Integrated intelligent test platform for hydrostatic pressure test of pump body

By designing an integrated intelligent test platform for pump body hydrostatic pressure testing, the existing equipment covers a large area, consumes a lot of time, has a large number of personnel and uncertain test results, and has realized automated and intelligent testing, improving testing efficiency and accuracy.

CN119664651AActive Publication Date: 2025-03-21KAIQUAN PUMP INDAL MFG ZHENJIANG PROV

Patent Information

Application Number
CN202411886667.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-20
Publication Date
2025-03-21
Estimated Expiration
2044-12-20

AI Technical Summary

Technical Problem

The existing pump body hydrostatic pressure testing equipment covers a large area, has a large number of personnel allocations, is time-consuming and inefficient, and there are uncertain factors in the test results.

Method used

An integrated intelligent test platform was designed, including a constant temperature and humidity pump room, a test area and a pump body part feeding device. The platform adopts automated and intelligent means to identify parts through cameras, automatically match hydraulic flange tooling, automatic exhaust valves and purge devices to achieve automated operations to ensure the accuracy and safety of the test.

Benefits of technology

The automation and intelligence of pump body hydrostatic pressure testing is realized, reducing the time and human resource requirements for manual operation, improving the efficiency and accuracy of the test, and reducing the uncertainty of the test results.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119664651A_ABST
    Figure CN119664651A_ABST
Patent Text Reader

Abstract

The invention discloses an integrated intelligent test platform for hydrostatic pressure testing of a pump body, and relates to the technical field of pump body testing, the integrated intelligent test platform comprises a constant-temperature and constant-humidity pump room, the constant-temperature and constant-humidity pump room is provided with a test area, and the test area comprises a camera, a hydraulic flange tool, an automatic exhaust valve, a purging device and a hydraulic lifting spigot flange tool. The camera is arranged on the side of the hydraulic flange tool, the automatic exhaust valve is connected to the outer side of the hydraulic flange tool, the hydraulic lifting spigot flange tool is arranged on the side of the blowing device, and the hydraulic flange tool is arranged above the hydraulic lifting spigot flange tool. The alarm device is communicated with the control cabinet in the test process, test check is stopped under abnormal conditions, and the test is continued after faults are removed. Besides full-automatic intelligent test, a starting scram button is additionally arranged for starting, and a hydraulic flange tool control element meets the requirement of manual operation test. And the reliability of the test center is ensured through system self-inspection and periodic inspection.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pump body testing, and in particular to an integrated intelligent testing platform for hydrostatic pressure testing of pump bodies. Background Art

[0002] Pump bodies are widely used in many industrial fields such as water conservancy, chemical industry, and petroleum, and the reliability of their quality and performance is crucial. Hydrostatic pressure testing is an important means to detect key performance indicators such as pump body sealing and pressure resistance. Generally, pressure-bearing parts, including their fasteners, should be subjected to hydrostatic tests with a test pressure that is a certain multiple of the basic design pressure. The main purpose of this test center is to perform hydrostatic pressure testing on pump bodies in pressure-bearing parts, including pressure testing and test report output.

[0003] The hydrostatic pressure test centers of most existing manufacturers are still arranged in a regional open layout, that is, an area is divided in the workshop, and the booster pump, pressure gauge, control cabinet, pump parts, etc. are arranged scattered. The hydrostatic pressure test of a part often requires a forklift, two workers, a qualified tester, and a lot of time. Such a configuration will result in a large footprint, multiple personnel allocation, time-consuming and inefficient, and uncertain test results. To solve the above problems, an integrated intelligent test platform for pump hydrostatic pressure testing is proposed. Summary of the invention

[0004] The purpose of the present invention is to provide an integrated intelligent test platform for hydrostatic testing of pump bodies, so as to solve the problem that the prior art proposed in the above background technology requires a forklift, two workers, a qualified tester, and a lot of time when operating. Such a configuration will result in a large footprint, multiple personnel allocation, time-consuming and inefficient, and uncertain test results.

