Comprehensive pipeline integration support and construction method

By installing the boom at the bottom of the ceiling and setting up multiple fixtures, the problem of repeated erecting brackets and pipeline adjustments in the comprehensive pipeline construction in the prior art is solved, and the pipeline is quickly adjusted and reinstalled, which improves construction efficiency and flexibility.

CN119435832AActive Publication Date: 2025-02-14CHINA FIRST METALLURGICAL GROUP
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
CN202411674627.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-21
Publication Date
2025-02-14
Estimated Expiration
2044-11-21

AI Technical Summary

Technical Problem

In the prior art, there is a problem that requires repeated installation of brackets and pipeline adjustments in comprehensive pipeline construction, resulting in low construction efficiency, high cost and communication contradictions between construction teams.

Method used

By installing the vertical section of the boom and the horizontal section of the boom at the bottom of the ceiling, and a plurality of first fixing parts and second fixing parts are provided on the horizontal section of the boom, and a sleeve is provided on the second fixing part, the pipe position is realized Flexible adjustment to avoid repeated installation of brackets and pipelines.

Benefits of technology

It realizes rapid adjustment and reinstallation of pipelines without removing the brackets, saving construction costs, and improving construction efficiency and flexibility.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119435832A_ABST
    Figure CN119435832A_ABST
Patent Text Reader

Abstract

The invention discloses a comprehensive pipeline integrated support and a construction method.The integrated support comprises suspender vertical sections, suspender horizontal sections, first fixing pieces and second fixing pieces, the suspender vertical sections are arranged at the two ends of the suspender horizontal sections, and the first fixing pieces and the second fixing pieces are arranged on the suspender horizontal sections; a plurality of pipelines are arranged on the ceiling bottom, the first fixing parts and the second fixing parts are connected with the pipelines in a matched mode, each first fixing part comprises a first width adjusting mechanism, and each second fixing part comprises a second width adjusting mechanism and a height adjusting mechanism. A plurality of pipelines of different sizes can be fixed at the same time by hoisting the comprehensive pipeline integrated support once, when collision occurs during pipeline installation, rapid displacement is achieved, the problem of repeated erection of the support and the pipelines is avoided, the construction cost is saved, and the construction efficiency and flexibility are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of building auxiliary equipment installation, and more specifically, relates to an integrated pipeline integrated bracket and a construction method. Background Art

[0002] In modern construction, the layout of pipelines is a critical step in ensuring the normal operation of buildings. These pipelines include, but are not limited to, water supply and drainage pipes, fire protection pipes, smoke exhaust pipes, cable trays, cable ducts, and various process pipelines, responsible for transporting energy, information, and resources. Supports and hangers are required for the installation of electromechanical pipelines. The hanger rods of the supports and hangers are fixed to the bottom of the floor slab to achieve the installation and fixation of the electromechanical pipelines. However, this installation and construction method has some obvious limitations. First, when pipelines with different functions conflict in the spatial layout, traditional supports and hangers are difficult to adjust, and existing structures often need to be dismantled to avoid them. This is not only time-consuming and labor-intensive, but also easily leads to communication conflicts between construction teams. Second, each construction team needs to independently set up supports and hangers when installing pipelines. This process is cumbersome and labor-intensive, affecting construction efficiency. In addition, the frequent removal and reconstruction of supports and hangers also increases construction costs and prolongs the project period.

[0003] The patent number is: CN109099210A, and the name is: An invention patent for a modular integrated pipeline bracket. The main brackets are arranged at certain intervals as needed, and auxiliary brackets are respectively provided between any two adjacent main brackets. Multiple U-shaped rings can be set on multiple main brackets as needed to fix ordinary pipelines. Multiple rubber vibration-absorbing rings can be set on multiple main brackets through locking rings as needed to fix pipelines that vibrate during use. The purpose of this setting is to absorb the vibration of the pipeline and improve the aesthetics and space utilization of the pipeline layout. It does not improve the efficiency of the pipeline layout, and the bracket cannot be adjusted according to the position of the pipeline.

