Water tank glass mounting structure and construction method

By using the installation structure of supporting columns and enclosing glass in the sink, combined with the adhesive layer and reinforced crossbar, the problem of uneven inner wall of the sink is solved, and the effect of wave current experiment and the stability of glass installation are improved.

CN119145697AActive Publication Date: 2024-12-17SHANGHAI CONSTRUCTION NO 7 (GROUP) CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411169518.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-24
Publication Date
2024-12-17
Estimated Expiration
2044-08-24

AI Technical Summary

Technical Problem

Under special use requirements, the inner wall of the sink needs to be flat and smooth. The installation method of existing concrete or steel structure U-shaped slots will interfere with the water flow and affect the wave flow experimental data.

Method used

The installation structure of the supporting column and the enclosing glass is adopted, and the enclosing glass is bonded to the inner side of the supporting column by using the first adhesive layer, and the connection strength is strengthened by reinforcement of the crossbar and suction cup to ensure the flatness and stability of the inner wall of the sink.

Benefits of technology

The high flatness of the inner wall of the sink is achieved, the effect of the wave current experiment is improved, and the stability of glass installation is ensured by enhancing the connection strength.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119145697A_ABST
    Figure CN119145697A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of water tank glass installation, and provides a water tank glass installation structure which comprises a plurality of supporting stand columns and a plurality of pieces of enclosing glass. The supporting stand columns extend in the height direction of the water tank, the bottom ends of the supporting stand columns are embedded into the manufacturing face of the water tank, and the multiple supporting stand columns are arranged in the circumferential direction of the water tank at intervals. The surrounding glass is connected to the inner sides of the supporting stand columns, the water tank is defined by the multiple pieces of surrounding glass in the circumferential direction of the water tank, and the effects that the flatness of the inner wall of the water tank is improved, and the good effect of a wave current experiment is achieved are achieved. The invention further provides a construction method of the water tank glass installation structure. The construction method comprises the construction steps of supporting stand column construction, enclosure glass construction and the like.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of water tank glass installation technology, and in particular to a water tank glass installation structure and a construction method. Background Art

[0002] For common glass pool or glass trough structures, there are usually two ways to install the glass wall. One is to bury the glass wall directly into the concrete, and the other is to use a steel structure U-shaped slot to fix it to ensure the installation stability of the glass.

[0003] When the water tank has special use requirements, such as wave and flow experiments, the protruding concrete or steel structure U-shaped slot will interfere with the water flow, forming irregular waves, which will have a great impact on the experimental data. Therefore, under such special use requirements, the inner wall of the water tank is required to be flat and smooth, without protrusions, depressions, and large horizontal and vertical errors.

[0004] Based on this, a mounting structure and construction method of a water tank glass are needed to ensure the flatness of the inner wall of the water tank, so as to achieve good results in the wave flow experiment. Summary of the invention

[0005] In order to improve the flatness of the inner wall of a water tank and achieve good results in wave and flow experiments, the present application provides a water tank glass installation structure and a construction method.

[0006] On the one hand, the present application provides a water tank glass installation structure adopts the following technical solution: A water tank glass installation structure comprises a plurality of supporting columns and a plurality of enclosed glasses; the supporting columns are extended along the height direction of the water tank, the bottom ends of the supporting columns are embedded in the manufacturing surface of the water tank, and the plurality of supporting columns are arranged at intervals along the circumference of the water tank; the enclosed glasses are connected to the inner sides of the supporting columns, and the plurality of enclosed glasses are arranged along the circumference of the water tank to form the water tank; a first adhesive layer is arranged between the enclosed glasses and the supporting columns, the first adhesive layer comprises a structural adhesive portion and a weather-resistant adhesive portion, and the weather-resistant adhesive portion is arranged around the circumference of the structural adhesive portion.

[0007] By adopting the above technical solution, when constructing the water tank glass, the supporting columns are first arranged at intervals along the circumference of the water tank, and then the enclosed glass is bonded to the inner wall of the supporting columns through the first adhesive layer, so that the enclosed glass is mainly fixed by the supporting columns, and because the supporting columns are connected to the outer surface of the enclosed glass, that is, the outer wall of the water tank, the flatness of the inner wall of the water tank can be ensured, so that the wave flow experiment can achieve good results. Among them, the structural adhesive part of the first adhesive layer mainly plays a bonding role, and the weather-resistant adhesive part mainly plays a sealing and waterproofing role to ensure the connection stability between the enclosed glass and the supporting columns.