[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: an integrated intelligent test platform for hydrostatic test of a pump body, comprising a constant temperature and humidity pump room, a test area is arranged on the constant temperature and humidity pump room, the test area comprises a camera, a hydraulic flange tooling, an automatic exhaust valve, a purge device and a hydraulic lifting stop flange tooling, the camera is arranged on the side of the hydraulic flange tooling, the automatic exhaust valve is connected to the outside of the hydraulic flange tooling, the hydraulic lifting stop flange tooling is arranged on the side of the purge device, and the hydraulic flange tooling is arranged above the hydraulic lifting stop flange tooling; A pump body parts feeding device is arranged on the back of the constant temperature and humidity pump room, and the pump body parts feeding device includes a conveying rack, a conveyor belt is arranged on the inner side of the conveying rack, a conveying motor is arranged on one side of the conveying rack, a sliding block is arranged at the bottom of the conveying rack, a sliding rail is arranged on the outer side of the sliding block, a mounting rack is arranged at the bottom of the sliding rail, two spray boxes are arranged on the mounting rack, a plurality of spray nozzles are evenly distributed on the top of the spray box, a plurality of cleaning brushes are evenly distributed on both sides of the spray box, one end of the spray box is fixedly connected with a conveying pipe, one end of the conveying pipe is fixedly connected with a conveying pump, a connecting hose is fixedly connected to the side of the conveying pump, one end of the connecting hose is fixedly connected with a water storage box, and the spray nozzles are distributed below the conveyor belt.

[0006] Preferably, a threaded rod is movably installed on the inner side of the sliding rail, a translation motor is provided at one end of the sliding rail, an output end of the translation motor is connected to one end of the threaded rod, and the threaded rod is threadedly connected to the inner side of the sliding block.

[0007] Preferably, a filter screen is provided inside the water storage box, a bracket plate is symmetrically fixedly mounted on the inner wall of the water storage box, the filter screen is mounted on the bracket plate, and a drain pipe is provided at the bottom of the water storage box.

[0008] Preferably, a sliding groove is symmetrically fixedly installed at the bottom of the mounting frame, and connecting bars are provided on both sides of the water storage box, and the connecting bars are movably connected to the inner side of the sliding groove.

[0009] Preferably, the constant temperature and humidity pump room comprises a water inlet and a pump room, the water inlet is arranged at one end of the constant temperature and humidity pump room, and the pump room is arranged at the front of the constant temperature and humidity pump room.

[0010] Preferably, a control cabinet is arranged on the front of the constant temperature and humidity pump room, and the control cabinet includes a start and emergency stop button and an instrument panel, and the instrument panel is arranged above the start and emergency stop button.

[0011] Preferably, the control cabinet further includes a display and a printing window, and the printing window is arranged below the display.

[0012] Preferably, a hydraulic flange tooling control element is provided on the front of the test area, and an automatic liquid collection reflux end is provided at one end of the constant temperature and humidity pump room.

[0013] Preferably, an alarm device is fixedly installed on the top of the constant temperature and humidity pump room.

[0014] Preferably, the test area further includes a first safety protection door and a second safety protection door, and the first safety protection door and the second safety protection door are respectively arranged on the sides of the test area.

[0015] Compared with the prior art, the present invention has the following beneficial effects: 1. In the present invention, after the upper process of the horizontal / vertical pump body is completed, the pump body parts flow into the test area from the feeding device, the camera takes a snapshot, identifies the part model, and transmits the signal to the control cabinet. The control cabinet retrieves the test requirements and controls the corresponding size hydraulic flange tooling and hydraulic lifting stop flange tooling. After the hydraulic tooling is clamped, the control cabinet controls the first safety protection door and the second safety protection door to close, the pump room starts, and water delivery and pressurization begin. The automatic exhaust valve is exhausted and closed, and the pressure transmitter transmits the pressure to the control cabinet. The instrument panel and the display display in real time, and the pressure is maintained according to the test requirements. After the test is completed, the control cabinet turns off the booster pump, issues a test report and uploads it to the management platform. Unqualified parts are specially marked, and unqualified test records are issued. Qualified parts generate QR codes for circulation. The hydraulic flange tooling and hydraulic lifting stop flange tooling return to their original positions, and the test liquid flows through the water source of the automatic liquid collection reflux end, sedimentation filtration and recycling. After the parts leave the test area, the purge device removes water stains on the test bench and waits for the next part to flow in. During the test, the alarm device and the control cabinet are connected. In case of abnormal conditions, the test is stopped for inspection and the test is continued after the fault is eliminated. In addition to the fully automatic intelligent test, there is also a start-up emergency stop button, and the hydraulic flange tooling control element can meet the needs of manual operation test. The reliability of the test center is guaranteed through system self-test and periodic inspection.

