Construction method used when river-crossing pipe jacking machine head is blocked

By setting up cofferdams and grouting water stops, cutting round holes and using a new pipe head to rush in, the construction problem of pipe head being blocked within the river range is solved, low-cost and efficient construction methods are achieved, and construction is reduced Risks and costs avoid excavation and extraction processes and ensure the continuity and stability of the construction route.

CN119146275AActive Publication Date: 2024-12-17SHANDONG UNIV
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411386097.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-30
Publication Date
2024-12-17
Estimated Expiration
2044-09-30

AI Technical Summary

Technical Problem

In urban pipeline construction, when the pipe head is blocked within the river range, the existing technology requires excavation and extraction, resulting in high construction costs, high risks and long construction period. Especially when the water head height is large, it cannot be directly excavated and extracted. Increase construction difficulty and safety hazards.

Method used

By measuring the obstructed position and water depth of the machine head, setting up a cofferdam and grouting water stop, cutting a circular hole smaller than the diameter of the original machine head, using a new pipe head with a smaller diameter to hoist it from the working well, and continuing the construction through the cutting hole. , until the well is received, avoid excavation and extraction process, and reduce construction costs and risks.

Benefits of technology

It has achieved low-cost, safe and efficient handling of the obstruction of the pipe head of the river crossing the river, avoided the excavation and extraction process, shortened the construction period, and ensured the continuity and stability of the construction route.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119146275A_ABST
    Figure CN119146275A_ABST
Patent Text Reader

Abstract

The invention relates to a construction method used when a river-crossing pipe jacking machine head is blocked, and belongs to the technical field of pipeline construction. The construction method comprises the steps that S1, the blocked position of an original pipe jacking machine head and the water depth of the blocked position are measured, and a cofferdam is arranged in a river channel above the original pipe jacking machine head; s2, after the cofferdam is formed, grouting water stopping is conducted from the cofferdam to the position above and around the receiving well, water in the working well is pumped out, and the water stopping effect is confirmed; s3, a round hole with the diameter smaller than that of the original pipe jacking machine head is cut in the end face of the inner side of the blocked original pipe jacking machine head, and the outer wall of the original pipe jacking machine head is reserved to serve as a pipeline; and S4, a new pipe jacking machine head with the diameter smaller than that of the original pipe jacking machine head is selected, a new prefabricated pipe is jacked from the working well, and the new pipe jacking machine head penetrates through the round hole cut in the step S3 to the receiving well. Grouting and water stopping are conducted through the cofferdam on the upper portion, the blocked outer wall of the original pipe jacking machine head serves as a pipeline, construction work of excavation and extraction is avoided, the construction period is short, and safety is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of pipeline construction, and particularly relates to a construction method when a head of a river-crossing pipe jacking machine is blocked. Background Art

[0002] The information disclosed in this background technology section is only intended to enhance the understanding of the overall background of the invention, and should not necessarily be regarded as an admission or any form of suggestion that the information constitutes the prior art already known to a person skilled in the art.

[0003] The construction of underground pipelines can be done by open excavation or concealed excavation. Pipe jacking is a concealed excavation method, which belongs to the trenchless pipeline construction method. It basically does not require the change of the project site and has less construction disturbance. The construction method of pipe jacking includes: using a jack to push the prefabricated pipe section into the soil section by section, while the pipe jacking tool head digs the soil in front and excavates and transports the slag inside the pipe. In the process of pipe jacking construction of urban pipeline construction, pipe jacking is often blocked in the complex underground environment.

[0004] At present, the technology for handling blocked machine heads and laying remaining pipelines is still at the traditional processing technology level, using excavation and extraction technology. The excavation and extraction methods include: after determining the location of the blocked machine head, excavate from the ground until the machine head is blocked, and finally extract the machine head. This process requires additional work such as foundation pit excavation, foundation pit enclosure, and working well production. The treatment period is long and there are many safety hazards. If the construction route of the pipe jacking machine head passes through the riverbed, and the pipe jacking machine head is blocked within the river during construction, water seepage may even occur at the machine head when the water head height at the bottom of the river is high. At this time, direct excavation and extraction are impossible. Rash excavation will greatly increase the construction cost. At the same time, due to the high water head height, the construction risk will be greatly increased. Summary of the invention

[0005] In view of the deficiencies in the prior art, the purpose of the present invention is to provide a construction method when the head of a pipe jacking machine is blocked when crossing a river, thereby solving the technical problem that the pipe jacking machine head is blocked within the river and cannot continue to advance, thereby reducing construction costs.

