Control surface layer concrete protection layer device and construction technology

Through the coordination of cross beams and positioning components, the position and height of the steel mesh is adjusted, and the problems of cumbersome installation and high cost of steel mesh in the prior art are solved, thereby achieving efficient construction and cost savings of the concrete protective layer.

CN119102153APending Publication Date: 2024-12-10CCCC THIRD HARBOR ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411469147.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-21
Publication Date
2024-12-10

AI Technical Summary

Technical Problem

In the existing concrete surface layer construction technology, the steel mesh is prone to collapse and lift when it is under load, resulting in increased difficulty in controlling the thickness of the protective layer, cumbersome and high cost.

Method used

Using a device including cross beams, positioning components and vertical support components, the position and height of the steel mesh is adjusted through hooks and hydraulic telescopic cylinders to ensure that the steel mesh is accurately laid and positioned before concrete pouring, reducing the use of steel braces and simplifying the The installation process was completed.

Benefits of technology

It improves the installation efficiency and accuracy of steel mesh, saves material and labor costs, reduces the risk of surface cracking and rework costs, and significantly reduces construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119102153A_ABST
    Figure CN119102153A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of concrete protection layers, and discloses a control surface layer concrete protection layer device and a construction technology, the control surface layer concrete protection layer device comprises a plurality of cross beams, and the cross beams are arranged in parallel. According to the control surface layer concrete protection layer device, before concrete pouring, a reinforcing mesh is laid in a to-be-poured area, an on-site operator enables a cross beam to stretch across the two sides of a formwork, the top elevation of the reinforcing mesh elevation adjusting device is adjusted, the reinforcing mesh is lifted up by a constructor and tightly attached to a hook for limiting, and then concrete pouring is conducted; before initial setting of concrete, all the hooks are twisted to be separated from the reinforcing mesh, the device is integrally dismantled, the hooks are trimmed, the cross beams hang the reinforcing mesh through the hooks to transmit vertical loads, the vertical supporting assemblies roughly adjust the elevation of the reinforcing mesh, the positioning assemblies finely adjust the elevation of the reinforcing mesh, and the hooks and the reinforcing mesh are tightly attached and limited. The steel bar mesh elevation device is convenient to use and can be repeatedly used, and the cost is saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of concrete protective layers, and in particular to a control surface concrete protective layer device and a construction process. Background Art

[0002] At present, the construction of concrete surface layer has a relatively mature construction technology. Combined with the characteristics of the engineering structure, a layer of steel mesh is arranged in the concrete of the container stack surface. The fineness of the thickness control of the steel mesh protective layer not only affects the appearance quality and cracks of the surface concrete, but also directly determines the durability and service life of the concrete, affects the construction quality, and reflects the production process and technical level of the construction unit.

[0003] During the surface pouring process, the steel mesh bears the load from the construction workers and the concrete pouring, which can easily cause the steel mesh to collapse in the middle and warp around, increasing the difficulty of controlling the thickness of the protective layer. Therefore, in the steel mesh installation process, the steel bars are processed into stirrups according to the thickness of the structural layer and the protective layer, the stirrup spacing is reasonably arranged, the thickness of the surface protective layer is controlled, and the steel stirrups and the steel mesh are tied as a whole. The installation process requires the processing, installation, and tying of steel stirrups. The process is relatively cumbersome, which not only increases the workload, but also consumes a large amount of stirrup steel bars, increasing the cost. Summary of the invention

[0004] In view of the deficiencies in the prior art, the present invention provides a control surface concrete protective layer device and a construction process, which solves the problems mentioned in the above background.

[0005] The present invention provides the following technical solution: a device for controlling a surface concrete protective layer, comprising: a plurality of beams, wherein the plurality of beams are arranged parallel to each other, a plurality of installation grooves are opened on the surface of each beam, and a positioning assembly for limiting a steel mesh is arranged in the installation groove, a docking assembly is arranged at both ends of each beam, and a vertical support assembly is connected to the bottom of the docking assembly;

[0006] The positioning assembly includes a threaded sleeve and a hook, wherein the threaded sleeve is mounted on the inner wall of the mounting groove, and the hook is mounted on the inner wall of the threaded sleeve;

[0007] The docking assembly includes a bracket, a fixing pin and a pipe seat, wherein the pipe seat is connected to the bottom of the bracket, the surface of the crossbeam is connected to the inner wall of the bracket, a pin hole is provided on the surface of the bracket, a limiting hole is provided on the surface of the crossbeam corresponding to the pin hole, and the inner walls of the limiting hole and the pin hole are both connected to the surface of the fixing pin;

[0008] The vertical support assembly comprises a hydraulic telescopic cylinder and a bottom plate, wherein the bottom plate is connected to the bottom of the hydraulic telescopic cylinder, and the pipe seat is installed at the telescopic end of the hydraulic telescopic cylinder.