[0016] 2. In the present invention, the sliding connection between the sliding block and the sliding rail is convenient to provide a support for the conveying frame, and the installation frame support is convenient to provide installation for the spray box, and a plurality of spray nozzles and cleaning brushes are respectively distributed on the top and side of the spray box, and a delivery pipe is connected to one end of the spray box, which is connected to a delivery pump by the delivery pipe and connected to the inside of the water storage box by a connecting hose, so that the delivery pump can be used to extract the water source inside the water storage box, and then transport it to the inside of the spray box through the delivery pipe, and then the cleaning water source is sprayed out at high pressure through the spray nozzle to perform high-pressure flushing on the outer wall of the conveyor belt, which is conducive to providing a high-efficiency cleaning function and effectively ensuring the cleaning effect. At the same time, the cleaning brushes are evenly distributed and fit to the outer wall of the conveyor belt, so as to achieve an effective cleaning effect, and avoid the problem of residual impurities on the conveyor belt and adhering to the pump body, resulting in a decrease in the detection accuracy of the pump body. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 A three-dimensional diagram of an integrated intelligent test platform for a pump body hydrostatic pressure test according to the present invention; Figure 2 It is a front view structural schematic diagram of an integrated intelligent test platform for pump body hydrostatic pressure testing of the present invention; Figure 3 It is a side view structural schematic diagram of an integrated intelligent test platform for pump body hydrostatic pressure testing of the present invention; Figure 4 It is a structural schematic diagram of a conveying mechanism of an integrated intelligent test platform for a pump body hydrostatic pressure test according to the present invention; Figure 5 It is a structural schematic diagram of another angle of a conveying mechanism of an integrated intelligent test platform for a pump body hydrostatic pressure test of the present invention; Figure 6 It is a schematic diagram of the decomposed structure of a conveying mechanism of an integrated intelligent test platform for a pump body hydrostatic pressure test according to the present invention; Figure 7 The present invention is a schematic diagram of the structure of the conveying mechanism portion of an integrated intelligent test platform for pump body hydrostatic pressure testing.

[0018] In the figure: 1. Constant temperature and humidity pump room; 101. Water inlet; 102. Pump room; 2. Control cabinet; 201. Start and emergency stop button; 202. Instrument panel; 203. Display; 204. Print window; 3. Test area; 301. Hydraulic flange tooling control element; 302. Camera; 303. Hydraulic flange tooling; 304. Automatic exhaust valve; 305. Automatic liquid collection reflux end; 306. Purge device; 307. Hydraulic lifting stop flange tooling; 3081. First safety protection door; 3082. Second safety protection door; 4, pump body parts feeding device; 401, conveying frame; 402, conveyor belt; 403, conveying motor; 404, sliding block; 405, sliding rail; 406, threaded rod; 407, translation motor; 408, mounting frame; 409, spray box; 410, conveying pipe; 411, conveying pump; 412, connecting hose; 413, water storage box; 414, filter; 415, spray nozzle; 416, cleaning brush; 417, sliding groove; 418, lifting cylinder; 419, support frame; 5, alarm device. DETAILED DESCRIPTION

