Road and bridge crack reinforcing structure and reinforcing method
By setting up reinforced steel plates and multiple reinforced columns on the road bridge and fixing these structures by pouring concrete, the problem of fillings easily damaged or fall off under high traffic volume or heavy load in the prior art is solved, and the bridge is improved Effects of structural strength and stability.
Patent Information
- Application Number
- CN202411710497.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-27
- Publication Date
- 2025-02-14
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the prior art, in the subsequent use of road bridge cracks, when the traffic volume is too large or there are too many heavy-load vehicles, it is easy to cause greater pressure to the joint part of the filling and the original roadbed, resulting in damage to the filling or It falls off and needs to be repaired again.
A crack reinforcement structure of road bridge is designed, including opening a second rectangular groove and a first rectangular groove on the bridge body, and providing a plurality of reinforcement columns and steel plates therein, fixing these structures by concrete pouring to form a reinforcement structure, Improve the structural strength and stability of the bridge.
By setting up reinforced steel plates and multiple reinforced columns, the separation of fillers from the bridge can be effectively avoided, the overall strength and stability of the bridge structure can be improved, the demand for subsequent repairs can be reduced, and the service life of road bridges can be improved.
Smart Images

Figure CN119434134A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of reinforcement structures, and in particular to a road bridge crack reinforcement structure and a reinforcement method. Background Art
[0002] After the roads and bridges are laid, they will gradually become fragile after being subjected to high temperatures, severe cold and rain during the process of being put into use. If they are subjected to large loads, they will crack, causing cracks in the roads and bridges. If they are not repaired in time, the original cracks will gradually increase until the roads and bridges are damaged.
[0003] The most commonly used method for repairing road and bridge cracks is the filling and repair method. When repairing, a deep groove is first chiseled along the crack, and then cement mortar, epoxy mortar, asphalt, reinforcing agent and other bonding materials are embedded in the groove. The repair is completed after the bonding material solidifies, but the interior does not support the structure. It only relies on the strength of the bonding material itself to support the rolling pressure of vehicles. However, if the traffic volume on the repaired section is too large or there are too many heavy-loaded vehicles, especially at night when engineering vehicles often pass by, the engineering vehicles carrying engineering materials will exert greater pressure on the joint between the filler and the original roadbed. Only relying on the strength of the bonding material itself to support the rolling pressure of engineering vehicles can easily cause it to be damaged or fall off, and it needs to be repaired again. Therefore, a road and bridge crack reinforcement structure and reinforcement method are needed. Summary of the invention
[0004] The purpose of the present invention is to solve at least one of the technical problems existing in the prior art and to provide a road bridge crack reinforcement structure and reinforcement method, which can solve the problem that the most commonly used method for repairing road bridge cracks is the filling and repair method. In subsequent use, excessive traffic volume or too many heavy-loaded vehicles will produce greater pressure on the joint between the filler and the original roadbed, causing it to be damaged or fall off, and it needs to be repaired again.
[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a road bridge crack reinforcement structure, comprising a bridge body;
[0006] A second rectangular groove is provided on the bridge body, two first rectangular grooves are provided on the upper surface of the bridge body, and a plurality of first fixing holes are provided at the bottom of the second rectangular groove;
[0007] The left and right inner walls of the second rectangular groove are each provided with a plurality of second fixing holes, the inner wall of the second rectangular groove is provided with a concave frame, and the left and right inner walls of the concave frame are fixedly connected with a plurality of first reinforcing columns;
[0008] Among them, multiple first reinforcing columns are each provided with multiple first clamping holes, a reinforcing steel plate is provided on the upper surface of the concave frame, and multiple second reinforcing columns are fixedly connected to the lower surface of the reinforcing steel plate, and the lower ends of the multiple second reinforcing columns slide through the inner walls of the corresponding first clamping holes respectively.
[0009] Preferably, two clamping plates are fixedly connected to the bottom of the concave frame, concave clamping plates are arranged on the upper surfaces of the two clamping plates, and protective covers are fixedly connected to the opposite surfaces of the two concave clamping plates.