[0009] Preferably, the hook comprises a threaded section, one end of the threaded section is integrally connected with a handle, the other end of the threaded section is integrally connected with a connecting section, and one end of the connecting section is integrally connected with a hook portion;

[0010] The surface of the threaded section is threadedly connected to the inner wall of the threaded sleeve.

[0011] Preferably, the length of the connecting section is 5 cm, the length of the hook portion is 2 cm, and the length of the handle is 10 cm.

[0012] Preferably, the crossbeam is made of a galvanized square tube, and the outer side length of the cross section of the galvanized square tube is 150 mm×150 mm, and the thickness of the galvanized square tube is 6 mm.

[0013] Preferably, a spring is installed on the inner wall of the tube seat, the top end of the spring is connected to a top plate, a through slot is provided at the bottom of the bracket, and the top of the top plate passes through the through slot and is connected to the bottom of the crossbeam.

[0014] A construction process for a control surface concrete protective layer device comprises the following steps:

[0015] Step S1, making a crossbeam: the length of the crossbeam is determined according to the width of the concrete protective layer of the control surface layer, the number and spacing of the threaded sleeves are determined according to the width of the cast concrete protective layer and the size of the steel mesh, and the hook inside the threaded sleeve is ensured to be staggered with the longitudinal steel bars of the steel mesh. The crossbeam is made of a galvanized square tube with an outer side length of 150mm×150mm and a thickness of 6mm;

[0016] Step S2, installing the vertical support assembly: in order to make the entire device evenly bear the tensile force and facilitate the displacement of the entire device, the hook is installed in the sleeve of the beam, and the vertical support assemblies are installed at both ends of each beam, and the ends of the beams are docked with the vertical support assemblies through docking assemblies, so that the entire device is connected as a whole;

[0017] Step S3, installing the formwork, tie rods and steel mesh;

[0018] Step S4, installing the control surface concrete cover device, the on-site operator places the beam across both sides of the formwork, and the vertical support assembly is located on the outside of the formwork;

[0019] Step S5, disassembling the control surface concrete protective layer device: before the initial setting of the concrete, all hooks are twisted to separate from the steel mesh, the device is dismantled as a whole, and the hook parts are trimmed.

[0020] Preferably, in step S2, the bottom plate of the vertical support assembly provides a support surface for the overall control surface concrete protective layer device to prevent the control surface concrete protective layer device from overturning, and the hydraulic telescopic cylinder of the vertical support assembly adjusts the vertical displacement and the elevation of the crossbeam, thereby adjusting the position of the steel mesh and thereby roughly adjusting the thickness of the control surface concrete protective layer.

[0021] Preferably, in step S2, the end of the crossbeam is clamped into the interior of the bracket of the docking assembly, and the position is fixed using the fixing pin of the docking assembly.

[0022] Preferably, in step S3, before pouring concrete, the pouring formwork is fixed, and the tie rod is installed on the formwork, and the steel mesh is laid in the area to be poured.

[0023] Preferably, in step S4, the spacing between adjacent control surface concrete protective layer devices should be adjusted according to the size of the steel mesh for ease of construction, generally 2m is appropriate, and the top elevation of the hydraulic telescopic cylinder is adjusted according to the elevation of the steel mesh, and then the height of the beam is adjusted, and the construction personnel lift the steel mesh and limit it tightly with the hook, and then pour the concrete.

[0024] Compared with the prior art, the present invention has the following beneficial effects:

[0025] 1. The present invention, by arranging a crossbeam, a positioning assembly and a vertical support assembly, lays a steel mesh in the area to be poured before concrete is poured, and the on-site operator places the crossbeam across both sides of the template, adjusts the top elevation of the steel mesh elevation adjustment device, and the construction personnel lift the steel mesh and limit it closely with the hook, and then pours concrete, and before the initial setting of the concrete, all the hooks are twisted to separate from the steel mesh, the device is dismantled as a whole, and the hooks are repaired, and the crossbeam suspends the steel mesh through the hooks to transfer the vertical load, the vertical support assembly performs a rough adjustment on the steel mesh elevation, and the positioning assembly performs a fine adjustment on the steel mesh elevation, and the hooks and the steel mesh are closely limited to ensure the steel mesh elevation, which is easy to use, reusable, and cost-saving.

