Pre-tightening force steel structure construction platform
By using pre-tightened steel cables and winches on the steel structure construction platform, combined with the adsorption connections of the supporting steel columns, the problem of poor stability of the robotic arm at the steel structure construction site is solved, and stable support and efficient construction of the platform are achieved.
Patent Information
- Application Number
- CN202321692573.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-06-30
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2033-06-30
AI Technical Summary
At steel structure construction sites, it is difficult for robotic arms and sensor equipment to work stably on mobile lifts due to weight and height. They are prone to shaking and resonance, causing the construction platform to be unstable and affecting work efficiency.
A pre-tensioned steel structure construction platform is designed, which uses multiple steel cables and winches to provide pre-tensioning force, and is combined with supporting steel columns to connect through magnetic suction or vacuum adsorption to limit the platform's translational and rotational freedom to ensure the platform's stability. And adjust the height through lifting equipment.
It effectively reduces the vibration and vibration of the construction platform, ensures the stable operation of the robotic arm and sensor equipment, improves construction efficiency and safety, and reduces the structural weight and transportation difficulty.
Smart Images

Figure CN221878763U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of steel structure construction, and in particular relates to a pre-tightening force steel structure construction platform. Background Art
[0002] Due to the high strength, low price and convenient construction of steel, the application of steel structure is becoming more and more widespread. Steel structure refers to a whole formed by splicing multiple steel components, which are generally spliced by bolts or welding. The construction and maintenance of steel structure are mostly industrial control operations, which require manual work to climb up the steel structure for assembly and welding. The labor cost is high and the quality is difficult to unify.
[0003] With the development of science and technology, the welding and assembly of steel structures in factories has begun to use an automated operation system with robotic arms and optical sensors as core equipment, which has greatly improved work efficiency. However, this automated operation system is difficult to apply to external construction sites because the robotic arms can be fixed on the horizontal ground in the factory and can work stably.
[0004] However, the steel structure assembly and welding location at the external construction site is generally 10-20 meters above the ground, and requires the use of a mobile lift to carry equipment such as a robotic arm to work; the greater the height of the mobile lift, the worse the horizontal rigidity, and the mass of working equipment such as a robotic arm is itself large. If these devices are placed on a mobile lift, due to the influence of weight, the equipment will inevitably shake uncontrollably, causing the robotic arm and various sensors to fail to work, and may even resonate with the mobile lift, causing the mobile lift to overturn. Utility Model Content
[0005] In order to overcome the above-mentioned deficiencies of the prior art, the utility model proposes a pre-tightening steel structure construction platform, comprising:
[0006] A platform 11, multiple steel cables, multiple winches and a supporting steel column 41, wherein the multiple winches are fixedly installed on the platform 11, one end of each steel cable is connected to the corresponding winch, and the other end is detachably connected to the steel structure outside the platform 11; one end of the supporting steel column 41 is hinged to the platform 11, and the other end is detachably connected to the steel structure outside the platform 11; the platform 11 is installed above a mobile lifting device.
[0007] Preferably, the multiple steel cables include steel cable 1 21, steel cable 22 and steel cable 3 23, the multiple winches include winch 1 31, winch 2 32 and winch 3 33, one end of winch 1 31 is connected to steel cable 1 21, and the other end is connected to the platform 11, one end of winch 2 32 is connected to steel cable 2 22, and the other end is connected to the platform 11, and one end of winch 33 is connected to steel cable 3 23, and the other end is connected to the platform 11.
[0008] Preferably, the steel cable 1 21 , the steel cable 2 22 and the steel cable 3 23 are connected around the platform 11 , and the winch 1 31 , the winch 2 32 and the winch 3 33 are installed around the platform 11 .
[0009] Preferably, the detachable connection method between the support steel column 41 and the steel structure outside the platform 11 includes adsorption connection.
[0010] Preferably, the adsorption connection method includes magnetic adsorption or vacuum adsorption.
[0011] Preferably, a magnetic suction cup or a vacuum suction cup is provided at one end of the support steel column 41 connected to the steel structure outside the platform 11 .
[0012] Preferably, the platform 11 is a rigid platform, and the lower end of the rigid platform is connected to a mobile lifting device.
[0013] Compared with the closest prior art, the utility model has the following beneficial effects:
[0014] The utility model provides a pre-tightening steel structure construction platform, comprising: a platform 11, a plurality of steel cables, a plurality of winches and a supporting steel column 41, wherein the plurality of winches are fixedly mounted on the platform 11, one end of each steel cable is connected to the corresponding winch, and the other end is detachably connected to the steel structure outside the platform 11; one end of the supporting steel column 41 is hinged to the platform 11, and the other end is detachably connected to the steel structure outside the platform 11; the platform 11 is mounted above a mobile lifting device; the plurality of steel cables and the supporting steel column are connected to the platform through one end, and are connected to the steel structure outside the platform through the other end. , which limits the translational and rotational freedom of the platform, provides stable support for the platform, and can ensure the stable operation of the assembled and welded equipment on the platform; when the construction platform has no preload, there are gaps between the components, and the constraints are insufficient. There will be obvious vibrations in the gaps when the platform carries the equipment at work; and the construction platform uses multiple steel cables and winches to provide preload. As the steel cables are tightened, the pressure on the supporting steel columns increases, and the gaps between the columns and the steel structure are quickly closed, ultimately achieving close connections between the components and the construction platform and the steel structure, and a stable construction platform. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the top view of a pre-tightening steel structure construction platform of the utility model;
[0016] Figure 2 It is a side view structural schematic diagram of a pre-tightening steel structure construction platform of the utility model;
[0017] Among them, 11-platform; 21-steel cable 1; 22-steel cable 2; 23-steel cable 3; 31-winch 1; 32-winch 2; 33-winch 3; 41-supporting steel column. DETAILED DESCRIPTION
[0018] The specific implementation of the utility model is further described in detail below with reference to the accompanying drawings.