[0010] Preferably, a plurality of second fixing holes are provided on the upper surface of the protective cover and the bottom of the concave frame, and the lower ends of the plurality of second reinforcement columns are respectively engaged with the corresponding second fixing holes.
[0011] Preferably, a plurality of circular holes are provided on the lower surface of the concave frame, and the plurality of circular holes all penetrate the upper surface of the concave frame, and the inner walls of the plurality of circular holes are slidably sleeved with third reinforcing columns, and the upper ends of the outer surfaces of the plurality of third reinforcing columns are provided with threaded grooves.
[0012] Preferably, the lower ends of the plurality of third reinforcement columns are respectively snap-fitted with the corresponding first fixing holes, and the outer walls of the plurality of third reinforcement columns are all fixedly sleeved with a circular plate.
[0013] Preferably, the inner wall of the bridge body is provided with a plurality of fourth reinforcement columns, each of which is provided with a plurality of third fixing holes, and the lower ends of the plurality of third reinforcement columns respectively slide through the inner walls of the corresponding third fixing holes.
[0014] Preferably, through holes are opened on the left and right sides of the plurality of fourth reinforcing columns, the inner walls of the plurality of through holes are fixedly connected with springs, and the ends of the plurality of springs away from the inner walls of the through holes are fixedly connected with fixing columns.
[0015] Preferably, the plurality of fixing posts are slidably connected to the corresponding through holes respectively, and one end of the plurality of fixing posts away from the spring is fixedly connected with a semicircular block.
[0016] Preferably, the inner wall of the second rectangular groove is provided with a concrete block, and the concrete block is cast by concrete.
[0017] A road bridge crack reinforcement method comprises the following steps:
[0018] S1: First, a second rectangular groove is opened at the crack of the bridge body by an external tool, then a plurality of first fixing holes are opened at the bottom of the second rectangular groove, and then a plurality of second fixing holes are opened on the left and right inner walls of the second rectangular groove, and finally two first rectangular grooves are opened on the upper surface of the bridge body;
[0019] S2: After the second rectangular groove and the first rectangular groove are opened, the fourth reinforcing column is picked up as a whole, and the fourth reinforcing column is placed horizontally on the inner wall of the second rectangular groove, and the two semicircular blocks contact the inner wall of the second rectangular groove. The two semicircular blocks push the two fixing columns into the inner walls of the two through holes under pressure and compress the two springs;
[0020] Among them, when the two semicircular blocks contact the inner walls of the two second fixing holes, under the action of the two springs, the two semicircular blocks and the two fixing columns are clamped into the inner walls of the two second fixing holes to complete the fixing of the fourth reinforcement column. The installation method of other multiple fourth reinforcement columns is the same;
[0021] Among them, after the other multiple fourth reinforcement columns are installed, the third reinforcement column is taken out;
[0022] S3: Then, the lower end of the third reinforcing column is passed through the inner wall of the third fixing hole on the fourth reinforcing column, and the lower end of the third reinforcing column is clamped into the inner wall of the first fixing hole on the second rectangular groove, and the lower surface of the circular plate is in contact with the upper surface of the fourth reinforcing column, and then concrete is poured on the inner wall of the second rectangular groove by an external tool to fix the plurality of fourth reinforcing columns and the plurality of third reinforcing columns;
[0023] Among them, by arranging a plurality of fourth reinforcement columns and a plurality of third reinforcement columns, the plurality of fourth reinforcement columns and the plurality of third reinforcement columns are all arranged in a cross shape, and after the concrete is hardened, a concrete block is formed, so that the structural strength of the lower end of the entire reinforcement structure can be improved, and the stability of the bottom of the reinforcement structure can be improved;
[0024] S4: After the concrete hardens to form a concrete block, the concave frame is picked up and installed on the upper surface of the concrete block through multiple circular holes and multiple third reinforcement columns, and then fixed through multiple fixing nuts, and then the whole card plate is picked up, and the two concave card plates are clamped together with the two card plates to complete the installation of the protective cover;
[0025] Among them, after the protective cover is installed, take out the reinforcing steel plate;
[0026] S5: Then, the lower ends of the plurality of second reinforcing columns on the lower surface of the reinforcing steel plate are sequentially passed through the inner walls of the first clamping holes on the corresponding first reinforcing columns, and finally, the lower ends of the plurality of second reinforcing columns are respectively clamped into the inner walls of the second fixing holes on the corresponding concave frame and the protective cover, and the lower surface of the reinforcing steel plate is in contact with the inner walls of the two first rectangular grooves;
[0027] S6: Finally, concrete is poured into the concave frame through the grouting holes to fix the plurality of first reinforcement columns, the plurality of second reinforcement columns and the reinforcement steel plate. After the poured concrete is hardened, the installation of the reinforcement structure can be completed.
