Rapid disassembly construction method for large-size high-formwork plate buckle frame
Through the combination of modular brackets and transportation hooks, the rapid disassembly of large-volume high-support mold clasp is achieved, solving the problem of low removal efficiency, improving construction efficiency and safety, and reducing cost and environmental impact.
Patent Information
- Application Number
- CN202411236908.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-05
- Publication Date
- 2024-12-10
- Estimated Expiration
- 2044-09-05
AI Technical Summary
Large-volume high-support mold clasp is not easy to remove after construction is completed, especially when space is limited, the removal efficiency is low, which affects construction efficiency and safety.
Modular bracket design and transportation hook device are adopted. By removing the connections between the module bracket and the structure, the module bracket is transported out one by one with the transportation hook, and the support column and guide rail are removed. Combined with the sliding design of the guide rail and transportation hook, it can achieve rapid disassembly and repeat. use.
It improves construction efficiency and safety, shortens construction cycle, reduces material costs and labor intensity, ensures the stability and safety of the brackets, and promotes sustainable development.
Smart Images

Figure CN119102369A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of supporting buildings, and in particular to a method for quickly disassembling a large-volume high-support formwork buckle frame. Background Art
[0002] Large-volume high-support formwork disc buckle frame is a scaffolding system widely used in the construction industry. It is particularly suitable for projects that require high-support formwork, such as high-rise building construction, road and bridge construction, etc. Large-volume high-support formwork disc buckle frame is mainly made of high-strength steel, which makes it have excellent durability and load-bearing capacity, and can meet the stability and safety requirements in various construction processes.
[0003] In some special cases, it is necessary to continue to build other buildings on the already built buildings. However, in order not to affect the lower buildings, a platform is usually built on the basic building first, and the second-floor building is constructed on this platform. After the construction is completed, the scaffolding needs to be removed. However, due to space limitations, it is not easy to remove the large-volume high-support formwork disc buckle frame. Therefore, a large-volume high-support formwork disc buckle frame quick disassembly construction method is applied. Summary of the invention
[0004] In view of the deficiencies in the prior art, the purpose of this application is to provide a method for quickly disassembling a large-volume high-support formwork disc buckle frame, which is used to solve the technical problem that it is difficult to dismantle a large-volume high-support formwork disc buckle frame.
[0005] The above-mentioned object of the present application is achieved through the following technical solution: A method for quickly disassembling a large-volume high-support formwork buckle frame, comprising the following steps:
[0006] S1. Use a transport hook or other tools to remove the remaining materials on the building to ensure that there is no debris in the building;
[0007] S2. Remove the connectors between the module bracket and other structures, and remove the fixing devices between the module brackets;
[0008] S3. Use transport hooks or other lifting equipment to transport the module brackets out of the building one by one;
[0009] S4. After the module bracket is removed, the guide and transport device including the support column and the guide rail is removed;
[0010] S5. Check and clean the residues generated during the disassembly process, such as bolts, nuts, gaskets, etc. Check whether all disassembled parts are complete. If there is any damage, record it and replace it.
[0011] By adopting the above technical solution, the rapid construction of modular brackets and the use of fixtures greatly improve the construction efficiency and the stability of the brackets. The modular design makes the bracket construction more convenient, and the fixtures ensure the close connection between the brackets, improving the stability and safety of the entire structure. The construction of support columns and guide rails provides an efficient path for the transportation of building materials. The sliding design of the transport hook on the guide rail allows the building materials to be transported to the construction site quickly and smoothly, greatly improving the construction efficiency and reducing the labor intensity of manual handling. During the construction process, the use of transport hooks greatly speeds up the transportation of building materials. This not only improves the construction efficiency, but also helps to shorten the project cycle and reduce construction costs. The disassembly of modular brackets and the use of transport hooks make the cleaning work after the completion of the building simple and efficient. By disassembling the fixtures, the modular brackets can be quickly separated and then transported out of the building by the transport hooks, which greatly improves the efficiency of the demolition work. After the transportation of the modular brackets is completed, the disassembly of the support columns and guide rails is also simple and quick. These components are highly reusable, which reduces the construction cost, and is also conducive to environmental protection and sustainable development.
