have been puttyed twice, and manually assist in grinding the areas that cannot be covered by the putty grinding robot; S6: The N-5th floor uses indoor cleaning robots to clean the floor, and manual cleaning robots are transferred and maintained between households; S7: On the N-6th floor, a paint spraying robot is used to spray the walls and ceilings with paint, and manual finishing is arranged for special parts.

2. The decoration robot human-machine collaborative construction method according to claim 1 is characterized in that: The step S1 comprises: The flatness and verticality of the walls and ceilings should be measured on the spot. If the concrete base does not meet the relevant national standards, the labor team should be arranged in time to repair and smooth it.

3. The decoration robot human-machine collaborative construction method according to claim 1 is characterized in that: The step S2 comprises: Hang corner strips in advance at the inner and outer corners of the wall, install the keel according to the elastic line position. The keel must be installed firmly and evenly spaced. Fix the cut gypsum board on the keel, use joint tape and gypsum putty to cover the joints of the gypsum board and grind and level them.

4. The decoration robot human-machine collaborative construction method according to claim 1, characterized in that: The step S3 comprises: Mix putty powder and clean water in a suitable proportion and stir thoroughly with a blender to ensure that there are no particles. Use a scraper to apply the putty evenly on the wall and ceiling from top to bottom or from left to right. The thickness should be controlled between 1-2mm. After the putty is applied, let it dry naturally for 24 hours.

5. The decoration robot human-machine collaborative construction method according to claim 1, characterized in that: The step S4 comprises: Before work, set the starting height, ending height, running speed, robot moving speed and other parameters in the robot APP, and click to start work; when grinding the ceiling, the height of the robot arm needs to be readjusted, and the joint of each putty needs to be greater than 20cm; After the putty coating robot completes the construction work of a single household, it moves to the next household in transfer mode. Special parts are finished manually. After the single layer of putty is applied, it is naturally dried in the shade for 24 hours.

6. The decoration robot human-machine collaborative construction method according to claim 1, characterized in that: The step S5 comprises: Before work, set the starting height, ending height, running speed, robot moving speed and other parameters in the robot APP, and click to start work; the joint of each putty is greater than 10cm; the height of the robot arm needs to be readjusted when polishing the ceiling; Edge finishing is done manually using a hand-held grinder or sandpaper within 30 cm from the ground on the wall, near pipe boxes, in entrance hallways, and in narrow areas.

7. The decoration robot human-machine collaborative construction method according to claim 1, characterized in that: The step S6 comprises: Before the cleaning robot starts working, the large debris, long steel bars and wires, and large concrete stones in the house should be cleaned up manually in advance; Press the power button to start cleaning. After starting, the robot vacuum cleaner will autonomously plan the cleaning route according to the map generated by scanning. It will clean each partition one by one by first cleaning along the wall and then filling in a "Z" shape. The terrain is relatively complex, and the narrow space area is cleaned manually with a broom; After the cleaning robot has been working for a long time, the dust box needs to be cleaned in time; open the upper cover of the cleaning robot, press the dust box buckle to take out the dust box upwards, and pour the garbage in the box into the trash can; after injecting clean water into the dust box, close the dust box cover, shake it left and right, and pour out the dirty water; remove the filter, rinse it with water, and repeatedly rinse and tap the filter frame to knock out the dirt until it is clean, wipe the filter dry and put it back for continued use.

8. The decoration robot human-machine collaborative construction method according to claim 1, characterized in that: The step S7 comprises: Before work, set the starting height, ending height, running speed, robot moving speed and other parameters in the robot APP, and click to start work; when grinding the ceiling, the height of the robot arm needs to be readjusted, and each joint needs to be greater than 20cm; After the topcoat spraying robot completes the construction work of a single household, it moves to the next household in a transfer mode, and the special parts are manually finished; After the putty coating and topcoat spraying robots complete their daily tasks, they need to be cleaned and maintained in a timely manner.

9. The decoration robot human-machine collaborative construction method according to claim 8, characterized in that: The timely cleaning and maintenance of the robot includes: After the remaining putty and topcoat are discharged and recovered, inject an appropriate amount of clean water, place the reflux pipe of the putty coating robot or topcoat spraying robot in the waste bucket, open the reflux valve for reflux, and reflux until clean water flows out; Close the return valve, aim the nozzle at the waste barrel, open the spray gun and start circulating the cleaning pipeline, gradually increase the hydraulic system pressure until clear water is sprayed out, and the pipeline cleaning is completed; Remove the spray gun filter and nozzle, rinse them, and then install them back; Finally, wipe the whole machine and each laser distance sensor to keep them clean; then return the robot arm to zero and return to the normal position, and the cleaning and maintenance are completed; The putty grinding robot needs to transfer the dust in its dust storage bag to the waste area, then clean the whole machine, return the robot arm to zero and return to normal, and the maintenance is completed; After the indoor cleaning robot is finished, use a soft dry cloth to wipe the main body and mobile base; Move the robots to a dedicated charging area, turn off the power, and connect them to a power source for charging in preparation for next use. For indoor cleaning robots, put excess wires into the wire trough before charging, place the charging base against the wall on a horizontal surface, connect the power source, and ensure that there is more than 0.5 meters of space on both sides of the charging base and more than 1 meter of space in front. Press and hold the power button to start the charging base, and after the power indicator light is on, place the main unit on the charging base for charging.

10. The decoration robot human-machine collaborative construction method according to claim 1, characterized in that: Before step S1, the method further includes: Before construction, the robot operation team and robot team will be briefed on the construction plan to clarify the responsibilities of each person, the robot operation path, safety precautions, etc.; Place the required putty powder, topcoat and other materials on the floor in advance, and ensure normal water and power supply; Use a construction elevator to transport the robot to the working floor. The construction elevator must have a load-bearing capacity greater than 1000kg, a door opening height greater than 1.8m, and a door opening width greater than 1.2m to meet the robot's passage needs.