By designing a tritium removal system in the transient radiation test system of the nuclear fuel reactor, using drying tower adsorption and regeneration unit heating and regeneration technology, the problem of tritium diffusion is solved, efficient tritium removal is achieved, and the safety of the system is improved. purity.
Patent Information
- Application Number
- CN202411327435.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-23
- Publication Date
- 2024-12-17
- Estimated Expiration
- 2044-09-23
AI Technical Summary
In the transient radiation test system of the nuclear fuel reactor, the diffusion of tritiated water in the helium circuit causes the release of radioactive tritium to the environment, increasing the absorbed dose of operators, and the prior art is difficult to effectively remove tritium, affecting the radiation test Purity and safety.
A tritium removal system is designed, including a tritium removal unit, an input unit, a regeneration unit, an output unit and an emptying unit. The tritiumized water is dried and adsorbed through the drying tower, and the molecular sieve desiccant is heated and regenerated by the regeneration unit to achieve continuous operation. and efficient tritium removal.
It improves tritium removal efficiency, extends the large gas processing volume and continuous running time, ensures the purity of the helium circuit, reduces the release of radioactive tritium, and improves the safety and operation convenience of the system.
Smart Images

Figure CN119139889A_ABST
Abstract
Description
Technical Field
[0001] The embodiments of the present application relate to the technical field of nuclear fuel in-pile irradiation, and in particular to a detritiation system and a detritiation method. Background Art
[0002] In the research reactor, the helium loop of the transient irradiation test system in the nuclear fuel pile can be used to quickly and evenly change the irradiation power of the nuclear fuel. The rapid transient power change is very important for exploring the integrity and safety of the fuel elements. In order to ensure the purity of the helium in the irradiation test system loop, reduce the diffusion of tritiated water generated during the operation of the helium loop, prevent the release of radioactive tritium into the environment, and reduce the absorbed dose of operators, the helium loop needs to be detritiated. Summary of the invention
[0003] The present invention aims to solve at least one of the technical problems existing in the prior art or related art.
[0004] To this end, a first aspect of the present invention provides a detritus removal system.
[0005] A second aspect of the present invention provides a method for removing tritium.
[0006] In view of this, according to a first aspect of an embodiment of the present application, a detritus removal system is proposed, comprising:
[0007] Detritiation unit;
[0008] An input unit, the input unit being connected to an input end of the detritium removal unit;
[0009] a regeneration unit, the regeneration unit being connected to an input end of the detritus removal unit;
[0010] an output unit, the output unit being connected to an output end of the detritus removal unit;
[0011] an emptying unit, the emptying unit being connected to an output end of the detritus removal unit;
[0012] Wherein, the detritiation unit includes a plurality of detritiation components arranged in parallel, each of the detritiation components includes a drying tower, a first control valve and a second control valve, the first control valve is arranged at the input end of the drying tower, and the second control valve is arranged at the output end of the drying tower.
[0013] In a feasible implementation manner, the input unit includes:
[0014] An input pipeline, the input pipeline being connected to an input end of the detritus removal unit;
[0015] A pre-filter, wherein the pre-filter is arranged on the input pipeline;
[0016] a third control valve, the third control valve being arranged at an input end of the input pipeline;
[0017] A first pressure detection component is connected to the input pipeline.
[0018] In a feasible implementation manner, the regeneration unit comprises:
[0019] a regeneration pipeline, the regeneration pipeline being connected to an input end of the detritus removal unit;
[0020] A heater, wherein the heater is arranged on the regeneration pipeline;
[0021] a fourth control valve, the fourth control valve being arranged at an input end of the regeneration pipeline;
[0022] a first temperature sensor connected to the heater;
[0023] A second temperature sensor is connected to the regeneration pipeline and is located at the output end of the heater.
[0024] In a feasible implementation manner, the invention further comprises: an experimental simulation unit, wherein the experimental simulation unit comprises:
[0025] A regeneration medium supply component, a detrition simulation experiment component, a regulating pipeline and an output path, wherein the regeneration medium supply component and the detrition simulation experiment component are connected in parallel, the regulating pipeline and the output path are connected in parallel, the regulating pipeline is connected to the regeneration medium supply component and the detrition simulation experiment component, and the output path is connected to the regeneration medium supply component and the detrition simulation experiment component.
[0026] In a feasible implementation manner, the regeneration medium supply assembly includes: a supply pipeline, a first gas cylinder, a fifth control valve, and a first flow meter, the supply pipeline is connected to the first gas cylinder, the fifth control valve and the first flow meter are arranged on the supply pipeline, and the regulating pipeline and the output path are connected to the supply pipeline;
[0027] The detritium simulation experiment assembly comprises: a simulation pipeline, a second gas cylinder, a humidifier, a steam-water separator and a sixth control valve, the simulation pipeline is connected to the second gas cylinder, the humidifier, the steam-water separator and the sixth control valve are sequentially arranged on the simulation pipeline, and the regulating pipeline and the output path are connected to the simulation pipeline;
[0028] A seventh control valve is provided on the regulating pipeline;
[0029] The output path includes a first output port and a second output port, the first output port is used to be connected to the input unit, and the second output port is used to be connected to the regeneration unit.
[0030] In a feasible implementation manner, the output unit includes:
[0031] an output pipeline, the output pipeline being connected to an output end of the detritus removal unit;
[0032] A post-filter, the output pipeline is arranged on the output pipeline;
[0033] an eighth control valve, the eighth control valve being arranged at an output end of the output pipeline;
[0034] a third pressure detection component, the third pressure detection component being connected to the output pipeline;
[0035] a first dew point meter, the first dew point meter being connected to the output pipeline;
[0036] An eleventh control valve, wherein the eleventh control valve is arranged between the first dew point meter and the output pipeline.
[0037] In a feasible implementation manner, the emptying unit includes:
[0038] an exhaust pipeline, the exhaust pipeline being connected to an output end of the detritus removal unit;
[0039] A vacuum pumping pipeline, the vacuum pumping pipeline is connected to the output end of the exhaust pipeline;
[0040] a ninth control valve, the ninth control valve being arranged on the vacuum pumping pipeline;
[0041] an exhaust pipe, the exhaust pipe being connected to an output end of the exhaust pipeline;
[0042] a muffler, the muffler being arranged on the exhaust pipe;
[0043] a third temperature sensor, the third temperature sensor being connected to the exhaust pipeline;
[0044] A tenth control valve is provided on the exhaust pipe.