[0012] Further, according to the transportation device described in step S4, it includes a guide rail and a transportation hook, a pair of support columns are provided at both ends of the guide rail, a T-shaped slot is opened at the upper end of the support column, T-shaped blocks matching the T-shaped slot are extended at both ends of the guide rail, the middle part of the guide rail is a contraction structure, threaded holes are opened at the lower ends of the support columns on both sides, threaded columns are provided in the threaded holes, a bolt is fixedly provided at one end of the threaded column, and a nut is threadedly provided at the other end, a pair of limit buckles are installed at the lower end of the guide rail, and a transportation hook is installed between the pair of limit buckles.
[0013] By adopting the above technical solution, the guide rail is supported by the support column and fixed on the T-slot of the support column by inserting the T-block. The transport hook is slidably connected to the guide rail through the limit buckle on the guide rail. When the formwork bracket needs to be removed, it is hooked through the guide rail and then slid through the guide rail for transportation.
[0014] Furthermore, the transport hook includes a hook and a vertical pole, the vertical pole is slidably connected to the lower end of the guide rail through a limit buckle, a pair of extension plates are arranged in the middle of the vertical pole, a winding shaft is rotatably arranged between the extension plates, a traction line is fixedly arranged on the winding shaft and wound on the winding shaft, the winding shaft penetrates the extension plate, a driving motor is fixedly arranged on the extension plate, and the output end of the driving motor is fixedly connected to the winding shaft.
[0015] By adopting the above technical solution, considering the different heights of module brackets, it is necessary to hook module brackets of different heights, and drive the motor to drive the traction rope to transport the templates of different heights.
[0016] Furthermore, a pair of the limit buckles are provided with straight grooves at their upper ends, and movable wheels are rotatably provided at both ends of the vertical rod.
[0017] By adopting the above technical solution and arranging moving wheels, the movement of the transport hook between the guide rails can be accelerated, thereby increasing the transport speed.
[0018] Furthermore, a universal wheel is fixedly provided at the bottom of the support column, a limiting sleeve slidably connected to the support column is provided at the upper end of the universal wheel, and a hard rubber layer is fixedly provided on the inner side of the limiting sleeve.
[0019] By adopting the above technical solution, considering that it may be necessary to fine-tune the position of the guide rail after installation, a universal wheel is provided to facilitate this purpose. At the same time, a limit sleeve is provided at the upper end of the universal wheel. When locking is required, it is only necessary to slide the limit sleeve toward the universal wheel with force, and the hard rubber layer inside the limit sleeve will jam the universal wheel, thereby fixing it.
[0020] Furthermore, each group of the module brackets includes multiple starting poles and multiple sweeping rods, and multiple pairs of fixing rings are fixedly arranged on the starting poles. Extension columns are fixedly arranged at both ends of the sweeping rods. An extension groove is provided at one end of the sweeping rod close to the extension column, and the extension column is inserted into the extension groove. Multiple sweeping rods are inserted between a pair of fixing rings, and a groove is also provided on one end of the sweeping rod close to the extension column. A pair of semicircular rings are evenly arranged on the outside of the fixing ring, and flanges are fixedly arranged at the bottom of the semicircular rings.
[0021] By adopting the above technical solution, the sweeping rod is plugged together in the mortise and tenon structure, and a pair of semicircular rings are added to the fixing ring. The flange fixed on the semicircular ring and the groove opened on the sweeping rod are used for secondary reinforcement, so that it can be completely fixed.
