Efficient boiler heat recovery equipment

By designing a series structure of docking components and heat exchange tubes on both sides of the boiler, the problem of heat recovery in the boiler wall is solved, efficient heat recovery and environmental impact reduction are achieved, and the installation and maintenance convenience of the equipment are improved.

CN221840238UActive Publication Date: 2024-10-15JIANGSU WEICHENYI TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420170611.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-24
Publication Date
2024-10-15
Estimated Expiration
2034-01-24

AI Technical Summary

Technical Problem

In the existing technology, it is difficult to recover heat from the furnace wall of the boiler, resulting in waste of heat and impact on the surrounding environment.

Method used

Design a high-efficiency boiler heat recovery equipment, including first and second recovery components set on both sides of the boiler. The heat exchange tubes are connected in series through connecting components and connected to the boiler wall. The thermal conductive plates and connecting sleeves are used to connect the furnace. The wall heat is introduced into the heat exchange tube to achieve heat recovery.

Benefits of technology

It effectively avoids the waste of heat in the boiler wall and reduces the impact on the surrounding environment temperature. It also improves the convenience of installation and disassembly of the equipment and facilitates maintenance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221840238U_ABST
    Figure CN221840238U_ABST
Patent Text Reader

Abstract

The utility model discloses efficient boiler heat recovery equipment, which relates to the technical field of waste heat recovery and comprises a first recovery component and a second recovery component which are respectively sleeved on two sides of a boiler, the first recovery component comprises three fixing frames and a first heat exchange tube, and the second recovery component comprises three fixing frames and a second heat exchange tube. The three fixing frames are rotationally connected through connecting assemblies, and the first heat exchange pipe and the second heat exchange pipe are connected into the fixing frames in series. By the adoption of the structure, the first recycling assembly and the second recycling assembly are in butt joint through the butt joint assembly, the first recycling assembly and the second recycling assembly are arranged on the outer wall of the boiler in a sleeving mode, and then heat of the boiler wall of the boiler can be recycled through the first heat exchange pipe and the second heat exchange pipe; therefore, the boiler wall heat waste of the boiler is effectively avoided, the influence on the surrounding environment temperature is avoided, and the first recovery assembly and the second recovery assembly are more convenient and faster to mount and dismount.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of waste heat recovery, and in particular relates to a high-efficiency boiler heat recovery device. Background Art

[0002] A boiler is an energy conversion device. The energy input into the boiler includes chemical energy and electrical energy in the fuel. The boiler outputs steam, high-temperature water or organic heat carrier with a certain amount of thermal energy. The hot water or steam generated in the boiler can directly provide the required thermal energy for industrial production and people's lives, and can also be converted into mechanical energy through a steam power device, or the mechanical energy can be converted into electrical energy through a generator.

[0003] In the prior art, waste heat recovery of boilers is an important means of energy conservation and emission reduction. For example, a boiler flue heat recovery device disclosed in Chinese patent publication number CN210463072U recovers the heat generated by boiler combustion in a centralized manner, reduces the unsafe hidden dangers caused by excessive temperature around the boiler, and utilizes the surplus generated by combustion to recover cold water for heating and reuse, which can improve the heat recovery effect and efficiency and save energy.

[0004] The boiler heat recovery devices in the prior art mostly recover the heat from the flue gas and steam of the boiler. However, during the use of the boiler, the furnace wall of the boiler will also emit a large amount of heat. If this heat is not recovered, a large amount of heat will be wasted and the surrounding ambient temperature will be affected. Utility Model Content

[0005] In view of the problems mentioned in the background technology, the purpose of the utility model is to provide a high-efficiency boiler heat recovery device to solve the problem that it is difficult to recover heat from the furnace wall of the boiler in the prior art, thereby resulting in waste of heat generated by the furnace wall of the boiler and affecting the surrounding environment.

[0006] The above technical objectives of the utility model are achieved through the following technical solutions:

[0007] A high-efficiency boiler heat recovery device comprises a first recovery component and a second recovery component respectively sleeved on both sides of the boiler, the first recovery component comprises three fixing frames and a first heat exchange tube, the second recovery component comprises three fixing frames and a second heat exchange tube, the three fixing frames are rotatably connected by a connecting component, the first heat exchange tube and the second heat exchange tube are respectively connected in series inside, one end of the first heat exchange tube and the second heat exchange tube are respectively docked with an external heat exchange device, the other end of the first heat exchange tube is docked with the other end of the second heat exchange tube, and the first recovery component is docked with the second recovery component through a docking component; by docking the first recovery component and the second recovery component, and sleeved on the outer wall of the boiler, the heat of the furnace wall of the boiler can be recovered through the first heat exchange tube and the second heat exchange tube, thereby effectively avoiding heat waste of the furnace wall of the boiler and avoiding affecting the ambient temperature.

