Grouting controllable locking foot supporting system with spiral blade

Through the controllable grouting technology of setting spiral blades and grouting holes on the locking anchors, the problem of low bearing capacity of traditional locking anchors in weak surrounding rocks is solved, and the compression and pullout bearing capacity is improved. It reduces construction risks and simplifies the construction process, making it suitable for standardized construction of large-span tunnels.

CN221838370UActive Publication Date: 2024-10-15GANSU PROVINCE TRANSPORTATION PLANNING SURVEY & DESIGN INST
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202420567759.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-22
Publication Date
2024-10-15
Estimated Expiration
2034-03-22

AI Technical Summary

Technical Problem

During tunnel construction, traditional locking anchors have low initial support bearing capacity in weak, loose surrounding rock or loess strata, resulting in high construction risks and difficulty in effectively controlling ground deformation and improving tunnel stability.

Method used

A grouting controllable locking foot support system with spiral blades is adopted. By setting spiral blades and grouting holes on the locking foot anchor rod body, combined with positioning tubes and grouting pipes, controllable grouting reinforcement is achieved and the pullout resistance is improved. , compressive bearing capacity, and fixed by welding and slotted rods to reduce the drilling process.

Benefits of technology

It significantly improves the compression and pull-out bearing capacity of the locking anchor, reduces construction risks, controls the convergence deformation of the initial support, simplifies the construction process, reduces costs, and is suitable for the standardized construction of large-span tunnels.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221838370U_ABST
    Figure CN221838370U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of feet-lock bolts, in particular to a grouting controllable feet-lock supporting system with spiral blades. The problem that in the prior art, the bearing capacity of the bottom-falling locking foot position of a primary support in a tunnel is low is solved. Comprising a foot anchor rod body, the foot anchor rod body is divided into a spiral blade section and a non-spiral blade section, spiral blades are arranged on the spiral blade section, and grouting holes are evenly formed in the spiral blade section of the foot anchor rod body; the positioning pipe is detachably mounted on the primary support steel arch and used for positioning and placing the feet-lock bolt body; and the grouting pipe is arranged in the foot-lock anchor rod body in a sectioned and sealed mode, and grout outlet holes are evenly formed in a pipe body of the grouting pipe 7. The purpose of primary supporting is achieved, and the safety risk of tunnel construction is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of locking foot anchor rods, in particular to a grouting controllable locking foot support system with spiral blades. Background Art

[0002] During the construction of highway tunnels, some sections pass through soft, loose surrounding rock or loess strata. The surrounding rock of such strata has weak cementation and poor self-stabilization ability. After excavation, it is easy to have risks such as landslides and arch falls. In order to reduce the above risks, the tunnel design specification proposes locking anchor support to improve the bearing capacity of the tunnel, control the deformation of the stratum or rock mass, and enhance the stability of the tunnel. In recent years, with the increase in traffic flow on high-speed highways, two-lane tunnels can no longer meet the needs of social development, and three-lane and multi-lane tunnels have gradually increased. For such large-span tunnels, the excavation method generally adopts multi-step or single and double sidewall excavation. When such tunnels pass through soft, loose surrounding rock or loess strata, the construction risk is extremely high, and the requirements for locking anchors are also high.

[0003] Traditional locking anchor rods generally use Φ42mm or Φ60mm seamless steel pipes with holes, which are generally 3 to 4m long. Cement slurry is injected into the anchor rods in stone tunnels and enters the surrounding rock from the reserved holes, which plays a role in reinforcing the surrounding rock and enhancing the bearing capacity of the anchor rods. However, cement slurry in earth tunnels has a softening effect on the stratum, so the cement slurry is replaced with cement mortar, which only improves the strength of the locking anchor rod body. Utility Model Content

[0004] In view of the problem of low bearing capacity of the locking foot position at the bottom of the initial support in the tunnel in the prior art, the utility model abandons the traditional single-rod locking foot anchor support system and proposes a grouting controllable locking foot support system with spiral blades. While expanding the diameter of the far end of the anchor rod, the surrounding loose rock mass is reinforced by controllable grouting, which greatly increases the tensile and compressive bearing capacity of the locking foot anchor rod, so as to achieve the purpose of supporting the initial support and reduce the safety risk of tunnel construction.

[0005] The technical solution of the utility model is as follows:

[0006] A grouting controllable locking foot support system with spiral blades, comprising: a locking foot anchor rod body, the locking foot anchor rod body is divided into a spiral blade section and a non-spiral blade section, the spiral blade section is provided with spiral blades, and grouting holes are evenly opened on the spiral blade section of the locking foot anchor rod body;

[0007] Positioning tube, which can be detachably installed on the initial support steel arch frame and is used to position and place the locking foot anchor rod body;

[0008] The grouting pipe is sealed in sections and placed in the locking foot anchor rod body, and grouting holes are evenly opened on the grouting pipe 7 body.

[0009] Furthermore, the end of the locking foot anchor rod body with the spiral blade segment is provided with an anchor rod tip.

