Prefabricated tubular pile cap construction formwork and mold

By designing prefabricated pipe pile pile cap construction templates with vertical formwork structures, modular connection structures and positioning back support structures, the problems of low installation efficiency and low utilization rate in the existing technology have been solved, and fast and efficient installation and high stability have been achieved. , reducing material and labor costs.

CN221850589UActive Publication Date: 2024-10-18ROAD & BRIDGE INT CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323508557.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-22
Publication Date
2024-10-18
Estimated Expiration
2033-12-22

AI Technical Summary

Technical Problem

The existing prefabricated pipe pile pile cap construction formwork has low installation efficiency and is easily deformed. The bamboo plywood is easily damaged during disassembly and has low utilization rate, resulting in material waste and high labor costs.

Method used

A prefabricated pipe pile pile cap construction formwork including a vertical formwork structure, a modular connection structure and a positioning back support structure is designed. It uses components such as rectangular steel plates, plug-in sockets and reinforced channel steel frames, and uses pull bolts and back corrugations. The reinforced structure enables quick installation and efficient formwork, improving overall stability.

Benefits of technology

It achieves fast and efficient installation of pile cap molds, reduces waste of manpower and materials, and improves utilization rate and functional practicability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221850589U_ABST
    Figure CN221850589U_ABST
Patent Text Reader

Abstract

The utility model discloses a prefabricated tubular pile cap construction formwork and a mold. The prefabricated tubular pile cap construction formwork comprises a vertical formwork structure and a horizontal formwork structure, the splicing connecting structures are correspondingly and fixedly connected to the two side parts of the vertical position template structure respectively; and the positioning back supporting structure is assembled on the back side part of the vertical position template structure in a switching manner. The problems that in the prior art, pile cap construction formworks for prefabricated pipe piles are low in installation efficiency and prone to deformation, bamboo plywood is prone to being damaged when the formworks are dismantled, the utilization rate is low, reprocessing materials are damaged, and the labor cost is wasted are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of prefabricated pipe pile cap construction, in particular to a prefabricated pipe pile cap construction template and a mold. Background Art

[0002] At present, the installation of the pile cap construction template for prefabricated pipe piles is generally done by splicing bamboo plywood and square wood strips for reinforcement, and then further using clips to fully surround and fix them on all sides, and setting hooks to connect with the pile cap steel mesh to complete auxiliary fixation. Although the above construction structure can meet the construction needs to a certain extent, its installation process is inefficient, the template is very easy to deform after installation, and the bamboo plywood is easily damaged during the removal of the template, the utilization rate is low, a large amount of reprocessing materials are damaged and labor costs are wasted. Utility Model Content

[0003] To this end, the utility model provides a prefabricated pipe pile cap construction template and mold to solve the problems in the prior art that the pile cap construction template for prefabricated pipe piles has low installation efficiency and is easy to deform, and the bamboo plywood is easily damaged when the template is removed, resulting in low utilization rate, damage to reprocessed materials and waste of labor costs.

[0004] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0005] A prefabricated pipe pile cap construction template, comprising:

[0006] Standing template structure;

[0007] The assembly connection structure is respectively fixedly connected to the two side parts of the standing template structure;

[0008] The positioning back support structure is transfer-assembled and arranged on the back side of the standing template structure.

[0009] On the basis of the above technical solution, the utility model is further described as follows:

[0010] As a further solution of the utility model, the standing template structure includes a template body, frame side panels and a frame top panel;

[0011] The template body is configured as a rectangular steel plate structure;

[0012] The frame side panels are provided in two groups, and the two groups of frame side panels are respectively and vertically fixedly assembled on one group of opposite side portions of the rectangular template body in a one-to-one correspondence;

[0013] The frame top plates are provided in two groups, and the two groups of frame top plates are respectively and vertically fixedly assembled on the other group of opposite side parts of the rectangular template body in a one-to-one correspondence.