[0019] Embodiment 1:
[0020] The utility model provides a pre-tightening steel structure construction platform, such as Figure 1 , Figure 2 As shown, it includes: a platform 11, multiple steel cables, multiple winches and a supporting steel column 41, wherein the multiple winches are fixedly installed on the platform 11, one end of each steel cable is connected to the corresponding winch, and the other end is detachably connected to the steel structure outside the platform 11; one end of the supporting steel column 41 is hinged to the platform 11, and the other end is detachably connected to the steel structure outside the platform 11; the platform 11 is installed above the mobile lifting equipment.
[0021] The platform 11 is a rigid platform. In the present embodiment, the rigid platform is a circular flat plate with relatively high rigidity. The circular flat plate is connected to the main steel structure outside the platform 11 through steel cables and supporting steel columns. The lower end of the rigid platform is connected to a mobile lifting device. By moving the lifting device, the height of the platform 11 is changed to realize construction operations at different positions.
[0022] The multiple steel cables include steel cable 1 21, steel cable 22 and steel cable 3 23, and the multiple winches include winch 1 31, winch 2 32 and winch 3 33. One end of winch 1 31 is connected to steel cable 1 21, and the other end is connected to the platform 11. One end of winch 2 32 is connected to steel cable 2 22, and the other end is connected to the platform 11. One end of winch 33 is connected to steel cable 3 23, and the other end is connected to the platform 11.
[0023] Steel cable 1 21, steel cable 22 and steel cable 3 23 are connected around the platform 11, and winch 1 31, winch 2 32 and winch 3 33 are installed around the platform 11, and the three steel cables are not coplanar.
[0024] By tightening the steel cable with a winch, sufficient preload is provided to ensure the stability of the platform. Compared with a structure without preload, the utility model is relatively light because: slender steel is prone to instability under pressure, but will not become unstable when under tension, but will only yield. Therefore, the tensile capacity of the steel cable is much better than its compressive capacity, especially for high-strength steel. Among the four supporting components in the utility model, only one supporting steel column 41 bears the pressure, and the rest are steel cables, which greatly reduces the weight of the structure. The steel cables are relatively soft and more convenient to store than steel columns, which greatly facilitates the transportation of the construction platform.
[0025] The detachable connection method between the support steel column 41 and the steel structure outside the platform 11 includes an adsorption connection, and the adsorption connection method includes magnetic attraction or vacuum attraction. Therefore, a magnetic suction cup or a vacuum suction cup is set at one end of the support steel column 41 connected to the steel structure outside the platform 11. When working, the suction cup can be placed on the steel structure outside the platform 11, and the adsorption switch is turned on, and the support steel column 41 can be tightly connected to the steel structure.
[0026] The combined force of the three steel cables and the gravity of the platform 11 may generate pressure or tension in the direction of the support steel column 41, so the combined force is balanced by a rigid object such as the support steel column 41. When processing the support steel column 41 and connecting it, it is not necessary to be very precise, and the gaps between the various connection structures will not have a negative impact on the stability of the construction platform. Because after the platform is erected, the winch applies pre-tightening force to the steel cables, and the gaps between the various components are quickly closed.
[0027] Specifically, compared with structures without prestressing, the utility model has very low processing requirements and is relatively convenient to construct. In the absence of prestressing force, there will be certain gaps between the various components of the working platform, and the constraints are insufficient. When the platform bears the dynamic load of the load, the tiny gaps between the supporting components and the platform will cause obvious vibrations, making it impossible to carry out construction work on the platform. In this construction platform, the three steel cables are tensioned and tightly connected to the steel frame structure on the outside of the platform 11; when the supporting steel column 41 is just installed, there is a gap in the connection with the steel frame steel structure, but as the winch tightens the steel cable, the pressure in the supporting steel column 41 becomes greater and greater, and the above gaps will be quickly bridged to ensure that the supporting steel column is tightly connected to the steel structure and the construction platform is stable.
[0028] Three steel cables and one supporting steel column limit the two translational degrees of freedom and three rotational degrees of freedom of the platform 11, providing stable support for the platform 11. The degree of freedom of the platform in the vertical direction 41 is constrained by the supporting steel column and the lifting equipment.