[0008] Optionally, the manufacturing surface is provided with a first mounting groove, which is arranged around the circumference of the water tank, and the enclosed glass is inserted into the first mounting groove; the top of the supporting column is connected to a plurality of supporting cross columns, and the plurality of supporting cross columns are arranged end to end along the circumference of the water tank, and the side walls of the supporting cross columns are used for connection to the top of the enclosed glass; a second adhesive layer is provided between the enclosed glass and the supporting cross columns.

[0009] By adopting the above technical solution, when installing the enclosed glass, the enclosed glass is first inserted into the first installation groove, and then the enclosed glass is bonded and fixed to the supporting columns and supporting horizontal columns, thereby improving the installation stability of the enclosed glass.

[0010] Optionally, it further includes a bottom glass, wherein the bottom glass is located at the bottom of the water tank, and the side wall of the bottom glass abuts against the inner wall of the enclosing glass.

[0011] By adopting the above technical solution, after the installation of the enclosing glass is completed, the ground glass is placed on the bottom wall of the water tank to ensure the flatness of the bottom wall of the water tank, thereby further improving the experimental effect of the wave and flow experiment.

[0012] Optionally, it also includes a plurality of reinforcing cross columns, which are all horizontally arranged and arranged along the circumference of the water tank; the length of the reinforcing cross columns is greater than the spacing between adjacent supporting columns, and the two ends of the reinforcing cross columns are respectively connected to adjacent supporting columns; the surface of the reinforcing cross columns facing the enclosed glass is provided with a suction cup, and the suction cup is adsorbed on the enclosed glass.

[0013] By adopting the above technical solution and adding reinforcing cross columns and suction cups, the connection strength between the enclosing glass and the supporting columns is further strengthened.

[0014] Optionally, a support frame is provided on the outer wall of the support column, and the reinforcing cross bar is slidably connected to the support frame along the thickness direction of the enclosed glass; a first airbag is provided between the reinforcing cross bar and the support column, and the first airbag is connected to a first connecting tube, and the tube cavity of the first connecting tube is away from the end of the first airbag and passes through the surface of the suction cup; a first one-way valve is provided in the inner cavity of the first connecting tube, and the first one-way valve is used to prevent the gas in the first airbag from entering between the suction cup and the enclosed glass; the first airbag is also connected to a second connecting tube, and the other end of the second connecting tube is connected to the second airbag; a second one-way valve is provided in the second connecting tube, and the second one-way valve is used to prevent the gas in the second airbag from entering the first airbag.

[0015] By adopting the above technical solution, if the enclosed glass falls off or tends to fall off relative to the supporting column, the enclosed glass will drive the reinforcing cross column to move toward the supporting column through the suction cup. During the movement, the reinforcing cross column pressurizes the singular air bag, and the gas in the first air bag enters the second air bag. Under the action of air pressure, the gas between the suction cup and the enclosed glass enters the first air bag, thereby reducing the gas between the suction cup and the enclosed glass and increasing the connection strength between the suction cup and the enclosed glass.

[0016] Optionally, a second adhesive layer is provided between the suction cup and the enclosing glass, and the second adhesive layer is provided around the central axis of the suction cup.

[0017] By adopting the above technical solution, the second adhesive layer is used to seal the space between the suction cup and the enclosing glass, thereby reducing the risk of external gas entering between the suction cup and the enclosing glass, and further strengthening the connection strength between the suction cup and the enclosing glass.

[0018] On the other hand, the present application provides a method for constructing a water tank glass, which is used to construct the above-mentioned water tank glass installation structure, comprising the following steps: S1: opening a second installation groove on the manufacturing surface of the water tank, wherein the width of the second installation groove is not less than the sum of the thickness of the enclosed glass and the thickness of the supporting column; S2: first inject concrete slurry into the second installation groove, and then insert a plurality of the support columns into the concrete slurry of the second installation groove at intervals; before the concrete slurry solidifies, support the support columns with support components; after the concrete slurry solidifies, the support columns, the groove wall of the second installation groove define the first installation groove; S3: Determine the first bonding surface between the enclosed glass and the support column, and apply structural glue at the middle of the first bonding surface; then insert the enclosed glass into the first installation groove, and make the first bonding surface abut against the support column; then use weather-resistant glue to seal the edge of the first bonding surface; S4: using weather-resistant glue to seal the inner surface of the enclosed glass and the groove wall of the first installation groove, and making the weather-resistant glue protrude from the groove wall of the first installation groove during the edge sealing; S5: After the weather-resistant adhesive is completely solidified, the weather-resistant adhesive protruding from the inner surface of the enclosed glass is cut off to ensure that the inner surface of the enclosed glass is smooth.