[0045] According to a second aspect of an embodiment of the present application, a detritium removal method is proposed, which is applied to a detritium removal system as described in any of the above technical solutions. The detritium removal method includes:
[0046] Performing a vacuum process on the detritus removal unit by means of the evacuation unit;
[0047] Inputting the medium containing tritiated water into the detritiation unit, and discharging it through the output unit after detritiation treatment;
[0048] Closing the input unit and the output unit, and emptying the detritus removal unit through the emptying unit;
[0049] The regeneration unit is turned on to regenerate the detritus removal unit.
[0050] In a feasible implementation, the detritium method further comprises:
[0051] In response to a leak detection instruction, an experimental medium is supplied to the detritiation system through an experimental simulation unit, and an output end of the detritiation system is controlled to be in a closed state to perform leak point detection;
[0052] In response to a test instruction, supplying a test medium having a dew point temperature greater than or equal to a first threshold to the detritium removal unit through the experimental simulation unit, and testing a dew point value of a medium discharged through an output end of the detritium removal unit;
[0053] In response to the regeneration experiment instruction, the regeneration medium is supplied to the detritiation unit through the regeneration medium supply component of the experimental simulation unit to regenerate the detritiation unit, and then the detritiation simulation experiment component outputs a test medium with a dew point temperature greater than or equal to a first threshold to the detritiation unit to test the dew point value of the medium discharged through the output end of the detritiation unit.
[0054] In a feasible embodiment, the step of supplying the regeneration medium to the detritus removal unit through the regeneration unit in response to the regeneration instruction includes:
[0055] The heater of the regeneration unit is turned on, and a regeneration medium is supplied to the detritus removal unit through a regeneration pipeline. The regeneration medium heats and regenerates the molecular sieve desiccant in the drying tower, and then the gas is discharged through an exhaust unit.
[0056] Compared with the prior art, the present invention has at least the following beneficial effects:
[0057] The detritium removal system provided in the embodiment of the present application includes a detritium removal unit, an input unit, a regeneration unit, an output unit and an emptying unit. In the detritium removal system provided in the embodiment of the present application, during use, helium containing tritiated water can enter the detritium removal unit through the input unit, and after the detritium removal unit dries and adsorbs the tritiated water in the helium through a drying tower, the helium is discharged into the helium circuit through the output unit. The detritium removal unit of the detritium removal system provided in the embodiment of the present application includes a plurality of detritium removal components arranged in parallel, and each drying tower can work independently through the arrangement of the first control valve and the second control valve, and has the characteristics of high detritium removal efficiency, large gas processing capacity and long continuous operation time. Further, the detritium removal system provided in the embodiment of the present application is provided with a regeneration unit. After the detritium removal unit has been detritium removed for a period of time, a medium with a higher temperature can be supplied to the detritium removal unit through the regeneration unit to heat and regenerate the molecular sieve desiccant in the drying tower, and then the medium used for regeneration can be discharged to the outside of the detritium removal unit through the emptying unit, so that the detritium removal system can operate continuously, making the detritium removal system highly safe and easy to operate. Further, in addition to being used to discharge the medium that has completed the regeneration of the drying tower through the setting of the emptying unit, the impurity gas in the detritium removal system can also be emptied through the emptying unit before the detritium removal system is detritiumed, making the use of the detritium removal system more efficient. BRIEF DESCRIPTION OF THE DRAWINGS
[0058] Various other advantages and benefits will become apparent to those of ordinary skill in the art by reading the detailed description of the preferred embodiments below. The accompanying drawings are only for the purpose of illustrating the preferred embodiments and are not to be considered as limiting the present application. Also, the same reference symbols are used throughout the accompanying drawings to represent the same components. In the accompanying drawings:
[0059] Figure 1 A schematic structural diagram of a detritus removal system according to an embodiment of the present application;
[0060] Figure 2 A schematic structural diagram of a detritus removal system performance experiment according to an embodiment of the present application;
[0061] Figure 3 A schematic flowchart of the steps of a detritus removal method according to an embodiment of the present application.
[0062] in, Figure 1 to Figure 2 The corresponding relationship between the reference numerals and the component names is as follows:
[0063] 110 detritiation unit, 120 input unit, 130 regeneration unit, 140 output unit, 150 exhaust unit, 160 experimental simulation unit;
[0064] 111 drying tower, 112 first control valve, 113 second control valve;
[0065] 121 input pipeline, 122 pre-filter, 123 third control valve, 124 first pressure detection element;
[0066] 131 regeneration pipeline, 132 heater, 133 fourth control valve, 134 first temperature sensor, 135 second temperature sensor;
[0067] 141 output pipeline, 142 post-filter, 143 eighth control valve, 144 third pressure detection element, 145 first dew point meter, 146 eleventh control valve;
[0068] 151 exhaust pipeline, 152 vacuum pipeline, 153 ninth control valve, 154 exhaust pipe, 155 muffler, 156 third temperature sensor, 157 tenth control valve;
[0069] 161 regeneration medium supply assembly, 162 detritus removal simulation experiment assembly, 163 regulating pipeline, 164 output line, 165 seventh control valve, 166 second dew point meter, 167 regeneration test instrument valve, 168 fourth pressure detection component;
[0070] 1611 supply pipeline, 1612 first gas cylinder, 1613 fifth control valve, 1614 first flow meter;
[0071] 1621 simulation pipeline, 1622 second gas cylinder, 1623 humidifier, 1624 steam-water separator, 1625 sixth control valve, 1626 twelfth control valve;
[0072] 1641 is a first output port, 1642 is a second output port. DETAILED DESCRIPTION
[0073] In order to better understand the above-mentioned technical scheme, the technical scheme of the embodiments of the present application is described in detail below through the accompanying drawings and specific embodiments. It should be understood that the embodiments of the present application and the specific features in the embodiments are detailed descriptions of the technical scheme of the embodiments of the present application, rather than limitations on the technical scheme of the present application. In the absence of conflict, the embodiments of the present application and the technical features in the embodiments may be combined with each other.