[0019] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the implementation regulations described are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0020] Example 1: Figure 1-Figure 4As shown, the present invention provides a technical solution: an integrated intelligent test platform for hydrostatic test of a pump body, comprising a constant temperature and humidity pump room 1, a test area 3 is arranged on the constant temperature and humidity pump room 1, the test area 3 comprises a camera 302, a hydraulic flange tooling 303, an automatic exhaust valve 304, a purge device 306 and a hydraulic lifting stop flange tooling 307, the camera 302 is arranged on the side of the hydraulic flange tooling 303, the automatic exhaust valve 304 is connected to the outside of the hydraulic flange tooling 303, the hydraulic lifting stop flange tooling 307 is arranged on the side of the purge device 306, and the hydraulic flange tooling 303 is arranged above the hydraulic lifting stop flange tooling 307; A pump body parts feeding device 4 is arranged at the back of the constant temperature and humidity pump room 1, and the pump body parts feeding device 4 includes a conveying frame 401, a conveying belt 402 is arranged on the inner side of the conveying frame 401, a conveying motor 403 is arranged on one side of the conveying frame 401, a sliding block 404 is arranged at the bottom of the conveying frame 401, a sliding rail 405 is arranged on the outer side of the sliding block 404, and a mounting frame 408 is arranged at the bottom of the sliding rail 405. Two spray boxes 409 are arranged on the mounting frame 408, and a plurality of spray nozzles 415 are evenly distributed on the top of the spray box 409, and a plurality of cleaning brushes 416 are evenly distributed on both sides of the spray box 409. A conveying pipe 410 is fixedly connected to one end of the spray box 409, and a conveying pump 411 is fixedly connected to one end of the conveying pipe 410, and a connecting rod 414 is fixedly connected to the side of the conveying pump 411. A connecting hose 412 is provided, one end of which is fixedly connected to a water storage box 413, and a spray nozzle 415 is distributed below the conveyor belt 402. A threaded rod 406 is movably installed on the inner side of the sliding rail 405, and a translation motor 407 is provided at one end of the sliding rail 405. The output end of the translation motor 407 is connected to one end of the threaded rod 406, and the threaded rod 406 is threadedly connected to the inner side of the sliding block 404. A filter screen 414 is provided inside the water storage box 413, and a bracket plate is symmetrically fixedly installed on the inner wall of the water storage box 413, and the filter screen 414 is installed on the bracket plate. A drain pipe is provided at the bottom of the water storage box 413, and a sliding groove 417 is symmetrically fixedly installed at the bottom of the mounting frame 408. Connecting strips are provided on both sides of the water storage box 413, and the connecting strips are movably connected to the inner side of the sliding groove 417.

[0021] In this embodiment, parts are identified by a camera 302 and transmitted to a control cabinet. Meanwhile, the hydraulic flange tooling 303 can automatically match tooling of different sizes according to the pump model, thereby effectively improving the scope of use. The automatic exhaust valve 304 realizes the exhaust function during operation. The purge device 306 can provide a purge function during identification, thereby facilitating effective cleaning of dust and impurities on the surface of the pump body being tested, thereby helping to improve the accuracy of the test and ensuring the test effect. The hydraulic lifting stop flange tooling 307 can provide an effective docking connection function, thereby facilitating ensuring the stability of the connection.

