Shelf welding equipment and welding method
By designing a layer welding equipment including a handling robot, side rail loading device and welding device, the problems of low automation efficiency and lack of side rail material preparation and finishing mechanism of existing equipment are solved, and fully automatic welding processing and efficient material preparation are realized. Reduce labor intensity and cost and improve production efficiency.
Patent Information
- Application Number
- CN202411754319.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-02
- Publication Date
- 2025-02-11
AI Technical Summary
The automation efficiency of existing shelf welding equipment is low, resulting in slow production efficiency and lack of side rail material preparation and sorting mechanism, which requires manual material preparation and correction, resulting in high labor intensity and high cost.
A layer rack welding equipment was designed, including a transport robot, side rail loading device, welding device, base rack material placement device and control cabinet group, to realize automatic adjustment of side rail materials, preparation, feeding and automatic base rack material of side rail materials Feeding and welding to achieve fully automatic welding processing.
Through fully automatic welding processing, labor intensity and cost are reduced, production efficiency is improved, and manual participation is reduced through automated material preparation and finishing, and the feeding efficiency of sidebar materials is improved.
Smart Images

Figure CN119407388A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of layer frame processing equipment, and in particular to a layer frame welding equipment and a welding method. Background Art
[0002] The shelf structure of the storage rack is composed of a shelf and a side rail, which is made by welding the side rails to the four sides of the shelf. The traditional welding of the side rails and the shelf is to first position and fix the side rails and the shelf through the corresponding positioning equipment, and then weld the positioned and fixed side rails and the shelf by manually holding a welding gun, and it can only weld the side rails to one side of the shelf at a time, and it cannot weld the side rails to the two sides of the shelf at the same time, so that the manual welding of the side rails and the shelf not only has the shortcomings of low welding efficiency, poor welding accuracy and poor welding effect, but also leads to high labor intensity of workers and high labor costs of enterprises, which cannot meet the requirements of large-scale and batch production of enterprises. In response to the above problems, the publication number: CN202322667215.6 discloses a shelf side rail welding machine, including a feeding mechanism, a shelf support plate arranged on one side of the feeding mechanism, and a welding mechanism arranged above the contact between the shelf and the side rail. The overall structural design of the utility model can automatically complete a series of operations such as loading, material distribution and positioning, welding material collection, welding feeding, clamping and positioning before welding, and synchronous welding of the side fences of two adjacent sides of the rack, and the process of welding the side fences of the rack does not require human participation, so that the rack can automatically weld the side fences. It not only has the advantages of high welding efficiency, high welding precision and good welding effect, but also can reduce the labor intensity of workers and reduce the labor cost of enterprises, so as to effectively solve the problem of low welding efficiency, poor welding precision, poor welding effect, high labor intensity of workers and high labor cost of enterprises caused by the traditional method of using manual handheld welding guns to weld the side fences and racks. However, the rack side fence welding machine still has the following problems: low automation efficiency, affecting production efficiency, and the existing rack side fence welding machine has no side fence material preparation and sorting mechanism, and needs to manually prepare and correct the side fence materials, resulting in a waste of manpower and material resources, high manual labor intensity, high cost, and affecting the efficiency of the entire storage rack processing. Summary of the invention
[0003] This invention is aimed at the current technical deficiencies and provides a layer frame welding equipment and a welding method, aiming to solve the technical problems of low automation efficiency and slow production efficiency in the prior art of layer frame welding processing.
[0004] The technical solution adopted by the present invention to achieve the above-mentioned purpose is:
[0005] A layer shelf welding equipment includes a handling robot, a first side rail feeding device, a second side rail feeding device, two welding devices, a bottom frame material placement device, a product placement device and a control cabinet group; one of the welding devices is arranged in a horizontal manner on the outside of the handling robot, and the other welding device is arranged in a longitudinal manner at the end of the horizontally arranged welding device, the first side rail feeding device is arranged on the outside of one of the welding devices, the second side rail feeding device is arranged on the outside of the other welding device, and the bottom frame material placement device and the product placement device are respectively arranged on the other two outer sides of the handling robot.
[0006] As a further improvement, the size of the first side rail feeding device is larger than that of the second side rail feeding device; the first side rail feeding device and the second side rail feeding device both include a base, a platform, a material placement mechanism, a material organization mechanism and a feeding mechanism; the platform is arranged on the base, the material placement mechanism is arranged on the platform, the feeding mechanism is arranged below the material placement mechanism, and the material organization mechanism is arranged on the side in front of the material placement mechanism; the material placement mechanism is provided with a limiting discharge component, and the limiting discharge component is used for the transportation of a single material; the material organization mechanism is provided with an adjustable structure.