[0074] like Figure 1 and Figure 2As shown, according to the first aspect of an embodiment of the present application, a detritiation system is proposed, comprising: a detritiation unit 110; an input unit 120, connected to the input end of the detritiation unit 110; a regeneration unit 130, connected to the input end of the detritiation unit 110; an output unit 140, connected to the output end of the detritiation unit 110; an emptying unit 150, connected to the output end of the detritiation unit 110; wherein the detritiation unit 110 comprises a plurality of detritiation components arranged in parallel, each detritiation component comprises a drying tower 111, a first control valve 112 and a second control valve 113, the first control valve 112 is arranged at the input end of the drying tower 111, and the second control valve 113 is arranged at the output end of the drying tower 111.
[0075] The detritium removal system provided in the embodiment of the present application includes a detritium removal unit 110, an input unit 120, a regeneration unit 130, an output unit 140 and an emptying unit 150. In the detritium removal system provided in the embodiment of the present application, during use, helium containing tritiated water can enter the detritium removal unit 110 through the input unit 120, and after the detritium removal unit 110 dries and adsorbs the tritiated water in the helium through the drying tower 111, the helium is discharged into the helium loop through the output unit 140. The detritium removal unit 110 of the detritium removal system provided in the embodiment of the present application includes a plurality of detritium removal components arranged in parallel, and each drying tower 111 can work independently through the arrangement of the first control valve 112 and the second control valve 113, and has the characteristics of high detritium removal efficiency, large gas processing capacity and long continuous operation time. Furthermore, the detritiation system provided in the embodiment of the present application also includes a regeneration unit 130. After the detritiation unit 110 has been detritinated for a period of time, a medium with a higher temperature can be supplied to the detritiation unit 110 through the regeneration unit 130 to heat and regenerate the molecular sieve desiccant in the drying tower 111, and then the medium used for regeneration can be discharged to the outside of the detritiation unit 110 through the emptying unit 150, so that the detritiation system can operate continuously, and the detritiation system has high safety and convenient operation. Further, in addition to being used to discharge the medium that has completed the regeneration of the drying tower 111, the detritiation system can also be emptied of impurity gases in the detritiation system through the emptying unit 150 before the detritiation system is detritized, making the use of the detritiation system more efficient.
[0076] It can be understood that since the detritiation unit 110 includes multiple detritiation components arranged in parallel, and each detritiation component includes a drying tower 111, a first control valve 112 and a second control valve 113, the independent use of each drying tower 111 can be controlled by controlling the first control valve 112 and the second control valve 113 of each detritiation component. By setting up multiple drying towers 111, the continuous operation time of the detritiation system can be increased to meet the process requirements.
[0077] It can be understood that the input end of the detritiation unit 110 is connected to the input unit 120 and the regeneration unit 130. Based on this, during the use of the detritiation system, the input unit 120 can be connected to the process section or equipment that needs to be detritiated in the helium loop of the fuel transient irradiation test system, and the regeneration unit 130 is used to connect the regeneration medium. By remotely controlling the switching of the third control valve 123 and the fourth control valve 133, the detritiated helium or the regeneration medium can be conveniently and quickly connected to the input end of the detritiation unit 110.
[0078] Furthermore, the output end of the detritiation unit 110 is connected to the output unit 140 and the emptying unit 150. The output unit 140 is connected to the helium loop process section or equipment of the fuel transient irradiation test system that needs to discharge the detritiated helium. The independent setting of the emptying unit 150 can empty or evacuate the detritiation system when necessary, making the use of the detritiation system more efficient and convenient.
[0079] In some examples, the design pressure of the detritus removal system is 7 MPa, the design temperature is 300°C, and the rated flow rate is 0.04 Nm 3 / min, the main material is 022Cr17Ni12Mo2 stainless steel. The detritium system adopts modular design and layout, the system is skid-mounted, all equipment is installed in an integral frame, and connected to the fuel transient irradiation test system through the nozzle.
[0080] like Figure 1 and Figure 2 As shown, in a feasible embodiment, the input unit 120 includes: an input pipeline 121, connected to the input end of the detritus removal unit 110; a pre-filter 122, arranged on the input pipeline 121; a third control valve 123, arranged at the input end of the input pipeline 121; and a first pressure detection component 124, connected to the input pipeline 121.
[0081] In this technical solution, the structural composition of the input unit 120 is further provided. The input unit 120 may include an input pipeline 121, a pre-filter 122, a third control valve 123 and a first pressure detection component 124. During the detritiation process, the third control valve 123 may be opened to put the input pipeline 121 in a conducting state, and the helium containing tritiated water may enter the detritiation unit 110 after passing through the pre-filter 122. After the detritiation unit 110 dries and adsorbs the tritiated water in the helium through the drying tower 111, the helium is discharged into the helium circuit through the output unit 140. Through the setting of the pre-filter 122, solid and liquid particles in the helium can be filtered out, and then the helium enters the detritiation unit 110, which can make the operation of the detritiation unit 110 safer and more efficient, and at the same time can make the quality of the helium output by the output unit 140 higher.
[0082] It can be understood that, by providing the first pressure detection member 124 , the pressure of the medium input through the input pipeline 121 can be detected, which can make the use of the detritus removal system safer.
[0083] It can be understood that the filtration grade of the pre-filter 122 is 1 μm, that is, the pre-filter 122 is used to remove solid and liquid particles of μm level and above.
[0084] It can be understood that, in addition to being used to input helium that needs to be detritiated, the input pipeline 121 can also be used to input a medium for testing the detritiation system. For example, if the dew point of the test medium is known, the medium with a known dew point is then input into the detritiation unit 110 through the input pipeline 121, and then the dew point of the medium output through the output unit 140 is detected. The detritiation effect of the detritiation unit 110 can be determined, ensuring that the detritiation unit 110 can perform detritiation, thereby ensuring the reliability of the operation of the detritiation system.
[0085] like Figure 1 and Figure 2 As shown, in a feasible embodiment, the regeneration unit 130 includes: a regeneration pipeline 131, connected to the input end of the detritus unit 110; a heater 132, arranged on the regeneration pipeline 131; a fourth control valve 133, arranged at the input end of the regeneration pipeline 131; a first temperature sensor 134, connected to the heater 132; a second temperature sensor 135, connected to the regeneration pipeline 131, and located at the output end of the heater 132.