[0006] In order to achieve the above object, the technical solution of the present invention is:

[0007] A construction method for crossing a river when a pipe jacking machine head is blocked, comprising the following steps:

[0008] S1. Determine the obstructed position of the original jacking machine head and the water depth at the obstructed position, and set up a cofferdam in the river channel above the obstructed position;

[0009] S2. After the cofferdam is formed, grouting is performed from the cofferdam to the top and around the receiving well to stop water, and the water in the working well is pumped out to confirm the water-stopping effect;

[0010] S3, cutting a circular hole smaller than the diameter of the original jacking machine head on the inner end face of the blocked original jacking machine head, and retaining the outer wall of the original jacking machine head as a pipe;

[0011] S4, select a new jacking head with a smaller diameter than the original jacking head, fix the new prefabricated pipe on the new jacking head, and then re-jack the new prefabricated pipe from the working well. The new jacking head passes through the circular hole cut in S3 and continues to move forward until it reaches the receiving well;

[0012] S5. Remove the cofferdam and restore the river channel.

[0013] Optionally, in S1, the existing riverbed surface is measured to determine the position range of the cofferdam, which covers the obstructed position of the original jacking pipe head below; at the same time, the riverbed surface elevation at the designed cofferdam position is measured to determine the cofferdam height so that the cofferdam is higher than the river water surface.

[0014] Optionally, in S2, the position, depth, range and grouting pressure of the grouting holes are determined according to the water head at the obstructed position, grouting holes are drilled downward from the cofferdam, and grouting is performed through the grouting holes.

[0015] Optionally, in S2, the grouting range includes: from the cofferdam to the receiving well.

[0016] Optionally, in S2, cement-water glass mixed slurry is used as the grouting material.

[0017] Optionally, in S3, use a small drill to drill holes evenly on the machine head before cutting to check the water-stopping effect.

[0018] Optionally, in S3, the lower end of the cut circular hole is inscribed inwardly with the cylindrical outer wall of the original jacking pipe head, and the outer diameter of the new prefabricated pipe is slightly smaller than the inner diameter of the circular hole.

[0019] Optionally, in S4, a new prefabricated pipe is fixedly welded to the rear of a new pipe jacking machine head by means of a boot, and the new pipe jacking machine head and the new prefabricated pipe are jacked in by means of a hydraulic jack.

[0020] Optionally, in S4, the new prefabricated pipe is a steel prefabricated pipe, which is connected and fixed to the new jacking machine head by welding, and multiple sections of the steel prefabricated pipe are fixedly connected by welding.

[0021] Optionally, in S4, the axis of the new jacking machine head coincides with the center of the circular hole cut out in S3; during the continued jacking process, the new jacking machine head is constantly corrected to ensure that the axis of the new jacking machine head is on the same horizontal line as the circular hole in the old machine head.

[0022] Optionally, in S4, a flow rate sensor is added to the spiral excavator of the new jacking machine head to monitor the flow rate in the screw conveyor in real time to warn of gushing accidents; a soil pressure sensor is installed in the new jacking machine head, and a jacking force sensor is installed at the jack to monitor the soil pressure value in the soil bin and the change of the jack force at all times during the jacking process to meet the soil pressure balance condition and maintain the stability of the excavation surface.

[0023] The beneficial effects of the present invention are:

[0024] 1. The construction method proposed in the present invention can handle the situation where the head of the pipe jacking machine is blocked at a low cost. The upper cofferdam is grouting to stop water, and the outer wall of the blocked original pipe jacking machine head is used as a pipeline. There is no need to make a new working well above the blocked position to lift out the blocked head, avoiding the construction work of excavation and extraction, with a short construction period and high safety.