[0019] Optionally, the supporting assembly includes a first diagonal brace and a second diagonal brace, the first diagonal brace abuts against the inner wall of the supporting column, and the second diagonal brace abuts against the outer wall of the supporting column; the first diagonal brace is connected to a shaping strip, the width of the shaping strip is the same as the width of the enclosed glass, the shaping strip is inserted into the first mounting groove, and the shaping strip abuts against the inner wall of the supporting column.

[0020] By adopting the above technical solution, the first installation groove is formed by a shaping strip to ensure the flatness and regularity of the groove wall of the first installation groove. On the one hand, it is convenient for the subsequent installation of the enclosing glass. On the other hand, the fit between the enclosing glass and the groove wall of the first installation groove is improved, further ensuring the flatness of the inner wall of the water tank and improving the experimental effect of the wave and flow experiment.

[0021] Optionally, the second diagonal support includes an diagonal support plate, a first horizontal support plate and a second horizontal support plate; one side of the first horizontal support plate is connected to the diagonal support plate, and the other side is used to abut against the enclosed glass; one side of the second horizontal support plate is connected to the diagonal support plate, and the other side is used to abut against the enclosed glass; the shaping strip is connected to the lower surface of the second horizontal support plate; the lower surface of the first horizontal support plate is connected to a plurality of cylinders, and the plurality of cylinders are arranged at intervals along the length direction of the shaping strip, and the plurality of output ends of the plurality of cylinders are connected to vibrating rods; the second horizontal support plate is penetrated by a plurality of first through holes for the vibrating rods to pass through, and the shaping strip is penetrated by a plurality of second through holes for the vibrating rods to pass through, and the first through holes and the second through holes are connected to each other; the surface of the shaping strip facing away from the second horizontal support plate is connected to an elastic sheet, and the elastic sheet is used to isolate the concrete slurry in the second mounting groove from the second through hole.

[0022] By adopting the above technical solution, after the installation of the second diagonal brace is completed, the cylinder of the installed second diagonal brace is started, and the cylinder is used to drive the vibrating rod to move back and forth up and down in the first through hole and the second through hole. On the one hand, the concrete slurry in the second installation groove is vibrated, and on the other hand, the penetration of the concrete slurry into the inside of the water tank is reduced by increasing the pressure of the shaping strip on the concrete slurry.

[0023] Optionally, the shaping strip is detachably connected to the second diagonal brace.

[0024] By adopting the above technical solution, it is convenient to replace the shaping strips of different widths according to the different thicknesses of the enclosing glass to be installed, thereby improving the flexibility of use of the second diagonal brace.

[0025] In summary, the present application includes at least one of the following beneficial technical effects: 1. By arranging a plurality of supporting columns on the periphery of the water tank, the enclosed glass is bonded to the inner wall of the supporting columns by using the first adhesive layer, so as to improve the flatness of the inner wall of the water tank formed by the enclosed glass and improve the experimental effect of the wave and flow experiment; 2. Further strengthen the connection between the enclosed glass and the supporting columns by setting up reinforcing crossbars and suction cups; 3. By arranging a shaping strip on the second diagonal support, it is convenient to form a relatively flat first installation groove, which is convenient for the installation of the enclosed glass on the one hand, and further ensures the flatness of the inner wall of the water tank on the other hand. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a structural diagram of Example 1 of the present application.

[0027] Figure 2 It is a schematic diagram for showing the installation of the enclosed glass in Example 1.

[0028] Figure 3 It is a schematic diagram for showing the structure of the first bonding layer.

[0029] Figure 4 yes Figure 2 An enlarged schematic diagram in part A.

[0030] Figure 5 yes Figure 2 An enlarged schematic diagram in part B.

[0031] Figure 6 A schematic diagram showing the structure of the support assembly.

[0032] Figure 7 yes Figure 6 An enlarged schematic diagram of part C.

[0033] Figure 8 It is a schematic diagram for showing the connection relationship between the shaping strip and the second horizontal support plate in Example 1.

[0034] Fig. 9 It is a schematic diagram for showing the structure of Example 2.

[0035] Fig.10 It is a schematic diagram for showing the connection relationship between the first airbag and the second airbag in Example 2.

[0036] Fig.11 It is a schematic diagram for showing the installation position of the bottom glass in Example 2.