[0028] Compared with the prior art, the present invention has the following beneficial effects:
[0029] (1) The road bridge crack reinforcement structure can avoid direct contact between vehicles and filled concrete by setting a reinforcing steel plate, thereby preventing the filled concrete from separating from the bridge again and forming cracks again. By setting a plurality of fourth reinforcing columns and a plurality of third reinforcing columns, the plurality of fourth reinforcing columns and the plurality of third reinforcing columns are all arranged in a cross shape, and after the concrete hardens, they form concrete blocks, which can improve the structural strength of the lower end of the reinforcement structure as a whole and improve the stability of the bottom of the reinforcement structure. By setting a plurality of first reinforcing columns and a plurality of second reinforcing columns, the structural strength of the upper end of the reinforcement structure as a whole can be effectively improved after pouring concrete, thereby increasing the bearing pressure of the reinforcing steel plate, and effectively avoiding excessive traffic volume or too many heavy-loaded vehicles in subsequent use, which will cause greater pressure on the joint between the filler and the original roadbed, thereby causing damage or falling off. The concave frame also plays a role in limiting the concrete after pouring, thereby improving the practicality of the road bridge crack reinforcement structure.
[0030] (2) The road bridge crack reinforcement structure is provided with a plurality of fourth reinforcement columns and a plurality of third reinforcement columns. The plurality of fourth reinforcement columns and the plurality of third reinforcement columns are all arranged in a cross shape. After the concrete is hardened, the concrete blocks are formed, which can improve the structural strength of the lower end of the reinforcement structure as a whole and improve the stability of the bottom of the reinforcement structure.
[0031] (3) The road bridge crack reinforcement structure can enhance the integrity of the reinforcement structure as a whole and the bridge body after installation by providing a plurality of first fixing holes, a plurality of second fixing holes and a plurality of fixing columns.
[0032] (4) The road bridge crack reinforcement method uses a clamping method to install the reinforcement structure and then fixes it by pouring concrete, which can improve the convenience of installation of the reinforcement structure, as well as the structural strength after installation, and increase the service life of the reinforcement structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] The present invention is further described below in conjunction with the accompanying drawings and embodiments:
[0034] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0035] Figure 2 This is a schematic diagram of the bottom of the second rectangular groove of the present invention;
[0036] Figure 3 This is a schematic diagram of the connection between the second reinforcement column and the reinforcement steel of the present invention;
[0037] Figure 4 This is a schematic diagram of the connection between the protective cover and the concave card plate of the present invention;
[0038] Figure 5This is a schematic diagram of the surface of the fourth reinforcement column of the present invention;
[0039] Figure 6 This is a schematic diagram of the connection between the fixing column and the spring of the present invention;
[0040] Figure 7 It is a schematic diagram of the connection between the fourth reinforcement column and the third reinforcement column of the present invention.