[0004] The patent number is: CN117200107A, and the name is: An invention patent for an electromechanical integrated pipeline installation structure. By setting columns and load-bearing beams, it is prefabricated before installation. During installation, the intervals between adjacent columns are adjusted according to the actual size of the corridor and the position of the pipeline. At the same time, the position of the load-bearing beam can be adjusted according to the height position of the pipeline, so as to achieve the support of the electromechanical integrated support bracket for the pipeline in the corridor. However, when adjusting the upper and lower installation positions of the load-bearing beam, it can only be adjusted according to the socket position on the fixed bar. In addition, the moving rod needs to be pushed or pulled into the sleeve to adjust the length of the load-bearing beam, which is not convenient for telescopic adjustment and the adjustment is not flexible.

[0005] The patent number is: CN111271514A, and the name is: Invention patent for electromechanical integrated support and hanger and its installation method. By setting a horizontal rod and a vertical rod, and fixing the horizontal rod on the vertical rod, and then placing the pipeline on the horizontal rod to fix the pipeline, when fixing the pipeline, the pipeline clamp is passed around the pipeline so that the fixing block abuts against the pipeline, and then the end of the pipeline clamp is fixed to the horizontal rod through the first fixing piece, thereby fixing the pipeline on the horizontal rod to complete the fixation of the pipeline. Such a fixing structure is complex, not easy to operate, and reduces construction efficiency. Summary of the Invention

[0006] In view of the problem that the existing technology of integrated pipeline construction requires repeated erection of brackets and lacks flexibility in pipeline adjustment, the present invention provides an integrated pipeline integrated bracket and construction method. The integrated pipeline integrated bracket is installed by installing a vertical section of a hanger and a horizontal section of a hanger at the bottom of the ceiling, and multiple first fixing members and second fixing members are set on the horizontal section of the hanger. By hoisting the integrated pipeline integrated bracket once, multiple pipelines of different sizes can be fixed at the same time, saving construction costs and improving construction efficiency. At the same time, a sleeve is provided on the second fixing member to achieve vertical adjustment. When a collision occurs during pipeline installation, the position of the first fixing member and the second fixing member can be directly adjusted without removing the bracket, so as to achieve rapid displacement, and the reinstalled pipeline can be fixed, avoiding the problem of repeated erection of brackets and pipelines, saving construction costs, and improving construction flexibility.

[0007] To achieve the above-mentioned object, according to a first aspect of the present invention, there is provided an integrated pipeline integrated support, comprising a boom vertical section, a boom horizontal section, a first fixing member and a second fixing member, wherein the boom vertical section is vertically arranged at both ends of the boom horizontal section, and a plurality of the first fixing members and the second fixing members are arranged on the boom horizontal section, wherein: The top of the vertical section of the boom is fixedly connected to the bottom of the ceiling plate. A plurality of pipelines are provided on the bottom of the ceiling plate. The first fixing member and the second fixing member are cooperatively connected to the pipelines. The first fixing member includes a first width adjustment mechanism, and the first width adjustment mechanism is used to fix pipelines of different widths; The second fixing member includes a second width adjustment mechanism and a height adjustment mechanism, wherein the second width adjustment mechanism is used to fix pipelines of different widths, and the height adjustment mechanism is used to fix pipelines of different heights; When the pipeline is installed and collides, the pipeline position is directly adjusted, and the adjusted pipeline is re-fixed by adjusting the first width adjustment mechanism, the second width adjustment mechanism and the height adjustment mechanism, avoiding the need to reinstall the fixing bracket after the pipeline moves.

[0008] Preferably, the horizontal section of the boom is provided with teeth and nuts, there are a plurality of nuts engaged with the teeth, and the nuts are respectively connected to the first width adjustment mechanism and the second width adjustment mechanism.

[0009] Preferably, the first width adjustment mechanism includes a first connecting member, a second connecting member, a connecting nut and a first bolt, the first connecting member and the second connecting member are L-shaped tubes, one end opening of the first connecting member is socketed with the open end of the second connecting member, the other end of the first connecting member is connected to the first bolt through a connecting nut, the other end of the second connecting member is connected to the first bolt through a connecting nut, and the first bolt is connected to the nut.

[0010] Preferably, the diameter of the first connecting member is greater than the diameter of the second connecting member, and the wall thickness of the first connecting member and the second connecting member is 1 mm.

[0011] Preferably, the diameter of the first connecting member is 1 cm, and the diameter of the second connecting member is 0.8 cm.

