Method for regulating and controlling productivity of gas storage of oil and gas reservoir and related equipment

By monitoring and cutting off the channels between the oil and gas reservoir and pipeline network in real time, and using preset gas production solutions to continuously produce gas in the gas storage, the problem of gas storage stopping gas production in advance due to insufficient pressure is solved, and a higher level is achieved The gas output and gas injection volume improve the utilization rate and economic benefits of the gas storage.

CN119468020AActive Publication Date: 2025-02-18PIPECHINA SOUTH CHINA CO +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411394216.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-08
Publication Date
2025-02-18
Estimated Expiration
2044-10-08

AI Technical Summary

Technical Problem

The lower limit pressure of some oil and gas reservoirs is lower than the operating pressure of the pipeline network, resulting in the gas storage that needs to stop gas production in advance and cannot exert maximum production capacity.

Method used

By monitoring the outbound pressure of the injector and production station in real time, when it is lower than the preset pipeline pressure, the gas storage and pipeline channels are cut off, and the gas storage is continuously extracted through the preset gas production plan until the preset lower limit is reached pressure.

Benefits of technology

Effectively increase the gas output and gas injection volume of the gas storage, give full play to the peak regulating effect of the gas storage, improve utilization, reduce the pipe storage pressure during the peak period of gas use, and increase the storage and transfer fee income.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119468020A_ABST
    Figure CN119468020A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of oil and gas reservoir type gas storages, and discloses an oil and gas reservoir gas storage capacity regulation and control method and related equipment. The method comprises the following steps: monitoring the outbound pressure of an injection-production station of the oil and gas reservoir in real time; when the outbound pressure of the injection and production station is lower than the preset pipe network pressure, a channel between the oil and gas reservoir and the pipe network is cut off; and continuous gas production is conducted on the gas storage of the oil and gas reservoir through the preset gas production scheme, and gas production is stopped until the preset lower limit pressure is reached. The method can effectively increase the produced gas amount of the gas storage, increase the gas injection amount, give full play to the peak regulation effect of the gas storage, and improve the utilization rate of the gas storage; the pipe storage pressure in the gas consumption peak period is reduced, and the pipe network gas transmission pressure is relieved; storage and transfer earnings of the gas storage are increased, and the return time of the gas storage is shortened; the operation time of the gas storage branch line is reduced, and the maintenance content of the trunk line can be properly reduced according to actual needs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of oil and gas reservoir type gas storage, and in particular to a production capacity control method of an oil and gas reservoir type gas storage and related equipment. Background Art

[0002] Depleted oil and gas reservoir gas storage is built using depleted gas or oil layers. It is currently the most commonly used and most economical form of underground gas storage due to its large gas storage capacity, fast transformation speed, reliable operation, and wide peak-shaving range. It accounts for more than 75% of the total number of underground gas storages, and plays an increasingly important role in my country's natural gas supply and peak-shaving.

[0003] To ensure the safe, efficient and stable operation of gas storages, they should operate within a set pressure range. Most of my country's gas storages are buried at a large depth and have a high operating pressure range. The operating pressure of the national pipeline network is about 6-11MPa. Most of my country's oil and gas reservoirs are buried at a large depth and have a lower limit pressure higher than the operating pressure of the national pipeline network. Therefore, the pipeline system can receive gas sources from various gas storages at any time to maximize the production capacity of the gas storages.

[0004] However, there are still some gas storage reservoirs whose lower limit pressure is lower than the pipeline network operating pressure. When the formation pressure of the gas storage reservoir drops to the pipeline network pressure, the gas production process needs to be stopped in advance due to the pressure. The working gas of the gas storage reservoir cannot be fully produced, and the maximum production capacity of the gas storage reservoir cannot be utilized. Summary of the invention

[0005] The technical problem to be solved by the present invention is to provide a method for regulating the production capacity of an oil and gas reservoir and related equipment in view of the problems existing in the prior art.

[0006] In a first aspect, the present invention provides a method for regulating the production capacity of an oil and gas reservoir gas storage, comprising:

[0007] Real-time monitoring of the outlet pressure of injection and production stations in oil and gas reservoirs and gas storage facilities;

[0008] When the outlet pressure of the injection and production station is lower than the preset pipeline network pressure, the passage between the oil and gas reservoir and the pipeline network is cut off;

[0009] The preset gas production plan is used to continuously produce gas from the oil and gas reservoir storage until the preset lower limit pressure is reached and gas production is stopped.

