Maintenance and cooling integrated pipe for large-section beam

By embedding a combined system of cooling pipes, water spray pipes and pressure regulating pipes in large-section beams, and using cooling water for spray maintenance, the problem of insufficient maintenance of the sides and bottom of the beam is solved, and effective cooling and moisturizing are achieved. Save water resources.

CN221907710UActive Publication Date: 2024-10-29CHINA AEROSPACE CONSTR ENG GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323411183.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-14
Publication Date
2024-10-29
Estimated Expiration
2033-12-14

AI Technical Summary

Technical Problem

In the existing technology, the sides and bottom of the large-section rectangular beam are not properly maintained after the pouring is completed, and the cooling water derived from the cooling pipe cannot be effectively used, resulting in a large temperature difference between the inside and outside and a waste of water resources.

Method used

A maintenance and cooling integrated pipe system including pre-embedded cooling pipes, L-shaped water spray pipes and straight pressure regulating pipes is designed. It uses cooling water for spray maintenance, combines internal cooling and external insulation and moisturizing, and controls it by adjusting the water flow rate. Temperature difference between inside and outside, saving water resources.

Benefits of technology

It achieves effective cooling and maintenance of large-section beams, reduces the temperature difference between inside and outside, saves water resources, and ensures the moisturizing and cooling effects of the beams.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221907710U_ABST
    Figure CN221907710U_ABST
Patent Text Reader

Abstract

The utility model relates to a maintenance and cooling integrated pipe for a large-section beam, which comprises a cooling pipe (1) embedded in the beam, an external L-shaped water spraying pipe (2) connected with the cooling pipe and an external straight pressure regulating pipe (3) connected with the cooling pipe, and is characterized in that the cooling pipe (1) is made of a DN32 cold galvanized steel pipe and is embedded in the beam, and the cooling pipe in the uppermost row is led out towards the beam side through a tee joint; the water spraying pipe (2) is formed by bending a DN32 cold galvanized steel pipe into an L shape, the pipe wall is perforated, the perforated end is blocked, the open end is inserted into a beam side guide-out opening during use, and cooling water is sprayed out and then used for maintenance; the pressure regulating pipe (3) is formed by nesting DN32 and DN40 cold galvanized steel pipes, when the pressure regulating pipe is used, the opening end of the pressure regulating pipe is inserted into a plate face leading-out opening, and the DN40 sleeve is moved up and down to regulate the water flow speed. Cooling water is comprehensively utilized for spraying maintenance, maintenance and cooling are both considered, and the purposes of internal cooling, external heat preservation and moisture preservation, internal and external temperature difference reduction and water resource saving are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, and is suitable for concrete curing of cast-in-place reinforced concrete structural beams, in particular to large-section rectangular beams with a section size greater than 1m. Background Art

[0002] Generally, after the pouring of beam and slab concrete is completed, watering maintenance is mostly carried out on the slab surface. The side of the beam is often not properly maintained, and the support frames at the bottom of the beam are densely distributed, so the effect of direct water spraying is poor.

[0003] Large-section beams generally use the cooling pipe cooling method. The cooling pipe is led out to the post-casting zone, and the cooling water is not reused after flowing out. Utility Model Content

[0004] In order to solve the above problems, the utility model provides an integrated pipe for maintenance and cooling of large-section beams, including a cooling pipe pre-buried inside the beam, an external L-shaped water spray pipe connected to the cooling pipe, and an external straight pressure regulating pipe connected to the cooling pipe. Cooling water is comprehensively utilized for spray maintenance, taking into account both maintenance and cooling, thereby achieving internal cooling, external thermal insulation and moisture retention, reducing the temperature difference between the inside and the outside, and saving water resources at the same time.

[0005] The technical solution adopted by the utility model is that the cooling pipes are embedded in the beams before pouring concrete, and the uppermost row of cooling pipes are led out to the beam side through a tee; the water spray pipe is inserted into the lead-out port on the beam side when in use, and the cooling water is used for maintenance after being sprayed out; the open end of the pressure regulating pipe is inserted into the lead-out port on the board surface when in use, and the water flow rate of the water spray pipe is adjusted by the upper and lower movable sleeves depending on the water pressure conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0006] Figure 1 A longitudinal cross-sectional view showing the working principle of the utility model in a beam;

[0007] Figure 2 A cross-sectional view showing the working principle of the utility model in a beam;

[0008] Figure 3 It is a large sample detailed drawing of the cooling pipe in the utility model;

[0009] Figure 4 It is a large detailed drawing of the water spray pipe in the utility model;

[0010] Figure 5 This is a large detailed drawing of the pressure regulating tube in the utility model.