[0012] Preferably, the second width adjustment mechanism includes a third connecting member, a fourth connecting member and a second bolt, the third connecting member and the fourth connecting member are both "├"-shaped rods, the side opening end of the third connecting member is relatively sleeved with the side opening end of the fourth connecting member, and the bottom of the third connecting member and the fourth connecting member are connected to the nut through the second bolt.

[0013] Preferably, the height adjustment mechanism includes a sleeve, and a threaded section is provided at the bottom of the third connecting member and the fourth connecting member. The sleeve is connected to the threaded section, and the height of the third connecting member and the fourth connecting member is adjusted by rotating the length of the connection between the sleeve and the threaded section.

[0014] Preferably, the diameter of the third connecting member is greater than the diameter of the fourth connecting member, and the wall thickness of the third connecting member and the fourth connecting member is 1 mm.

[0015] Preferably, the first connecting member, the second connecting member, the third connecting member and the fourth connecting member are made of lightweight and high-strength materials, including aluminum alloy, carbon fiber composite material, high-strength steel and magnesium alloy.

[0016] To achieve the above object, according to a second aspect of the present invention, a method for constructing an integrated pipeline integrated support is provided, which is implemented using any of the above-mentioned integrated pipeline integrated supports, and is characterized in that it specifically includes the following steps: S1. Drill holes at the bottom of the ceiling plate to install the vertical section of the boom, and install the horizontal section of the boom at the bottom of the vertical section; S2. Lay pipelines according to actual needs and install a corresponding number of nuts on the tooth grooves of the horizontal section of the boom according to the number of pipelines; S3. When there is no requirement for the height of the pipelines during construction and they all need to be on the same horizontal line, install the first fixing piece on the nut; S4. According to the width of the pipeline, the first connecting member and the second connecting member are connected to each other to fix the pipeline, and then the first bolt and the nut are connected to prevent the pipeline from moving in the horizontal direction; S5. When there are requirements for the height of the pipelines during construction, and all pipelines need to be on the same horizontal line or the height of the pipelines needs to be adjusted, install the second fixing piece on the nut; S6. According to the width of the pipeline, the third connecting piece and the fourth connecting piece are connected to and fix the pipeline, and then the second bolt and the nut are connected to prevent the pipeline from moving in the horizontal direction. The connection length between the rotating sleeve and the threaded section is adjusted to prevent the pipeline from moving in the vertical direction.

[0017] In general, the above technical solutions conceived by the present invention can achieve the following beneficial effects compared with the prior art: 1. The integrated pipeline integrated bracket and construction method of the present invention install a vertical section and a horizontal section of the hanger at the bottom of the ceiling, and set multiple first fixing members and second fixing members on the horizontal section of the hanger. By hoisting the integrated pipeline integrated bracket once, multiple pipelines of different sizes can be fixed at the same time, saving construction costs and improving construction efficiency.

[0018] 2. The present invention provides a first fixing member and a second fixing member, and a sleeve is provided on the second fixing member to achieve adjustment in the vertical direction. When a collision occurs during pipeline installation, the positions of the first fixing member and the second fixing member can be directly adjusted without removing the bracket, so as to achieve rapid shifting, thereby achieving fixation of reinstalled pipelines, avoiding the problem of repeatedly setting up brackets and pipelines, saving construction costs, and improving construction flexibility. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 This is a schematic diagram of the connection of the integrated pipeline integrated bracket in Example 1 of the present invention.

[0020] Figure 2 This is an exploded view of the first fixing member structure of the present invention.

[0021] Figure 3 This is an exploded view of the second fixing member structure of the present invention.

[0022] Figure 4 This is an enlarged view of the vertical section and horizontal section structure of the boom in Example 1 of the present invention.

[0023] Figure 5 This is a flow chart of the construction method of the integrated pipeline integrated support of the present invention.

[0024] In the figure: 1. Vertical section of the boom; 2. Horizontal section of the boom; 3. First fixing member; 4. Second fixing member; 5. Pipeline; 6. Tooth groove; 7. Nut; 8. First connecting member; 9. Second connecting member; 10. Connecting nut; 11. First bolt; 12. Second bolt; 13. Third connecting member; 14. Fourth connecting member; 15. Sleeve; 16. Threaded section; 17. Third bolt; 18. Bolt hole. DETAILED DESCRIPTION

[0025] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only intended to illustrate the present invention and are not intended to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below may be combined with each other as long as they do not conflict with each other.