[0010] The beneficial effects of the present invention are as follows: when the present invention monitors that the outlet pressure of the injection and production station is lower than the preset pipeline network pressure, the passage between the oil and gas reservoir gas storage and the pipeline network is cut off, and the oil and gas reservoir gas storage is continuously produced through a preset gas production plan, which can effectively increase the gas production of the gas storage, and at the same time increase the gas injection volume, give full play to the peak-shaving role of the gas storage, and improve the utilization rate of the gas storage; reduce the pipeline storage pressure during the peak gas consumption period, and ease the gas transmission pressure of the pipeline network; increase the storage and transfer fee income of the gas storage, and shorten the payback time of the gas storage; reduce the operating time of the gas storage branch line, and appropriately reduce the maintenance content of the trunk line according to actual needs.

[0011] Based on the above technical solution, the present invention can also be improved as follows.

[0012] Furthermore, continuous gas production is carried out from the oil and gas reservoir and gas storage through a preset gas production plan, including: transporting the stored gas in the oil and gas reservoir and gas storage to distribution users in the distribution network through a pre-established distribution network.

[0013] The beneficial effect of adopting the above further scheme is that in order to increase the production capacity of the gas storage, it is necessary to transform the gas storage injection and production station in combination with the industrial gas use and residential gas use in the area where the gas storage is located. After the pressure of the gas storage drops to the pipeline network pressure, the passage between the gas storage and the pipeline network is cut off, and the residual pressure of the gas storage is used to continue to produce gas by increasing downstream users, and the reservoir pressure of the gas storage is continuously produced to the lower limit pressure. While giving full play to the production capacity of the gas storage, the utilization efficiency of the gas storage is improved, and as much gas as possible is produced to improve the economic benefits of the gas storage.

[0014] Furthermore, the distribution pressure of the distribution network is lower than the preset pipeline pressure.

[0015] The beneficial effect of adopting the above further scheme is that the distribution pressure of the distribution network is lower than the preset pipeline pressure. After the gas storage pressure drops to the pipeline pressure, the reservoir pressure of the gas storage can be continuously exploited to the lower limit pressure, thereby giving full play to the production capacity of the gas storage and improving the utilization efficiency of the gas storage. As much gas as possible can be extracted to improve the economic benefits of the gas storage.

[0016] Furthermore, the oil and gas reservoir gas storage reservoir is continuously produced with a preset gas production plan, including: configuring a hydraulic storage tank for the oil and gas reservoir gas storage reservoir, pressurizing and cooling the gas produced from the oil and gas reservoir gas storage reservoir, and compressing it into the hydraulic storage tank, so as to facilitate its transportation to scattered users by tank trucks.

[0017] The beneficial effect of adopting the above further scheme is that after the pressure of the gas storage reservoir drops to the pipeline pressure, the passage between the gas storage reservoir and the pipeline network is cut off, and the residual pressure of the gas storage reservoir is used to continue to produce gas by means of liquefied compressed natural gas, and the reservoir pressure of the gas storage reservoir is continuously produced to the lower limit pressure, so as to give full play to the production capacity of the gas storage reservoir, improve the utilization efficiency of the gas storage reservoir, and produce as much gas as possible to improve the economic benefits of the gas storage reservoir.

[0018] In a second aspect, the present invention provides a gas storage capacity control system for oil and gas reservoirs, comprising:

[0019] The pressure monitoring module is used to monitor the outlet pressure of the injection and production station of the oil and gas reservoir in real time;

[0020] The main control module is used to cut off the passage between the oil and gas reservoir and the pipeline network when the outlet pressure of the injection and production station is lower than the preset pipeline network pressure;

[0021] It is also used to continuously produce gas from an oil and gas reservoir through a preset gas production plan until the gas production is stopped when a preset lower limit pressure is reached.