[0014] As a further solution of the utility model, two groups of the assembly connection structures are provided, and the two groups of the assembly connection structures are respectively and one-to-one fixedly assembled on the outer sides of the two groups of the frame side panels.

[0015] As a further solution of the utility model, the assembled connection structure is configured as a plug-in tube socket or a plug-in pin body, and / or two groups of the assembled connection structures are configured as plug-in tube sockets and plug-in pin bodies in a one-to-one correspondence.

[0016] As a further solution of the utility model, it also includes:

[0017] The back rib reinforcement structure includes two groups of reinforcement channel steel frames, which are respectively fixedly installed in the middle position of one side of the two groups of frame top plates facing away from the template body, and the extension direction of the two groups of reinforcement channel steel frames is perpendicular to the extension direction of the frame top plates.

[0018] As a further solution of the utility model, one end portion of the two groups of reinforcement channel steel frames extends to the outer side of the frame top plate, and a predetermined spacing is maintained between the two groups of reinforcement channel steel frames to form a corresponding tension bolt gap.

[0019] As a further solution of the utility model, the positioning back support structure includes an adapter body and a support extension rod;

[0020] The adapter seat body is transversely fixedly assembled between the two groups of the reinforced channel steel frames; one end of the support extension rod along its extension direction is adapter-assembled and connected to the adapter seat body.

[0021] As a further solution of the utility model, the positioning back support structure also includes buried diagonal rods;

[0022] One end of the buried oblique rod is connected to the other end of the supporting extension rod along its extension direction by an integral fixed assembly.

[0023] A pile cap construction mould comprises the prefabricated pipe pile cap construction template.

[0024] As a further solution of the utility model, it also includes:

[0025] The tension bolt structure is tension-fixedly arranged between gaps between two opposing groups of tension bolts formed after a number of prefabricated pipe pile cap construction templates are enclosed and spliced.

[0026] The utility model has the following beneficial effects:

[0027] This formwork framework can effectively serve as the main formwork framework for the construction of prefabricated pipe pile caps through the coordination of the standing formwork structure and the assembly connection structure. At the same time, it can significantly improve the overall stability of the main formwork framework during application by utilizing the back rib reinforcement structure and the positioning back support structure. This enables the pile cap mold to be installed and constructed quickly and efficiently, reduces the waste of manpower and reprocessing materials, and improves the utilization rate and functional practicality. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] In order to more clearly illustrate the implementation methods of the utility model or the technical solutions in the prior art, the drawings required for the implementation methods or the description of the prior art will be briefly introduced below. The structures, proportions, sizes, etc. illustrated in this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read. Any structural modification, change in proportional relationship or adjustment of size should still fall within the scope of the technical contents disclosed in the utility model without affecting the effects and purposes that can be achieved by the utility model.

[0029] Figure 1 This is one of the overall front view structural schematic diagrams of the prefabricated pipe pile cap construction template and mold provided in the embodiment of the utility model.

[0030] Figure 2 This is one of the overall side view structural schematic diagrams of the prefabricated pipe pile cap construction template and mold provided in an embodiment of the utility model.

[0031] Figure 3 The second schematic diagram of the overall front view structure of the prefabricated pipe pile cap construction template and mold provided in the embodiment of the utility model.

[0032] Figure 4 The second schematic diagram of the overall side view structure of the prefabricated pipe pile cap construction template and mold provided in the embodiment of the utility model.

[0033] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0034] Standing template structure 1: template body 11, frame side plate 12, frame top plate 13;

[0035] Back rib reinforcement structure 2: reinforcement channel steel frame 21, tension bolt gap 22;

[0036] Positioning back support structure 3: adapter seat body 31, support extension rod 32, buried inclined rod 33;

[0037] Assemble and connect the structures 4. DETAILED DESCRIPTION

[0038] The following is a specific embodiment of the present invention. People familiar with the technology can easily understand the other advantages and functions of the present invention from the contents disclosed in this specification. Obviously, the described embodiment is a part of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0039] The terms such as "upper", "lower", "left", "right", and "middle" used in this specification are only for the convenience of description and are not intended to limit the scope of the present invention. Changes or adjustments to their relative relationships shall be deemed to be within the scope of the present invention without substantially changing the technical content.