[0007] As a further improvement, both sides of the platform are provided with mounting seats; the material-forming mechanism includes two material-forming components, the adjustable structure includes two sets of slide rail groups, the slide rail groups are respectively arranged on the mounting seats, the slide rail groups are each provided with a base with a slider, the base with a slider is provided with a locking wrench; the base with a slider is provided with a support, and the material-forming component is arranged on the support;
[0008] As a further improvement, the monolithic components all include a rotary drive member; the rotary drive member may be a rotary cylinder or a servo motor; the rotary drive member is provided with a rotary shaft, the rotary shaft is provided with a connecting seat, and the connecting seat is provided with a clamping jaw;
[0009] The platform includes two baffles, which are arranged on the base in a mirror-image manner. Both of the baffles are right-angled trapezoidal plates, and the high end of the baffle is arranged at the tail end, and the low end of the baffle is close to the whole material component; two cross bars are arranged between the two baffles, and the bottom of the cross bars is provided with a slide rail.
[0010] As a further improvement, the material placement mechanism includes a plurality of support rails, a guide groove group and a clamp 1, the guide groove group includes two guide grooves, the guide grooves each include a slide plate, and the slide plates are respectively arranged on the inner side surface of the baffle in a mirror-image manner and tilted; a fixed column is also arranged between the two baffles, and the plurality of support rails are arranged between the two guide grooves and on the fixed column, and the support rails are provided with a guide groove 1; the cross bar is provided with a plurality of slide seats 1 and a plurality of slide seats 2, and the clamp 1 is respectively arranged on the slide seats 2;
[0011] The slide seat 1 and the slide seat 2 are both provided with a plurality of sliders 1, the sliders 1 are arranged on the slide rail 1, the slide seat 1 and the slide seat 2 are provided with a mounting plate 1, the mounting plate 1 is arranged above the cross bar, the mounting plate 1 is provided with threaded holes, and the threaded holes are provided with quick wrenches; the slide seat 1 is arranged at both ends of the cross bar, and the slide seat 2 is arranged between the slide seats 1.
[0012] As a further improvement, the position-limiting discharge assembly includes a partition assembly and a position-limiting assembly, the partition assembly includes a plurality of cylinder groups, each of the cylinder groups includes two cylinders 1, one of the cylinders 1 is arranged at the bottom of the slide seat 2, and the other cylinder is arranged at the end of the support rail and below the clamp 1; each of the cylinders 1 is provided with a corner block, and a material isolation distance is provided between the two corner blocks;
[0013] The limit assembly includes two cylinders 2, which are respectively arranged on the slide seat 1 and at the ends of the guide groove, and the driving shafts of the cylinders 2 are each provided with a stop column.
[0014] As a further improvement, the feeding mechanism includes a servo motor, a linear module and a loading assembly, the servo motor is connected to the linear module and is arranged on the platform; the linear module is provided with a platform 1, and the loading assembly is arranged on the platform 1;
[0015] The material loading assembly includes a lifting cylinder, a plurality of guide sleeves 2 and a platform 3. The lifting cylinder and the plurality of guide sleeves 2 are both arranged on the platform 1; the guide sleeves 2 are each provided with guide pillars 2, and the platform 3 is arranged on the guide pillars 2; the platform 3 is provided with a clamp 2.
[0016] As a further improvement, the two welding devices each include a frame, a welding head mechanism and a welding platform mechanism, the welding head mechanism is arranged on the top of the welding platform mechanism; the welding head mechanism includes two or more welding head assemblies, the welding platform mechanism is provided with a slide rail and a plurality of welding platform chuck assemblies, the plurality of welding platform chuck assemblies are all arranged on the slide rail, and the welding platform chuck assemblies are respectively arranged below the welding head assemblies; the welding head assemblies are each provided with a lifting cylinder.
[0017] As a further improvement, the chassis material placement device includes a lifting material rack and a sorting platform. The lifting material rack is provided with a servo lifting mechanism and a clamp. The clamp is provided with a moving mechanism. The moving mechanism is used to transport the chassis material to the sorting platform; the product placement device is a collection trolley, and the collection trolley is provided with a collection frame; the transport robot is provided with a clamping claw.
[0018] A welding method for implementing the layer frame welding device comprises the following steps:
[0019] (1) Material preparation: the first side rail loading device and the second side rail loading device respectively prepare the side rail materials, and the bottom frame material placement device prepares the bottom frame materials, and the material preparation is completed;
[0020] (2) Carrying of chassis materials: the carrying robot moves the chassis materials on the chassis material placement device to the welding device;
[0021] (3) The first welding process of the shelf: the first side rail feeding device transports one of the side rail materials to the welding device, and then the transport robot transports one side of the bottom frame material to one of the welding devices, the side of the bottom frame material is bonded to the side rail material, and the welding device performs the first welding, and the first welding process is completed;
[0022] (4) Second welding process of the shelf: the handling robot removes the base frame material that has been welded for the first time, rotates 180° to the side of the other mirror image and aligns it with the welding device. At the same time, the first side rail feeding device transports the other side rail material to the welding device. The handling robot transports the other side of the base frame material to the welding device. The other side of the base frame material is bonded to the side rail material. The welding device performs a second welding, and the second welding process is completed.