[0022] The beneficial effects of the present invention are as follows: when the present invention monitors that the outlet pressure of the injection and production station is lower than the preset pipeline network pressure, the passage between the oil and gas reservoir gas storage and the pipeline network is cut off, and the oil and gas reservoir gas storage is continuously produced through a preset gas production plan, which can effectively increase the gas production of the gas storage, and at the same time increase the gas injection volume, give full play to the peak-shaving role of the gas storage, and improve the utilization rate of the gas storage; reduce the pipeline storage pressure during the peak gas consumption period, and ease the gas transmission pressure of the pipeline network; increase the storage and transfer fee income of the gas storage, and shorten the payback time of the gas storage; reduce the operating time of the gas storage branch line, and appropriately reduce the maintenance content of the trunk line according to actual needs.

[0023] Based on the above technical solution, the present invention can also be improved as follows.

[0024] Furthermore, the oil and gas reservoir gas storage reservoir capacity control system also includes a pre-established distribution network; the pre-established distribution network is used to transport the stored gas in the oil and gas reservoir gas storage reservoir to the distribution users in the distribution network.

[0025] The beneficial effect of adopting the above further scheme is that in order to increase the production capacity of the gas storage, it is necessary to transform the gas storage injection and production station in combination with the industrial gas use and residential gas use in the area where the gas storage is located. After the pressure of the gas storage drops to the pipeline network pressure, the passage between the gas storage and the pipeline network is cut off, and the residual pressure of the gas storage is used to continue to produce gas by increasing downstream users, and the reservoir pressure of the gas storage is continuously produced to the lower limit pressure. While giving full play to the production capacity of the gas storage, the utilization efficiency of the gas storage is improved, and as much gas as possible is produced to improve the economic benefits of the gas storage.

[0026] Furthermore, the distribution pressure of the distribution network is lower than the preset pipeline pressure.

[0027] The beneficial effect of adopting the above further scheme is that the distribution pressure of the distribution network is lower than the preset pipeline pressure. After the gas storage pressure drops to the pipeline pressure, the reservoir pressure of the gas storage can be continuously exploited to the lower limit pressure, thereby giving full play to the production capacity of the gas storage and improving the utilization efficiency of the gas storage. As much gas as possible can be extracted to improve the economic benefits of the gas storage.

[0028] Furthermore, the oil and gas reservoir gas storage reservoir capacity control system also includes a hydraulic storage tank configured for the oil and gas reservoir gas storage reservoir; after the gas stored in the oil and gas reservoir gas storage reservoir is extracted, it is pressurized and cooled, and compressed into the hydraulic storage tank, so that it is convenient to be transported to scattered users by tank trucks.

[0029] The beneficial effect of adopting the above further scheme is that after the pressure of the gas storage reservoir drops to the pipeline pressure, the passage between the gas storage reservoir and the pipeline network is cut off, and the residual pressure of the gas storage reservoir is used to continue to produce gas by means of liquefied compressed natural gas, and the reservoir pressure of the gas storage reservoir is continuously produced to the lower limit pressure, so as to give full play to the production capacity of the gas storage reservoir, improve the utilization efficiency of the gas storage reservoir, and produce as much gas as possible to improve the economic benefits of the gas storage reservoir.

[0030] In a third aspect, the present invention further provides a computer-readable storage medium, comprising instructions, which, when executed on a computer, enable the computer to execute a method for controlling the production capacity of an oil and gas reservoir provided in any of the above schemes.

[0031] In a fourth aspect, the present invention further provides an electronic device, comprising: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the method for controlling the production capacity of an oil and gas reservoir provided in any of the above schemes is implemented.

[0032] In a fifth aspect, the present invention further provides a computer program product, the computer program product comprising computer instructions, the computer instructions being stored in a computer-readable storage medium. A processor of a computer device reads the computer instructions from the computer-readable storage medium, and the processor executes the computer instructions, so that the computer device executes the oil and gas reservoir gas storage capacity control method provided by the above solution.

[0033] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description or learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 A flow chart of a method for controlling the production capacity of a gas storage reservoir in an oil and gas reservoir according to an exemplary embodiment of the present application;

[0035] Figure 2 A block diagram of a gas storage capacity control system for an oil and gas reservoir according to an exemplary embodiment of the present application;

[0036] Figure 3 A schematic diagram of a gas storage gas production process provided by an exemplary embodiment of the present invention. DETAILED DESCRIPTION

[0037] The following describes the embodiments of the present disclosure through specific examples, and those skilled in the art can easily understand other advantages and effects of the present disclosure from the contents disclosed in this specification. Obviously, the described embodiments are only part of the embodiments of the present disclosure, rather than all of the embodiments. The present disclosure can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present disclosure. It should be noted that the following embodiments and features in the embodiments can be combined with each other without conflict. Based on the embodiments in the present disclosure, all other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of the present disclosure.