[0041] Figure numerals: 1. Bridge body; 2. Reinforced steel plate; 3. First reinforcing column; 4. Concave frame; 5. Concrete block; 6. Protective cover; 7. Grouting hole; 8. First rectangular groove; 9. First fixing hole; 10. Second rectangular groove; 11. Second fixing hole; 12. Second reinforcing column; 13. First clamping hole; 14. Second fixing hole; 15. Concave clamping plate; 16. Clamping plate; 17. Third reinforcing column; 18. Circular plate; 19. Through hole; 20. Third fixing hole; 21. Fourth reinforcing column; 22. Fixed column; 23. Spring; 24. Semicircular block; 25. Circular hole. DETAILED DESCRIPTION
[0042] This section will describe in detail the specific embodiments of the present invention. The preferred embodiments of the present invention are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the present invention, but it cannot be understood as a limitation on the scope of protection of the present invention.
[0043] In the description of the present invention, it should be understood that descriptions involving orientations, such as up, down, front, back, left, right, etc., and orientations or positional relationships indicated are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0044] In the description of the present invention, "greater than", "less than", "exceed" etc. are understood as not including the number itself, and "above", "below", "within" etc. are understood as including the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing technical features, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.
[0045] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.
[0046] See also Figure 1-7The present invention provides a technical solution: a road bridge crack reinforcement structure and reinforcement method, comprising a bridge body 1, a second rectangular groove 10 is opened on the bridge body 1, two first rectangular grooves 8 are opened on the upper surface of the bridge body 1, and a plurality of first fixing holes 9 are opened at the bottom of the second rectangular groove 10;
[0047] The left and right inner walls of the second rectangular groove 10 are both provided with a plurality of second fixing holes 11, the inner wall of the second rectangular groove 10 is provided with a concave frame 4, and the left and right inner walls of the concave frame 4 are fixedly connected with a plurality of first reinforcing columns 3;
[0048] Among them, multiple first reinforcing columns 3 are each provided with multiple first clamping holes 13, the upper surface of the concave frame 4 is provided with a reinforcing steel plate 2, and the lower surface of the reinforcing steel plate 2 is fixedly connected with multiple second reinforcing columns 12, and the lower ends of the multiple second reinforcing columns 12 respectively slide through the inner walls of the corresponding first clamping holes 13.
[0049] Furthermore, two clamping plates 16 are fixedly connected to the bottom of the concave frame 4 , concave clamping plates 15 are provided on the upper surfaces of the two clamping plates 16 , and the protective covers 6 are fixedly connected to the opposite surfaces of the two concave clamping plates 15 .
[0050] Furthermore, a plurality of second fixing holes 14 are formed on the upper surface of the protective cover 6 and the bottom of the concave frame 4 , and the lower ends of the plurality of second reinforcing columns 12 are respectively engaged with the corresponding second fixing holes 14 .
[0051] Furthermore, a plurality of circular holes 25 are provided on the lower surface of the concave frame 4, and the plurality of circular holes 25 all penetrate the upper surface of the concave frame 4. The inner walls of the plurality of circular holes 25 are slidably sleeved with third reinforcing columns 17, and the upper ends of the outer surfaces of the plurality of third reinforcing columns 17 are provided with threaded grooves.
[0052] Furthermore, the lower ends of the plurality of third reinforcement columns 17 are respectively engaged with the corresponding first fixing holes 9 , and the outer walls of the plurality of third reinforcement columns 17 are all fixedly sleeved with a circular plate 18 .
[0053] Furthermore, a plurality of fourth reinforcing columns 21 are provided on the inner wall of the bridge body 1 , and a plurality of third fixing holes 20 are opened on the plurality of fourth reinforcing columns 21 , and the lower ends of the plurality of third reinforcing columns 17 slide through the inner walls of the corresponding third fixing holes 20 , respectively.
[0054] Furthermore, through holes 19 are opened on both sides of the fourth reinforcing columns 21 , the inner walls of the through holes 19 are fixedly connected with springs 23 , and the ends of the springs 23 away from the inner walls of the through holes 19 are fixedly connected with fixing columns 22 .