[0086] In the technical solution, the structural composition of the regeneration unit 130 is further provided. The regeneration unit 130 may include a regeneration pipeline 131, a heater 132, a fourth control valve 133, a first temperature sensor 134 and a second temperature sensor 135. Based on this, during the use of the regeneration unit 130, the regeneration medium can be input into the detritus removal unit 110 through the regeneration pipeline 131. During the regeneration process, the heater 132 can be turned on. The heater 132 can heat the regeneration medium. The heated medium enters the drying tower 111 and is in contact with the drying tower 111. By contacting the molecular sieve desiccant in 11, the molecular sieve desiccant can be heated, carrying the water vapor on the molecular sieve desiccant, and then discharged to the detritus removal system through the emptying unit 150, which can improve the regeneration efficiency of the drying tower 111. The fourth control valve 133 is arranged to facilitate the control of the opening and closing of the regeneration pipeline 131. The first temperature sensor 134 is arranged to facilitate the monitoring of the operating temperature of the heater 132. The second temperature sensor 135 is arranged to facilitate the monitoring of the temperature of the heated medium, thereby ensuring the feasibility of regeneration.
[0087] In some examples, the adsorbent in the drying tower 111 is a spherical molecular sieve with a diameter of φ3 mm to φ5 mm, and the filter elements in the pre-filter 122 and the post-filter 142 are both made of 06Cr19Ni10 sintered stainless steel material.
[0088] In some examples, in order to ensure the reliability of heating, the heater 132 can be an electric heater, a heating resistance wire is arranged in the inner cavity of the electric heater, the heating power of the electric heater is 1 kW, and the electric heating wire is a Ni20Cr80 heating resistance wire.
[0089] like Figure 1 and Figure 2 As shown, in a feasible embodiment, it also includes an experimental simulation unit 160, and the experimental simulation unit 160 includes a regeneration medium supply component 161, a detrition simulation experimental component 162, an adjustment pipeline 163 and an output path 164. The regeneration medium supply component 161 and the detrition simulation experimental component 162 are connected in parallel, the adjustment pipeline 163 and the output path 164 are connected in parallel, the adjustment pipeline 163 is connected to the regeneration medium supply component 161 and the detrition simulation experimental component 162, and the output path 164 is connected to the regeneration medium supply component 161 and the detrition simulation experimental component 162.
[0090] In this technical solution, the structural composition of an experimental simulation unit 160 is further provided. In addition to being used for heating the regenerated medium, the experimental simulation unit 160 can also store the regenerated medium to output the regenerated medium, and can also be used to store the medium for actual measurement and simulation of the detritiation system. Through the setting of the experimental simulation unit 160, the actual detritiation effect of the detritiation unit 110 can be tested, and the regeneration performance can also be tested.
[0091] In this technical solution, the experimental simulation unit 160 includes a regeneration medium supply component 161. Based on this, when the drying tower 111 in the detritiation unit 110 is regenerated by the regeneration unit 130, the regeneration medium supply component 161 can be opened to output the regeneration medium. The regeneration medium adjusts the output flow of the regeneration medium through the adjustment pipeline 163, and then the regeneration medium can be output to the regeneration pipeline 131 of the regeneration unit 130 through the output path 164, and then supplied to the drying tower 111 after being further heated by the heater 132, so as to heat and regenerate the molecular sieve desiccant in the drying tower 111, so that the detritiation system can operate efficiently.
[0092] In this technical solution, the experimental simulation unit 160 also includes a detritiation simulation experimental component 162. Based on this, helium can be stored in the detritiation simulation experimental component 162. When the performance of the detritiation system is then tested, the detritiation simulation experimental component 162 can output a test medium whose dew point value is greater than or equal to a first threshold value. The test medium can be input into the detritiation unit 110 through the input unit 120. After that, it is only necessary to detect the dew point of the medium output through the output unit 140 to determine the detritiation effect of the detritiation unit 110. Based on the same principle, after the drying tower 111 is regenerated through the regeneration medium supply component 161 and the heater 132, the detritus removal simulation experiment component 162 can also output a test medium with a dew point value greater than or equal to the first threshold value. The test medium can be input into the detritus removal unit 110 through the input unit 120. After that, it is only necessary to detect the dew point of the medium output through the output unit 140 to determine the regeneration effect of the detritus removal unit 110 drying tower 111, which is convenient for clarifying the temperature and supply flow rate of the regeneration medium, making the use of the detritus removal system safer and more efficient.
[0093] like Figure 1 and Figure 2 As shown, in a feasible embodiment, the regeneration medium supply component 161 includes: a supply pipeline 1611, a first gas cylinder 1612, a fifth control valve 1613, and a first flow meter 1614. The supply pipeline 1611 is connected to the first gas cylinder 1612, the fifth control valve 1613 and the first flow meter 1614 are arranged on the supply pipeline 1611, and the regulating pipeline 163 and the output pipeline 164 are connected to the supply pipeline 1611.
[0094] In this technical solution, a structural composition of a regeneration medium supply component 161 is further provided. The first gas cylinder 1612 can be used to store the regeneration medium. The setting of the fifth control valve 1613 facilitates the control of the output, closing and opening of the first gas cylinder 1612. The setting of the first flow meter 1614 facilitates the detection of the medium output from the supply pipeline 1611. Based on this, when the detritiation unit 110 is regenerated through the regeneration medium supply assembly 161, the fifth control valve 1613 can be opened, the first gas cylinder 1612 outputs the regeneration medium, and the supply pipeline 1611 is connected to the regulating pipeline 163. In this case, the opening of the fifth control valve 1613 can be adjusted, and the degree of the first flow meter 1614 can be observed. When the flow rate of the regeneration medium supply meets the expected requirements, the regulating pipeline 163 can be closed, and the supply pipeline 1611 is connected to the output pipeline 164. The output pipeline 164 can output the regeneration medium of the target flow rate to the regeneration pipeline 131. After the regeneration medium is heated by the heater 132, the molecular sieve desiccant in the drying tower 111 can be regenerated.
[0095] In some examples, in order to reduce costs and ensure the reliability of the detritus removal system, the medium stored in the first gas cylinder 1612 may be nitrogen.
[0096] In some examples, in order to facilitate the detection of the dew point and pressure of the medium output through the detritus removal simulation experiment component 162 and the medium output through the regeneration medium supply component 161, a second dew point meter 166, a regeneration test instrument valve 167 and a fourth pressure detection component 168 can also be arranged on the output line 164.
[0097] In a feasible embodiment, the tritium removal simulation experiment component 162 includes: a simulation pipeline 1621, a second gas cylinder 1622, a humidifier 1623, a gas-water separator 1624 and a sixth control valve 1625, the simulation pipeline 1621 is connected to the second gas cylinder 1622, the humidifier 1623, the gas-water separator 1624 and the sixth control valve 1625 are sequentially arranged on the simulation pipeline 1621, and the regulating pipeline 163 and the output line 164 are connected to the simulation pipeline 1621.