[0023] (5) The third welding process of the shelf: the handling robot removes the welded bottom frame material, the second side rail feeding device transports one of the prepared side rail materials to the other welding device, the handling robot rotates the bottom frame material 90°, and after the rotation is completed, transports the side of the bottom frame material to the welding device and fits it with the side rail material, the welding device moves to perform the third welding process, and the third welding process is completed;
[0024] (6) The fourth welding process of the shelf: the handling robot withdraws the bottom shelf material, and the second side rail feeding device moves the other side rail material that has been prepared forward to the welding device in step (5). At the same time, the handling robot rotates the bottom shelf material 180°, and after the rotation is completed, the side of the bottom shelf material is transported to the welding device and fits it with the side rail material. The welding device moves to perform the fourth welding process, and the fourth welding process is completed;
[0025] (7) Unloading of shelf products: The handling robot removes the shelf products that have been welded and transports the processed shelf products to the product placement device, and then transports new shelf materials, and the entire process is completed.
[0026] As a further improvement, the (1) further comprises the following steps:
[0027] (1.1) The material placement mechanism slides down to the exit of the limit material discharge component under the action of gravity, and the limit material discharge component is actuated to perform limit material discharge, allowing a side fence material to be discharged. The clamp 1 on the material placement mechanism clamps the side fence material and places it on the frontmost clamping claw cylinder group of the clamp 2 on the feeding mechanism, and the feeding mechanism is actuated to transport the side fence material to the material sorting mechanism to adjust the first side fence material; at the same time, the material placement mechanism slides down to the exit of the limit material discharge component under the action of gravity, and the limit material discharge component is actuated to perform limit material discharge, allowing the second side fence material to be discharged; after the adjustment of the first side fence material is completed, the material sorting mechanism is released, and the frontmost clamping claw cylinder group fixes the side material after the sorting is completed;
[0028] (1.2) The feeding mechanism moves forward, and the clamp 1 on the material placement mechanism clamps the side fence material and places it on the clamping claw cylinder group at the tail end of the clamp 2 on the feeding mechanism. The feeding mechanism transports the side fence material to the material adjustment mechanism to adjust the second side fence material. After the adjustment is completed, the clamping claw cylinder group at the tail end fixes the second side fence material, and the entire side fence material preparation process is completed.
[0029] The beneficial effects of the present invention are as follows: the present invention realizes the adjustment, preparation and feeding of multiple side bar materials, automatic loading of bottom frame materials, automatic welding of side bar materials and bottom frame materials, and full-automatic welding processing of automatic unloading of shelves by arranging a handling manipulator, a first side bar loading device, a second side bar loading device, two welding devices, a welding bottom frame material placement device, a product placement device and a control cabinet group, thereby reducing manual labor intensity and cost and improving production efficiency; the first side bar loading device and the second side bar loading device are arranged to realize the preparation of multiple side bar materials and improve the side bar preparation efficiency; the material placement mechanism, the material sorting mechanism and the feeding mechanism are arranged to realize automatic discharge, sorting and correction and feeding actions and improve the feeding efficiency of the side bar materials; the material placement mechanism is arranged for the placement and inversion of the side bar materials to ensure the consistency of the orientation of the side bar material placement, and the side bar material is equipped with a plurality of side bar loading devices, a plurality of side bar loading devices and ... The platform is combined so that the side rail material can be automatically conveyed according to its own weight; by arranging a partition component for separating the side rail materials from each other, the overlap of materials is prevented, and the limiting component is used for limiting the side rail material separation action to ensure the stability and efficiency of material conveying; by arranging a feeding mechanism with multiple groups of clamping claws and cylinder groups, the conveying and docking of one side rail material or two side rail materials can be realized according to needs, thereby improving the subsequent welding efficiency; by arranging a material-forming component for rotating and adjusting the side rail material, and cooperating with the material placement mechanism, the welding direction of the side rail material is ensured without manual adjustment, thereby reducing the labor intensity and cost and improving the feeding efficiency; by arranging an adjustable structure for adjusting the spacing of the material-forming mechanism, the material-forming mechanism can be used for the clamping and rotating actions of side rail materials of different lengths and specifications, thereby improving applicability.