[0055] Furthermore, the plurality of fixing posts 22 are slidably connected to the corresponding through holes 19 , and one end of the plurality of fixing posts 22 away from the spring 23 is fixedly connected to a semicircular block 24 .
[0056] Furthermore, a concrete block 5 is provided on the inner wall of the second rectangular groove 10 , and the concrete block 5 is cast by concrete.
[0057] A road bridge crack reinforcement method comprises the following steps:
[0058] S1: First, a second rectangular groove 10 is opened at the crack of the bridge body 1 by an external tool, and then a plurality of first fixing holes 9 are opened at the bottom of the second rectangular groove 10, and then a plurality of second fixing holes 11 are opened on the left and right inner walls of the second rectangular groove 10, and finally two first rectangular grooves 8 are opened on the upper surface of the bridge body 1;
[0059] S2: After the second rectangular groove 10 and the first rectangular groove 8 are opened, the fourth reinforcing column 21 is picked up as a whole and placed horizontally on the inner wall of the second rectangular groove 10, and the two semicircular blocks 24 contact the inner wall of the second rectangular groove 10. The two semicircular blocks 24 push the two fixing columns 22 into the inner walls of the two through holes 19 under pressure and compress the two springs 23;
[0060] When the two semicircular blocks 24 contact the inner walls of the two second fixing holes 11, under the action of the two springs 23, the two semicircular blocks 24 and the two fixing columns 22 are clamped into the inner walls of the two second fixing holes 11, thereby completing the fixing of the fourth reinforcement column 21. The installation method of the other multiple fourth reinforcement columns 21 is the same;
[0061] After the other plurality of fourth reinforcement columns 21 are installed, the third reinforcement column 17 is taken out;
[0062] S3: Then, the lower end of the third reinforcing column 17 is passed through the inner wall of the third fixing hole 20 on the fourth reinforcing column 21, and the lower end of the third reinforcing column 17 is clamped into the inner wall of the first fixing hole 9 on the second rectangular groove 10, and the lower surface of the circular plate 18 is in contact with the upper surface of the fourth reinforcing column 21, and then concrete is poured on the inner wall of the second rectangular groove 10 by an external tool to fix the plurality of fourth reinforcing columns 21 and the plurality of third reinforcing columns 17;
[0063] Among them, by setting a plurality of fourth reinforcement columns 21 and a plurality of third reinforcement columns 17, the plurality of fourth reinforcement columns 21 and the plurality of third reinforcement columns 17 are all arranged in a cross shape, and after the concrete is hardened, the concrete block 5 is formed, which can improve the structural strength of the lower end of the entire reinforcement structure and improve the stability of the bottom of the reinforcement structure;
[0064] S4: After the concrete hardens to form a concrete block 5, the concave frame 4 is then taken up and installed on the upper surface of the concrete block 5 through the multiple circular holes 25 and the multiple third reinforcement columns 17, and then fixed by multiple fixing nuts, and then the clamping plate 16 is taken up as a whole, and the two concave clamping plates 15 and the two clamping plates 16 are clamped together to complete the installation of the protective cover 6;
[0065] After the protective cover 6 is installed, the reinforcing steel plate 2 is taken out;
[0066] S5: Then, the lower ends of the plurality of second reinforcing columns 12 on the lower surface of the reinforcing steel plate 2 are sequentially passed through the inner walls of the first clamping holes 13 on the corresponding first reinforcing columns 3, and finally, the lower ends of the plurality of second reinforcing columns 12 are respectively clamped into the inner walls of the second fixing holes 14 on the corresponding concave frame 4 and the protective cover 6, and the lower surface of the reinforcing steel plate 2 is in contact with the inner walls of the two first rectangular grooves 8;
[0067] S6: Finally, pour concrete into the concave frame 4 through the grouting holes 7 to fix the first reinforcement columns 3, the second reinforcement columns 12 and the reinforcement steel plate 2. After the poured concrete hardens, the installation of the reinforcement structure is completed.