[0022] Furthermore, a fixing device is provided between the module brackets, and the fixing device includes a pair of arc plates, the pair of arc plates are rotatably connected, a protrusion extends from one of the arc plates, and a concave plate is fixedly provided on the other arc plate, a rotating column is rotatably provided on the protrusion, a strip block is fixedly provided on the upper end of the rotating column, locking columns are fixedly provided at both ends of the strip block, and sliding grooves matching the locking columns are provided on the protrusion and the concave plates.
[0023] By adopting the above technical solution, the purpose of this design is to fix the brackets to each other so that the brackets are fixed into a modular whole. The brackets are fixed by a pair of arc plates, which are clamped on the sweeping rod on the adjacent module brackets. At the same time, the protrusion on one arc plate is docked with the concave plate on the other arc plate, and the strip block on the protrusion is rotated so that the locking column is stuck in the slide slot to fix it. When it needs to be removed, it only needs to rotate the strip block to make the locking column disengage from the slide slot to complete the removal.
[0024] Furthermore, an adsorption magnet is fixedly provided at the bottom of the locking column, and a placement magnet is installed in the middle of the slide groove on the protrusion and the concave plate.
[0025] By adopting the above technical solution, after the locking column is rotated, the adsorption magnet and the placement magnet are used to fix it so that it cannot be easily detached.
[0026] Furthermore, support platforms are slidably arranged on both sides of the lower end of each group of the starting upright poles, threaded holes are provided on the support platforms, and the threaded holes penetrate through the support platforms and extend to the starting upright poles, and bolts are threadedly arranged in the threaded holes.
[0027] By adopting the above technical solution, the support platform provides an additional support surface for the uprights, enhancing the stability of the entire scaffolding structure. The bolt connection design makes the installation and removal of the support platform simple and quick, without the need for complex tools or techniques, thus improving work efficiency.
[0028] Furthermore, the starting pole is made of carbon steel.
[0029] In summary, the present application includes at least one of the following beneficial technical effects:
[0030] 1. The modular bracket is easy to build and disassemble, which greatly shortens the construction period. The fixing device ensures the close connection between the brackets and improves the construction efficiency. The sliding design of the transport hook on the guide rail enables the building materials to be transported to the construction site quickly and smoothly, further improving the construction efficiency.
[0031] 2. The modular design allows the brackets and components to be reused, reducing material costs. The use of transport hooks and guide rails reduces the need for manual handling and reduces labor costs. The efficient construction cycle and reduced rework rate further reduce construction costs.
[0032] 3. The stability of the modular bracket and the firmness of the fixing device ensure the safety during the construction process. The precise control of the transport hook and guide rail reduces the accidental damage and safety hazards of materials during transportation. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 It is a schematic diagram of the overall structure in the embodiment;
[0034] Figure 2 In the embodiment Figure 1 A partial enlarged schematic diagram of the part in the middle;
[0035] Figure 3 2 is a schematic diagram of the structure of the guide rail and the transport hook in the embodiment;
[0036] Figure 4 In the embodiment Figure 3 A partial enlarged schematic diagram of the part at B in the middle;
[0037] Figure 5 2 is a schematic diagram of the structure of the universal wheel and the limiting sleeve in the embodiment;
[0038] Figure 6 is an exploded schematic diagram of a starting pole and a sweeping pole in the embodiment;
[0039] Figure 7 Schematic diagram of the structure of the fixing device in the embodiment.
[0040] : 1. guide rail; 11. T-block; 2. support column; 20. T-slot; 21. threaded column; 22. nut; 3. limit buckle; 4. hook; 40. winding shaft; 41. driving motor; 42. extension plate; 43. traction line; 44. vertical pole; 45. straight groove; 46. moving wheel; 5. universal wheel; 50. limit sleeve; 51. hard rubber layer; 6. starting vertical pole; 60. sweeping pole; 61. fixing ring; 62. extension column; 63. extension groove; 64. flange; 65. semicircular ring; 66. groove; 7. arc plate; 70. convex block; 71. concave plate; 72. rotating column; 73. bar block; 74. locking column; 75. slide groove; 8. adsorption magnet; 80. placement magnet; 9. support table. DETAILED DESCRIPTION
[0041] The present application is further described in detail below in conjunction with the accompanying drawings.