[0025] 2. The present invention uses a new pipe jacking machine head to continue construction along the original construction route, avoiding the need to change the construction route. The lower end of the cut circular hole is inscribed with the cylindrical outer wall of the original pipe jacking machine head, so that the newly pushed prefabricated pipe contacts the original prefabricated pipe, avoiding the new prefabricated pipe from being suspended inside the original prefabricated pipe, and ensuring the reliability and durability of the new pipe section. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.

[0027] Figure 1 This is a schematic diagram of the construction method in Example 1.

[0028] Figure 2 This is a schematic diagram of the positions of the new and old pipelines in Example 1.

[0029] Figure 3 Schematic diagram of the connection relationship between the new steel prefabricated pipe segment and the new pipe jacking machine head in Example 1.

[0030] Among them: 1. Working well; 2. Receiving well; 3. Original pipe section; 4. River; 5. Obstructed position; 6. Cofferdam; 7. Grouting hole; 8. Round hole; 9. Cylindrical outer wall; 10. New steel prefabricated pipe section; 11. New jacking machine head; 12. Overshoe; 13. Formation. DETAILED DESCRIPTION

[0031] It should be noted that the following detailed descriptions are exemplary and are intended to provide further explanation of the present invention. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present invention belongs.

[0032] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit exemplary embodiments according to the present invention. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprising" and / or "including" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.

[0033] Example 1

[0034] like Figure 1 As shown in the figure, when the pipe jacking method is used for underground pipeline construction, a working well 1 and a receiving well 2 leading to the underground construction position are set up on the ground at the starting and ending ends of the construction route. At the beginning of the construction, the original pipe jacking machine head is hoisted into the underground construction position at the working well 1, and the original pipe section 3 is gradually pushed in by the jack. When the pipe jacking machine head reaches below the river 4, the on-site personnel find that the pipe jacking machine head does not push in. It is initially judged that the pipe jacking machine head is damaged or hits a hard obstacle. After 20 minutes, water begins to seep from the opening of the pipe jacking working well 1.

[0035] Judging from the debris discharged from the mud on site, the debris on site is concrete blocks, steel bar heads, and iron sheet fragments; the machine head in this example is a soil excavation machine head, which will cause damage to the machine head blade when encountering hard geology. The solution includes: after taking grouting and water-stopping measures, cut off the machine head, select a pipe jacking machine smaller than the current machine head, and directly push a pipe section smaller than the original pipe section 3 from the working pit to the receiving well 2.

[0036] The construction method when the head of the river-crossing pipe jacking machine is blocked includes the following steps:

[0037] S1, measuring the original pipe jacking machine head obstruction position 5 and the water depth at the obstruction position 5, and setting a cofferdam 6 in the river channel above the obstruction position 5;

[0038] S2. After the cofferdam 6 is formed, grouting is performed from the cofferdam 6 to the top and around the receiving well 2 to stop water, and the water in the working well 1 is pumped out to confirm the water-stopping effect;

[0039] S3, cutting a circular hole 8 smaller than the diameter of the original jacking head on the inner end face of the blocked original jacking head, and retaining the outer wall of the original jacking head as a pipe;

[0040] S4, select a new jacking head 11 with a smaller diameter than the original jacking head, fix the new prefabricated pipe on the new jacking head 11, push the new prefabricated pipe from the working well 1, and the new jacking head 11 passes through the circular hole 8 cut in S3, and continues to move forward to the receiving well 2;

[0041] S5. Remove cofferdam 6 and restore the river channel.

[0042] Through the above method, the situation where the head of the jacking machine is blocked when crossing the river can be dealt with at a low cost: grouting is performed through the upper cofferdam 6 to stop water, and the outer wall of the original blocked jacking machine head is used as a pipeline. There is no need to make a new working well above the blocked position 5 to lift out the blocked head, thus avoiding the construction work of excavation and extraction, with a short construction period and high safety.