[0098] In this technical solution, the structural composition of the detritiation simulation experiment component 162 is further provided. When the performance of the detritiation system needs to be tested, the sixth control valve 1625 can be opened, and then the second gas cylinder 1622 outputs the test medium, and the humidifier 1623 and the gas-water separator 1624 are turned on at the same time. In this case, the test medium can be output through the adjustment pipeline 163. In this process, the dew point temperature of the test medium can be adjusted by adjusting the humidifier 1623 and the gas-water separator 1624. When the dew point temperature meets the test requirements, the adjustment pipeline 163 can be closed, so that the test medium is output to the input unit 120 via the output path 164, and the test medium can enter the detritiation unit 110. Thereafter, the dew point of the test medium output via the detritiation unit 110 is detected to test the actual detritiation effect of the detritiation unit 110.
[0099] It can be understood that, based on the same principle, when it is necessary to test the regeneration effect of the detritiation unit 110, after completing the regeneration of the detritiation unit 110, the sixth control valve 1625 can be opened, and then the second gas cylinder 1622 outputs the test medium, and the humidifier 1623 and the gas-water separator 1624 are turned on at the same time. In this case, the test medium can be output through the adjustment pipeline 163. In this process, the dew point temperature of the test medium can be adjusted by adjusting the humidifier 1623 and the gas-water separator 1624. When the dew point temperature meets the test requirements, the adjustment pipeline 163 can be closed, so that the test medium is output to the input unit 120 via the output path 164, and the test medium can enter the detritiation unit 110. Thereafter, the dew point of the test medium output through the detritiation unit 110 is detected to test the actual regeneration effect of the detritiation unit 110.
[0100] In a feasible implementation, a seventh control valve 165 is provided on the regulating pipeline 163. Such a configuration facilitates the control of the opening and closing of the regulating pipeline 163. When adjusting the dew point of the test medium or the flow rate of the regeneration medium, the seventh control valve 165 can be in an open state. After the test medium or the regeneration medium is debugged, the seventh control valve 165 can be closed to allow the test medium or the regeneration medium to be output through the output path 164.
[0101] like Figure 1 and Figure 2 As shown, in a feasible implementation, the output path 164 includes a first output port 1641 and a second output port 1642, the first output port 1641 is used to connect to the input unit 120, and the second output port 1642 is used to connect to the regeneration unit 130. Based on this, it is convenient to connect the output path 164 with the input unit 120 and the regeneration unit 130, so that different medium gases can be supplied to the expected units, which can make the use of the detritus removal system more convenient, avoid frequent switching of the connection mode of the pipeline, and reduce the probability of erroneous operation.
[0102] like Figure 1 and Figure 2 As shown, in a feasible implementation, the output unit 140 includes: an output pipeline 141, connected to the output end of the detritiation unit 110; a post-filter 142, arranged on the output pipeline 141; an eighth control valve 143, arranged at the output end of the output pipeline 141; a third pressure detection member 144, connected to the output pipeline 141; a first dew point meter 145, connected to the output pipeline 141; and an eleventh control valve 146, arranged between the first dew point meter 145 and the output pipeline 141. Based on this, after the detritiation unit 110 is used to detritate the helium containing tritiated water, the post-filter 142 can be used to further filter out solid and liquid particles, and then input into the helium circuit to complete the detritiation of the helium containing tritiated water. The eighth control valve 143 is used to facilitate the control of the opening and closing of the output pipeline 141.
[0103] In this technical solution, in addition to outputting detritiated helium during actual operation, the output unit 140 can also be used to output a medium for testing the detritiation system. By opening the eleventh control valve 146, the detritiated test medium can be tested through the first dew point meter 145, and then the actual detritiation effect and regeneration effect of the detritiation unit 110 can be detected, making the use of the detritiation system safer and more efficient.
[0104] In some examples, in order to improve filtering efficiency, the interior of the pre-filter 122 and the post-filter 142 are filled with sintered 304 stainless steel material.
[0105] like Figure 1 and Figure 2 As shown, in a feasible embodiment, the emptying unit 150 includes: an emptying pipeline 151, connected to the output end of the detritus unit 110; a vacuum pipeline 152, connected to the output end of the emptying pipeline 151; a ninth control valve 153, arranged on the vacuum pipeline 152; an emptying pipe 154, connected to the output end of the emptying pipe 151; a muffler 155, arranged on the emptying pipe 154; a third temperature sensor 156, connected to the emptying pipeline 151; and a tenth control valve 157, arranged on the emptying pipe 154.
[0106] In this technical solution, the structural composition of the emptying unit 150 is further provided. The emptying unit 150 may include an emptying pipeline 151, a vacuum pipeline 152, and a ninth control valve 153. Based on this, the vacuum pipeline 152 can be connected through a vacuum device, and then the ninth control valve 153 is opened. The detritiation unit 110 can be evacuated through the emptying pipeline 151, so that the detritiation system enters a state ready for use.
[0107] In this technical solution, the exhaust unit 150 may also include an exhaust pipe 154 and a muffler 155. Based on this, when the detritiation system is emptied, the gas medium can be discharged to the outside of the detritiation system through the exhaust pipe 154 and the muffler 155, which can reduce the exhaust noise and make it safer to use.
[0108] In some examples, in order to facilitate the control of the exhaust line 151 , the tenth control valve 157 may be disposed at the front end of the muffler 155 .
[0109] like Figure 3 As shown, according to the second aspect of the embodiment of the present application, a detritium removal method is proposed, which is applied to a detritium removal system as in any of the above technical solutions. The detritium removal method includes:
[0110] Step 301: vacuuming the detritus removal unit through an evacuation unit;
[0111] Step 302: inputting the medium containing tritiated water into a detritiation unit, and discharging the medium through an output unit after detritiation treatment;
[0112] Step 303: closing the input unit and the output unit, and emptying the detritus removal unit through the emptying unit;
[0113] Step 304: Start the regeneration unit to regenerate the detritus removal unit.
[0114] The detritiation method provided in the embodiment of the present application is applied to a detritiation system as in any of the above-mentioned technical solutions, so the detritiation method has all the beneficial effects of the detritiation system of the above-mentioned technical solutions.