[0042] Example, see Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 6 and Figure 7A method for quickly disassembling a large-volume high-support formwork buckle frame includes the following steps: S1. First, use a transport hook or other tools to remove the remaining materials on the building to ensure that there is no debris in the building; S2. Remove the connectors between the module bracket and other structures, and remove the fixings between the module brackets; S3. Use a transport hook or other lifting equipment to transport the module brackets out of the building one by one; S4. After the module brackets are removed, remove the guide and transportation devices including the support columns 2 and the guide rails 1; S5. Check and clean the residues generated during the disassembly process, such as bolts, nuts 22, gaskets, etc., and check whether all the disassembled parts are complete. If there is any damage, record and replace them. The rapid construction of modular brackets and the use of fixing devices greatly improve the construction efficiency and the stability of the brackets. The modular design makes the bracket construction more convenient, and the fixing devices ensure the close connection between the brackets, improving the stability and safety of the entire structure. The construction of the support columns 2 and the guide rails 1 provides an efficient path for the transportation of building materials. The sliding design of the transport hook 4 on the guide rail 1 allows the construction materials to be transported to the construction site quickly and smoothly, greatly improving the construction efficiency and reducing the labor intensity of manual handling. During the construction process, the use of the transport hook 4 greatly speeds up the transportation of construction materials. This not only improves the construction efficiency, but also helps to shorten the project period and reduce construction costs. The disassembly of the modular bracket and the use of the transport hook 4 make the cleaning work after the completion of the building simple and efficient. By disassembling the fixing device, the module bracket can be quickly separated and then transported out of the building by the transport hook 4, which greatly improves the efficiency of the demolition work. After the transportation of the module bracket is completed, the disassembly of the support column 2 and the guide rail 1 is also simple and quick. These components are highly reusable, which reduces construction costs and is also beneficial to environmental protection and sustainable development.
[0043] In this embodiment, the transport device includes a guide rail 1 and a transport hook 4. A pair of support columns 2 are provided at both ends of the guide rail 1. A T-shaped slot 20 is provided at the upper end of the support column 2. T-shaped blocks 11 matching the T-shaped slot 20 extend from both ends of the guide rail 1. The middle part of the guide rail 1 is a contraction structure. Threaded holes are provided at the lower ends of the support columns 2 on both sides. Threaded columns 21 are provided in the threaded holes. A bolt is fixed at one end of the threaded column 21, and a nut 22 is threadedly provided at the other end. A pair of limit buckles 3 are installed at the lower end of the guide rail 1, and a transport hook 4 is installed between the pair of limit buckles 3.
[0044] In this embodiment, the guide rail 1 is supported by the support column 2 and is fixed by inserting the T-block 11 into the T-slot 20 of the support column 2. The transport hook 4 is slidably connected to the guide rail 1 through the limit buckle 3 on the guide rail 1. When the formwork bracket needs to be removed, it is hooked through the guide rail 1 and then slides through the guide rail 1 for transportation.
[0045] In this embodiment, the transport hook includes a hook 4 and a vertical rod 44, the vertical rod 44 is slidably connected to the lower end of the guide rail 1 through a limit buckle 3, a pair of extension plates 42 are arranged in the middle of the vertical rod 44, a winding shaft 40 is rotatably arranged between the extension plates 42, a traction line 43 is fixedly arranged on the winding shaft 40, and is wound on the winding shaft 40, the winding shaft 40 penetrates the extension plate 42, a driving motor 41 is fixedly arranged on the extension plate 42, and the output end of the driving motor 41 is fixedly connected to the winding shaft 40. Considering the different heights of the module brackets, it is necessary to hook the module brackets of different heights, and the driving motor 41 drives the traction rope 43, so that it can transport the templates of different heights.