[0040] like Figures 1 to 4 As shown, the embodiment of the utility model provides a prefabricated pipe pile cap construction template and a pile cap construction mold including the prefabricated pipe pile cap construction template, wherein the prefabricated pipe pile cap construction template includes a standing template structure 1, a back rib reinforcement structure 2, a positioning back support structure 3 and an assembly connection structure 4, which is used to effectively serve as the main formwork framework for the construction of the prefabricated pipe pile cap through the standing template structure 1 in conjunction with the assembly connection structure 4, and can significantly improve the overall stability of the main formwork framework when applied by utilizing the back rib reinforcement structure 2 and the positioning back support structure 3, thereby achieving fast and efficient installation and construction of the pile cap mold, reducing the waste of manpower and reprocessing materials, and improving the utilization rate. The specific settings are as follows:

[0041] Please refer to Figures 1 to 4 The standing formwork structure 1 includes a formwork body 11, a frame side panel 12 and a frame top panel 13; wherein the formwork body 11 is configured as a rectangular steel plate structure with a size of 1200×300×6mm; the frame side panels 12 are provided with two groups, both groups of the frame side panels 12 are configured as rectangular steel plate structures with a size of 50×276×12mm, and the two groups of the frame side panels 12 are respectively and one by one vertically fixedly assembled on one group of opposite side portions of the rectangular formwork body 11; the frame top panel 13 is provided with two groups, both groups of the frame top panels 13 are configured as rectangular steel plate structures with a size of 50×1200×12mm, and the two groups of the frame top panels 13 are respectively and one by one vertically fixedly assembled on another group of opposite side portions of the rectangular formwork body 11; so as to effectively form the formwork main frame for the construction of pipe pile caps.

[0042] The splicing connection structure 4 is provided with two groups, and the two groups of the splicing connection structures 4 are respectively and one-to-one fixedly assembled on the outer sides of the two groups of the frame side panels 12. Specifically, the splicing connection structure 4 is configured as a plug-in pipe socket or a plug-in pin body, and / or the two groups of the splicing connection structures 4 are respectively and one-to-one configured as a plug-in pipe socket and a plug-in pin body, so as to realize that a plurality of supporting formwork main structures are enclosed and spliced ​​with the help of the two groups of splicing connection structures 4 on both sides thereof, and finally form an enclosed structure of the pile cap construction mold.

[0043] Please refer to Figure 1 and Figure 3 The back rib reinforcement structure 2 includes two groups of reinforcement channel steel frames 21, and the two groups of reinforcement channel steel frames 21 are respectively fixedly assembled on the middle position of the side of the two groups of frame top plates 13 facing away from the template body 11, and the extension direction of the two groups of reinforcement channel steel frames 21 is perpendicular to the extension direction of the frame top plate 13, so as to significantly improve the stability of the formwork main body structure through the reinforcement channel steel frames 21.

[0044] As a preferred solution of this embodiment, please continue to refer to Figure 1 and Figure 3 One end portion of the two groups of reinforcing channel steel frames 21 extends to the outer side of the frame top plate 13, and a predetermined spacing is maintained between the two groups of reinforcing channel steel frames 21 to form a tension bolt gap 22, so as to configure a tension bolt structure between two opposite groups of tension bolt gaps 22 formed after a number of supporting formwork main frames are enclosed and spliced, and effectively use the tension bolt structure to significantly improve the forming stability of the pile cap construction mold.