[0022] The pump body parts feeding device 4 is arranged on the side of the test area 3, and a conveyor belt 402 is arranged on the conveying frame 401 and is driven by a conveying motor 403, so as to facilitate the transmission and conveying function of the conveyor belt 402. The sliding block 404 is slidably connected to the sliding rail 405, so as to facilitate the provision of erection support for the conveying frame 401. The support is provided by the mounting frame 408, so as to facilitate the installation of the spray box 409. A plurality of spray nozzles 415 and a cleaning brush 416 are respectively distributed on the top and the side of the spray box 409, and a conveying pipe 410 is connected to one end of the spray box 409. The conveying pipe 410 is used to connect the conveying pump 411, and the inside of the water storage box 413 is connected through the connecting hose 412, so as to facilitate the delivery of the conveying pump 411. The water source inside the water storage box 413 is extracted and then transported to the inside of the spray box 409 through the delivery pipe 410, and then the cleaning water source is sprayed out at high pressure through the spray nozzle 415 to perform high-pressure flushing on the outer wall of the conveyor belt 402, which is conducive to providing a high-efficiency cleaning function and effectively ensuring the cleaning effect. At the same time, the cleaning brush 416 is evenly distributed and fits to the outer wall of the conveyor belt 402, thereby achieving an effective cleaning effect and avoiding the problem of residual impurities on the conveyor belt 402 and adhering to the pump body, resulting in a decrease in the detection accuracy of the pump body. The translation motor 407 drives the threaded rod 406 to rotate, thereby driving the sliding block 404 and the conveying frame 401 to achieve mobile adjustment, which is conducive to more efficiently transporting the material into the interior of the test area 3 and achieving efficient processing. After the upper process of the horizontal / vertical pump body is completed, it flows into the test area 3 from the pump body part feeding device 4, the camera 302 takes a snapshot, identifies the part model, and transmits the signal to the control cabinet 2. The control cabinet 2 retrieves the test requirements and controls the corresponding size hydraulic flange tooling 303 and the hydraulic lifting stop flange tooling 307. After the hydraulic tooling is clamped, the control cabinet controls the first safety protection door 3081 and the second safety protection door 3082 to close, the pump room 102 starts, and water delivery and pressurization begin. The automatic exhaust valve 304 exhausts and closes, and the pressure transmitter transmits the pressure to the control cabinet. The instrument panel 202 and the display 203 display in real time, and the pressure is maintained according to the test requirements. After the test, the control cabinet turns off the booster pump, issues a test report and uploads it to the management platform, special marks are placed on unqualified parts, unqualified test records are issued, and qualified parts generate QR codes for circulation. The hydraulic flange fixture 303 and the hydraulic lifting stop flange fixture 307 return to their original positions, and the test liquid flows to the water source through the automatic liquid collection reflux end 305, and is recycled for sedimentation and filtration. After the parts leave the test area, the purge device 306 removes the water stains on the test bench and waits for the next part to flow in. During the test, the alarm device 5 is connected to the control cabinet, and the test is stopped and checked in case of abnormal conditions, and the test is continued after the fault is eliminated. In addition to the fully automatic intelligent test, a start-up emergency stop button 201 is set to start, and the hydraulic flange fixture control element 301 can meet the needs of manually operated tests. The reliability of the test center is guaranteed through system self-test and periodic inspection.

[0023] Example 2: Figure 1-Figure 4 As shown, the constant temperature and humidity pump room 1 includes a water inlet end 101 and a pump room 102. The water inlet end 101 is arranged at one end of the constant temperature and humidity pump room 1. The pump room 102 is arranged at the front of the constant temperature and humidity pump room 1. A control cabinet 2 is arranged at the front of the constant temperature and humidity pump room 1. The control cabinet 2 includes a start and emergency stop button 201 and an instrument panel 202. The instrument panel 202 is arranged above the start and emergency stop button 201. The control cabinet 2 also includes a display 203 and a print window 204. The print window 204 is arranged below the display 203.

[0024] In this embodiment, the water inlet end 101 facilitates water inlet connection and input of water source. The pump room 102 is provided with a booster pump, a soundproof cover, a vibration isolation pad, a low resistance filter, a check valve, a pipe valve and a pressure transmitter, etc., so as to effectively provide the function of water pressure delivery. The start emergency stop button 201 and the instrument panel 202 facilitate pneumatic and closing control and pressure viewing. The display 203 can form a time-pressure curve in real time, and the print window 204 can print an unqualified report and generate a qualified QR code.

[0025] Example 3: Figure 1-Figure 4 As shown, a hydraulic flange tooling control element 301 is provided on the front of the test area 3, an automatic liquid collection reflux end 305 is provided at one end of the constant temperature and humidity pump room 1, an alarm device 5 is fixedly installed on the top of the constant temperature and humidity pump room 1, and the test area 3 also includes a first safety protection door 3081 and a second safety protection door 3082, and the first safety protection door 3081 and the second safety protection door 3082 are respectively arranged on the sides of the test area 3.

[0026] In this embodiment, the hydraulic flange tooling control element 301 can provide control, the automatic liquid collection reflux end 305 facilitates reflux, and provides sedimentation filtration. The alarm device 5 tests the center sensing system, timeout alarm, abnormal sound alarm, and abnormal drop in pressure gauge data alarm. The first safety protection door 3081 and the second safety protection door 3082 can provide protection during use, thereby improving the safety of use.