[0037] Description of reference numerals: 1. Support column; 11. Support frame; 2. Enclosed glass; 3. First adhesive layer; 31. Structural adhesive portion; 32. Weather-resistant adhesive portion; 4. Second mounting groove; 41. Concrete slurry; 42. First mounting groove; 5. Supporting horizontal column; 6. Support assembly; 61. First diagonal brace; 62. Second diagonal brace; 621. Diagonal support plate; 622. First horizontal support plate; 623. Second horizontal support plate; 624. First magnet; 625. First through hole; 63. Shaping strip; 631. Second magnet; 632. Second through hole; 633. Elastic sheet; 64. Cylinder; 641. Vibrating rod; 7. Reinforcing cross column; 71. Suction cup; 72. Air pipe; 73. First air bag; 731. First connecting pipe; 732. First one-way valve; 733. Second connecting pipe; 734. Second air bag; 735. Second one-way valve; 736. Second adhesive layer; 8. Bottom glass. DETAILED DESCRIPTION

[0038] The following is combined with Figure 1-11 This application is described in further detail.

[0039] The embodiments of the present application disclose a water tank glass installation structure and a construction method.

[0040] Example 1 This embodiment discloses a water tank glass installation structure and a construction method.

[0041] Reference Figure 1 , Figure 2 and Figure 3 A water tank glass installation structure includes a plurality of support columns 1 and a plurality of enclosed glasses 2. The support columns 1 are extended along the height direction of the water tank, and the bottom ends of the support columns 1 are embedded in the manufacturing surface of the water tank (in this embodiment, the manufacturing surface of the water tank is the ground. In other embodiments, the manufacturing surface of the water tank can also be a roof or other horizontal surface), and the plurality of support columns 1 are arranged at intervals along the circumference of the water tank. The enclosed glasses 2 are connected to the inner sides of the support columns 1, and the plurality of enclosed glasses 2 are arranged along the circumference of the water tank to form the water tank. A first adhesive layer 3 is arranged between the enclosed glass 2 and the support columns 1, and the first adhesive layer 3 includes a structural adhesive portion 31 and a weather-resistant adhesive portion 32, and the weather-resistant adhesive portion 32 is arranged around the circumference of the structural adhesive portion 31.

[0042] During the construction of the water tank glass, the supporting columns 1 are first arranged at intervals along the circumference of the water tank, and then the enclosed glass 2 is bonded to the inner wall of the supporting columns 1, so that the enclosed glass 2 is mainly fixed by the supporting columns 1. Since the supporting columns 1 are connected to the outer surface of the enclosed glass 2, that is, the outer wall of the water tank, the flatness of the inner wall of the water tank can be ensured, so that the wave and flow experiment can achieve good results.

[0043] In this embodiment, the supporting column 1 is an I-beam.

[0044] Reference Figure 2 and Figure 4 Specifically, a second installation groove 4 is provided on the manufacturing surface of the water tank. The second installation groove 4 is arranged around the circumference of the water tank. The width of the second installation groove 4 is not less than the sum of the thickness of the enclosed glass 2 and the thickness of the supporting column 1. The second installation groove 4 is used to insert the enclosed glass 2 and the supporting column 1. When installing the enclosed glass 2 and the supporting column 1, concrete slurry 41 is first poured into the second installation groove 4, and then a plurality of supporting columns 1 are inserted into the concrete slurry 41. After the concrete slurry 41 solidifies, the solidified concrete, the groove wall of the second installation groove 4 and the supporting column 1 define a first installation groove 42 for inserting the enclosed glass 2, so as to further ensure the installation stability of the enclosed glass 2.

[0045] Reference Figure 5 Furthermore, the top of the support column 1 is connected to a plurality of support cross columns 5, and the plurality of support cross columns 5 are arranged end to end along the circumference of the water tank, and the side walls of the support cross columns 5 are used for connection with the top of the enclosed glass 2. A third adhesive layer (not shown in the figure) is provided between the enclosed glass 2 and the support cross columns 5, and the enclosed glass 2 and the support cross columns 5 are bonded and fixed by the third adhesive layer. In this embodiment, the support cross column 5 is an angle steel, and one flange of the support cross column 5 is connected to the upper side wall of the enclosed glass 2.

[0046] Reference Figure 3 , wherein the specific structure of the first adhesive layer 3 and the second adhesive layer 736 is as follows: Taking the first adhesive layer 3 as an example, the second adhesive layer 736 is the same. The connection surface between the enclosed glass 2 and the supporting column 1 is defined as the first connection surface, and the first adhesive layer 3 includes a structural adhesive portion 31 and a weather-resistant adhesive portion 32. The structural adhesive portion 31 is located in the middle of the first connection surface and plays a major connecting role. The weather-resistant adhesive portion 32 is arranged around the circumference of the structural adhesive portion 31 and is used to perform edge sealing treatment at the edge of the first connection surface to play a role of sealing and waterproofing to ensure the bonding reliability of the structural adhesive portion 31.