[0030] The present invention is further described below in conjunction with the accompanying drawings and specific implementation methods. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0032] Figure 1 This is a schematic diagram of the overall structure of the rack welding equipment of this embodiment;
[0033] Figure 2 It is a front view schematic diagram of the layer frame welding equipment of this embodiment;
[0034] Figure 3 It is a side view schematic diagram of the layer frame welding equipment of this embodiment;
[0035] Figure 4Schematic diagram of the structure of the welding device of this embodiment;
[0036] Figure 5 Schematic diagram of the structure of the handling robot of this embodiment;
[0037] Figure 6 It is a schematic diagram of the first side rail feeding device and the second side rail feeding device of this embodiment;
[0038] Figure 7 It is a front view schematic diagram of the first side rail feeding device and the second side rail feeding device of this embodiment;
[0039] Figure 8 is a schematic structural diagram of the monolithic assembly of this embodiment;
[0040] Fig. 9 is a schematic structural diagram of a partition assembly of this embodiment;
[0041] Fig.10 Schematic diagram of the welding method of this embodiment. DETAILED DESCRIPTION
[0042] The following descriptions are merely preferred embodiments of the present invention and are not intended to limit the protection scope of the present invention.
[0043] For example, see the attached Figures 1 to 10 A layer rack welding device 1 includes a handling robot 2, a first side rail feeding device 3, a second side rail feeding device 4, two welding devices 5, a welding chassis material placement device 6, a product placement device 7 and a control cabinet group 8; one of the welding devices 5 is arranged on the outside of the handling robot 2 in a horizontal manner, and the other welding device 5 is arranged on the end of the horizontally arranged welding device 5 in a longitudinal manner. The first side rail feeding device 3 is arranged on the outside of one of the welding devices 5, and the second side rail feeding device 4 is arranged on the outside of the other welding device 5. The welding chassis material placement device 6 and the product placement device 7 are respectively arranged on the other two outer sides of the handling robot 2. The layer rack welding equipment 1 realizes the handling of chassis materials, the sorting of side rail materials, the welding between chassis materials and side rail materials, and the automatic unloading of layer rack products after welding is completed, which greatly improves the automation efficiency of layer rack processing and reduces manual labor intensity and cost.
[0044] The size of the first side rail feeding device 3 is larger than that of the second side rail feeding device 4; the first side rail feeding device 3 and the second side rail feeding device 4 both include a base 9, a platform 10, a material placement mechanism 11, a material sorting mechanism 12 and a feeding mechanism 13; the platform 10 is arranged on the base 9, the material placement mechanism 11 is arranged on the platform 10, the feeding mechanism 13 is arranged below the material placement mechanism 11, and the material sorting mechanism 12 is arranged on the side in front of the material placement mechanism 11; the material placement mechanism 11 is provided with a limiting discharge component 14, and the limiting discharge component 14 is used for conveying a single material; the material sorting mechanism 12 An adjustable structure 15 is provided, and mounting seats 100 are provided on both sides of the platform 10; the material-forming mechanism 12 includes two material-forming components 120, and the adjustable structure 15 includes two sets of slide rail groups 150, and the slide rail groups 150 are respectively arranged on the mounting seats 100, and the slide rail groups 150 are each provided with a base 150a with a slider, and the base 150a with a slider is provided with a locking wrench 150b; the base 150a with a slider is provided with a support, and the material-forming component 120 is arranged on the support, and the adjustable structure 15 is used to adjust the spacing of the material-forming mechanism 12, so that the material-forming mechanism 12 can be used for the clamping and rotating actions of side rail materials of different length specifications, thereby improving applicability.
[0045] The whole material assembly 120 includes a rotating drive member 120a; the rotating drive member 120a can be a rotating cylinder or a servo motor; the rotating drive member 120a is provided with a rotating shaft, the rotating shaft is provided with a connecting seat, and the connecting seat is provided with a clamping clamp 120b. The whole material assembly 120 is used to perform a rotation adjustment action on the side rail material to ensure the welding direction of the side rail material.
[0046] The platform 10 includes two baffles, which are arranged on the base 9 in a mirror-image manner. Both of the baffles are right-angled trapezoidal plates, and the higher end of the baffle is arranged at the tail end, and the lower end of the baffle is close to the monolithic assembly 120; two cross bars 101 are arranged between the two baffles, and the bottom of each cross bar 101 is provided with a slide rail.