[0038] It should be noted that various aspects of the embodiments within the scope of the appended claims are described below. It should be apparent that the aspects described herein may be embodied in a wide variety of forms, and any specific structure and / or function described herein is merely illustrative. Based on the present disclosure, it should be understood by those skilled in the art that an aspect described herein may be implemented independently of any other aspect, and two or more of these aspects may be combined in various ways. For example, any number of aspects described herein may be used to implement the device and / or practice the method. In addition, other structures and / or functionalities other than one or more of the aspects described herein may be used to implement this device and / or practice this method.

[0039] The solution provided in the embodiment of the present invention can be executed by any electronic device, for example, a terminal device, or jointly executed by a terminal device and a server. The server can be an independent server, or a cloud server that provides basic cloud computing services such as cloud services, cloud databases, cloud computing, cloud functions, cloud storage, network services, cloud communications, middleware services, domain name services, security services, content delivery networks (CDNs), and big data and artificial intelligence platforms, etc., and is not limited here.

[0040] Figure 1 The flowchart of the method for controlling the production capacity of an oil and gas reservoir storage facility is shown as an exemplary embodiment of the present application. Figure 1 As shown, in an exemplary embodiment, the oil and gas reservoir gas storage capacity control may include steps S1 to S3, which are described in detail as follows:

[0041] S1, real-time monitoring of the outlet pressure of the injection and production station of the oil and gas reservoir;

[0042] S2, when the outlet pressure of the injection and production station is lower than the preset pipeline network pressure, the passage between the oil and gas reservoir and the pipeline network is cut off;

[0043] S3, continuously extracting gas from the oil and gas reservoir through a preset gas extraction plan until the preset lower limit pressure is reached and gas extraction is stopped.

[0044] In the embodiment of the present invention, by real-time monitoring of the outlet pressure of the injection and production station of the oil and gas reservoir gas storage, when it is monitored that the outlet pressure of the injection and production station is lower than the preset pipeline network pressure, the channel between the oil and gas reservoir gas storage and the pipeline network is cut off, and the oil and gas reservoir gas storage is continuously produced through a preset gas production plan, which can effectively increase the gas production of the gas storage, and at the same time increase the gas injection volume, give full play to the peak regulation role of the gas storage, and improve the utilization rate of the gas storage; reduce the pipeline storage pressure during the peak gas consumption period, and ease the gas transmission pressure of the pipeline network; increase the storage and transfer fee income of the gas storage, and shorten the payback time of the gas storage; reduce the operating time of the gas storage branch line, and appropriately reduce the main line maintenance content according to actual needs.

[0045] Optionally, in an exemplary embodiment, continuous gas production is performed on an oil and gas reservoir storage reservoir through a preset gas production plan, including: transporting the stored gas in the oil and gas reservoir storage reservoir to distribution users in the distribution network through a pre-established distribution network.

[0046] In order to increase the production capacity of gas storage, it is necessary to transform the injection and production station of gas storage in combination with the industrial and residential gas consumption in the area where the gas storage is located. Specifically, in areas suitable for the construction of oil and gas reservoir gas storage, the gas demand of local industrial and residential users should be fully investigated, and a distribution network should be established during the construction of the gas storage, and distribution users should be configured.

[0047] In general, the pressure of downstream distribution users is about 3-5MPa, which is much lower than the lower limit operating pressure of the gas storage. During the gas production process of the gas storage, when it is monitored that the pressure of the gas storage drops to the pipeline pressure, the channel between the gas storage and the pipeline is cut off, and gas supply to the natural gas pipeline is stopped. Instead, gas is supplied to distribution users, and the residual pressure of the gas storage is used to continue gas production. The reservoir pressure of the gas storage is continuously exploited to the lower limit pressure, so as to give full play to the production capacity of the gas storage and improve the utilization efficiency of the gas storage. As much gas as possible is produced to improve the economic benefits of the gas storage.