[0043] Among them, in S1, the cause of the obstruction of the machine head was first investigated. In this example, it was preliminarily determined that the jacking machine head was damaged or hit a hard obstacle. After judging from the debris discharged from the mud on site, the debris on site was concrete blocks, steel bar heads, and iron sheet fragments. The machine head in this example was an earth tunneling machine head, and the machine head blade would be damaged if the geology was hard.

[0044] In S1, the existing riverbed surface is measured to determine the position range of the cofferdam 6, which covers the obstructed position 5 of the original jacking head below. At the same time, the riverbed surface elevation at the designed cofferdam position is measured to determine the height of the cofferdam 6 so that the cofferdam 6 is higher than the water surface of the river 4. When constructing the cofferdam 6, water-stopping measures must be taken for the water-facing surface. The cofferdam 6 provides a grouting channel and construction space for the grouting water-stopping in S2. In this example, according to the actual situation of the project, sandbags were used to build a cofferdam at the original head stagnation position 5. According to the hydrological calculation results, the water depth during the construction period was 1.258 meters, the silt thickness was 1 meter, and the water level rise protection was not considered during the rainy season. The total height of the cofferdam 6 was 2.758 meters and the width was 2.5 meters. The range of the cofferdam 6 was 20 meters in the north-south direction and 15 meters in the east-west direction. The sandbag cofferdam was filled in layers, and the length of the sandbags was determined according to the specific conditions on site. To ensure the water-stopping performance of the cofferdam 6, the water-facing surface of the cofferdam 6 must be fully covered with a water-stopping film, which was pressed tightly with small sandbags. The size of the small sandbags was 50*30*20cm.

[0045] In S2, the position, depth, range and grouting pressure of the grouting hole 7 are determined, the grouting hole 7 is drilled downwardly from the cofferdam 6, and grouting is injected through the grouting hole 7; Figure 1 In the embodiment, the grouting holes 7 are arranged in a matrix on the cofferdam 6; the grouting range covers the upper part and the periphery of the obstructed position 5 of the original jacking head to form a comprehensive water-stopping barrier to prevent water from seeping inward during the subsequent construction process.

[0046] In S2, this example uses cement-water glass mixed slurry as the grouting material. The grouting material has an adjustable gel time, which can effectively control the diffusion speed and distance of the slurry in the formation, ensuring that the water flow channel is quickly blocked when there is water flowing, and the gel solidification of the slurry is non-toxic and pollution-free; the grouting length starts from 5 meters north of the head position and grouts southward to the receiving pit, which is about 63 meters long; the grouting width is 5 meters on both sides of the center line of the jacking pipe, and the grouting depth into the soil is about 10 meters. After the grouting is completed, the water in the working well 1 is pumped out and the grouting water-stopping effect is observed. If the water-stopping effect does not meet the requirements, continue to increase the grouting through the grouting holes 7 on the cofferdam 6 to the seepage position of the original jacking head obstruction position 5 until the water-stopping requirements are met.

[0047] In S2, the grouting range includes: from the cofferdam 6 to the receiving well 2, not limited to the top and around the blocked position 5. This is because there is a high construction risk in the cross-river jacking. If the excavation surface becomes unstable and the riverbed collapses, it will cause serious construction accidents. For safety reasons, grouting is performed from the cofferdam 6 to the receiving well 2.

[0048] In S3, in this example, after ensuring the safety of the water-stopping effect, the scrapped components in the current machine head are removed, and the machine head cutter disc cuts a circular hole 8 with a diameter slightly smaller than the original pipe diameter, and the original machine head outer wall is retained to serve as an outer sleeve; before cutting, a small drill is used to drill holes evenly in the machine head to check the water-stopping effect. If the water-stopping effect is not good, the construction personnel will immediately withdraw the machine head and continue to perform dense grouting at the water seepage location. The machine head is dismantled in sections according to the local 1 / 3 range to ensure the water-stopping effect.

[0049] In S3, Figure 2 As shown, the lower end of the cut circular hole 8 is inscribed inwardly with the cylindrical outer wall 9 of the original jacking machine head, the outer diameter of the new prefabricated pipe is slightly smaller than the circular hole 8, and the bottom of the newly jacked prefabricated pipe is in contact with the original prefabricated pipe, avoiding the new prefabricated pipe from being suspended inside the original prefabricated pipe, thereby ensuring the reliability and durability of the new pipe section.