[0046] In this embodiment, a pair of limit buckles 3 have straight grooves 45 at their upper ends, and two ends of the vertical rod 44 are rotatably provided with moving wheels 46. By providing the moving wheels 46, the movement of the transport hook 4 between the guide rails 1 can be accelerated, thereby increasing the transport speed.
[0047] In this embodiment, a universal wheel 5 is fixedly arranged at the bottom of the support column 2, a limiting sleeve 50 slidably connected to the support column 2 is arranged at the upper end of the universal wheel 5, and a hard rubber layer 51 is fixedly arranged inside the limiting sleeve 50. Considering that the position of the guide rail 1 may need to be fine-tuned after the guide rail 1 is installed, the universal wheel 5 is arranged to facilitate the purpose, and the limiting sleeve 50 is arranged at the upper end of the universal wheel 5. When locking is required, it is only necessary to slide the limiting sleeve 50 toward the universal wheel 5 with force, and the hard rubber layer 51 inside the limiting sleeve 50 will clamp the universal wheel 5, thereby fixing it.
[0048] In this embodiment, each set of module brackets includes multiple starting poles 6 and multiple sweeping poles 60. Multiple pairs of fixing rings 61 are fixedly arranged on the starting poles 6. Extension columns 62 are fixedly arranged at both ends of the sweeping poles 60. An extension groove 63 is provided at one end of the sweeping pole 60 close to the extension column 62. The extension column 62 is inserted into the extension groove 63. Multiple sweeping poles 60 are inserted between a pair of fixing rings 61. A groove 66 is also provided at one end of the sweeping pole 60 close to the extension column 62. A pair of semicircular rings 65 are evenly arranged on the outside of the fixing ring 61. The bottom of the semicircular rings 65 are fixedly arranged with flanges 64. The sweeping poles 60 are plugged together with the mortise and tenon structure, and a pair of semicircular rings 65 are added to the fixing ring 61. The flanges 64 fixed on the semicircular rings 65 and the grooves 66 provided on the sweeping poles 60 are used for secondary reinforcement, so that they are completely fixed.
[0049] In this embodiment, a fixing device is provided between the module brackets, and the fixing device includes a pair of arc plates 7, which are rotatably connected, a protrusion 70 extends from one of the arc plates 7, a concave plate 71 is fixedly provided on the other arc plate 7, a rotating column 72 is rotatably provided on the protrusion 70, a strip block 73 is fixedly provided on the upper end of the rotating column 72, locking columns 74 are fixedly provided at both ends of the strip block 73, and sliding grooves 75 matching the locking columns 74 are provided on the protrusion 70 and the concave plate 71. The purpose of this design is to fix the brackets to each other so that the brackets are fixed into a modular whole. It is fixed by a pair of arc plates 7, which are clamped on the sweeping rod 60 on the adjacent module bracket, and at the same time, the protrusion 70 on one arc plate 7 is connected to the concave plate 71 on the other arc plate 7, and then the strip block 73 on the protrusion 70 is rotated so that the locking column 74 is stuck in the slide groove 75 to fix it. When it needs to be removed, it only needs to rotate the strip block 73 to disengage the locking column 74 from the slide groove 75 to complete the removal.
[0050] In this embodiment, the bottom of the locking column 74 is fixedly provided with an adsorption magnet 8, and the middle of the slide groove 75 on the protrusion 70 and the concave plate 71 is provided with a placement magnet 80. After the locking column 74 is rotated, the adsorption magnet 8 and the placement magnet 80 are fixed so that they cannot be easily separated.
[0051] In this embodiment, support platforms 9 are slidably arranged on both sides of the lower end of each group of starting uprights 6, and threaded holes are provided on the support platforms 9. The threaded holes penetrate through the support platforms 9 and extend to the starting uprights 6, and bolts are threadedly arranged in the threaded holes. The arrangement of the support platforms 9 provides an additional support surface for the uprights 44, thereby enhancing the stability of the entire scaffolding structure. The bolt connection design makes the installation and removal process of the support platforms 9 simple and quick, without the need for complex tools or techniques, thereby improving work efficiency.