[0026] 2. The present invention provides a docking assembly, wherein the crossbeam is installed in the bracket and the position is fixed by a fixing pin, so that the vertical support assembly and the crossbeam can be docked conveniently.

[0027] 3. The present invention eliminates the use of steel stirrups in the steel protection layer control process, which can be used in a cyclical manner, saving material costs and production labor costs. The improved quality reduces the rework costs caused by surface layer cracking, and the benefits are obvious. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a schematic diagram of the three-dimensional structure of the present invention;

[0029] Figure 2 It is a front view structural schematic diagram of the present invention;

[0030] Figure 3 It is a side view structural schematic diagram of the present invention;

[0031] Figure 4 It is a schematic diagram of the side section structure of the docking assembly of the present invention;

[0032] Figure 5 This is a schematic diagram of the explosion structure of the crossbeam and the threaded sleeve of the present invention;

[0033] Figure 6 This is a schematic diagram of the hook structure of the present invention;

[0034] Figure 7 It is a schematic diagram of the construction process flow of the control surface concrete protective layer device of the present invention.

[0035] In the figure: 1. crossbeam; 2. mounting groove; 3. positioning assembly; 31. threaded sleeve; 32. hook; 321. handle; 322. threaded section; 323. connecting section; 324. hook portion; 4. vertical support assembly; 41. hydraulic telescopic cylinder; 42. bottom plate; 5. steel mesh; 6. template; 7. pull rod; 8. docking assembly; 81. bracket; 82. fixing pin; 83. pipe seat; 9. spring; 10. top plate. DETAILED DESCRIPTION

[0036] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0037] See also Figure 1-7A device and construction process for controlling a surface concrete protective layer, comprising: a plurality of crossbeams 1, and the plurality of crossbeams 1 are arranged parallel to each other, a plurality of installation grooves 2 are provided on the surface of each crossbeam 1, and a positioning component 3 for limiting a steel mesh 5 is provided in the installation groove 2, a docking component 8 is provided at both ends of each crossbeam 1, and a vertical support component 4 is connected to the bottom of the docking component 8, the positioning component 3 comprises a threaded sleeve 31 and a hook 32, the threaded sleeve 31 is installed on the inner wall of the installation groove 2, and the hook 32 is installed on the inner wall of the threaded sleeve 31, the docking component 8 comprises a bracket 81, a fixing pin 82 and a pipe seat 83, the pipe seat 83 is connected to the bottom of the bracket 81, the surface of the crossbeam 1 is connected to the inner wall of the bracket 81, a pin hole is provided on the surface of the crossbeam 1 corresponding to the pin hole, a limiting hole is provided on the surface of the crossbeam 1 corresponding to the pin hole, and the inner walls of the limiting hole and the pin hole are connected to the surface of the fixing pin 82, the vertical support component Component 4 includes a hydraulic telescopic cylinder 41 and a base plate 42, the base plate 42 is connected to the bottom of the hydraulic telescopic cylinder 41, and the pipe seat 83 is installed at the telescopic end of the hydraulic telescopic cylinder 41. Before pouring concrete, the steel mesh 5 is laid in the area to be poured, and the on-site operator places the crossbeam 1 across both sides of the template 6. The top elevation of the steel mesh 5 elevation adjustment device is lifted by the construction personnel and is tightly limited with the hook 32, and then the concrete is poured. Before the initial setting of the concrete, all the hooks 32 are twisted to separate from the steel mesh 5, the device is dismantled as a whole, and the hook 32 is repaired. The crossbeam 1 hangs the steel mesh 5 through the hook 32 to transfer the vertical load, the vertical support component 4 roughly adjusts the elevation of the steel mesh 5, and the positioning component 3 finely adjusts the elevation of the steel mesh 5. The hook 32 is tightly limited with the steel mesh 5 to ensure the elevation of the steel mesh 5. It is easy to use and can be reused, saving costs.

[0038] The hook 32 includes a threaded section 322 , one end of which is integrally connected to a handle 321 , the other end of which is integrally connected to a connecting section 323 , one end of which is integrally connected to a hook portion 324 , and the surface of the threaded section 322 is threadedly connected to the inner wall of the threaded sleeve 31 .

[0039] The length of the connecting section 323 is 5 cm, the length of the hook portion 324 is 2 cm, and the length of the handle 321 is 10 cm.