[0050] In S4, based on the on-site debris found in S1, it was found that the head cutter was damaged by rocks, resulting in the head being blocked. Therefore, the type of the new jacking head 11 was determined to be a rock head to avoid subsequent construction being blocked due to the aforementioned reasons; Figure 3 As shown, the new steel prefabricated pipe section 10 is welded to the rear of the new jacking machine head 11 through the boot 12, and the newly replaced new jacking machine head 11 and the new steel prefabricated pipe section 10 are pushed in by the hydraulic jack, and the surrounding stratum 13 is reinforced by grouting;

[0051] Specifically, a laser theodolite is set up at the bottom of the working shaft 1, and the laser is projected onto the target of the manual excavation tool pipe to ensure that the laser theodolite beam is in a straight line with the center axis of the newly jacked steel prefabricated pipe and the center axis of the original jacking machine head.

[0052] In S4, the new prefabricated pipe is a steel prefabricated pipe, which is firm and durable, and can withstand greater pressure than the original pipe section 3. It is connected and fixed to the new jacking machine head 11 by welding, and multiple sections of steel prefabricated pipes are fixedly connected by welding;

[0053] Specifically, the hydraulic jack in the working well 1 retracts, and a new jacking head 11 with a smaller diameter than the blocked head is replaced for re-jacking: the newly replaced head and the first section of prefabricated tool steel pipe are hoisted into the working well 1, the prefabricated tool steel pipe is welded to the new head through the boot 12, and a hydraulic jack is used to jack along the same construction route as the original pipe section 3. After the first section of the steel pipe is jacked, the second section of the steel pipe is welded until it is jacked into the receiving well 2. On the other hand, a flow rate sensor is added to the spiral excavator of the new jacking machine head 11 to monitor the flow rate in the screw conveyor in real time to warn of gushing accidents. If the flow rate measured by the flow rate sensor exceeds the warning value, the jacking should be stopped immediately and the grouting at the machine head position should be increased. At the same time, the machine head travel position should be checked at any time during the jacking process. If it is found that the water inflow in the working well 1 exceeds the warning value, the jacking should also be stopped and the grouting at the machine head position should be increased immediately. After the water stopping meets the requirements, the jacking should be continued. During this process, the new jacking machine head is corrected at all times to ensure that the axis of the new jacking machine head is on the same horizontal line as the circular hole 8 in the old machine head.

[0054] Since the jacking pipe in this example crosses the river 4, an earth pressure sensor is installed in the new jacking machine head 11, and a jacking force sensor is installed at the jack. During the jacking process, the earth pressure value in the soil bin and the change value of the jack force are monitored at all times to strictly meet the earth pressure balance condition (as shown in the following formula) and maintain the stability of the excavation surface.

[0055] N f +F f =F p +F s ;

[0056] Ff=πDLfk.

[0058] Where:

[0059] N f ——The sum of water and soil pressures on the tunnel face in front of the jacking pipe (kN);

[0060] F f ——Friction force on the jacking pipe (kN);

[0061] F p ——Pipe jacking force (kN);

[0062] F s ——Earth pressure in soil bin (kN);

[0063] D——top pipe diameter (m);

[0064] L——pipe jacking length (m);

[0065] f k ——The unit area friction between the outer wall of the pipe and the soil (kN / m 2 ).

[0066] In S4, the axis of the new jacking machine head 11 coincides with the center of the circular hole 8 cut in S3, that is: Figure 1 As shown, a new layer of prefabricated steel pipe segment 10 is added to the original pipe segment 3, and the new prefabricated steel pipe segment 10 passes through the circular hole 8 cut in S3 and continues to be pushed forward into the receiving well 2 to complete the construction of the underground pipeline.