[0048] Optionally, the distribution pressure of the distribution network is lower than the preset pipeline pressure. The distribution pressure of the distribution network is lower than the preset pipeline pressure. After the gas storage pressure drops to the pipeline pressure, the reservoir pressure of the gas storage can be continuously exploited to the lower limit pressure, so as to give full play to the production capacity of the gas storage, improve the utilization efficiency of the gas storage, and extract as much gas as possible to improve the economic benefits of the gas storage.

[0049] Optionally, in an exemplary embodiment, gas is continuously extracted from an oil and gas reservoir gas storage reservoir through a preset gas extraction plan, including: configuring a hydraulic storage tank for the oil and gas reservoir gas storage reservoir, pressurizing and cooling the gas extracted from the oil and gas reservoir gas storage reservoir, and compressing it into the hydraulic storage tank, so as to facilitate its transportation to scattered users by tank trucks.

[0050] In the embodiment of the present invention, during the gas production process of the gas storage, when it is monitored that the pressure of the gas storage drops to the pipeline pressure, the passage between the gas storage and the pipeline is cut off, and gas supply to the natural gas pipeline is stopped. Instead, the residual pressure of the gas storage is used to continue gas production by liquefying and compressing natural gas, and the reservoir pressure of the gas storage is continuously produced to the lower limit pressure. While giving full play to the production capacity of the gas storage, the utilization efficiency of the gas storage is improved, and as much gas as possible is produced to improve the economic benefits of the gas storage.

[0051] Figure 2 This is a block diagram of an oil and gas reservoir gas storage capacity control system according to an exemplary embodiment of the present application. Figure 2 As shown, the oil and gas reservoir gas storage capacity control system includes: a pressure monitoring module and a main control module.

[0052] The pressure monitoring module is used to monitor the outlet pressure of the injection and production station of the oil and gas reservoir in real time;

[0053] The main control module is used to cut off the passage between the oil and gas reservoir and the pipeline network when the outlet pressure of the injection and production station is lower than the preset pipeline network pressure; it is also used to continuously produce gas from the oil and gas reservoir through a preset gas production plan until the preset lower limit pressure is reached and gas production is stopped.

[0054] In the embodiment of the present invention, when it is monitored that the outlet pressure of the injection and production station is lower than the preset pipeline pressure, the passage between the oil and gas reservoir gas storage and the pipeline is cut off, and the oil and gas reservoir gas storage is continuously produced through the preset gas production plan. Compared with the traditional gas production method of only supplying gas to the pipeline and stopping production when the pressure is equal to the pipeline pressure, the gas production volume of the implementation scheme of the present invention is significantly increased, and the amount of gas that can be injected in the next stage is also increased, and the annual injection and production gas volume is increased. The reservoir voids near the bottom of the well are fully flushed, the permeability around the well is improved, the skin coefficient is reduced, the bottom of the well pollution is improved, and the gas injection and production capacity of a single well is further improved, which is conducive to the gas storage to reach full capacity and production.

[0055] The embodiments of the present invention can effectively increase the gas output of the gas storage and increase the gas injection volume at the same time, give full play to the peak-shaving effect of the gas storage, and improve the utilization rate of the gas storage; reduce the pipeline storage pressure during the peak gas consumption period and ease the gas transmission pressure of the pipeline network; increase the storage and transfer fee income of the gas storage and shorten the payback time of the gas storage; reduce the operating time of the gas storage branch line, and appropriately reduce the maintenance content of the trunk line according to actual needs.

[0056] Optionally, in an exemplary embodiment, the oil and gas reservoir gas storage facility capacity control system also includes a pre-established distribution network; the pre-established distribution network is used to transport the stored gas in the oil and gas reservoir gas storage facility to distribution users in the distribution network.

[0057] In order to increase the production capacity of the gas storage, it is necessary to transform the gas storage injection and production station in combination with the industrial and residential gas consumption in the area where the gas storage is located. After the pressure of the gas storage drops to the pipeline pressure, the channel between the gas storage and the pipeline is cut off, and the residual pressure of the gas storage is used to continue gas production by increasing downstream users. The reservoir pressure of the gas storage is continuously exploited to the lower limit pressure, so as to give full play to the production capacity of the gas storage, improve the utilization efficiency of the gas storage, and extract as much gas as possible to improve the economic benefits of the gas storage.