[0115] like Figures 1 to 3 As shown, through the detritium removal method provided by the embodiment of the present application, the detritium removal unit 110 is first evacuated through the emptying unit 150, so that the detritium removal system enters a standby state, and then when detritium removal is required, the helium containing tritiated water can enter the detritium removal unit 110 through the input unit 120, and after the detritium removal unit 110 dries and adsorbs the tritiated water in the helium through the drying tower 111, the helium is discharged into the helium circuit through the output unit 140. After the detritium removal operation is completed, the system is depressurized, and specifically, the gas in the detritium removal system is emptied through the emptying unit 150. After that, the regeneration medium can be output through the regeneration unit 130, and the regeneration medium is heated at the same time, so that the regeneration medium heats and regenerates the molecular sieve desiccant in the drying tower 111, and then the medium used for regeneration can be discharged to the outside of the detritium removal unit 110 through the emptying unit 150, so that the detritium removal system can operate continuously, so that the detritium removal system is highly safe and easy to operate.
[0116] like Figure 1 and Figure 2 As shown, the detritium removal method provided in the embodiment of the present application, combined with the specific structure of the detritium removal system, may include the following steps:
[0117] The system is connected to connect the detritiation system to the fuel transient irradiation test circuit, wherein the input unit 120 and the output unit 140 are connected to the helium pipeline system of the test circuit, the exhaust pipe 154 of the exhaust unit 150 is connected to the exhaust system of the test circuit, and the vacuum pipeline 152 of the exhaust unit 150 is connected to the vacuum system of the test circuit.
[0118] The system is evacuated, and the detritiation system is evacuated using the fuel transient irradiation test circuit evacuation system and the evacuation pipeline 152. After the vacuum degree of the detritiation system meets the requirements, the ninth control valve 153 is closed, and the detritiation system is in a standby state.
[0119] The system removes tritium, opens the third control valve 123, and the helium containing tritiated water enters the drying tower 111 of the detritiated unit 110 from the input unit 120. After drying and adsorbing the tritiated water, it is discharged into the test loop helium pipeline system through the post-filter 142 and the eighth control valve 143 in sequence.
[0120] The system is depressurized, the third control valve 123 and the eighth control valve 143 are closed, the tenth control valve 157 and the second control valve 113 at the outlet of the detritus removal component are opened in sequence, and the helium in the detritus removal unit 110 is discharged to the exhaust system of the irradiation test circuit through the exhaust pipe 154.
[0121] The system is regenerated. The heater 132 and the fourth control valve 133 are turned on. The dry nitrogen is electrically heated and enters the drying tower 111 of the detritus removal unit 110 to heat and regenerate the molecular sieve desiccant. The regenerated gas coming out of the drying tower 111 is silenced by the exhaust port muffler 155 and then discharged into the exhaust system of the irradiation test circuit.
[0122] Therefore, the embodiment of the present invention aims at the detritium removal requirements of the transient irradiation test system in the nuclear fuel pile, realizes the removal of tritium from the helium loop, which is the core component of the test system, ensures the purity of the helium in the irradiation test loop, and prevents the release of radioactive tritium into the environment. The present invention adopts a molecular sieve drying and adsorption process to remove tritiated water in the helium loop. The detritium removal system is provided with 6 groups of parallel detritium removal components, each group of detritium removal components can be operated independently in sequence, and a pre-filter 122 and a post-filter 142 are respectively provided at the inlet and outlet of the detritium removal unit 110, which has the characteristics of high detritium removal efficiency, large gas processing capacity and long continuous operation time. In addition, the present invention adopts an inert gas electric heating method to regenerate the molecular sieve desiccant, and the detritium removal waste gas is discharged to the waste gas treatment system, and the detritium removal and regeneration are performed through a computer remote operation system. The detritium removal system adopts a modular design and layout, and has the characteristics of high safety, convenient installation and operation, etc.
[0123] like Figure 1 and Figure 2 As shown, in a feasible implementation, the detritiation method further includes: in response to a leak detection instruction, supplying an experimental medium to the detritiation system through the experimental simulation unit 160, and controlling the output end of the detritiation system to be in a closed state to perform leak detection.
[0124] In this technical solution, considering the safe operation of the detritiation system, the leakage points of the detritiation system can also be detected. Based on this, the experimental medium can be supplied to the detritiation unit 110, and the detritiation system can be kept at a certain pressure. After that, the output end of the detritiation unit 110 is controlled to be in a closed state, and the leakage points of the detritiation system can be detected, thereby ensuring the safe operation of the equipment.
[0125] like Figure 1 and Figure 2 As shown, in some examples, in combination with the specific structure of the detritium removal system, in response to the leak detection instruction, the specific control of the detritium removal system may include the following steps:
[0126] Open the fifth control valve 1613 of the experimental simulation unit 160, the instrument valve before the fourth pressure detection member 168 and the first output port 1641, and close the second output port 1642 and the twelfth control valve 1626 of the experimental simulation unit 160;
[0127] Open the third control valve 123, the first control valve 112 and the second control valve 113 of the detritiation system, close the eighth control valve 143, the tenth control valve 157 and the fourth control valve 133 of the detritiation system, first slowly increase the pressure of the detritiation system to 3.5MPa, and then increase the pressure by 0.5MPa in steps until it reaches the test pressure and then maintain the pressure for 30 minutes. Preferably, the test pressure is 7MPa. During the pressure maintenance period, apply a leak detection agent to the welds and mechanical connections for inspection. After the test, reduce the pressure of the detritiation system to atmospheric pressure. Specifically, the test is qualified if there are no bubbles, abnormal sounds, or visible deformations in the welds and mechanical connections during the test.
[0128] In a feasible embodiment, the detritiation method further includes: in response to a test instruction, supplying a test medium having a dew point temperature greater than or equal to a first threshold to the detritiation unit 110 through the experimental simulation unit 160 to test the dew point value of the medium discharged through the output end of the detritiation unit 110.
[0129] In this technical solution, considering the need to accurately understand the detritiation capability of the detritiation system, it is also possible to respond to a test instruction, and then supply a test medium with a known dew point to the detritiation unit 110, and then detect the dew point value of the medium output by the detritiation unit 110, so that the detritiation effect of the detritiation system can be known, making the use of the equipment more reliable.