[0008] Furthermore, as a preferred technical solution, a heat conduction plate is fixedly installed on the inner wall of the fixed frame, and the inner walls of the heat conduction plate are respectively fitted with the outer walls of the first heat exchange tube and the second heat exchange tube; the other end of the first heat exchange tube is fixedly connected with a connecting sleeve, and the other end of the second heat exchange tube is inserted into the inside of the connecting sleeve; the heat of the furnace wall can be introduced into the first heat exchange tube and the second heat exchange tube through the heat conduction plate, and the first heat exchange tube and the second heat exchange tube are connected into a whole through the connecting sleeve, so that the first recovery component and the second recovery component can be connected in series to facilitate the recovery of the heat from the furnace wall.

[0009] Furthermore, as a preferred technical solution, the connecting assembly includes a connecting frame and a connecting block, the connecting frame is fixedly installed on one side of the fixing frame, the connecting block is fixedly installed on the other side of the fixing frame, and the connecting block is rotatably connected to the inside of the connecting frame; by adopting the connecting assembly, multiple fixing frames can be rotatably connected so that the fixing frames can be attached to the furnace wall.

[0010] Furthermore, as an optimal technical scheme, the docking assembly includes a first bracket, a screw, a second bracket and a nut. The first bracket is fixedly installed on one side of the outer wall of the fixed frame, the screw is rotatably connected to the inside of the first bracket, the second bracket is fixedly installed on one side of the outer wall of the other fixed frame, one end of the screw is inserted into the inside of the second bracket, the nut is threadedly connected to the outer wall of one end of the screw, and one side of the nut is fitted with one side of the second bracket; a support rod is fixedly installed inside the first bracket, a support block is sleeved on the outer wall of the support rod, and the screw is fixedly connected to one side of the support block; a threaded groove is provided on the outer side of the upper end of the second bracket, and a bolt is threadedly connected to the inner thread of the thread groove, the lower end of the bolt extends into the interior of the second bracket through the threaded groove, and the inner side of the bolt is fitted with the outer side of the screw; by adopting the docking assembly, the fixed frames on the outside of the first recovery assembly and the second recovery assembly can be docked to effectively stabilize the position of the fixed frame and prevent the fixed frame from falling off.

[0011] In summary, the utility model mainly has the following beneficial effects:

[0012] First, by using a docking assembly to dock the first recovery assembly and the second recovery assembly, and by sleeve-mounting the first recovery assembly and the second recovery assembly on the outer wall of the boiler, the heat of the furnace wall of the boiler can be recovered through the first heat exchange tube and the second heat exchange tube, thereby effectively avoiding the waste of heat from the furnace wall of the boiler and avoiding the impact on the ambient temperature. In addition, the first recovery assembly and the second recovery assembly are more convenient and quick to install and disassemble;

[0013] Second, by using a connecting component to rotatably connect multiple fixing frames to each other, and by docking the fixing frames on the outside of the first recovery component and the second recovery component through a docking component, it is convenient to set the multiple fixing frames on the furnace wall of the boiler, so that the first recovery component and the second recovery component are more convenient to install, and after the docking component is separated, the first recovery component and the second recovery component can be disassembled, so that maintenance work can be carried out more conveniently. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a structural schematic diagram of the utility model;

[0015] Figure 2 It is a rear view structural schematic diagram of the utility model;

[0016] Figure 3 It is a schematic diagram of the top view structure of the utility model;

[0017] Figure 4 It is a structural schematic diagram of the docking assembly of the utility model.