[0067] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A construction method when a pipe jacking machine head is blocked when crossing a river, characterized in that: The following steps are involved: S1. Determine the obstructed position of the original jacking machine head and the water depth at the obstructed position, and set up a cofferdam in the river channel above the obstructed position; S2. After the cofferdam is formed, grouting is performed from the cofferdam to the top and around the receiving well to stop water, and the water in the working well is pumped out to confirm the water-stopping effect; S3, cutting a circular hole smaller than the diameter of the original jacking machine head on the inner end face of the blocked original jacking machine head, and retaining the outer wall of the original jacking machine head as a pipe; S4, select a new jacking head with a smaller diameter than the original jacking head, fix the new prefabricated pipe on the new jacking head, push the new prefabricated pipe from the working well, and let the new jacking head pass through the circular hole cut in S3, and continue the construction forward to the receiving well; S5. Remove the cofferdam and restore the river channel.

2. The construction method when the head of the river-crossing pipe jacking machine is blocked as described in claim 1, characterized in that: In S1, the existing riverbed surface is measured to determine the location range of the cofferdam, which covers the obstructed position of the original jacking pipe head below; at the same time, the riverbed surface elevation at the designed cofferdam location is measured to determine the cofferdam height so that the cofferdam is higher than the river water surface.

3. The construction method when the head of the river-crossing pipe jacking machine is blocked as described in claim 1, characterized in that: In S2, the position, depth, range and grouting pressure of the grouting holes are determined according to the water head at the obstructed position, and grouting holes are drilled downward from the cofferdam, and grouting is injected through the grouting holes.

4. The construction method when the head of the river-crossing pipe jacking machine is blocked as described in claim 3, characterized in that: The grouting holes are arranged in a matrix on the cofferdam; the grouting range covers the upper and outer parts of the obstructed position of the original jacking pipe head.

5. The construction method when the head of the river-crossing pipe jacking machine is blocked as claimed in claim 1, characterized in that: In S2, cement-water glass mixed slurry is used as the grouting material.

6. The construction method when the head of the river-crossing pipe jacking machine is blocked as claimed in claim 1, characterized in that: In S3, a small drill was used to drill holes evenly on the machine head before cutting to check the water-stopping effect.

7. The construction method when the head of the river-crossing pipe jacking machine is blocked as claimed in claim 1, characterized in that: In S3, the lower end of the cut circular hole is inscribed inwardly with the cylindrical outer wall of the original jacking pipe head, and the outer diameter of the new prefabricated pipe is slightly smaller than the inner diameter of the circular hole.

8. The construction method when the head of the river-crossing pipe jacking machine is blocked as claimed in claim 1, characterized in that: In S4, the new prefabricated pipe is fixedly connected to the rear of the new jacking head by means of a boot, and the new jacking head and the new prefabricated pipe are jacked in by means of a hydraulic jack.

9. The construction method when the head of the river-crossing pipe jacking machine is blocked as claimed in claim 8, characterized in that: The new prefabricated pipe is a steel prefabricated pipe, which is connected and fixed to the new jacking machine head by welding, and multiple sections of the steel prefabricated pipe are fixedly connected by welding.

10. The construction method when the head of the river-crossing pipe jacking machine is blocked as claimed in claim 1, characterized in that: In S4, the axis of the new jacking machine head coincides with the center of the circular hole cut in S3; during the jacking process, the new jacking machine head is always corrected to ensure that the axis of the new jacking machine head is on the same horizontal line as the circular hole in the old machine head; Optionally, a flow rate sensor is added to the spiral excavator of the new pipe jacking machine head to monitor the flow rate in the screw conveyor in real time to warn of eruption accidents; a soil pressure sensor is installed in the new pipe jacking machine head, and a jacking force sensor is installed at the jack to monitor the soil pressure value in the soil bin and the change of the jack force at all times during the jacking process; the soil pressure balance condition is met to maintain the stability of the excavation surface.

Citation Information

Patent Citations

  • Construction technology for jacking pipe in river or lake

    CN102537517A

  • Top pipe construction method

    CN108930323A

  • Slurry balance type pipe jacking machine and construction process thereof in quicksand stratum

    CN112012757A

  • Supporting and water stopping construction method for pipe-jacking working well and pipe ditch on beach

    CN112695803A

  • Miscellaneous fill geology pipe jacking construction method

    CN117513410A