[0010] Furthermore, the spiral blades include spiral blades with a taper and spiral blades without a taper that are connected to each other, and the spiral blades with a taper and the spiral blades without a taper are welded and fixed to the spiral blade segments of the locking foot anchor rod body.

[0011] Furthermore, the blade edge gradient angle of the tapered spiral blade is 5 to 10 degrees.

[0012] Furthermore, the end of the non-spiral blade section of the locking foot anchor rod body is provided with a slot, a slot rod is installed through the slot, and the locking foot anchor rod body and the positioning tube are limited by the slot rod.

[0013] Furthermore, a rubber valve sleeve is provided on the rod body of the locking foot anchor rod at the grouting hole position.

[0014] Furthermore, the segmented closure of the grouting pipe is achieved by installing an upper stop grouting plug and a lower stop grouting plug on the grouting pipe. After the grouting pipe is placed in the locking foot anchor rod body, the upper stop grouting plug and the lower stop grouting plug both abut against the inner wall of the grouting pipe and the locking foot anchor rod body.

[0015] The beneficial effects of the utility model are as follows: by welding the tapered spiral blades to the locking foot anchor rod body, the rod is directly screwed into the surrounding rock formation using a drill with a chuck, reducing the drilling process of the traditional locking foot anchor rod, and reinforcing the loose rock formation around the anchor rod through closed grouting, greatly improving the compression and pull-out bearing capacity of the locking foot anchor rod, effectively controlling the convergence deformation of the initial support, and reducing the construction risks of arch instability, collapse, etc. In addition, the support structure can be centrally manufactured in a factory, with a simple structure, low cost, and high on-site construction efficiency, and can become a part of the standardized construction of tunnels. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 1. It is a schematic diagram of the locking foot anchor rod body;

[0017] Figure 2 It is an overall schematic diagram of a locking foot anchor rod with spiral blades;

[0018] Figure 3 is a schematic diagram of a spiral blade;

[0019] Figure 4 It is a schematic diagram of the proximal end of the locking foot anchor rod;

[0020] Figure 5 yes Figure 4 Schematic diagram of section Ⅰ-Ⅰ;

[0021] Figure 6 This is a schematic diagram of the construction positioning of the locking foot anchor;

[0022] Figure 7 yes Figure 6 Schematic diagram of view B in the middle.

[0023] Figure 8 This is a schematic diagram of the grouting end of the locking anchor. Figure 1 Middle II-II section);

[0024] As shown in the figure: initial support steel arch frame A, locking foot anchor rod body 1, anchor rod tip 2, slot rod 3, tapered spiral blade 4, non-tapered spiral blade 5, positioning pipe 6, grouting pipe 7, grouting hole 8, rubber valve sleeve 9, upper slurry stop plug 10, lower slurry stop plug 11, slurry outlet hole 12. DETAILED DESCRIPTION

[0025] The technical solution of the utility model is further described below with reference to the accompanying drawings and through specific embodiments:

[0026] Example 1

[0027] See attached Figures 1 to 8 The present invention is a controllable locking foot support system with spiral blades for grouting. The locking foot system is mainly composed of a locking foot anchor rod body 1, a spiral blade, a positioning tube 6 and a grouting tube 7. The locking foot anchor rod body 1 can be made of a Φ42mm or Φ60mm steel pipe, an anchor rod tip 2 is arranged at one end of the locking foot anchor rod body 1, and a slot is arranged at the other end, in which a slot rod 3 is clamped, and the length of the locking foot anchor rod body 1 is generally 2 to 3m.

[0028] The locking foot anchor rod body 1 is divided into a spiral blade section and a non-spiral blade section. The spiral blade section is provided with a spiral blade. The spiral blade is divided into a tapered spiral blade 4 and a non-tapered spiral blade 5. The tapered spiral blade 4 belongs to a gradual section. The longitudinal layout length should not be too long, generally not more than 1m; the blade edge gradual angle is about 5 to 10°; the maximum width of the blade can be determined according to the softness and hardness of the surrounding rock, generally about 10 to 20cm; the wave crest distance of each blade is the same, about 15 to 30cm. The longitudinal layout length of the non-tapered spiral blade 5 is generally controlled at 3 times the wave crest distance. The thickness of the spiral blades 4 and 5 is generally controlled at about 5 to 10mm, and can also be flexibly adjusted according to the softness and hardness of the surrounding rock.

[0029] After the spiral blade is processed, the locking foot anchor rod body 1 with a pointed head 2 is passed through the tapered spiral blade 4 and the non-tapered spiral blade 5 along the center, and the spiral blade is welded to the locking foot anchor rod body 1 at the contact position. Double-sided full welding is used when necessary. During the construction process, in order to prevent the locking foot anchor rod body 1 from shaking too much, a positioning tube 6 is set on the side of the initial support steel arch frame A. When the spiral blade enters the surrounding rock and conflicts with the initial support steel arch frame A, the longitudinal driving angle can be appropriately adjusted, and the height of the positioning tube 6 can be appropriately adjusted. At the same time, because one end of the locking foot anchor rod body 1 is clamped with the slot rod 3, the locking foot anchor rod body 1 can be effectively prevented from completely entering the positioning tube 6, and the locking foot anchor rod body 1 is limited.