[0047] The material placement mechanism 11 includes a plurality of support rails 110, a guide groove group 111 and a clamp 112, the guide groove group 111 includes two guide grooves, the guide grooves each include a slide plate, and the slide plates are respectively arranged on the inner side surface of the baffle in a mirror-image manner and tilted; a fixed column is also provided between the two baffles, and the plurality of support rails 110 are arranged between the two guide grooves and on the fixed column, and the support rail 110 is provided with a guide groove 1; the cross bar 101 is provided with a plurality of slide seats 101a and a plurality of slide seats 2 101b, and the clamp 112 is respectively arranged on the slide seat 2 101b; the clamp 112 is provided with a vertical cylinder 112a, and the vertical cylinder 112a is used to control the clamp 112 to perform a clamping action of a single sidebar material; the material placement mechanism 11 is used for placing sidebar materials, and cooperates with the platform 10 so that the sidebar materials can be automatically transported according to their own weight.
[0048] The slide seat 101a and the slide seat 2 101b are both provided with a plurality of sliders 1, and the sliders 1 are arranged on the slide rail 1. The slide seat 101a and the slide seat 2 101b are provided with a mounting plate 1, and the mounting plate 1 is arranged above the cross bar 101. The mounting plate 1 is provided with threaded holes, and the threaded holes are provided with quick wrenches. The slide seat 101a is arranged at both ends of the cross bar 101, and the slide seat 2 101b is arranged between the slide seat 101a. The slide seat 101a and the slide seat 2 101b are used to adjust the spacing between the limiting discharge assembly 14 and the clamp 1 112, so that the material placement mechanism 11 can be used for the transportation of side rail materials of different lengths, thereby improving applicability.
[0049] The position limiting discharge assembly 14 includes a partition assembly 140 and a position limiting assembly 141. The partition assembly 140 includes a plurality of cylinder groups 140a. The cylinder groups 140a each include two cylinders 1, one of which is arranged at the bottom of the slide seat 101b, and the other is arranged at the end of the support rail 110 and below the clamp 1 112; each cylinder 1 is provided with a corner block, and a material isolation distance is provided between the two corner blocks. The partition assembly 140 is used to separate side fence materials from side fence materials to prevent material stacking and ensure the stability and efficiency of material transportation;
[0050] The limiting assembly 141 includes two cylinders 141a, which are respectively arranged on the slide 101a and at the ends of the guide groove. The driving shafts of the cylinders 141a are provided with blocking columns. The limiting assembly 141 is used for limiting the side fence material separation action.
[0051] The feeding mechanism 13 includes a servo motor 130, a linear module 131 and a loading assembly 132. The servo motor 130 is connected to the linear module 131 and is arranged on the platform 10; the linear module 131 is provided with a platform one, and the loading assembly 132 is arranged on the platform one; the loading assembly 132 includes a lifting cylinder, a multi-two guide sleeve two and a platform three, and the lifting cylinder and the multi-two guide sleeve two are both arranged on the platform one; the guide sleeve two is provided with a guide column two, and the platform three is arranged on the guide column two; the platform three is provided with a clamp two 132a; the loading assembly 132 is used for the feeding action of the side rail material.
[0052] The two welding devices 5 each include a frame 50, a welding head mechanism 51 and a welding platform mechanism 52, wherein the welding head mechanism 51 is arranged on the top of the welding platform mechanism 52; the welding head mechanism 51 includes two or more welding head assemblies, and the welding platform mechanism 52 is provided with a slide rail and a plurality of welding platform chuck assemblies, wherein the plurality of welding platform chuck assemblies are all arranged on the slide rail, and the welding platform chuck assemblies are respectively arranged below the welding head assemblies; the welding head assemblies are each provided with a lifting cylinder, and the welding device 5 is used for performing electric welding processing, thereby welding the side rail material to the side of the chassis material.
[0053] The welding equipment chassis material placement device 6 includes a lifting material rack 60 and a sorting platform 61. The lifting material rack 60 is provided with a servo lifting mechanism and a clamp. The clamp is provided with a moving mechanism. The moving mechanism is used to transport the chassis material to the sorting platform 61; the product placement device 7 is a collection trolley, and the collection trolley is provided with a collection frame; the handling robot 2 is provided with a gripper clamp 20. The handling robot 2 is provided as a multi-axis handling robot. A rotating shaft is provided between the handling robot 2 and the gripper clamp 20. The gripper clamp 20 is used for grabbing chassis materials.