[0047] It is understandable that adjacent enclosure glasses 2 are also bonded and fixed to each other using a structure similar to the first bonding layer 3. In this embodiment, two sides of the support column 1 are respectively connected to two adjacent enclosure glasses 2 to enhance the waterproof performance between adjacent enclosure glasses 2.

[0048] This embodiment also provides a construction method of a water tank glass installation structure, which is used to install the above-mentioned water tank glass installation structure, comprising the following steps: S1: a second installation groove 4 is opened on the manufacturing surface of the water tank, and the width of the second installation groove 4 is slightly larger than the sum of the thickness of the enclosed glass 2 and the thickness of the supporting column 1.

[0049] S2: First, inject concrete slurry 41 into the second installation groove 4, and then insert multiple support columns 1 into the concrete slurry 41 of the second installation groove 4 at intervals. Before the concrete slurry 41 solidifies, use the support assembly 6 to support the support column 1. At the same time, place three positioning steel wires at the top, middle and bottom based on the central axis of the water tank to adjust the flatness and verticality. After the concrete slurry 41 solidifies, it defines the first installation groove 42 with the support column 1 and the groove wall of the second installation groove 4. Then fix the support cross column 5 to the upper end of the support column 1.

[0050] S3: Confirm the first bonding surface between the enclosed glass 2 and the support column 1 through measurement, and apply a certain amount of structural glue in the middle of the first bonding surface. Then insert the enclosed glass 2 into the first installation groove 42, and make the first bonding surface abut against the support column 1, use the structural glue to bond the enclosed glass 2 to the support column 1, and squeeze out the excess structural glue. After the bonding is stable, use a long-nosed glue gun to add the internal structural glue, and finally use weather-resistant glue to perform edge sealing at the edge of the first bonding surface.

[0051] S4: Use weather-resistant glue to perform edge sealing processing on the inner surface of the enclosed glass 2 and the groove wall of the first installation groove 42, and make the weather-resistant glue protrude from the groove wall of the first installation groove 42 during edge sealing.

[0052] S5: After the weather-resistant glue is completely solidified, the weather-resistant glue that exceeds or protrudes from the inner surface of the enclosing glass 2 is cut off to ensure the flatness of the inner surface of the enclosing glass 2 and further ensure the flatness of the inner wall of the water tank.

[0053] Reference Figure 6 and Figure 7 , wherein the support assembly 6 includes a first diagonal brace 61 and a second diagonal brace 62, the first diagonal brace 61 abuts against the inner wall of the support column 1, and the second diagonal brace 62 abuts against the outer wall of the support column 1. The first diagonal brace 61 is detachably connected with a shaping strip 63, and the shaping strip 63 is extended along the length direction of the first mounting groove 42, and the width of the shaping strip 63 is the same as the thickness of the enclosed glass 2. The shaping strip 63 is inserted into the first mounting groove 42, and the shaping strip 63 abuts against the inner wall of the support column 1. Thus, the first mounting groove 42 is formed by the shaping strip 63 to ensure the flatness and regularity of the groove wall of the first mounting groove 42, which is convenient for the subsequent installation of the enclosed glass 2 on the one hand, and improves the fit between the enclosed glass 2 and the groove wall of the first mounting groove 42 on the other hand, further ensures the flatness of the inner wall of the water tank, and improves the experimental effect of the wave and flow experiment.

[0054] The specific structure of the second diagonal support 62 is as follows: the second diagonal support 62 includes a diagonal support plate 621, a first horizontal support plate 622 and a second horizontal support plate 623. One side of the first horizontal support plate 622 is connected to the middle of the diagonal support plate 621, and the other side is used to abut against the enclosure glass 2. The second horizontal support plate 623 is located below the first horizontal support plate 622, one side of the second horizontal support plate 623 is connected to the bottom of the diagonal support plate 621, and the other side is used to abut against the enclosure glass 2. The shaping strip 63 is connected to the lower surface of the second horizontal support plate 623.

[0055] Reference Figure 8 A first magnet 624 is embedded on the side of the second horizontal support plate 623 close to the enclosed glass 2, and a second magnet 631 is embedded inside the shaping strip 63, so that the shaping strip 63 and the second horizontal support plate 623 are detachably connected through the magnetic attraction cooperation between the first magnet 624 and the second magnet 631, and then the shaping strip 63 and the second diagonal brace 62 are detachably connected, so that shaping strips 63 of different widths can be replaced according to the different thicknesses of the enclosed glass 2 to be installed, thereby improving the flexibility of use of the second diagonal brace 62.