[0052] Specific implementation process: First, build a module bracket, including multiple starting poles 6 and multiple sweeping rods 60. Multiple pairs of fixed rings 61 are fixed on the starting poles 6, and the sweeping rods 60 are inserted between the fixed rings 61 through the extension columns 62 and extension grooves 63 at both ends. A flange 64 is fixed on one end of the sweeping rod 60 close to the extension column 62, and a pair of semicircular rings 65 are evenly arranged on the outside of the fixed ring 61. Secondary reinforcement is performed through the flange 64 fixed on the semicircular ring 65 and the groove 66 opened on the sweeping rod 60, and the support column 2 is built, and a transport device is built on the support column 2 bracket. The transport device includes a guide rail 1 and a transport hook 4. The two ends of the guide rail 1 are matched and fixed with the T-slot 20 of the support column 2 through the T-block 11. The middle part of the guide rail 1 is designed as a contraction structure to meet the needs of different lengths. A pair of limit buckles 3 are installed at the lower end of the guide rail 1, and the transport hook 4 is slidably connected to the guide rail 1 through the limit buckle 3. When construction work begins, the construction materials are quickly and smoothly transported to the construction site by using the sliding design of the transport hook 4 on the guide rail 1. After the construction is completed, the module bracket is removed. The module bracket can be quickly separated by removing the fixing device (including a pair of arc plates 7, a protrusion 70, a concave plate 71, a locking column 74, etc.). The disassembled module bracket is transported out of the building through the guide rail 1 by using the transport hook 4. After the module bracket is transported, the support column 2 and the guide rail 1 are removed. The universal wheel 5 and the limit sleeve 50 at the bottom of the support column 2 are designed so that the position of the guide rail 1 can be fine-tuned and fixed.
[0053] The embodiments of this specific implementation method are all preferred embodiments of the present application, and are not intended to limit the protection scope of the application. Therefore, all equivalent changes made based on the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A method for quickly disassembling a large-volume high-support formwork buckle frame, characterized in that: The following steps are involved: S1. Use a transport hook or other tools to remove the remaining materials on the building to ensure that there is no debris in the building; S2. Remove the connectors between the module bracket and other structures, and remove the fixing devices between the module brackets; S3. Use transport hooks or other lifting equipment to transport the module brackets out of the building one by one; S4. After the module bracket is removed, the guide and transport device including the support column (2) and the guide rail (1) is removed; S5. Check and clean the residues generated during the disassembly process, such as bolts, nuts (22), gaskets, etc. Check whether all disassembled parts are complete. If any damage is found, record it and replace it.
2. According to claim 1, a method for quickly disassembling a large-volume high-support formwork buckle frame is characterized in that: The transport device in step S4 comprises a guide rail (1) and a transport hook (4), wherein a pair of support columns (2) are provided at both ends of the guide rail (1), and a T-shaped slot (20) is provided at the upper end of the support column (2). T-shaped blocks (11) matching the T-shaped slot (20) are extended from both ends of the guide rail (1), and threaded holes are provided at the lower ends of the support columns (2) on both sides, and threaded columns (21) are threadedly provided in the threaded holes, and a bolt is fixedly provided at one end of the threaded column (21), and a nut (22) is threadedly provided at the other end, and a pair of limit buckles (3) are installed at the lower end of the guide rail (1), and a transport hook (4) is installed between the pair of limit buckles (3).