[0026] Example 1 Depend on Figures 1 to 4 As shown, the integrated pipeline integrated support of the present invention includes a vertical section 1 of the boom, a horizontal section 2 of the boom, a first fixing member 3, and a second fixing member 4. The vertical section 1 of the boom is provided at both ends of the horizontal section 2 of the boom. The top of the vertical section 2 of the boom is fixedly connected to the bottom of the ceiling plate. The bottom of the vertical section 1 of the boom is provided with a bolt hole 18. The two ends of the horizontal section 2 of the boom are also provided with bolt holes 18. The vertical section 1 of the boom and the horizontal section 2 of the boom are fixedly connected by passing a third bolt 17 through the bolt holes. The horizontal section 2 of the boom is provided with a tooth groove 6 in the horizontal direction. The tooth groove 6 is provided with a plurality of bolts 7. The bolts 7 and the tooth groove 6 are meshed with each other. There are multiple first fixing members 3 and second fixing members 4, which are connected to the tooth groove 6 by bolts 7.

[0027] The first fixing member 3 includes a first width adjustment mechanism, which includes a first connecting member 8, a second connecting member 9, a connecting nut 10 and a first bolt 11. The first connecting member 8 and the second connecting member 9 are L-shaped circular tubes. One end opening of the first connecting member 8 is socketed with the open end of the second connecting member 9. The other end of the first connecting member 8 is connected to the first bolt 11 through the connecting nut 10. The other end of the second connecting member 8 is connected to the first bolt 11 through the connecting nut 10. The first bolt 11 is connected to the nut 7. The diameter of the first connecting member 8 is 1 cm, the diameter of the second connecting member 9 is 0.8 cm, and the wall thickness of the first connecting member 8 and the second connecting member 9 is 1 mm.

[0028] The working principle of the first fixing member 3 is: by controlling the depth of the connection between the first connecting member 8 and the second connecting member 9 and then controlling the width of the first fixing member 3, pipelines 5 of different sizes are fixed. The bottoms of the first connecting member 8 and the second connecting member 9 are respectively connected to the nut 7 by the first bolt 11. The first bolt 11 passes through the tooth groove 6 and the connecting nut 10 from bottom to top, and is fixed in the tooth groove 6 by tightening the first bolt 11, so as to prevent the first connecting member 8 and the second connecting member 9 from sliding left and right in the horizontal direction, thereby further fixing the pipeline 5.

[0029] The second fixing member 4 includes a second width adjustment mechanism and a height adjustment mechanism. The second width adjustment mechanism includes a third connecting member 13, a fourth connecting member 14, and a second bolt 12. The third connecting member 13 and the fourth connecting member 14 are both "├"-shaped rods. The side open end of the third connecting member 13 is relatively sleeved with the side open end of the fourth connecting member 14. The bottoms of the third connecting member 13 and the fourth connecting member 14 are connected to the nut 7 via the second bolt 12. The height adjustment mechanism includes a sleeve 15. The bottom surfaces of the third connecting member 13 and the fourth connecting member 14 are provided with a threaded section 16. The sleeve 15 is connected to the threaded section 16. The bottom of the sleeve 15 is also meshed with the tooth groove 6. The diameter of the third connecting member 13 is 1 cm, the diameter of the fourth connecting member 14 is 0.8 cm, and the wall thickness of the third connecting member 13 and the fourth connecting member 14 is 1 mm.

[0030] The working principle of the second fixing member 4 is as follows: by controlling the depth of the sleeve of the side open ends of the third connecting member 13 and the fourth connecting member 14, the width of the second fixing member 4 is controlled to fix pipelines 5 of different sizes. The bottoms of the third connecting member 13 and the fourth connecting member 14 are respectively connected to the nut 7 through the second bolt 12. The second bolt 12 passes through the tooth groove 6 and is connected to the internal thread of the bottom of the third connecting member 13 and the fourth connecting member 14, and is fixed in the tooth groove 6 by tightening the second bolt 12, so as to prevent the third connecting member 13 and the fourth connecting member 14 from sliding left and right in the horizontal direction, thereby further fixing the pipeline 5.