[0045] The positioning back-support structure 3 includes an adapter seat body 31, a support extension rod 32 and a buried diagonal rod 33; wherein the adapter seat body 31 is transversely fixedly assembled between the two groups of the reinforced channel steel frames 21; the support extension rod 32 is connected to the adapter seat body 31 by an adapter assembly at one end along its extension direction, so that the support extension rod 32 can be effectively adjusted to the back support to the ground based on the adapter seat body 31; and the other end of the support extension rod 32 along its extension direction is connected to one end of the buried diagonal rod 33 by an integrated fixed assembly, and the extension direction of the buried diagonal rod 33 is at an angle of 135° with the extension direction of the support extension rod 32, so as to utilize the buried diagonal rod 33 to effectively form an oblique burying effect based on the ground, thereby further significantly improving the overall forming stability performance of the pile cap construction mold.

[0046] Although the utility model has been described in detail above with general descriptions and specific embodiments, it is obvious to those skilled in the art that some modifications or improvements can be made to the utility model. Therefore, these modifications or improvements made without departing from the spirit of the utility model are within the scope of protection claimed by the utility model.

Claims

1. A prefabricated pipe pile cap construction template, It is characterized in that include: Standing template structure; The assembly connection structure is respectively fixedly connected to the two side parts of the standing template structure; A positioning back support structure is connected and assembled on the back side of the standing template structure; The standing template structure includes a template body, frame side panels and a frame top panel; The template body is configured as a rectangular steel plate structure; The frame side panels are provided in two groups, and the two groups of frame side panels are respectively and vertically fixedly assembled on one group of opposite side portions of the rectangular template body in a one-to-one correspondence; The frame top plates are provided in two groups, and the two groups of frame top plates are respectively and vertically fixedly assembled on the other group of opposite side parts of the rectangular template body in a one-to-one correspondence.

2. The prefabricated pipe pile cap construction template according to claim 1, It is characterized in that The two groups of the assembly connection structures are provided, and the two groups of the assembly connection structures are respectively fixedly assembled and arranged on the outer sides of the two groups of the frame side panels in a one-to-one correspondence.

3. The prefabricated pipe pile cap construction template according to claim 2, It is characterized in that The assembled connection structure is configured as a plug-in tube socket or a plug-in pin body, and / or two groups of assembled connection structures are configured as plug-in tube sockets and plug-in pin bodies in a one-to-one correspondence.

4. The prefabricated pipe pile cap construction template according to claim 1, It is characterized in that Also includes: The back rib reinforcement structure includes two groups of reinforcement channel steel frames, which are respectively fixedly installed in the middle position of one side of the two groups of frame top plates facing away from the template body, and the extension direction of the two groups of reinforcement channel steel frames is perpendicular to the extension direction of the frame top plates.

5. The prefabricated pipe pile cap construction template according to claim 4, It is characterized in that One end portion of the two groups of reinforcement channel steel frames both extend to the outer side of the frame top plate, and a predetermined spacing is maintained between the two groups of reinforcement channel steel frames to form a tension bolt gap.

6. The prefabricated pipe pile cap construction template according to claim 5, It is characterized in that The positioning back support structure includes an adapter seat body and a support extension rod; The adapter seat body is transversely fixedly assembled between the two groups of the reinforced channel steel frames; one end of the support extension rod along its extension direction is adapter-assembled and connected to the adapter seat body.

7. The prefabricated pipe pile cap construction template according to claim 6, It is characterized in that The positioning back support structure also includes buried diagonal rods; One end of the buried oblique rod is connected to the other end of the supporting extension rod along its extension direction by an integral fixed assembly.

8. A pile cap construction mold, It is characterized in that It comprises a prefabricated pipe pile cap construction template as described in any one of claims 5-7.

9. The pile cap construction mold according to claim 8, It is characterized in that Also includes: The tension bolt structure is tension-fixedly arranged between gaps between two opposing groups of tension bolts formed after a number of prefabricated pipe pile cap construction templates are enclosed and spliced.