[0054] A welding method for implementing the layer frame welding device 1 comprises the following steps:
[0055] (1) Material preparation: the first side rail feeding device 3 and the second side rail feeding device 4 respectively prepare the side rail materials, and the welding frame material placement device 6 prepares the frame materials, and the material preparation is completed;
[0056] (2) Carrying of chassis materials: the transporting robot 2 moves the chassis materials on the welding chassis material placement device 6 to the welding device 5;
[0057] (3) The first welding process of the shelf: the first side rail feeding device 3 transports one of the side rail materials to the welding device 5, and then the transport robot 2 transports one side of the bottom frame material to one of the welding devices 5, the side of the bottom frame material is bonded to the side rail material, and the welding device 5 performs the first welding, and the first welding process is completed;
[0058] (4) Second welding process of the shelf: the handling robot 2 removes the base frame material that has been welded for the first time, rotates 180° to the side of the other mirror image to align with the welding device 5, and at the same time, the first side rail feeding device 3 transports the other side rail material to the welding device 5, and the handling robot 2 transports the other side of the base frame material to the welding device 5, and the other side of the base frame material is bonded to the side rail material, and the welding device 5 performs a second welding, and the second welding process is completed;
[0059] (5) The third welding process of the shelf: the handling robot 2 removes the welded bottom frame material, the second side rail feeding device 4 transports one of the prepared side rail materials to the other welding device 5, the handling robot 2 rotates the bottom frame material 90°, and after the rotation is completed, transports the side of the bottom frame material to the welding device 5 and fits it with the side rail material, the welding device 5 is actuated to perform the third welding process, and the third welding process is completed;
[0060] (6) The fourth welding process of the shelf: the handling robot 2 withdraws the bottom shelf material, and the second side fence feeding device 4 moves the other side fence material that has been prepared forward to the welding device 5 of step (5). At the same time, the handling robot 2 rotates the bottom shelf material by 180°, and after the rotation is completed, the side of the bottom shelf material is transported to the welding device 5 and fits it with the side fence material. The welding device 5 is actuated to perform the fourth welding process, and the fourth welding process is completed;
[0061] (7) Unloading of shelf products: The handling robot 2 removes the shelf products that have been welded, and transports the processed shelf products to the product placement device 7, and then transports new shelf materials, and the entire process is completed.
[0062] The method (1) further comprises the following steps:
[0063] (1.1) The material placement mechanism 11 slides down to the exit of the limit discharge assembly 14 under the action of gravity, and the limit discharge assembly 14 is actuated to perform limit discharge, allowing a side fence material to be discharged. The clamp 1 112 on the material placement mechanism 11 clamps the side fence material and places it on the frontmost clamping claw cylinder group 140a of the clamp 2 132a on the feeding mechanism 13, and the feeding mechanism 13 is actuated to transport the side fence material to the material sorting mechanism 12 to adjust the first side fence material; at the same time, the material placement mechanism 11 slides down to the exit of the limit discharge assembly 14 under the action of gravity, and the limit discharge assembly 14 is actuated to perform limit discharge, allowing the second side fence material to be discharged; after the adjustment of the first side fence material is completed, the material sorting mechanism 12 is released, and the frontmost clamping claw cylinder group 140a fixes the side material after the sorting is completed;
[0064] (1.2) The feeding mechanism 13 moves forward, and the clamp 1 112 on the material placement mechanism 11 clamps the side fence material and places it on the clamping claw cylinder group 140a at the tail end of the clamp 2 132a on the feeding mechanism 13. The feeding mechanism 13 moves the side fence material to the material sorting mechanism 12 to adjust the second side fence material. After the adjustment is completed, the clamping claw cylinder group 140a at the tail end fixes the second side fence material, and the entire side fence material preparation process is completed.
[0065] The present invention realizes the adjustment, preparation and feeding of multiple side bar materials, automatic loading of bottom frame materials, automatic welding of side bar materials and bottom frame materials, and full-automatic welding processing of automatic unloading of shelves by arranging a handling manipulator, a first side bar loading device, a second side bar loading device, two welding devices, a welding bottom frame material placement device, a product placement device and a control cabinet group, thereby reducing manual labor intensity and cost and improving production efficiency; the first side bar loading device and the second side bar loading device are arranged to realize the preparation of multiple side bar materials and improve the side bar preparation efficiency; the material placement mechanism, the material sorting mechanism and the feeding mechanism are arranged to realize automatic discharge, sorting and correction and feeding actions and improve the feeding efficiency of the side bar materials; the material placement mechanism is arranged for the placement and inversion of the side bar materials to ensure the consistency of the orientation of the side bar material placement, and cooperate with the platform The side rail material can be automatically conveyed according to its own weight; a partition component is set to separate the side rail material from the side rail material to prevent the occurrence of overlapping materials, and a limit component is set to limit the side rail material separation action to ensure the stability and efficiency of material transportation; a feeding mechanism with multiple groups of clamping claws and cylinder groups can be set to realize the conveying and docking of one side rail material or two side rail materials according to needs; improve the subsequent welding efficiency; a whole material component is set to perform the rotation and adjustment action of the side rail material, and a material placement mechanism is set to ensure the welding direction of the side rail material without manual adjustment, thereby reducing the labor intensity and cost and improving the feeding efficiency; an adjustable structure is set to adjust the spacing of the whole material mechanism, so that the whole material mechanism can be used for the clamping and rotating action of side rail materials of different lengths and specifications, thereby improving applicability.