[0018] Figure numerals: 1. first recovery component, 2. second recovery component, 3. fixing frame, 31. connecting component, 311. connecting frame, 312. connecting block, 32. heat conducting plate, 4. first heat exchange tube, 41. connecting sleeve, 5. second heat exchange tube, 6. docking assembly, 61. first bracket, 611. support rod, 612. support block, 62. screw, 63. second bracket, 631. threaded groove, 632. bolt, 64. nut. DETAILED DESCRIPTION

[0019] Example

[0020] See also Figure 1-Figure 4In an embodiment of the present invention, a high-efficiency boiler heat recovery device includes a first recovery component 1 and a second recovery component 2 respectively sleeved on both sides of the boiler, the first recovery component 1 includes three fixing frames 3 and a first heat exchange tube 4, the second recovery component 2 includes three fixing frames 3 and a second heat exchange tube 5, the three fixing frames 3 are rotatably connected by a connecting component 31, the first heat exchange tube 4 and the second heat exchange tube 5 are respectively connected in series inside, one end of the first heat exchange tube 4 and the second heat exchange tube 5 are respectively docked with an external heat exchange device, the other end of the first heat exchange tube 4 is docked with the other end of the second heat exchange tube 5, and the first recovery component 1 is docked with the second recovery component 2 through a docking component 6;

[0021] When the heat of the furnace wall of the boiler is needed, multiple fixing frames 3 are attached to the furnace wall through the connecting component 31, and then the fixing frames 3 on the outside of the first recovery component 1 and the second recovery component 2 are docked through the docking component 6, so that the first recovery component 1 and the second recovery component 2 are sleeved on the furnace wall of the boiler, and then the heat of the furnace wall can be collected through the first heat exchange tube 4 and the second heat exchange tube 5 to achieve the purpose of recovering the heat of the furnace wall.

[0022] refer to Figure 2 The inner wall of the fixing frame 3 is fixedly mounted with a heat conducting plate 32, and the inner wall of the heat conducting plate 32 is respectively in contact with the outer wall of the first heat exchange tube 4 and the outer wall of the second heat exchange tube 5; Figure 2 The other end of the first heat exchange tube 4 is fixedly connected with a connecting sleeve 41, and the other end of the second heat exchange tube 5 is inserted into the inside of the connecting sleeve 41; the heat of the furnace wall can be introduced into the first heat exchange tube 4 and the second heat exchange tube 5 through the heat conduction plate 32, and the first heat exchange tube 4 and the second heat exchange tube 5 are connected through the connecting sleeve 41, so that the first heat exchange tube 4 and the second heat exchange tube 5 are connected into a whole, so that the first recovery component 1 and the second recovery component 2 are connected in series.

[0023] refer to Figure 3 The connecting assembly 31 includes a connecting frame 311 and a connecting block 312. The connecting frame 311 is fixedly installed on one side of the fixing frame 3, and the connecting block 312 is fixedly installed on the other side of the fixing frame 3. The connecting block 312 is rotatably connected to the inside of the connecting frame 311; by making the connecting block 312 rotatably connected to the inside of the connecting frame 311, the fixing frame 3 can be rotated on one side of the other fixing frame 3 through the connecting assembly 31.

[0024] refer to Figure 4The docking assembly 6 includes a first bracket 61, a screw 62, a second bracket 63 and a nut 64. The first bracket 61 is fixedly mounted on one side of the outer wall of the fixing frame 3, the screw 62 is rotatably connected to the inside of the first bracket 61, the second bracket 63 is fixedly mounted on one side of the outer wall of the other fixing frame 3, one end of the screw 62 is inserted into the inside of the second bracket 63, the nut 64 is threadedly connected to the outer wall of one end of the screw 62, and one side of the nut 64 is in contact with one side of the second bracket 63; refer to Figure 4 , a support rod 611 is fixedly installed inside the first bracket 61, a support block 612 is sleeved on the outer wall of the support rod 611, and a screw rod 62 is fixedly connected to one side of the support block 612; Figure 4 A thread groove 631 is provided on the outer side of the upper end of the second bracket 63, and a bolt 632 is connected to the inner thread of the thread groove 631. The lower end of the bolt 632 extends into the interior of the second bracket 63 through the thread groove 631, and the inner side of the bolt 632 fits with the outer side of the screw rod 62; the screw rod 62 is rotated inside the first bracket 61 through the support rod 611 and the support block 612 so that the screw rod 62 can be inserted into the second bracket 63, and the screw rod 62 is positioned by the bolt 632 to prevent the screw rod 62 from separating from the second bracket 63, and then the position of the screw rod 62 is tightened by the nut 64, and the fixing frame 3 on the outer side of the first recovery component 1 and the second recovery component 2 can be docked through the docking component 6.