[0058] Optionally, the distribution pressure of the distribution network is lower than the preset pipeline pressure. The distribution pressure of the distribution network is lower than the preset pipeline pressure. After the gas storage pressure drops to the pipeline pressure, the reservoir pressure of the gas storage can be continuously exploited to the lower limit pressure, so as to give full play to the production capacity of the gas storage, improve the utilization efficiency of the gas storage, and extract as much gas as possible to improve the economic benefits of the gas storage.

[0059] Optionally, in an exemplary embodiment, the oil and gas reservoir gas storage reservoir capacity control system also includes a hydraulic storage tank configured for the oil and gas reservoir gas storage reservoir; the gas stored in the oil and gas reservoir gas storage reservoir is pressurized and cooled after being produced, and compressed into the hydraulic storage tank, so as to be transported to scattered users by tank trucks.

[0060] In the embodiment of the present invention, after the pressure of the gas storage reservoir drops to the pipeline pressure, the passage between the gas storage reservoir and the pipeline network is cut off, and the residual pressure of the gas storage reservoir is used to continue gas extraction by adding a liquefied natural gas / compressed natural gas device, and the reservoir pressure of the gas storage reservoir is continuously extracted to the lower limit pressure, so as to give full play to the production capacity of the gas storage reservoir, improve the utilization efficiency of the gas storage reservoir, extract as much gas as possible, and improve the economic benefits of the gas storage reservoir.

[0061] An embodiment of the present invention further provides a computer-readable storage medium, comprising instructions, which, when executed on a computer, enable the computer to execute the method for controlling the production capacity of an oil and gas reservoir provided in any of the above embodiments.

[0062] An embodiment of the present invention also provides an electronic device, comprising: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the method for controlling the production capacity of an oil and gas reservoir provided in any of the above embodiments is implemented.

[0063] The embodiment of the present invention further provides a computer program product, which includes computer instructions, and the computer instructions are stored in a computer-readable storage medium. The processor of the computer device reads the computer instructions from the computer-readable storage medium, and the processor executes the computer instructions, so that the computer device executes the oil and gas reservoir gas storage capacity control method provided in the above various optional embodiments.

[0064] The technical solution of the present invention is further described in detail below in conjunction with a specific example. Figure 3A schematic diagram of a gas storage gas production process provided by an exemplary embodiment of the present invention.

[0065] like Figure 3 As shown, the underground gas storage is connected to the gas storage well field, the gas storage well field is connected to the station, the station is connected to the long-distance pipeline, and the pipeline connecting the station and the long-distance pipeline is provided with a valve connected to the trunk line. The station is also directly connected to the distribution users (which may include multiple distribution users, Figure 3 Only user 1 is shown in the figure. The station is also connected to a liquefied gas tank. When the outlet pressure of the injection and production station is lower than the preset pipeline pressure, the gas in the gas storage reservoir is produced, pressurized and cooled, and compressed into a hydraulic storage tank (i.e., the liquefied gas tank in the figure) to facilitate transportation to scattered users (such as Figure 3 User 2).

[0066] Assuming that the design operating pressure of the gas storage in the embodiment of the present invention is 5-12MPa, during the winter supply guarantee period, the minimum pressure of the pipeline network connected to the gas storage is about 6MPa. When the wellhead pressure reaches 7MPa, affected by the operating pressure of the pipeline network, the outlet pressure of the produced gas is lower than the pipeline network pressure, and the produced gas cannot be transported to the pipeline network. The gas production period ends prematurely, the reservoir inventory is not effectively utilized, and the production capacity of the gas storage is not effectively utilized.

[0067] Based on this operating condition, two distribution users are designed for the gas storage, with distribution pressures of 3.8MPa and 4.2MPa respectively, and one compressed natural gas user. When the outlet pressure reaches the same level as the pipeline pressure, the channel between the gas storage and the gas transmission trunk line is cut off, and the gas storage directly supplies downstream users.

[0068] During the 2022-2023 winter supply guarantee period, the gas storage reservoir used the oil and gas reservoir gas storage capacity control method provided by the embodiment of the present invention from February 12 to March 10 to produce 19.02 million cubic meters of gas. During the 2023-2024 winter supply guarantee period, the gas storage reservoir used the oil and gas reservoir gas storage capacity control method provided by the embodiment of the present invention from February 5 to February 26 to produce a total of 8.3 million cubic meters of gas.