[0068] Among them, by setting the reinforcing steel plate 2, it is possible to avoid direct contact between vehicles and the filled concrete, prevent the filled concrete from separating from the bridge again and forming cracks again, and by setting a plurality of fourth reinforcing columns 21 and a plurality of third reinforcing columns 17, the plurality of fourth reinforcing columns 21 and the plurality of third reinforcing columns 17 are all arranged in a cross shape, and after the concrete is hardened, the concrete block 5 is formed, which can improve the structural strength of the lower end of the entire reinforced structure and improve the stability of the bottom of the reinforced structure. By setting a plurality of first reinforcing columns 3 and a plurality of second reinforcing columns 12, the structural strength of the upper end of the entire reinforced structure can be effectively improved after pouring concrete, thereby increasing the bearing pressure of the reinforcing steel plate 2, and effectively avoiding excessive traffic volume or too many heavy-loaded vehicles in subsequent use, which will generate greater pressure on the joint between the filler and the original roadbed, thereby causing damage or falling off, and the concave frame 4 plays a role in limiting the concrete after pouring, thereby improving the practicality of the road bridge crack reinforcement structure;
[0069] Among them, by installing the reinforcement structure by a clamping method and then fixing it by pouring concrete, the convenience of installing the reinforcement structure and the structural strength after installation can be improved, thereby increasing the service life of the reinforcement structure;
[0070] Among them, by providing a plurality of first fixing holes 9, a plurality of second fixing holes 11 and a plurality of fixing columns 22, the integrity of the entire reinforcement structure and the bridge body 1 after installation can be strengthened.
[0071] Working principle: First, a second rectangular groove 10 is opened at the crack of the bridge body 1 using an external tool, and then a plurality of first fixing holes 9 are opened at the bottom of the second rectangular groove 10, and then a plurality of second fixing holes 11 are opened on the left and right inner walls of the second rectangular groove 10, and finally two first rectangular grooves 8 are opened on the upper surface of the bridge body 1.
[0072] Further, after the opening is completed, the fourth reinforcing column 21 is picked up as a whole, and the fourth reinforcing column 21 is placed horizontally on the inner wall of the second rectangular groove 10, and the two semicircular blocks 24 contact the inner wall of the second rectangular groove 10. The two semicircular blocks 24 push the two fixing columns 22 into the inner walls of the two through holes 19 under pressure and compress the two springs 23;
[0073] Among them, when the two semicircular blocks 24 contact the inner walls of the two second fixing holes 11, under the action of the two springs 23, the two semicircular blocks 24 and the two fixing columns 22 are clamped into the inner walls of the two second fixing holes 11 to complete the fixation of the fourth reinforcement column 21. The installation method of other multiple fourth reinforcement columns 21 is the same.
[0074] Furthermore, the third reinforcing column 17 is then picked up, the lower end of the third reinforcing column 17 is passed through the inner wall of the third fixing hole 20, and the lower end of the third reinforcing column 17 is clamped into the inner wall of the first fixing hole 9, so that the lower surface of the circular plate 18 is in contact with the upper surface of the fourth reinforcing column 21, and then concrete is poured on the inner wall of the second rectangular groove 10 through external tools to fix multiple fourth reinforcing columns 21 and multiple third reinforcing columns 17.
[0075] Furthermore, after the concrete hardens to form a concrete block 5, the concave frame 4 is picked up and installed on the upper surface of the concrete block 5 through multiple circular holes 25 and multiple third reinforcement columns 17, and then fixed by multiple fixing nuts, and then the clamping plate 16 is picked up as a whole, and the two concave clamping plates 15 and the two clamping plates 16 are clamped together to complete the installation of the protective cover 6.