[0056] Reference Figure 6 and Figure 7 Furthermore, a plurality of cylinders 64 are connected to the lower surface of the first horizontal support plate 622 , and the output shafts of the cylinders 64 are extended along the height direction of the second diagonal support 62 , and the plurality of second cylinders 64 are arranged at intervals along the length direction of the shaping strip 63 .

[0057] The output end of the second cylinder 64 is threadedly connected with a vibrating rod 641, and the second horizontal support plate 623 is penetrated by a plurality of first passages for the vibrating rod 641 to pass through. The plurality of first passage holes 625 are arranged at intervals along the length direction of the shaping strip 63 and correspond one-to-one to the plurality of vibrating rods 641.

[0058] The shaping strip 63 is penetrated by a plurality of second through holes 632 for the vibrating rod 641 to pass through. The plurality of second through holes 632 are arranged at intervals along the length direction of the shaping strip 63 . The plurality of second through holes 632 are connected to the plurality of first through holes 625 in a one-to-one correspondence and are coaxially arranged.

[0059] An elastic sheet 633 is bonded and fixed to the surface of the shaping strip 63 facing away from the second horizontal support plate 623 , and the elastic sheet 633 isolates the shaping strip 63 from the concrete slurry 41 in the second installation groove 4 .

[0060] After the support column 1 is inserted into the concrete slurry 41 of the second installation groove 4, the first diagonal braces 61 are supported on the outer wall of the support column 1, and the number of the first diagonal braces 61 corresponds to the number of the support columns 1. Then, a suitable number of second diagonal braces 62 are selected to support the inner wall of the support column 1. When the second diagonal braces 62 are constructed, it is important to make the shaping strips 63 of adjacent second diagonal braces 62 abut against each other.

[0061] After completing the installation of the second diagonal brace 62, start the cylinder 64 of the installed second diagonal brace 62, and use the cylinder 64 to drive the vibrating rod 641 to move back and forth up and down in the first through hole 625 and the second through hole 632. On the one hand, the concrete slurry 41 in the second installation groove 4 is vibrated, and on the other hand, the pressure of the shaping strip 63 on the concrete slurry 41 is increased to reduce the penetration of the concrete slurry 41 into the inside of the water tank.

[0062] Example 2 This embodiment discloses a water tank glass installation structure.

[0063] Reference Fig. 9 The difference between this embodiment and the water tank glass installation structure in Embodiment 1 is that the water tank glass installation structure further includes a plurality of reinforcing cross columns 7, and the plurality of reinforcing cross columns 7 are all horizontally arranged and spaced apart along the circumference of the water tank.

[0064] The length of the reinforcement column 7 is greater than the distance between two adjacent support columns 1, and both ends of the reinforcement column 7 are respectively connected to the adjacent root support columns 1. The surface of the reinforcement column 7 facing the enclosed glass 2 is connected with a suction cup 71, and the suction cup 71 is adsorbed on the enclosed glass 2, so as to enhance the installation stability of the enclosed glass 2 by the adsorption of the suction cup 71.

[0065] In this embodiment, the suction cup 71 and the reinforcing horizontal column 7 are connected to each other through an air tube 72, and the end of the tube cavity of the air tube 72 passes through the surface of the suction cup 71 facing the enclosed glass 2. In other embodiments, the suction cup 71 and the reinforcing horizontal column 7 can also be connected by a solid rod.

[0066] Furthermore, the outer wall of the support column 1 is fixedly connected to the support frame 11, and the reinforcing cross bar is slidably connected to the support frame 11 along the thickness direction of the enclosed glass 2. A first air bag 73 is arranged between the reinforcing cross bar and the support column 1, and two surfaces of the first air bag 73 facing away from each other are respectively used for the reinforcing cross bar to abut against the support column 1.

[0067] Reference Fig. 9 and Fig.10The first airbag 73 is connected to a first connecting tube 731, one end of the first connecting tube 731 away from the first airbag 73 is connected to the air pipe 72, and a first one-way valve 732 is installed in the tube cavity of the first connecting tube 731. The first one-way valve 732 is used to prevent the gas in the first airbag 73 from entering between the suction cup 71 and the enclosed glass 2.

[0068] The first airbag 73 is also connected to a second connecting tube 733, the other end of which is connected to a second airbag 734, and the inner cavity of the first airbag 73 and the inner cavity of the second airbag 734 are connected to each other through the lumen of the second connecting tube 733. A second one-way valve 735 is installed in the second connecting tube 733, and the second one-way valve 735 is used to prevent the gas in the second airbag 734 from entering the first airbag 73.