[0040] The crossbeam 1 is made of a galvanized square tube, and the outer side length of the cross section of the galvanized square tube is 150 mm×150 mm, and the thickness of the galvanized square tube is 6 mm.

[0041] In a specific embodiment, a spring 9 is installed on the inner wall of the tube seat 83, and the top of the spring 9 is connected to the top plate 10. A through groove is opened at the bottom of the bracket 81, and the top of the top plate 10 passes through the through groove and is connected to the bottom of the beam 1. After the beam 1 is docked into the bracket 81, the spring 9 pushes the top plate 10 to support the beam 1, so that the beam 1 supports the fixing pin 82, so that the beam 1 is not easy to shake.

[0042] A construction process for a control surface concrete protective layer device, characterized in that it comprises the following steps:

[0043] Step S1, manufacturing the cross beam 1: determining the length of the cross beam 1 according to the width of the control surface concrete protective layer, determining the number and spacing of the threaded sleeves 31 according to the width of the cast concrete protective layer and the size of the steel mesh 5, ensuring that the hook 32 inside the threaded sleeve 31 is staggered with the longitudinal steel bars of the steel mesh 5, and the cross beam 1 is manufactured using a galvanized square tube with an outer side length of 150 mm × 150 mm and a thickness of 6 mm;

[0044] Step S2, installing the vertical support assembly 4: In order to make the entire device evenly bear the tensile force and facilitate the displacement of the entire device, the hook 32 is installed in the sleeve of the beam 1, and the vertical support assembly 4 is installed at both ends of each beam 1, and the end of the beam 1 is docked with the vertical support assembly 4 through the docking assembly 8, so that the entire device is connected as a whole;

[0045] Step S3, installing the template 6, the tie rod 7 and the steel mesh 5;

[0046] Step S4, installing the control surface concrete protective layer device, the on-site operator places the beam 1 across both sides of the template 6, and the vertical support assembly 4 is located on the outside of the template 6;

[0047] Step S5, disassembling the control surface concrete protective layer device: before the initial setting of the concrete, all the hooks 32 are twisted to separate from the steel mesh 5, the device is completely dismantled, and the hook 32 part is trimmed.

[0048] In step S2, the bottom plate 42 of the vertical support assembly 4 provides a support surface for the overall control surface concrete protective layer device to prevent the control surface concrete protective layer device from overturning. The hydraulic telescopic cylinder 41 of the vertical support assembly 4 adjusts the vertical displacement and the elevation of the beam 1, and can adjust the position of the steel mesh 5, thereby roughly adjusting the thickness of the control surface concrete protective layer.

[0049] In step S2 , the end of the crossbeam 1 is clamped into the interior of the bracket 81 of the docking assembly 8 , and the position is fixed using the fixing pin 82 of the docking assembly 8 .

[0050] In step S3, before pouring concrete, the pouring formwork 6 is fixed, and the tie rod 7 is installed on the formwork 6, and the steel mesh 5 is laid in the area to be poured.

[0051] In step S4, the spacing between the adjacent control surface concrete protection layer devices should be adjusted according to the size of the steel mesh 5 for ease of construction, generally 2m is appropriate, and the top elevation of the hydraulic telescopic cylinder 41 is adjusted according to the elevation of the steel mesh 5, and then the height of the beam 1 is adjusted, and the construction personnel lift the steel mesh 5 and close it to the hook 32 for limiting, and then pour the concrete.

[0052] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A device for controlling a surface concrete protective layer, characterized in that: include: A plurality of cross beams (1), wherein the plurality of cross beams (1) are arranged parallel to each other, a plurality of installation grooves (2) are provided on the surface of each cross beam (1), and a positioning component (3) for limiting the position of a steel mesh (5) is provided in the installation groove (2), and a docking component (8) is provided at both ends of each cross beam (1), and a vertical support component (4) is connected to the bottom of the docking component (8); The positioning assembly (3) comprises a threaded sleeve (31) and a hook (32), wherein the threaded sleeve (31) is mounted on the inner wall of the mounting groove (2), and the hook (32) is mounted on the inner wall of the threaded sleeve (31); The docking assembly (8) comprises a bracket (81), a fixing pin (82) and a pipe seat (83), wherein the pipe seat (83) is connected to the bottom of the bracket (81), the surface of the crossbeam (1) is connected to the inner wall of the bracket (81), a pin hole is provided on the surface of the bracket (81), a limiting hole is provided on the surface of the crossbeam (1) corresponding to the pin hole, and the inner walls of the limiting hole and the pin hole are both connected to the surface of the fixing pin (82); The vertical support assembly (4) comprises a hydraulic telescopic cylinder (41) and a base plate (42), wherein the base plate (42) is connected to the bottom of the hydraulic telescopic cylinder (41), and the pipe seat (83) is installed at the telescopic end of the hydraulic telescopic cylinder (41).