[0031] When the height of the pipeline 5 needs to be adjusted, the connection length of the rotating sleeve 15 and the threaded section 16 is adjusted, and the second bolt 12 is passed through the tooth groove 6 and the sleeve 15 from bottom to top in sequence, and the height adjustment and fixation of the second fixing member 4 are completed by tightening the second bolt 12.

[0032] The tooth groove 6 is composed of multiple horizontal grooves, and its shape is similar to that of a gear. The size of each groove is the same as that of the nut 7 and the sleeve 15. The groove can just hold a nut 7 or sleeve 15. When it needs to be shifted left or right, it is necessary to pick up the nut 7 or sleeve 15 and put it into the groove corresponding to the adjusted position, and tighten it to fix the first fixing member 3 and the second fixing member 4.

[0033] The first connecting member 8, the second connecting member 9, the third connecting member 13 and the fourth connecting member 14 are made of lightweight and high-strength materials, including aluminum alloy, carbon fiber composite material, high-strength steel and magnesium alloy, which can reduce the overall structural weight and improve construction efficiency.

[0034] Depend on Figure 5 As shown, a construction method of an integrated pipeline integrated support of the present invention is implemented by using the above-mentioned integrated pipeline integrated support, and specifically includes the following steps: S1. According to the actual situation of the construction site, drill holes at the bottom of the ceiling plate to install the vertical section 1 of the hanger, and install the horizontal section 2 of the hanger at the bottom of the vertical section 1 of the hanger. Specifically, pass the third bolt 17 through the bolt hole 18 to fix the vertical section 1 of the hanger and the horizontal section 2 of the hanger.

[0035] S2. Lay the pipelines 5 according to actual construction requirements, and install a corresponding number of nuts 7 on the tooth grooves 6 of the horizontal section 2 of the boom according to the number of pipelines 5.

[0036] S3. When there is no requirement on the height of the pipelines 5 during construction and they all need to be on the same horizontal line, install the first fixing member 3 on the nut 7.

[0037] S4. According to the width of the pipeline 5, the first connecting member 8 and the second connecting member 9 are sleeved together to fix the pipeline 5, and then the first bolt 11 and the nut 7 are connected to prevent the pipeline 5 from moving in the horizontal direction.

[0038] S5. When there are requirements for the height of pipeline 5 during construction, all pipelines need to be on the same horizontal line or the height of pipeline 5 needs to be adjusted. For example, the fire pipe and water and electricity pipe are on the same plane, but the cable tray is higher. In this case, the height of pipeline 5 needs to be adjusted, and the second fixing member 4 is installed on the nut 7.

[0039] S6. According to the width of the pipeline 5, the third connecting piece 13 and the fourth connecting piece 14 are connected and fixed to the pipeline 5. Then the second bolt 12 and the nut 7 are connected to prevent the pipeline 5 from moving in the horizontal direction. The connection length between the rotating sleeve 15 and the threaded section 16 is adjusted to prevent the pipeline 5 from moving in the vertical direction. At the same time, the During the installation process, the number of first fixing members 3 and second fixing members 4 is determined according to the specific number of pipelines. On the same horizontal section 2 of the boom, only the first fixing member 3 or the second fixing member 4 can be installed, or the first fixing member 3 and the second fixing member 4 can be connected alternately, etc., depending on the actual construction conditions.

[0040] Example 2 The structure and construction method of the integrated bracket in this embodiment are the same as those in Example 1. On this basis, a plurality of adjustment holes are evenly opened in the vertical direction on the vertical section 1 of the boom to facilitate connection with the horizontal section 2 of the boom and further adjust the height. There is no need to process the vertical section 1 of the boom to the required length according to the construction conditions, which facilitates mass production.