3. According to claim 2, a method for quickly disassembling a large-volume high-support formwork buckle frame is characterized in that: The transport hook comprises a hook (4) and a vertical rod (44); the vertical rod (44) is slidably connected to the lower end of the guide rail (1) through a limit buckle (3); a pair of extension plates (42) are arranged in the middle of the vertical rod (44); a winding shaft (40) is rotatably arranged between the extension plates (42); a traction line (43) is fixedly arranged on the winding shaft (40) and wound on the winding shaft (40); the winding shaft (40) penetrates the extension plate (42); a driving motor (41) is fixedly arranged on the extension plate (42); and an output end of the driving motor (41) is fixedly connected to the winding shaft (40).
4. According to claim 2, a method for quickly disassembling a large-volume high-support formwork buckle frame is characterized in that: A pair of the limit buckles (3) are provided with straight grooves (45) at their upper ends, and moving wheels (46) are rotatably provided at both ends of the vertical rod (44), and the moving wheels are slidably connected in the straight grooves.
5. According to claim 2, a method for quickly disassembling a large-volume high-support formwork buckle frame is characterized in that: A universal wheel (5) is fixedly arranged at the bottom of the support column (2), a limiting sleeve (50) slidably connected to the support column (2) is arranged at the upper end of the universal wheel (5), and a hard rubber layer (51) is fixedly arranged on the inner side of the limiting sleeve (50).
6. According to claim 1, a method for quickly disassembling a large-volume high-support formwork buckle frame is characterized in that: Each group of the module brackets comprises a plurality of starting upright poles (6) and a plurality of sweeping rods (60), wherein a plurality of pairs of fixing rings (61) are fixedly arranged on the starting upright poles (6), and extension columns (62) are fixedly arranged at both ends of the sweeping rods (60), and an extension groove (63) is provided on the side of the sweeping rod (60) close to the extension column (62), and the extension column (62) is plugged into the extension groove (63), and the plurality of sweeping rods (60) are plugged between the pair of fixing rings (61), and a groove (66) is further provided on one end of the sweeping rod (60) close to the extension column (62), and a pair of semicircular rings (65) are evenly arranged on the outer side of the fixing ring (61), and flanges (64) are fixedly arranged at the bottom of each of the semicircular rings (65).
7. According to claim 1, a method for quickly disassembling a large-volume high-support formwork buckle frame is characterized in that: A fixing device is arranged between the module brackets, and the fixing device comprises a pair of arc plates (7). The pair of arc plates (7) are rotatably connected, a protrusion (70) extends from the free end of one of the arc plates (7), and a concave plate (71) is fixedly arranged on the free end of the other arc plate (7), a rotating column (72) is rotatably arranged on the protrusion (70), a strip block (73) is fixedly arranged on the upper end of the rotating column (72), and locking columns (74) are fixedly arranged at both ends of the strip block (73), and a sliding groove (75) matching the locking column (74) is provided on the protrusion (70) and the concave plate (71).
8. According to claim 7, a method for quickly disassembling a large-volume high-support formwork buckle frame is characterized in that: The bottom of the locking column (74) is fixedly provided with an adsorption magnet (8), and the middle of the sliding groove (75) on the protrusion (70) and the concave plate (71) is installed with a placement magnet (80).
9. According to claim 6, a method for quickly disassembling a large-volume high-support formwork buckle frame is characterized in that: Support platforms (9) are slidably arranged on both sides of the lower end of each group of the starting upright poles (6), and threaded holes are provided on the support platforms (9). The threaded holes penetrate through the support platforms (9) and extend to the starting upright poles (6), and bolts are threadedly connected in the threaded holes.
10. According to claim 6, a method for quickly disassembling a large-volume high-support formwork buckle frame is characterized in that: The starting pole (6) is made of carbon steel.
Citation Information
Patent Citations
High-rise building demolition equipment and high-rise building demolition method
CN115807562A
Building formwork construction method
CN118029703A
Pipe fitting integrated scaffold
CN211286532U
Super-heavy load high formwork supporting frame
CN218467127U
Coupling plate for mechanically coupling several modular scaffold uprights and multi-part scaffold uprights with such a coupling plate, especially as part of a heavy-duty support
DE102018217043A1