[0066] The present invention is not limited to the above-mentioned embodiments. Other equipment and methods for rack welding obtained by using the same or similar structures, devices, processes or methods as the above-mentioned embodiments of the present invention are within the protection scope of the present invention.
Claims
1. A layer welding device, characterized in that: The shelf welding equipment includes a handling robot, a first side rail loading device, a second side rail loading device, two welding devices, a bottom frame material placement device, a product placement device and a control cabinet group; one of the welding devices is arranged horizontally on the outside of the handling robot, and the other welding device is arranged longitudinally at the end of the horizontally arranged welding device, the first side rail loading device is arranged on the outside of one of the welding devices, the second side rail loading device is arranged on the outside of the other welding device, and the bottom frame material placement device and the product placement device are respectively arranged on the other two outer sides of the handling robot.
2. The layer welding equipment according to claim 1, characterized in that: The size of the first side rail feeding device is larger than that of the second side rail feeding device; the first side rail feeding device and the second side rail feeding device both include a base, a platform, a material placement mechanism, a material organization mechanism and a feeding mechanism; the platform is arranged on the base, the material placement mechanism is arranged on the platform, the feeding mechanism is arranged below the material placement mechanism, and the material organization mechanism is arranged on the side in front of the material placement mechanism; the material placement mechanism is provided with a limiting discharge component, and the limiting discharge component is used for conveying a single material; the material organization mechanism is provided with an adjustable structure.
3. The layer welding equipment according to claim 2 is characterized in that: Both sides of the platform are provided with mounting seats; the material-forming mechanism includes two material-forming components, the adjustable structure includes two sets of slide rails, the slide rails are respectively arranged on the mounting seats, the slide rails are each provided with a base with a slider, the base with a slider is provided with a locking wrench; the base with a slider is provided with a support, the material-forming component is arranged on the support; The monolithic components all include a rotary drive member; the rotary drive member may be a rotary cylinder or a servo motor; the rotary drive member is provided with a rotary shaft, the rotary shaft is provided with a connecting seat, and the connecting seat is provided with a clamping jaw; The platform includes two baffles, which are arranged on the base in a mirror-image manner. Both of the baffles are right-angled trapezoidal plates, and the high end of the baffle is arranged at the tail end, and the low end of the baffle is close to the whole material component; two cross bars are arranged between the two baffles, and the bottom of the cross bars is provided with a slide rail.
4. The layer welding equipment according to claim 3 is characterized in that: The material placement mechanism includes a plurality of support rails, a guide groove group and a clamp 1, the guide groove group includes two guide grooves, the guide grooves each include a slide plate, and the slide plates are respectively arranged on the inner side surface of the baffle in a mirror-image manner and tilted; a fixed column is also arranged between the two baffles, and the plurality of support rails are arranged between the two guide grooves and on the fixed column, and the support rails are provided with a guide groove 1; the cross bar is provided with a plurality of slide seats 1 and a plurality of slide seats 2, and the clamp 1 is respectively arranged on the slide seats 2; The slide seat 1 and the slide seat 2 are both provided with a plurality of sliders 1, the sliders 1 are arranged on the slide rail 1, the slide seat 1 and the slide seat 2 are provided with a mounting plate 1, the mounting plate 1 is arranged above the cross bar, the mounting plate 1 is provided with threaded holes, and the threaded holes are provided with quick wrenches; the slide seat 1 is arranged at both ends of the cross bar, and the slide seat 2 is arranged between the slide seats 1.
5. The layer welding equipment according to claim 4, characterized in that: The position-limiting discharge assembly includes a partition assembly and a position-limiting assembly, the partition assembly includes a plurality of cylinder groups, each of the cylinder groups includes two cylinders 1, one of the cylinders 1 is arranged at the bottom of the slide seat 2, and the other cylinder is arranged at the end of the support rail and below the clamp 1; each of the cylinders 1 is provided with a corner block, and a material isolation distance is provided between the two corner blocks; The limit assembly includes two cylinders 2, which are respectively arranged on the slide seat 1 and at the ends of the guide groove, and the driving shafts of the cylinders 2 are each provided with a stop column.