[0041] A locking device is also provided on the horizontal section 2 of the boom. The locking device engages with the tooth groove 6 through a bolt 7 to ensure that the locking device is fixed at a designated position on the horizontal section 2 of the boom. The locking device is located between or beside the first fixing member 3 and the second fixing member 4 to provide an additional fixing point when needed. The locking device is connected to the connecting nut 10 or the second bolt 12 of the first fixing member 3 and the second fixing member 4 through other bolts to ensure stability between the lock and the fixing members. The locking device includes a locking body, a movable locking baffle, a spring and an adjustment mechanism. The locking body is fixed to the horizontal section 2 of the boom and aligned with the tooth groove 6 so that it can be fixed by the bolt 7 on the tooth groove 6. The locking baffle is moved to the locking position by spring force or manual operation, and contacts and fixes the pipeline 5. The spring is provided between the locking body and the locking baffle. The adjustment mechanism is an adjusting bolt. The position of the locking baffle is adjusted by rotating the adjusting bolt.

[0042] The working principle of the locking device is as follows: the position of the locking device is adjusted by moving the bolt 7 along the tooth groove 6 to accommodate pipelines 5 in different positions. Locked state: through manual operation or spring force, the locking baffle moves to a position engaged with the locking body to fix the pipeline 5; released state: through manual operation and rotation of the adjusting bolt, the locking baffle is removed from the locking body, allowing the pipeline 5 to be moved or replaced. When the lock position needs to be adjusted, the bolt 7 is removed from the current tooth groove 6 and placed in the tooth groove 6 corresponding to the new position, and then the bolt 7 is tightened to fix the lock. By adding a locking device to the horizontal section 2 of the boom, an additional fixing point can be provided, the stability of the pipeline 5 is enhanced, and the pipeline can be quickly adjusted or replaced without disassembling the entire support system, thereby improving the flexibility and safety of the pipeline support system.

[0043] The integrated pipeline integrated bracket and construction method of the present invention are as follows: the integrated pipeline integrated bracket is installed at the bottom of the ceiling by installing a vertical section of a hanger and a horizontal section of a hanger, and multiple first fixing members and second fixing members are provided on the horizontal section of the hanger. By hoisting the integrated pipeline integrated bracket once, multiple pipelines of different sizes can be fixed at the same time, saving construction costs and improving construction efficiency. At the same time, a sleeve is provided on the second fixing member to achieve the fixation of the pipeline in the horizontal and vertical directions. When a collision occurs during the installation of the pipeline, the position of the first fixing member and the second fixing member can be directly adjusted without removing the bracket, so that rapid displacement can be achieved, and the fixation of the reinstalled pipeline can be achieved, avoiding the problem of repeatedly setting up the bracket and pipeline, saving construction costs, and improving construction flexibility.

[0044] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A comprehensive pipeline integrated support, characterized in that: The invention comprises a boom vertical section (1), a boom horizontal section (2), a first fixing member (3) and a second fixing member (4), wherein the boom vertical section (1) is vertically arranged at two ends of the boom horizontal section (2), and a plurality of the first fixing members (3) and the second fixing members (4) are arranged on the boom horizontal section (2), wherein: The top of the vertical section (1) of the suspension rod is fixedly connected to the bottom of the ceiling plate, a plurality of pipelines (5) are provided on the bottom of the ceiling plate, and the first fixing member (3) and the second fixing member (4) are cooperatively connected to the pipelines; The first fixing member (3) comprises a first width adjustment mechanism, and the first width adjustment mechanism is used to fix pipelines (5) of different widths; The second fixing member (4) comprises a second width adjustment mechanism and a height adjustment mechanism, the second width adjustment mechanism is used to fix pipelines (5) of different widths, and the height adjustment mechanism is used to fix pipelines (5) of different heights; When the pipeline (5) is installed and a collision occurs, the position of the pipeline (5) is directly adjusted, and the adjusted pipeline (5) is re-fixed by adjusting the first width adjustment mechanism, the second width adjustment mechanism, and the height adjustment mechanism, thereby avoiding the need to re-install the fixing bracket after the pipeline (5) moves.

2. The integrated pipeline integrated support according to claim 1, characterized in that: The horizontal section (2) of the suspension rod is provided with tooth grooves (6) and nuts (7), a plurality of nuts (7) are engaged with the tooth grooves (6), and the nuts (7) are respectively connected to the first width adjustment mechanism and the second width adjustment mechanism.