[0130] like Figure 1 and Figure 2 As shown, in some examples, in combination with the specific structure of the detritium removal system, in response to the test instruction, the specific control of the detritium removal system may include the following steps:
[0131] Test flow adjustment: close the fifth control valve 1613, the first output port 1641 and the second output port 1642 of the test simulation unit 160, open the sixth control valve 1625, the tenth control valve 157 and the seventh control valve 165, and adjust the helium test flow output through the detritus simulation test component 162. Preferably, adjust the helium test flow to 2.4±0.1Nm 3 / h;
[0132] Helium dew point measurement and adjustment: after the helium test flow rate reaches the target value, open the regeneration test instrument valve 167, measure the helium dew point at the inlet of the detritus removal system, and adjust the helium dew point by changing the water level of the humidifier 1623. Preferably, the helium dew point is adjusted to ≥6°C;
[0133] The drying tower 111 adsorbs, and the input unit 120 of the detritiation system, the first control valve 112 and the second control valve 113 of the single group of drying towers 111 are opened, and the six groups of drying towers 111 of the detritiation unit 110 are subjected to adsorption tests in turn. The test time of each group of drying towers 111 is 4 hours. After the adsorption test of each group of drying towers 111 is completed, the helium dew point at the outlet of the drying tower 111 measured by the first dew point meter 145 of the output unit 140 is recorded. Preferably, the helium dew point measured by the first dew point meter 145 at the outlet of the drying tower 111 is ≤-40°C to be qualified.
[0134] like Figure 1 and Figure 2 As shown, in a feasible embodiment, the detritiation method also includes: in response to the regeneration experiment instruction, after completing the adsorption experiment of the detritiation unit 110, supplying regeneration medium to the detritiation unit 110 through the regeneration medium supply component 161 of the experimental simulation unit 160 to regenerate the detritiation unit 110, and then outputting a test medium with a dew point temperature greater than or equal to a first threshold to the detritiation unit 110 through the detritiation simulation experiment component 162, and testing the dew point value of the medium discharged through the output end of the detritiation unit 110 after the detritiation unit 110 is regenerated.
[0135] In this technical solution, considering that the detritiation unit 110 can be regenerated by the setting of the regeneration unit 130, the detritiation effect after the detritiation system is regenerated should be verified. Based on this, the detritiation system can also respond to the regeneration experiment instruction. The regeneration medium can be first supplied to the detritiation unit 110 through the regeneration medium supply component 161 of the experimental simulation unit 160, and the heater 132 heats the regeneration medium to regenerate the drying tower 111. After the regeneration is completed, the detritiation simulation experiment component 162 can output a test medium with a dew point temperature greater than or equal to the first threshold to the detritiation unit 110, and then the dew point value of the medium output through the detritiation unit 110 is detected, so that the regeneration effect of the detritiation system can be known, making the use of the equipment safer and more reliable.
[0136] In some examples, in combination with the specific structure of the detritus removal system, in response to the regeneration experiment instruction, the specific control of the detritus removal system may include the following steps:
[0137] Test flow adjustment: close the sixth control valve 1625 of the test system, the twelfth control valve 1626 set at the output end of the simulation pipeline 1621, the first output port 1641 and the second output port 1642, open the fifth control valve 1613 and the seventh control valve 165 of the test system, and adjust the nitrogen test flow output through the regeneration medium supply component 161; preferably, adjust the nitrogen test flow to 4.2±0.2Nm 3 / h;
[0138] Nitrogen dew point measurement and adjustment: after the nitrogen test flow rate reaches the target value, open the regeneration test instrument valve 167, measure the nitrogen dew point at the inlet of the detritus removal system, and adjust the nitrogen dew point by replacing the gas source; preferably, adjust the nitrogen dew point to ≤-40°C;
[0139] Regeneration by electric heating, open the fourth control valve 133 of the regeneration pipeline 131, the inlet and outlet valves of the single group of drying towers 111 and the tenth control valve 157 of the exhaust pipe 151, and perform regeneration tests on the six groups of drying towers 111 of the detritus removal unit 110 in turn; during the test, first set the temperature of the electric heater 132 to 290°C and turn on the electric heating, when the inlet and outlet nitrogen temperatures of the drying tower 111 stabilize at the set value, preferably, the inlet and outlet nitrogen temperature setting values of the drying tower 111 are 190°C±25°C and >100°C respectively, the electric heater 132 continues to heat for 30 minutes and then turns off, and continues to ventilate until the nitrogen temperature at the outlet of the drying tower 111 drops to below the target value of 60°C, and the regeneration is completed. The detritiation system is evacuated to remove the regeneration medium, and then the six groups of drying towers 111 of the detritiation unit 110 are subjected to adsorption tests in turn. The test time of each group of drying towers 111 is 4 hours. After the adsorption test of each group of drying towers 111 is completed, the helium dew point at the outlet of the drying tower 111 measured by the first dew point meter 145 of the output unit 140 is recorded. Preferably, the helium dew point measured by the first dew point meter 145 at the outlet is ≤-40°C, which means the regeneration test is qualified.
[0140] In a feasible embodiment, in response to the regeneration instruction, the step of supplying the regeneration medium to the detritiation unit 110 through the regeneration unit 130 includes: turning on the heater 132 of the regeneration unit 130, supplying the regeneration medium to the detritiation unit 110 through the regeneration pipeline 131, the regeneration medium heating and regenerating the molecular sieve desiccant in the drying tower 111, and then discharging the gas through the exhaust unit 150.
[0141] In this technical solution, specific steps of regeneration are further provided. The regeneration medium can be input into the detritiation unit 110 through the regeneration pipeline 131. The heater 132 can be turned on during the regeneration process. The heater 132 can heat the regeneration medium. The heated medium enters the drying tower 111 and contacts the molecular sieve desiccant in the drying tower 111, thereby heating the molecular sieve desiccant, carrying the water vapor on the molecular sieve desiccant, and then being discharged to the detritiation system through the emptying unit 150, thereby improving the regeneration efficiency of the drying tower 111. The fourth control valve 133 is provided to facilitate the control of the opening and closing of the regeneration pipeline 131. The first temperature sensor 134 is provided to facilitate the monitoring of the operating temperature of the heater 132. The second temperature sensor 135 is provided to facilitate the monitoring of the temperature of the heated medium, thereby ensuring the feasibility of regeneration.