2. A control surface concrete protective layer device according to claim 1, characterized in that: The hook (32) comprises a threaded section (322), one end of the threaded section (322) is integrally connected to a handle (321), the other end of the threaded section (322) is integrally connected to a connecting section (323), and one end of the connecting section (323) is integrally connected to a hook portion (324); The surface of the threaded section (322) is threadedly connected to the inner wall of the threaded sleeve (31).

3. A control surface concrete protective layer device according to claim 2, characterized in that: The length of the connecting section (323) is 5 cm, the length of the hook portion (324) is 2 cm, and the length of the handle (321) is 10 cm.

4. A control surface concrete protective layer device according to claim 1, characterized in that: The crossbeam (1) is made of a galvanized square tube, and the outer side length of the cross section of the galvanized square tube is 150 mm×150 mm, and the thickness of the galvanized square tube is 6 mm.

5. A control surface concrete protective layer device according to claim 1, characterized in that: A spring (9) is installed on the inner wall of the pipe seat (83), the top end of the spring (9) is connected to a top plate (10), a through slot is provided at the bottom of the bracket (81), and the top of the top plate (10) passes through the through slot and is connected to the bottom of the crossbeam (1).

6. A construction process for controlling a surface concrete protective layer device, characterized in that: The following steps are involved: Step S1, manufacturing the cross beam (1): the length of the cross beam (1) is determined according to the width of the concrete protective layer of the control surface layer, the number and spacing of the threaded sleeves (31) are determined according to the width of the cast concrete protective layer and the size of the steel mesh (5), and the hook (32) inside the threaded sleeve (31) is ensured to be staggered with the longitudinal steel bars of the steel mesh (5), and the cross beam (1) is manufactured using a galvanized square tube with an outer side length of 150 mm×150 mm and a thickness of 6 mm; Step S2, installing the vertical support assembly (4): in order to make the entire device evenly bear the tensile force and facilitate the displacement of the entire device, the hook (32) is installed in the sleeve of the crossbeam (1), and the vertical support assembly (4) is installed at both ends of each crossbeam (1), and the end of the crossbeam (1) is docked with the vertical support assembly (4) through a docking assembly (8), so that the entire device is connected as a whole; Step S3, installing the template (6), the tie rod (7) and the steel mesh (5); Step S4, installing the control surface concrete protective layer device, the on-site operator places the crossbeam (1) across the two sides of the formwork (6), and the vertical support assembly (4) is located on the outside of the formwork (6); Step S5, disassembling the control surface concrete protective layer device: before the concrete begins to set, all the hooks (32) are twisted to separate from the steel mesh (5), the device is dismantled as a whole, and the hook (32) part is trimmed.

7. The construction process of the control surface concrete protective layer device according to claim 6 is characterized in that: In step S2, the bottom plate (42) of the vertical support assembly (4) provides a support surface for the overall control surface layer concrete protective layer device to prevent the control surface layer concrete protective layer device from overturning. The hydraulic telescopic cylinder (41) of the vertical support assembly (4) adjusts the vertical displacement and the elevation of the crossbeam (1), thereby adjusting the position of the steel mesh (5) and thereby roughly adjusting the thickness of the control surface layer concrete protective layer.

8. The construction process of the control surface concrete protective layer device according to claim 7 is characterized in that: In the step S2, the end of the crossbeam (1) is clamped into the interior of the bracket (81) of the docking assembly (8), and the position is fixed using the fixing pin (82) of the docking assembly (8).

9. The construction process of the control surface concrete protective layer device according to claim 8 is characterized in that: In the step S3, before pouring concrete, the pouring template (6) is fixed, and the tie rod (7) is installed on the template (6), and the steel mesh (5) is laid in the area to be poured.

10. The construction process of the control surface concrete protective layer device according to claim 9, characterized in that: In step S4, the spacing between the adjacent control surface layer concrete protective layer devices should be adjusted according to the size of the steel mesh (5) for ease of construction, and 2 m is generally appropriate. The top elevation of the hydraulic telescopic cylinder (41) is adjusted according to the elevation of the steel mesh (5), and then the height of the crossbeam (1) is adjusted. The construction personnel lift the steel mesh (5) and close it to the hook (32) for limiting, and then pouring concrete.