3. The integrated pipeline support according to claim 2 is characterized in that: The first width adjustment mechanism comprises a first connecting member (8), a second connecting member (9), a connecting nut (10) and a first bolt (11); the first connecting member (8) and the second connecting member (9) are L-shaped tubes; an opening at one end of the first connecting member (8) is sleeved with an opening at the second connecting member (9); the other end of the first connecting member (8) is connected to the first bolt (11) via a connecting nut (10); the other end of the second connecting member (8) is connected to the first bolt (11) via a connecting nut (10); and the first bolt (11) is connected to the nut (7).

4. The integrated pipeline integrated support according to claim 2, characterized in that: The diameter of the first connecting member (8) is greater than the diameter of the second connecting member (9), and the wall thickness of the first connecting member (8) and the second connecting member (9) is 1 mm.

5. The integrated pipeline integrated support according to claim 4 is characterized in that: The diameter of the first connecting piece (8) is 1 cm, and the diameter of the second connecting piece (9) is 0.8 cm.

6. The integrated pipeline integrated support according to claim 2, characterized in that: The second width adjustment mechanism comprises a third connecting member (13), a fourth connecting member (14) and a second bolt (12); the third connecting member (13) and the fourth connecting member (14) are both "├"-shaped rods; the side opening end of the third connecting member (13) is relatively sleeved with the side opening end of the fourth connecting member (14); and the bottoms of the third connecting member (13) and the fourth connecting member (14) are connected to the nut (7) via the second bolt (12).

7. The integrated pipeline integrated support according to claim 6, characterized in that: The height adjustment mechanism comprises a sleeve (15), a threaded section (16) is provided at the bottom of the third connecting member (13) and the fourth connecting member (14), the sleeve (15) is connected to the threaded section (16), and the height of the third connecting member (13) and the fourth connecting member (14) is adjusted by rotating the sleeve (15) and the length of the connection with the threaded section (16).

8. The integrated pipeline integrated support according to any one of claims 6 or 7, characterized in that: The diameter of the third connecting piece (13) is greater than the diameter of the fourth connecting piece (14), and the wall thickness of the third connecting piece (13) and the fourth connecting piece (14) is 1 mm.

9. The integrated pipeline integrated support according to any one of claims 1 to 8, characterized in that: The first connecting member (8), the second connecting member (9), the third connecting member (13) and the fourth connecting member (14) are made of lightweight and high-strength materials, including aluminum alloy, carbon fiber composite material, high-strength steel and magnesium alloy.

10. A method for constructing an integrated pipeline integrated support, implemented by using an integrated pipeline integrated support as claimed in any one of claims 1 to 9, characterized in that: The specific steps include: S1, drilling holes at the bottom of the ceiling plate to install the vertical section of the suspension rod (1), and installing the horizontal section of the suspension rod (2) at the bottom of the vertical section of the suspension rod (1); S2. Laying pipelines (5) according to actual needs, and installing a corresponding number of nuts (7) on the tooth grooves (6) of the horizontal section (2) of the boom according to the number of pipelines (5); S3. When there is no requirement for the height of the pipeline (5) during construction and the pipelines (5) need to be on the same horizontal line, install the first fixing member (3) on the nut (7); S4. According to the width of the pipeline (5), the first connecting member (8) and the second connecting member (9) are sleeved and fixed to the pipeline (5), and then the first bolt (11) and the nut (7) are connected to prevent the pipeline (5) from moving in the horizontal direction; S5. When there is a requirement for the height of the pipeline (5) during construction, and all pipelines need to be on the same horizontal line or the height of the pipeline (5) needs to be adjusted, install the second fixing member (4) on the nut (7); S6. According to the width of the pipeline (5), the third connecting member (13) and the fourth connecting member (14) are sleeved and fixed to the pipeline (5), and then the second bolt (12) and the nut (7) are connected to prevent the pipeline (5) from moving in the horizontal direction. The connection length between the rotating sleeve (15) and the threaded section (16) is adjusted to prevent the pipeline (5) from moving in the vertical direction.

Citation Information

Patent Citations

  • Modular comprehensive pipeline support

    CN109099210A

  • Electromechanical comprehensive support hanger and installation method thereof

    CN111271514A

  • Electromechanical integrated pipeline mounting structure

    CN117200107A

  • Electromechanical pipeline mounting hanging bracket convenient to adjust

    CN210106760U

  • Telescopic support hanger

    CN215635430U