[0142] In the present invention, the terms "first", "second", and "third" are used for descriptive purposes only and should not be understood as indicating or implying relative importance; the term "plurality" refers to two or more, unless otherwise clearly defined. The terms "installed", "connected", "connected", "fixed", etc. should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; "connected" can be a direct connection or an indirect connection through an intermediate medium. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0143] In the description of the present invention, it is necessary to understand that the directions or positional relationships indicated by terms such as “upper”, “lower”, “left”, “right”, “front” and “back” are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or unit referred to must have a specific direction, be constructed and operated in a specific orientation, and therefore, cannot be understood as a limitation on the present invention.
[0144] In the description of this specification, the description of the terms "one embodiment", "some embodiments", "specific embodiments", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0145] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A detritium removal system, characterized in that: include: Detritium unit; An input unit, the input unit being connected to an input end of the detritium removal unit; a regeneration unit, the regeneration unit being connected to an input end of the detritus removal unit; an output unit, the output unit being connected to an output end of the detritus removal unit; an emptying unit, the emptying unit being connected to an output end of the detritus removal unit; Wherein, the detritiation unit includes a plurality of detritiation components arranged in parallel, each of the detritiation components includes a drying tower, a first control valve and a second control valve, the first control valve is arranged at the input end of the drying tower, and the second control valve is arranged at the output end of the drying tower.
2. The detritium removal system according to claim 1, characterized in that: The input unit comprises: An input pipeline, the input pipeline being connected to an input end of the detritus removal unit; A pre-filter, wherein the pre-filter is arranged on the input pipeline; a third control valve, the third control valve being arranged at an input end of the input pipeline; A first pressure detection component is connected to the input pipeline.
3. The detritium removal system according to claim 1, characterized in that: The regeneration unit comprises: a regeneration pipeline, the regeneration pipeline being connected to an input end of the detritus removal unit; A heater, wherein the heater is arranged on the regeneration pipeline; a fourth control valve, the fourth control valve being arranged at an input end of the regeneration pipeline; a first temperature sensor connected to the heater; A second temperature sensor is connected to the regeneration pipeline and is located at the output end of the heater.
4. The detritium removal system according to claim 3, characterized in that: Also includes: An experimental simulation unit, the experimental simulation unit comprising: A regeneration medium supply component, a detrition simulation experiment component, a regulating pipeline and an output path, wherein the regeneration medium supply component and the detrition simulation experiment component are connected in parallel, the regulating pipeline and the output path are connected in parallel, the regulating pipeline is connected to the regeneration medium supply component and the detrition simulation experiment component, and the output path is connected to the regeneration medium supply component and the detrition simulation experiment component.
5. The detritiation system according to claim 4, characterized in that: The regeneration medium supply assembly comprises: a supply pipeline, a first gas cylinder, a fifth control valve, and a first flow meter, wherein the supply pipeline is connected to the first gas cylinder, the fifth control valve and the first flow meter are arranged on the supply pipeline, and the regulating pipeline and the output path are connected to the supply pipeline; The detritium simulation experiment assembly comprises: a simulation pipeline, a second gas cylinder, a humidifier, a steam-water separator and a sixth control valve, the simulation pipeline is connected to the second gas cylinder, the humidifier, the steam-water separator and the sixth control valve are sequentially arranged on the simulation pipeline, and the regulating pipeline and the output path are connected to the simulation pipeline; A seventh control valve is provided on the regulating pipeline; The output path includes a first output port and a second output port, the first output port is used to be connected to the input unit, and the second output port is used to be connected to the regeneration unit.
6. The detritiation system according to claim 1, characterized in that: The output unit comprises: an output pipeline, the output pipeline being connected to an output end of the detritus removal unit; A post-filter, the output pipeline is arranged on the output pipeline; an eighth control valve, the eighth control valve being arranged at an output end of the output pipeline; a third pressure detection component, the third pressure detection component being connected to the output pipeline; a first dew point meter, the first dew point meter being connected to the output pipeline; An eleventh control valve, wherein the eleventh control valve is arranged between the first dew point meter and the output pipeline.
7. The detritium removal system according to claim 1, characterized in that: The emptying unit comprises: an exhaust pipeline, the exhaust pipeline being connected to an output end of the detritus removal unit; A vacuum pumping pipeline, the vacuum pumping pipeline is connected to the output end of the exhaust pipeline; a ninth control valve, the ninth control valve being arranged on the vacuum pumping pipeline; an exhaust pipe, the exhaust pipe being connected to an output end of the exhaust pipeline; a muffler, the muffler being arranged on the exhaust pipe; a third temperature sensor, the third temperature sensor being connected to the exhaust pipeline; A tenth control valve is provided on the exhaust pipe.
8. A method for removing tritium, characterized in that: Applied to the detritiation system according to any one of claims 1 to 7, the detritiation method comprises: Performing a vacuum process on the detritus removal unit by means of the evacuation unit; Inputting the medium containing tritiated water into the detritiation unit, and discharging it through the output unit after detritiation treatment; Closing the input unit and the output unit, and emptying the detritus removal unit through the emptying unit; The regeneration unit is turned on to regenerate the detritus removal unit.
9. The detritium removal method according to claim 8, characterized in that: Also includes: In response to a leak detection instruction, an experimental medium is supplied to the detritiation system through an experimental simulation unit, and an output end of the detritiation system is controlled to be in a closed state to perform leak point detection; In response to a test instruction, supplying a test medium having a dew point temperature greater than or equal to a first threshold to the detritium removal unit through the experimental simulation unit, and testing a dew point value of a medium discharged through an output end of the detritium removal unit; In response to the regeneration experiment instruction, the regeneration medium is supplied to the detritiation unit through the regeneration medium supply component of the experimental simulation unit to regenerate the detritiation unit, and then the detritiation simulation experiment component outputs a test medium with a dew point temperature greater than or equal to a first threshold to the detritiation unit to test the dew point value of the medium discharged through the output end of the detritiation unit.
10. The detritium removal method according to claim 9, characterized in that: The step of supplying a regeneration medium to the detritus removal unit through the regeneration unit in response to the regeneration instruction comprises: The heater of the regeneration unit is turned on, and a regeneration medium is supplied to the detritus removal unit through a regeneration pipeline. The regeneration medium heats and regenerates the molecular sieve desiccant in the drying tower, and then the gas is discharged through an exhaust unit.
Citation Information
Patent Citations
Tritiated water recycling device and achieving method thereof
CN105032122A
Glove box tritium removal purification treatment system and using method thereof