[0076] Furthermore, pick up the reinforcing steel plate 2, and pass the lower ends of the multiple second reinforcing columns 12 on the lower surface of the reinforcing steel plate 2 through the inner walls of the corresponding first clamping holes 13 in sequence. Finally, the lower ends of the multiple second reinforcing columns 12 are respectively clamped to the inner walls of the corresponding second fixing holes 14, and the lower surface of the reinforcing steel plate 2 is in contact with the inner walls of the two first rectangular grooves 8.
[0077] Furthermore, concrete is poured into the concave frame 4 through the grouting holes 7 to fix the first reinforcement columns 3, the second reinforcement columns 12 and the reinforcement steel plate 2. After the poured concrete hardens, the installation of the reinforcement structure is completed.
[0078] The embodiments of the present invention are described in detail above with reference to the accompanying drawings. However, the present invention is not limited to the above embodiments. Various changes can be made within the knowledge scope of ordinary technicians in the technical field without departing from the purpose of the present invention.
Claims
1. A road bridge crack reinforcement structure, characterized in that: include: Bridge body (1); A second rectangular groove (10) is provided on the bridge body (1), two first rectangular grooves (8) are provided on the upper surface of the bridge body (1), and a plurality of first fixing holes (9) are provided at the bottom of the second rectangular groove (10); The left and right inner walls of the second rectangular groove (10) are each provided with a plurality of second fixing holes (11), the inner wall of the second rectangular groove (10) is provided with a concave frame (4), and the left and right inner walls of the concave frame (4) are fixedly connected with a plurality of first reinforcing columns (3); A plurality of first reinforcing columns (3) are each provided with a plurality of first clamping holes (13); a reinforcing steel plate (2) is provided on the upper surface of the concave frame (4); a plurality of second reinforcing columns (12) are fixedly connected to the lower surface of the reinforcing steel plate (2); and the lower ends of the plurality of second reinforcing columns (12) respectively slide through the inner walls of the corresponding first clamping holes (13).
2. A road bridge crack reinforcement structure according to claim 1, characterized in that: The bottom of the concave frame (4) is fixedly connected to two clamping plates (16), the upper surfaces of the two clamping plates (16) are provided with concave clamping plates (15), and the opposite surfaces of the two concave clamping plates (15) are fixedly connected to a protective cover (6).
3. A road bridge crack reinforcement structure according to claim 2, characterized in that: The upper surface of the protective cover (6) and the bottom of the concave frame (4) are both provided with a plurality of second fixing holes (14), and the lower ends of the plurality of second reinforcing columns (12) are respectively snap-fitted with the corresponding second fixing holes (14).
4. A road bridge crack reinforcement structure according to claim 1, characterized in that: The lower surface of the concave frame (4) is provided with a plurality of circular holes (25), and the plurality of circular holes (25) all penetrate the upper surface of the concave frame (4). The inner walls of the plurality of circular holes (25) are all slidably sleeved with third reinforcing columns (17), and the upper ends of the outer surfaces of the plurality of third reinforcing columns (17) are all provided with threaded grooves.
5. A road bridge crack reinforcement structure according to claim 3, characterized in that: The lower ends of the plurality of third reinforcement columns (17) are respectively snap-fitted with the corresponding first fixing holes (9), and the outer walls of the plurality of third reinforcement columns (17) are all fixedly sleeved with a circular plate (18).
6. A road bridge crack reinforcement structure according to claim 1, characterized in that: The inner wall of the bridge body (1) is provided with a plurality of fourth reinforcement columns (21), each of which is provided with a plurality of third fixing holes (20), and the lower ends of the plurality of third reinforcement columns (17) respectively slide through the inner walls of the corresponding third fixing holes (20).
7. A road bridge crack reinforcement structure according to claim 6, characterized in that: Through holes (19) are provided on both left and right sides of the plurality of fourth reinforcing columns (21), and springs (23) are fixedly connected to the inner walls of the plurality of through holes (19); Wherein, one end of each of the plurality of springs (23) away from the inner wall of the through hole (19) is fixedly connected to a fixing column (22).