[0029] Since the friction coefficient between steel and steel is about 0.2, when the angle between the support steel column 41 and the steel structure support surface is greater than 80 degrees, the friction self-locking phenomenon will occur. In this case, even if there is no constraint on the support column, the support column can reliably withstand the pressure. However, in order to ensure safety, it is recommended that the magnetic or vacuum suction cup of the support column be turned on in any case after the working platform is unfolded to ensure the stability of the construction platform.
[0030] Embodiment 2:
[0031] The utility model provides a pre-tightening steel structure construction platform, such as Figure 1 , Figure 2As shown, it includes: a platform 11, multiple steel cables, multiple winches and a supporting steel column 41, wherein the multiple winches are fixedly installed on the platform 11, one end of each steel cable is connected to the corresponding winch, and the other end is detachably connected to the steel structure outside the platform 11; one end of the supporting steel column 41 is hinged to the platform 11, and the other end is detachably connected to the steel structure outside the platform 11; the platform 11 is installed above the mobile lifting equipment.
[0032] At the construction site of the steel frame structure, the platform 11 is installed above the mobile lifting equipment and transported to the construction site by the lifting equipment. One end of the steel cable is connected to the platform through a winch, and the other end is connected to the steel structure. The supporting steel column 41 is connected to the platform 11 and the steel structure. The winch is used to tension the steel cable to bridge the gap between the components. At this time, all degrees of freedom of the platform are effectively constrained, the vibration of the platform 11 is greatly reduced, and it is more stable, so that the working equipment on the platform 11 can work smoothly.
[0033] Embodiment 3:
[0034] The utility model provides a pre-tightening steel structure construction platform, wherein the positions and cross-sectional dimensions of a plurality of steel cables and the positions of supporting steel columns 41 are set automatically, and the cross-sectional dimensions of supporting steel columns 41 are determined according to the forces they bear in the pre-tightening steel structure construction platform.
[0035] The force of the supporting steel column 41 in the pre-tightening steel structure construction platform is obtained according to the following formula:
[0036] F4=(F1 cosθ1+F2 cosθ2+F3 cosθ3) / cosθ4
[0037] Among them, F4 represents the force of the supporting steel column 41 in the preloaded steel structure construction platform; F1 represents the force of the steel cable 21 in the preloaded steel structure construction platform; F2 represents the force of the steel cable 22 in the preloaded steel structure construction platform; F3 represents the force of the steel cable 3 23 in the preloaded steel structure construction platform; θ1, θ2, θ3, θ4 represent the angles between F1, F2, F3, F4 and the vertical direction respectively.
[0038] The calculation formula for the cross-sectional dimensions of the support steel column 41 is:
[0039]
[0040] Wherein, A represents the cross-sectional area of the supporting steel column 41, i.e., the cross-sectional dimension; F4 represents the force of the supporting steel column 41 in the preloaded steel structure construction platform; φ represents the stability coefficient of the supporting steel column 41, which can be obtained by looking up the table according to my country's "Steel Structure Design Standard"; f y It represents the yield strength of the steel material used for the supporting steel column 41.
[0041] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model rather than to limit its protection scope. Although the utility model is described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that after reading the utility model, those skilled in the art can still make various changes, modifications or equivalent substitutions to the specific implementation methods of the application, but these changes, modifications or equivalent substitutions are all within the protection scope of the claims to be approved.
Claims
1. A preloaded steel structure construction platform, characterized in that: include: A platform (11), a plurality of steel cables, a plurality of hoists and a supporting steel column (41), wherein the plurality of hoists are fixedly mounted on the platform (11), one end of each steel cable is connected to a corresponding hoist, and the other end is detachably connected to a steel structure outside the platform (11); one end of the supporting steel column (41) is hinged to the platform (11), and the other end is detachably connected to the steel structure outside the platform (11), wherein the detachable connection method comprises an adsorption connection, and the adsorption connection method comprises magnetic attraction or vacuum attraction; A magnetic suction cup or a vacuum suction cup is provided at one end of the support steel column (41) connected to the steel structure outside the platform (11); after the platform (11) is unfolded during construction, the magnetic suction cup or the vacuum suction cup is opened in any case to ensure the stability of the platform (11); The platform (11) is installed above the mobile lifting device, and the platform (11) is a circular rigid platform.
2. A pre-tightening steel structure construction platform as claimed in claim 1, characterized in that: The plurality of steel cables include a steel cable 1 (21), a steel cable 2 (22) and a steel cable 3 (23); the plurality of winches include a winch 1 (31), a winch 2 (32) and a winch 3 (33); one end of the winch 1 (31) is connected to the steel cable 1 (21) and the other end is connected to the platform (11); one end of the winch 2 (32) is connected to the steel cable 2 (22) and the other end is connected to the platform (11); one end of the winch 3 (33) is connected to the steel cable 3 (23) and the other end is connected to the platform (11).
3. A pre-tightening steel structure construction platform as claimed in claim 2, characterized in that: The steel cable 1 (21), the steel cable 2 (22) and the steel cable 3 (23) are connected around the platform (11), and the winch 1 (31), the winch 2 (32) and the winch 3 (33) are installed around the platform (11).