[0027] In the present invention, when the integrated intelligent test platform for the hydrostatic test of the pump body is used, the camera 302 is first used to identify the parts and transmit them to the control cabinet. At the same time, the hydraulic flange tooling 303 can automatically match the tooling of different sizes according to the pump model, which effectively improves the scope of use. The automatic exhaust valve 304 realizes the exhaust function during operation. The purge device 306 can provide the purge function during identification, which is beneficial to effectively clean the dust and impurities on the surface of the pump body being tested, which helps to improve the accuracy of the test and ensure the effect of the test. The hydraulic lifting stop flange tooling 307 can provide the function of effective docking connection, which is beneficial to ensure the stability of the connection. The pump body parts feeding device 4 is arranged on the test On the side of area 3, a conveyor belt 402 is provided on the conveyor frame 401 and is driven by a conveying motor 403, which is conducive to the transmission and conveying function of the conveyor belt 402. The sliding block 404 is slidably connected to the sliding rail 405, which is convenient for providing a support for the conveyor frame 401. The support is provided by the mounting frame 408, which is convenient for providing installation for the spray box 409. A plurality of spray nozzles 415 and a cleaning brush 416 are respectively distributed on the top and side of the spray box 409, and a conveying pipe 410 is connected to one end of the spray box 409. The conveying pipe 410 is connected to the conveying pump 411, and is connected to the inside of the water storage box 413 through the connecting hose 412, so that the water storage box can be easily installed through the operation of the conveying pump 411. The water source inside 413 is extracted and then transported to the inside of the spray box 409 through the delivery pipe 410. Then, the cleaning water source is sprayed out at high pressure through the spray nozzle 415 to perform high-pressure flushing on the outer wall of the conveyor belt 402, which is conducive to providing a high-efficiency cleaning function and effectively ensuring the cleaning effect. At the same time, the cleaning brush 416 is evenly distributed and fits the outer wall of the conveyor belt 402, thereby achieving an effective cleaning effect and avoiding the problem of residual impurities on the conveyor belt 402 and adhering to the pump body, causing the detection accuracy of the pump body to decrease. The water inlet end 101 facilitates water inlet connection and input of water source. The pump room 102 is equipped with a booster pump, a soundproof cover, a vibration isolation pad, a low-resistance filter, a check valve, a pipe valve and a pressure transmitter, etc. , thereby effectively providing the function of water pressure delivery, starting the emergency stop button 201 and the instrument panel 202 to facilitate pneumatic and closing control and view the pressure, the display 203 can form a time-pressure curve in real time, the print window 204 can print the unqualified report, and the qualified QR code is generated. The hydraulic flange tooling control element 301 can provide control, and the automatic liquid collection reflux end 305 facilitates reflux and provides sedimentation filtration. The alarm device 5 test center sensing system, timeout alarm, abnormal sound alarm, pressure gauge data abnormal drop alarm, the first safety protection door 3081 and the second safety protection door 3082 can provide protection during use, thereby improving the safety of use.

[0028] Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. An integrated intelligent test platform for hydrostatic testing of a pump body, comprising a constant temperature and humidity pump room (1), characterized in that: The constant temperature and humidity pump room (1) is provided with a test area (3), the test area (3) comprising a camera (302), a hydraulic flange tool (303), an automatic exhaust valve (304), a purge device (306) and a hydraulic lifting stop flange tool (307), the camera (302) being arranged on the side of the hydraulic flange tool (303), the automatic exhaust valve (304) being connected to the outside of the hydraulic flange tool (303), the hydraulic lifting stop flange tool (307) being arranged on the side of the purge device (306), and the hydraulic flange tool (303) being arranged above the hydraulic lifting stop flange tool (307); A pump body parts feeding device (4) is arranged at the back of the constant temperature and humidity pump room (1), and the pump body parts feeding device (4) comprises a conveying frame (401), a conveying belt (402) is arranged on the inner side of the conveying frame (401), a conveying motor (403) is arranged on one side of the conveying frame (401), a sliding block (404) is arranged at the bottom of the conveying frame (401), a sliding rail (405) is arranged on the outer side of the sliding block (404), a mounting frame (408) is arranged at the bottom of the sliding rail (405), and two spray boxes (408) are arranged on the mounting frame (408). 09), a plurality of spray nozzles (415) are evenly distributed on the top of the spray box (409), a plurality of cleaning brushes (416) are evenly distributed on both sides of the spray box (409), one end of the spray box (409) is fixedly connected to a delivery pipe (410), one end of the delivery pipe (410) is fixedly connected to a delivery pump (411), a side of the delivery pump (411) is fixedly connected to a connecting hose (412), one end of the connecting hose (412) is fixedly connected to a water storage box (413), and the spray nozzles (415) are distributed below the conveyor belt (402).