[0069] According to the above examples, it can be seen that the embodiments of the present invention can effectively increase the gas production of the gas storage by configuring the oil and gas reservoir gas storage with distribution users or hydraulic storage tanks, while increasing the gas injection volume and improving the utilization rate of the gas storage. In the later stage of gas production, the pipeline network is replaced to transmit gas to downstream users, reducing the pipeline storage pressure during the peak period of gas consumption and alleviating the gas transmission pressure of the pipeline network. Give full play to the peak-shaving role of the gas storage and effectively increase the working gas volume. Shorten the pipeline transmission distance of the consignor, and directly supply the downstream users from the gas storage to reduce the pipeline transmission fee. Increase the storage and transfer fee income of the gas storage and shorten the payback time of the gas storage. Reduce the operating time of the gas storage branch line, and appropriately reduce the maintenance content of the trunk line according to actual needs.

[0070] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the above-described devices and units can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.

[0071] In the several embodiments provided in this application, it should be understood that the disclosed devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic, for example, the division of units is only a logical function division, and there may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed.

[0072] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the embodiments of the present invention.

[0073] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0074] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention is essentially or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including a number of instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the methods of each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk and other media that can store program codes.

[0075] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for regulating the production capacity of an oil and gas reservoir, characterized in that: include: Real-time monitoring of the outlet pressure of injection and production stations in oil and gas reservoirs and gas storage facilities; When the outlet pressure of the injection and production station is lower than the preset pipeline network pressure, the passage between the oil and gas reservoir and the pipeline network is cut off; The gas storage reservoir of the oil and gas reservoir is continuously produced with gas through a preset gas production plan until the gas production is stopped when the preset lower limit pressure is reached.

2. The method according to claim 1, characterized in that The method of continuously extracting gas from the oil and gas reservoir gas storage by using a preset gas extraction scheme includes: The gas stored in the oil and gas reservoir gas storage is transported to the distribution users in the distribution network through the pre-established distribution network.

3. The method according to claim 2, characterized in that The distribution pressure of the distribution network is lower than the preset pipeline pressure.

4. The method according to any one of claims 1 to 3, characterized in that: The method of continuously extracting gas from the oil and gas reservoir gas storage by using a preset gas extraction scheme includes: A hydraulic storage tank is configured for the oil and gas reservoir gas storage reservoir, and the gas stored in the oil and gas reservoir gas storage reservoir is pressurized and cooled after being produced, and compressed into the hydraulic storage tank, so that it is convenient to be transported to scattered users by tank trucks.

5. A gas storage capacity control system for oil and gas reservoirs, characterized in that: include: The pressure monitoring module is used to monitor the outlet pressure of the injection and production station of the oil and gas reservoir in real time; A main control module, used to cut off the passage between the oil and gas reservoir and the pipeline network when the outlet pressure of the injection and production station is lower than the preset pipeline network pressure; It is also used to continuously produce gas from the oil and gas reservoir through a preset gas production plan until the gas production is stopped when a preset lower limit pressure is reached.

6. The system according to claim 5, characterized in that It also includes pre-established distribution networks; The pre-established distribution network is used to transport the stored gas in the oil and gas reservoir gas storage to the distribution users in the distribution network.

7. The system according to claim 6, characterized in that The distribution pressure of the distribution network is lower than the preset pipeline pressure.

8. The system according to any one of claims 5 to 7, characterized in that: Also included is a hydraulic storage tank configured for the oil and gas reservoir gas storage; The gas stored in the oil and gas reservoir is pressurized and cooled after being extracted, and compressed into the hydraulic storage tank, so as to be transported to scattered users by tank trucks.

9. A computer-readable storage medium comprising instructions, characterized in that: When the instructions are executed on a computer, the computer is enabled to execute the method for controlling the production capacity of an oil and gas reservoir as claimed in any one of claims 1 to 7.

10. An electronic device, comprising: A memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the method for controlling the production capacity of an oil and gas reservoir storage facility as claimed in any one of claims 1 to 7 is implemented.

Citation Information

Patent Citations

  • Design method for improving recovery efficiency through oil reservoir gas injection and building gas storage

    CN116025313A

  • Gas storage gas production pressurization output system and method

    CN118088934A

  • Method and system of mode control of the underground gas storage exploitation

    RU2682819C1

  • Method for filling oil-gas well of fractured oil-gas reservoir with isolation particles to reduce water and increase oil production

    US20220098955A1