[0030] When the tunnel surrounding rock is soil or loess, it is only necessary to fill cement mortar inside the locking foot anchor rod, and there is no need to perform grouting operations on the spiral blade segment. When the tunnel surrounding rock is loose surrounding rock such as soft stone, pebble, loose sandstone, etc., the locking foot anchor rod body 1 is provided with grouting holes 8 in the spiral blade segment, with 3 holes in each ring and a diameter of about 10 to 20 mm. In order to prevent the grouting holes 8 from being blocked when the anchor rod is screwed into the stratum, a rubber valve sleeve 9 is provided on the outside. A grouting pipe 7 is placed inside the locking foot anchor rod body 1. The grouting pipe 7 can be a rubber tube with a diameter of 20 to 30 mm. The end portion is provided with a grouting hole 12 in the range of 20 to 40. An upper grouting plug 10 and a lower grouting plug 11 are provided at the front and rear. The grouting plug 10 and the lower grouting plug 11 are both made of rubber and are arranged in double layers. In the early stage of grouting construction, when the end of the grouting pipe 7 reaches the bottom of the locking foot anchor rod, firstly pressurize and blow air quickly to open the rubber valve sleeve 9, and then perform grouting operation from bottom to top. The cement slurry can be cement-water glass double slurry. After the grouting is completed, the inside of the locking foot anchor rod is filled with cement mortar to enhance its own strength.

[0031] Working principle: The processed locking anchor rod body 1 with spiral blades is transported to the tunnel working face by a transport vehicle. After a cycle of initial tunnel support is completed, there is no need to drill holes at the construction location. The locking anchor rod body 1 is directly screwed slowly into the surrounding rock of the tunnel side wall by a drill rig with a clamp. During the construction process, in order to prevent the locking anchor rod body from shaking too much, a positioning tube 6 is used to fix it to the steel arch frame. After the construction is completed, the positioning tube 6 is knocked off and fixed to the side edge of the initial support steel arch frame A with threaded steel bars. This forms a stable locking anchor rod to ensure the stability of the initial support.

[0032] When the tunnel surrounding rock is soil or loess, it is only necessary to fill cement mortar inside the locking foot anchor rod body 1, and there is no need to perform grouting operations on the spiral blade segment. When the tunnel surrounding rock is loose surrounding rock such as gravel layer, pebble layer, loose sandstone layer, etc., it is necessary to first perform grouting reinforcement on the stratum near the locking foot anchor rod body 1, and then perform cement mortar reinforcement on the locking foot anchor rod body 1 itself.

[0033] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or basic features of the present invention. Therefore, no matter from which point of view, the embodiments should be regarded as exemplary and non-restrictive, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present invention.

[0034] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A grouting controllable locking foot support system with spiral blades, characterized in that: include: The locking foot anchor rod body is divided into a spiral blade section and a non-spiral blade section, the spiral blade section is provided with spiral blades, and grouting holes are evenly opened on the spiral blade section of the locking foot anchor rod body; Positioning tube, which can be detachably installed on the initial support steel arch frame and is used to position and place the locking foot anchor rod body; The grouting pipe is sealed in sections and placed in the locking foot anchor rod body, and grouting holes are evenly opened on the grouting pipe 7 body.

2. A grouting controllable locking foot support system with spiral blades according to claim 1, characterized in that: The end of the locking foot anchor rod body with the spiral blade section is provided with an anchor rod tip.

3. A grouting controllable locking foot support system with spiral blades according to claim 1, characterized in that: The spiral blades include spiral blades with a taper and spiral blades without a taper that are connected to each other. The spiral blades with a taper and the spiral blades without a taper are welded and fixed to the spiral blade sections of the locking foot anchor rod body.

4. A grouting controllable locking foot support system with spiral blades according to claim 3, characterized in that: The blade edge gradient angle of the tapered spiral blade is 5 to 10 degrees.

5. A grouting controllable locking foot support system with spiral blades according to claim 1, characterized in that: The end of the non-helical blade section of the locking foot anchor rod body is provided with a slot, a slot rod is installed through the slot, and the locking foot anchor rod body and the positioning tube are limited by the slot rod.

6. A grouting controllable locking foot support system with spiral blades according to claim 1, characterized in that: A rubber valve sleeve is arranged on the rod body of the locking foot anchor rod at the grouting hole position.

7. A grouting controllable locking foot support system with spiral blades according to claim 1, characterized in that: The segmented closure of the grouting pipe is achieved by installing an upper grouting plug and a lower grouting plug on the grouting pipe. After the grouting pipe is placed in the locking foot anchor rod body, the upper grouting plug and the lower grouting plug both abut against the inner wall of the grouting pipe and the locking foot anchor rod body.

Citation Information

Cited By

  • Efficient grouting device for coal mine fault grouting

    CN121273384A

  • A high-efficiency grouting device for fault grouting in coal mines

    CN121273384B