2. The integrated intelligent test platform for pump hydrostatic pressure testing according to claim 1 is characterized in that: A threaded rod (406) is movably mounted on the inner side of the sliding rail (405), a translation motor (407) is arranged at one end of the sliding rail (405), an output end of the translation motor (407) is connected to one end of the threaded rod (406), and the threaded rod (406) is threadedly connected to the inner side of the sliding block (404).

3. The integrated intelligent test platform for pump hydrostatic pressure testing according to claim 2 is characterized in that: A filter screen (414) is arranged inside the water storage box (413), a bracket plate is symmetrically fixedly mounted on the inner wall of the water storage box (413), the filter screen (414) is mounted on the bracket plate, and a drainage pipe is arranged at the bottom of the water storage box (413).

4. The integrated intelligent test platform for pump hydrostatic pressure testing according to claim 3 is characterized in that: The bottom of the mounting frame (408) is symmetrically fixedly mounted with a sliding groove (417), and connecting bars are provided on both sides of the water storage box (413), and the connecting bars are movably connected to the inner side of the sliding groove (417).

5. The integrated intelligent test platform for pump hydrostatic pressure testing according to claim 1 is characterized in that: The constant temperature and humidity pump room (1) comprises a water inlet end (101) and a pump room (102), wherein the water inlet end (101) is arranged at one end of the constant temperature and humidity pump room (1), and the pump room (102) is arranged at the front of the constant temperature and humidity pump room (1).

6. The integrated intelligent test platform for pump hydrostatic pressure testing according to claim 1 is characterized in that: A control cabinet (2) is arranged on the front of the constant temperature and humidity pump room (1); the control cabinet (2) comprises a start and emergency stop button (201) and an instrument panel (202); the instrument panel (202) is arranged above the start and emergency stop button (201).

7. The integrated intelligent test platform for pump hydrostatic pressure testing according to claim 6 is characterized in that: The control cabinet (2) further comprises a display (203) and a printing window (204), wherein the printing window (204) is arranged below the display (203).

8. The integrated intelligent test platform for pump hydrostatic pressure testing according to claim 1 is characterized in that: A hydraulic flange tooling control element (301) is provided on the front of the test area (3), and an automatic liquid collection reflux end (305) is provided at one end of the constant temperature and humidity pump room (1).

9. The integrated intelligent test platform for pump hydrostatic pressure testing according to claim 1, characterized in that: An alarm device (5) is fixedly installed on the top of the constant temperature and humidity pump room (1).

10. The integrated intelligent test platform for pump hydrostatic pressure testing according to claim 8, characterized in that: The test area (3) further comprises a first safety protection door (3081) and a second safety protection door (3082), wherein the first safety protection door (3081) and the second safety protection door (3082) are respectively arranged on the sides of the test area (3).

Citation Information

Patent Citations

  • Integrated mobile intelligent pressure test integrated device

    CN111307604A

  • Walk-in motor load test damp and hot box for high-humidity test environment

    CN115902315A

  • Automatic static pressure test device for vertical centrifugal pump

    CN218098200U

  • Pump testing system

    US20160097397A1

  • KR20230105232A

Cited By

  • Mine water injection pump detection device

    CN120592863A

  • Mine water injection pump detection device

    CN120592863B