[0069] If the enclosed glass 2 falls off or tends to fall off relative to the supporting column 1, the enclosed glass 2 will drive the reinforcing cross column 7 to move towards the supporting column 1 through the suction cup 71. During the movement, the reinforcing cross column 7 pressurizes the singular air bag, and the gas in the first air bag 73 enters the second air bag 734. Under the action of air pressure, the gas between the suction cup 71 and the enclosed glass 2 enters the first air bag 73, thereby reducing the gas between the suction cup 71 and the enclosed glass 2 and increasing the connection strength between the suction cup 71 and the enclosed glass 2.

[0070] In this embodiment, the support frame 11 is tilted so that the reinforcing cross bar always tends to approach the enclosed glass 2, further ensuring the connection stability between the suction cup 71 and the enclosed glass 2.

[0071] Furthermore, a second adhesive layer 736 is provided between the suction cup 71 and the enclosed glass 2, and the suction cup 71 and the enclosed glass 2 are bonded and fixed by the second adhesive layer 736. The second adhesive layer 736 is arranged around the central axis of the suction cup 71, so that the second adhesive layer 736 is used to form a seal on the space between the suction cup 71 and the enclosed glass 2, thereby reducing the risk of external gas entering between the suction cup 71 and the enclosed glass 2, and further strengthening the connection strength between the suction cup 71 and the enclosed glass 2.

[0072] Reference Fig.11 , further, it also includes bottom glass 8, which is located at the bottom of the water tank, and the side wall of the bottom glass 8 abuts against the inner wall of the enclosure glass 2. After the enclosure glass 2 is installed, a floor glass is placed on the bottom wall of the water tank to ensure the flatness of the bottom wall of the water tank, further improving the experimental effect of the wave and current experiment.

[0073] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A water tank glass installation structure, Features: The invention comprises a plurality of supporting columns (1) and a plurality of enclosed glasses (2); the supporting columns (1) are extended along the height direction of the water tank, the bottom ends of the supporting columns (1) are embedded in the manufacturing surface of the water tank, and the plurality of supporting columns (1) are arranged at intervals along the circumference of the water tank; the enclosed glasses (2) are connected to the inner sides of the supporting columns (1), and the plurality of enclosed glasses (2) are arranged along the circumference of the water tank to form the water tank; a first adhesive layer (3) is arranged between the enclosed glasses (2) and the supporting columns (1), and the first adhesive layer (3) comprises a structural adhesive portion (31) and a weather-resistant adhesive portion (32), and the weather-resistant adhesive portion (32) is arranged along the circumference of the structural adhesive portion (31).

2. A water tank glass installation structure according to claim 1, Features: The manufacturing surface is provided with a first mounting groove (42), the first mounting groove (42) is arranged around the circumference of the water tank, and the enclosed glass (2) is inserted into the first mounting groove (42); the top of the supporting column (1) is connected to a plurality of supporting cross columns (5), the plurality of supporting cross columns (5) are arranged end to end along the circumference of the water tank, and the side walls of the supporting cross columns (5) are used for connection with the top of the enclosed glass (2); a second adhesive layer (736) is provided between the enclosed glass (2) and the supporting cross columns (5).

3. A water tank glass installation structure according to claim 2, Features: It also comprises a bottom glass (8), the bottom glass (8) being located at the bottom of the water tank, and the side wall of the bottom glass (8) being in contact with the inner wall of the enclosed glass (2).

4. A water tank glass installation structure according to claim 1, Features: It also comprises a plurality of reinforcing transverse columns (7), wherein the plurality of reinforcing transverse columns (7) are horizontally arranged and arranged along the circumference of the water tank; the length of the reinforcing transverse columns (7) is greater than the spacing between adjacent supporting columns (1), and the two ends of the reinforcing transverse columns (7) are respectively connected to adjacent supporting columns (1); and a suction cup (71) is arranged on the surface of the reinforcing transverse column (7) facing the enclosed glass (2), and the suction cup (71) is adsorbed on the enclosed glass (2).