[0025] Principle and advantages of use: When the heat of the furnace wall of the boiler is needed, the connecting block 312 is rotated to connect to the inside of the connecting frame 311, so that the fixing frame 3 is rotated on one side of another fixing frame 3 through the connecting component 31, so that multiple fixing frames 3 are attached to the furnace wall, and then the fixing frames 3 outside the first recovery component 1 and the second recovery component 2 are docked through the docking component 6, so that the first recovery component 1 and the second recovery component 2 are sleeved on the furnace wall of the boiler, and then the other end of the first heat exchange tube 4 and the other end of the second heat exchange tube 5 are docked through the connecting sleeve 41, and one end of the first heat exchange tube 4 is docked with the water outlet end of the external heat exchanger, and one end of the second heat exchange tube 5 is docked with the water inlet end of the external heat exchanger, and heat is transferred through the heat conducting plate 32, so that the heat of the furnace wall can be collected through the first heat exchange tube 4 and the second heat exchange tube 5, so as to achieve the effect of recovering the heat of the furnace wall, and the furnace wall temperature can be prevented from affecting the ambient temperature;

[0026] When docking the first recovery component 1 and the second recovery component 2, the screw 62 is rotated inside the first bracket 61 through the support rod 611 and the support block 612 so as to insert the screw 62 into the second bracket 63, and then the bolt 632 is rotated to move the bolt 632 downward through the thread groove 631, so as to restrict the screw 62 in the second bracket 63 through the bolt 632 to prevent the screw 62 from separating from the second bracket 63, and then the position of the screw 62 is tightened by the nut 64, so that the first recovery component 1 and the fixing frame 3 outside the second recovery component 2 can be docked through the docking component 6 to complete the positioning of the first recovery component 1 and the second recovery component 2.

Claims

1. A high-efficiency boiler heat recovery device, comprising a first recovery component (1) and a second recovery component (2) respectively mounted on both sides of the boiler, Features: The first recovery component (1) comprises three fixing frames (3) and a first heat exchange tube (4), and the second recovery component (2) comprises three fixing frames (3) and a second heat exchange tube (5). The three fixing frames (3) are rotatably connected to each other via a connecting component (31). The first heat exchange tube (4) and the second heat exchange tube (5) are respectively connected in series inside. One end of the first heat exchange tube (4) and the second heat exchange tube (5) are respectively connected to an external heat exchange device, and the other end of the first heat exchange tube (4) is connected to the other end of the second heat exchange tube (5). The first recovery component (1) is connected to the second recovery component (2) via a connecting component (6).

2. A high-efficiency boiler heat recovery device according to claim 1, Features: A heat conducting plate (32) is fixedly mounted on the inner wall of the fixing frame (3), and the inner wall of the heat conducting plate (32) is respectively fitted with the outer walls of the first heat exchange tube (4) and the second heat exchange tube (5).

3. A high-efficiency boiler heat recovery device according to claim 1, Features: The other end of the first heat exchange tube (4) is fixedly connected to a connecting sleeve (41), and the other end of the second heat exchange tube (5) is inserted into the interior of the connecting sleeve (41).

4. A high-efficiency boiler heat recovery device according to claim 1, Features: The connection assembly (31) comprises a connection frame (311) and a connection block (312); the connection frame (311) is fixedly mounted on one side of the fixing frame (3); the connection block (312) is fixedly mounted on the other side of the fixing frame (3); and the connection block (312) is rotatably connected to the interior of the connection frame (311).

5. A high-efficiency boiler heat recovery device according to claim 1, Features: The docking assembly (6) comprises a first bracket (61), a screw rod (62), a second bracket (63) and a nut (64); the first bracket (61) is fixedly mounted on one side of the outer wall of the fixing frame (3); the screw rod (62) is rotatably connected to the inside of the first bracket (61); the second bracket (63) is fixedly mounted on one side of the outer wall of the other fixing frame (3); one end of the screw rod (62) is inserted into the inside of the second bracket (63); the nut (64) is threadedly connected to the outer wall of one end of the screw rod (62); and one side of the nut (64) is in contact with one side of the second bracket (63).

6. A high-efficiency boiler heat recovery device according to claim 5, Features: A support rod (611) is fixedly installed inside the first bracket (61), a support block (612) is sleeved on the outer wall of the support rod (611), and the screw rod (62) is fixedly connected to one side of the support block (612).

7. A high-efficiency boiler heat recovery device according to claim 5, Features: A thread groove (631) is provided on the outer side of the upper end of the second bracket (63), and a bolt (632) is connected to the inner thread of the thread groove (631). The lower end of the bolt (632) extends into the interior of the second bracket (63) through the thread groove (631), and the inner side of the bolt (632) is in contact with the outer side of the screw rod (62).