8. A road bridge crack reinforcement structure according to claim 6, characterized in that: The plurality of fixing columns (22) are respectively slidably connected to the corresponding through holes (19), and one end of the plurality of fixing columns (22) away from the spring (23) is fixedly connected with a semicircular block (24).
9. A road bridge crack reinforcement structure according to claim 1, characterized in that: The inner wall of the second rectangular groove (10) is provided with a concrete block (5), and the concrete block (5) is cast by concrete.
10. A method for reinforcing cracks in a road or bridge, characterized in that: There are the following steps: S1: First, a second rectangular groove (10) is opened at the crack of the bridge body (1) by using an external tool, then a plurality of first fixing holes (9) are opened at the bottom of the second rectangular groove (10), and then a plurality of second fixing holes (11) are opened on the left and right inner walls of the second rectangular groove (10), and finally two first rectangular grooves (8) are opened on the upper surface of the bridge body (1); S2: After the second rectangular groove (10) and the first rectangular groove (8) are opened, the fourth reinforcing column (21) is picked up as a whole, and the fourth reinforcing column (21) is placed horizontally on the inner wall of the second rectangular groove (10), and the two semicircular blocks (24) contact the inner wall of the second rectangular groove (10). The two semicircular blocks (24) push the two fixing columns (22) into the inner walls of the two through holes (19) under pressure, and compress the two springs (23); When the two semicircular blocks (24) contact the inner walls of the two second fixing holes (11), under the action of the two springs (23), the two semicircular blocks (24) and the two fixing columns (22) are snapped into the inner walls of the two second fixing holes (11), thereby completing the fixing of the fourth reinforcement column (21). The installation method of the other multiple fourth reinforcement columns (21) is the same; After the other plurality of fourth reinforcement columns (21) are installed, the third reinforcement column (17) is taken out; S3: Then, the lower end of the third reinforcing column (17) is passed through the inner wall of the third fixing hole (20) on the fourth reinforcing column (21), and the lower end of the third reinforcing column (17) is clamped into the inner wall of the first fixing hole (9) on the second rectangular groove (10), and the lower surface of the circular plate (18) is in contact with the upper surface of the fourth reinforcing column (21), and then concrete is poured on the inner wall of the second rectangular groove (10) by an external tool to fix the plurality of fourth reinforcing columns (21) and the plurality of third reinforcing columns (17); By arranging a plurality of fourth reinforcement columns (21) and a plurality of third reinforcement columns (17), the plurality of fourth reinforcement columns (21) and the plurality of third reinforcement columns (17) are arranged in a cross shape, and after the concrete is hardened, a concrete block (5) is formed, so that the structural strength of the lower end of the entire reinforcement structure can be improved, and the stability of the bottom of the reinforcement structure can be improved; S4: After the concrete hardens to form a concrete block (5), the concave frame (4) is then taken up and installed on the upper surface of the concrete block (5) through the plurality of circular holes (25) and the plurality of third reinforcement columns (17), and then fixed by a plurality of fixing nuts, and then the clamping plate (16) is taken up as a whole, and the two concave clamping plates (15) and the two clamping plates (16) are clamped together to complete the installation of the protective cover (6); After the protective cover (6) is installed, the reinforcing steel plate (2) is taken out; S5: Then, the lower ends of the plurality of second reinforcing columns (12) on the lower surface of the reinforcing steel plate (2) are sequentially inserted through the inner walls of the first clamping holes (13) on the corresponding first reinforcing columns (3), and finally, the lower ends of the plurality of second reinforcing columns (12) are respectively clamped into the inner walls of the second fixing holes (14) on the corresponding concave frames (4) and the protective covers (6), and the lower surface of the reinforcing steel plate (2) is in contact with the inner walls of the two first rectangular grooves (8); S6: Finally, concrete is poured into the interior of the concave frame (4) through the grouting holes (7) to fix the plurality of first reinforcement columns (3), the plurality of second reinforcement columns (12) and the reinforcement steel plate (2). After the poured concrete hardens, the installation of the reinforcement structure is completed.