5. A water tank glass installation structure according to claim 4, Features: The outer wall of the support column (1) is provided with a support frame (11), and the reinforcing cross bar is slidably connected to the support frame (11) along the thickness direction of the enclosed glass (2); a first air bag (73) is provided between the reinforcing cross bar and the support column (1), and the first air bag (73) is connected to a first connecting tube (731), and the end of the tube cavity of the first connecting tube (731) away from the first air bag (73) passes through the surface of the suction cup (71); a first one-way valve (731) is provided in the inner cavity of the first connecting tube (731). 32), the first one-way valve (732) is used to prevent the gas in the first airbag (73) from entering between the suction cup (71) and the enclosed glass (2); the first airbag (73) is also connected to a second connecting tube (733), the other end of the second connecting tube (733) is connected to a second airbag (734); a second one-way valve (735) is provided in the second connecting tube (733), the second one-way valve (735) is used to prevent the gas in the second airbag (734) from entering into the first airbag (73).

6. A water tank glass installation structure according to claim 5, Features: A second adhesive layer (736) is provided between the suction cup (71) and the enclosed glass (2), and the second adhesive layer (736) is provided around the central axis of the suction cup (71).

7. A construction method for a water tank glass installation structure, used for constructing a water tank glass installation structure as claimed in any one of claims 2 to 6, Features: The following steps are involved: S1: a second installation groove (4) is formed on the manufacturing surface of the water tank, wherein the width of the second installation groove (4) is not less than the sum of the thickness of the enclosed glass (2) and the thickness of the supporting column (1); S2: first injecting concrete slurry (41) into the second installation groove (4), and then inserting a plurality of the support columns (1) into the concrete slurry (41) of the second installation groove (4) at intervals; before the concrete slurry (41) solidifies, supporting the support columns (1) using a support assembly (6); after the concrete slurry (41) solidifies, it defines a first installation groove (42) with the support columns (1) and the groove wall of the second installation groove (4); S3: determining a first bonding surface between the enclosed glass (2) and the supporting column (1), and applying structural adhesive to the middle of the first bonding surface; then inserting the enclosed glass (2) into the first mounting groove (42), and making the first bonding surface abut against the supporting column (1); and then sealing the edge of the first bonding surface with weather-resistant adhesive; S4: using weather-resistant glue to seal the inner surface of the enclosed glass (2) and the groove wall of the first installation groove (42), so that the weather-resistant glue protrudes from the groove wall of the first installation groove (42); S5: After the weather-resistant adhesive is completely solidified, the weather-resistant adhesive protruding from the inner surface of the enclosing glass (2) is cut off to ensure that the inner surface of the enclosing glass (2) is flat.

8. The construction method of a water tank glass installation structure according to claim 7, Features: The support assembly (6) comprises a first oblique support (61) and a second oblique support (62), wherein the first oblique support (61) abuts against the inner wall of the support column (1), and the second oblique support (62) abuts against the outer wall of the support column (1); the first oblique support (61) is connected to a shaping strip (63), the width of the shaping strip (63) being the same as the width of the enclosed glass (2), the shaping strip being inserted into the first installation groove (42), and the shaping strip (63) abuts against the inner wall of the support column (1).

9. The construction method of a water tank glass installation structure according to claim 8, Features: The second oblique support (62) comprises an oblique support plate (621), a first horizontal support plate (622) and a second horizontal support plate (623); one side of the first horizontal support plate (622) is connected to the oblique support plate (621), and the other side is used to abut against the enclosed glass (2); one side of the second horizontal support plate (623) is connected to the oblique support plate (621), and the other side is used to abut against the enclosed glass (2); the shaping strip (63) is connected to the lower surface of the second horizontal support plate (623); the lower surface of the first horizontal support plate (622) is connected to a plurality of cylinders (64), and the plurality of cylinders (64) are arranged at intervals along the length direction of the shaping strip (63). Multiple output ends of the multiple cylinders (64) are all connected to vibrating rods (641); the second horizontal support plate (623) is penetrated by a plurality of first through holes (625) for the vibrating rods (641) to pass through, the shaping strip (63) is penetrated by a plurality of second through holes (632) for the vibrating rods (641) to pass through, the first through holes (625) and the second through holes (632) being interconnected; the surface of the shaping strip (63) facing away from the second horizontal support plate (623) is connected to an elastic sheet (633), the elastic sheet (633) being used to isolate the concrete slurry (41) in the second installation groove (4) from the second through holes (632).

10. The construction method of a water tank glass installation structure according to claim 9, Features: The shaping strip (63) is detachably connected to the second diagonal support (62).

Citation Information

Patent Citations

  • Vacuum glass testing machine

    CN114739794A

  • Photovoltaic power generation glasshouse system

    CN204860333U

  • Glass curtain wall installing and connecting stand column

    CN215519410U

  • Method and apparatus for producing sink tops with integrated sinks by moulding a glass sheet

    EP1215178A2

  • Supporting structure of face glass

    JP2008297844A