6. The layer welding equipment according to claim 5, characterized in that: The feeding mechanism includes a servo motor, a linear module and a loading assembly, wherein the servo motor is connected to the linear module and is arranged on the platform; the linear module is provided with a platform 1, and the loading assembly is arranged on the platform 1; The material loading assembly includes a lifting cylinder, a plurality of guide sleeves 2 and a platform 3. The lifting cylinder and the plurality of guide sleeves 2 are both arranged on the platform 1; the guide sleeves 2 are each provided with guide pillars 2, and the platform 3 is arranged on the guide pillars 2; the platform 3 is provided with a clamp 2.
7. The layer welding equipment according to claim 6, characterized in that: The two welding devices both include a frame, a welding head mechanism and a welding platform mechanism, wherein the welding head mechanism is arranged on the top of the welding platform mechanism; the welding head mechanism includes two or more welding head assemblies, and the welding platform mechanism is provided with a slide rail and a plurality of welding platform chuck assemblies, wherein the plurality of welding platform chuck assemblies are all arranged on the slide rail, and the welding platform chuck assemblies are respectively arranged below the welding head assemblies; the welding head assemblies are all provided with a lifting cylinder.
8. The layer welding equipment according to claim 7, characterized in that: The chassis material placement device includes a lifting material rack and a sorting platform. The lifting material rack is provided with a servo lifting mechanism and a clamp. The clamp is provided with a moving mechanism. The moving mechanism is used to transport the chassis material to the sorting platform; the product placement device is a collection trolley, and the collection trolley is provided with a collection frame; the transport robot is provided with a clamping claw.
9. A welding method for implementing the layer welding equipment according to any one of claims 1 to 8, characterized in that: It includes the following steps: (1) Material preparation: the first side rail loading device and the second side rail loading device respectively prepare the side rail materials, and the bottom frame material placement device prepares the bottom frame materials, and the material preparation is completed; (2) Carrying of chassis materials: the carrying robot moves the chassis materials on the chassis material placement device to the welding device; (3) The first welding process of the shelf: the first side rail feeding device transports one of the side rail materials to the welding device, and then the transport robot transports one side of the bottom frame material to one of the welding devices, the side of the bottom frame material is bonded to the side rail material, and the welding device performs the first welding, and the first welding process is completed; (4) Second welding process of the shelf: the handling robot removes the base frame material that has been welded for the first time, rotates 180° to the side of the other mirror image and aligns it with the welding device. At the same time, the first side rail feeding device transports the other side rail material to the welding device. The handling robot transports the other side of the base frame material to the welding device. The other side of the base frame material is bonded to the side rail material. The welding device performs a second welding, and the second welding process is completed. (5) The third welding process of the shelf: the handling robot removes the welded bottom frame material, the second side rail feeding device transports one of the prepared side rail materials to the other welding device, the handling robot rotates the bottom frame material 90°, and after the rotation is completed, transports the side of the bottom frame material to the welding device and fits it with the side rail material, the welding device moves to perform the third welding process, and the third welding process is completed; (6) The fourth welding process of the shelf: the handling robot withdraws the bottom shelf material, and the second side rail feeding device moves the other side rail material that has been prepared forward to the welding device in step (5). At the same time, the handling robot rotates the bottom shelf material 180°, and after the rotation is completed, the side of the bottom shelf material is transported to the welding device and fits it with the side rail material. The welding device moves to perform the fourth welding process, and the fourth welding process is completed; (7) Unloading of shelf products: The handling robot removes the shelf products that have been welded and transports the processed shelf products to the product placement device, and then transports new shelf materials, and the entire process is completed.
10. The welding method according to claim 9, characterized in that: The method (1) further comprises the following steps: (1.1) The material placement mechanism slides down to the exit of the limit material discharge component under the action of gravity, and the limit material discharge component is actuated to perform limit material discharge, allowing a side fence material to be discharged. The clamp 1 on the material placement mechanism clamps the side fence material and places it on the frontmost clamping claw cylinder group of the clamp 2 on the feeding mechanism, and the feeding mechanism is actuated to transport the side fence material to the material sorting mechanism to adjust the first side fence material; at the same time, the material placement mechanism slides down to the exit of the limit material discharge component under the action of gravity, and the limit material discharge component is actuated to perform limit material discharge, allowing the second side fence material to be discharged; after the adjustment of the first side fence material is completed, the material sorting mechanism is released, and the frontmost clamping claw cylinder group fixes the side material after the sorting is completed; (1.2) The feeding mechanism moves forward, and the clamp 1 on the material placement mechanism clamps the side fence material and places it on the clamping claw cylinder group at the tail end of the clamp 2 on the feeding mechanism. The feeding mechanism transports the side fence material to the material adjustment mechanism to adjust the second side fence material. After the adjustment is completed, the clamping claw cylinder group at the tail end fixes the second side fence material, and the entire side fence material preparation process is completed.
Citation Information
Patent Citations
Shelf side rail welding machine
CN221047623U