[0011] In the figure, 1. Cooling pipe; 2. Water spray pipe; 3. Pressure regulating pipe. DETAILED DESCRIPTION

[0012] like Figure 3The cooling pipe (1) is made of DN32 cold-dip galvanized steel pipe, and branches are led out through tees at intervals of 500 mm. The length of the branch can be calculated based on the beam width and the number and spacing of the cooling pipes. Figure 4 The water spray pipe (2) is made of a DN32 cold-dip galvanized steel pipe bent into an L shape, and 5 to 6 holes of Ø1 are punched in a double row in the bending direction, with a hole spacing of 30 mm, and the pipe head at the punched end is sealed. Figure 5 The pressure regulating pipe (3) is composed of DN32 and DN40 cold-dip galvanized steel pipes nested together. The DN32 pipe wall is perforated with 5 to 6 holes in four rows of Ø3 with a hole spacing of 30 mm and one end is blocked.

[0013] Before the large-section beam is cast, the cooling pipe (1) is pre-buried in the beam according to the number and spacing of cooling pipes calculated by thermal engineering of large-volume concrete, and fixed with 20# iron wire. The top row of cooling pipes (1) are led out to branch pipes through a tee, and the horizontal spacing of the branch pipes is 500mm. The pipe ends of the branch pipe outlets are flush with the beam side mold to ensure that they can be exposed normally after the mold is removed. The cooling pipe (1) should be installed and fixed before the beam reinforcement is tied. After the concrete is poured and the final setting reaches a certain strength, the beam side mold is removed, and the open end of the water spray pipe (2) is inserted into the cooling water outlet on the beam side. The water inlet of the cooling pipe (1) is connected to the construction water supply pipe of the floor through a hose and a valve. When maintenance is required, open the valve and add clean water. The cooling pipe (1) cools the inside of the beam, and the water spray pipe (2) sprays the beam side for maintenance at the same time.

[0014] After measuring the temperature through the reserved temperature measuring holes, if the temperature inside the concrete rises quickly, or the temperature difference between the inside and outside is higher than the limit, and the cooling water flow rate needs to be increased, the DN40 sleeve of the pressure regulating pipe (3) is pulled upward to expose the Ф3 drainage holes, and the cooling water flow rate is adjusted by adjusting the number of exposed drainage holes. In this way, the water spraying pressure of the water spraying pipe (2) and the water flow rate of the cooling pipe (1) can be guaranteed, thereby controlling the internal temperature of the large volume of concrete.

[0015] Other matters needing attention: The spray pipes (2) should be installed in full at fixed intervals to avoid missing installation and water leakage. When adding clean water, the valve should be opened slowly to avoid the sudden rise of water pressure to flush the spray pipes (2). Due to the need for curing and cooling, the beam side formwork can be removed when the concrete strength reaches 1.2Mpa, and the beam bottom formwork and support system must not be removed before they meet the specifications and design requirements. The curing time of large-volume concrete is not less than 14 days. Concrete using silicate cement generally reaches the peak of hydration heat within 7 days and has the fastest temperature rise rate. Therefore, when using the utility model, the pressure regulating pipe (3) should be opened to the maximum within 7 days after concrete pouring, mainly to reduce the internal temperature of the beam with a large flow rate, and can be gradually lowered within 7 days to 14 days. When adjusting the pressure regulating pipe (3), avoid sudden opening and closing to avoid the water hammer effect that hits the spray pipe (2). The specific installation and adjustment methods of the cooling pipe, spray pipe, and pressure regulating pipe should be determined based on the thermal calculation of the large-volume concrete special plan and the actual situation on site.

[0016] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model rather than to limit the protection scope of the utility model. After reading this specification, those skilled in the art can make modifications to the embodiments without creative contribution as needed, but as long as they are within the scope of the claims of the utility model, they are protected by the patent law.

Claims

1. A maintenance and cooling integrated pipe for a large-section beam, comprising a cooling pipe (1) pre-buried inside the beam, an external L-shaped water spray pipe (2) connected to the cooling pipe, and an external straight pressure regulating pipe (3) connected to the cooling pipe, characterized in that: The cooling pipes (1) are pre-buried in the beam, and the top row of cooling pipes are led out to the beam side through a tee; the water spray pipe (2) is inserted into the lead-out port on the beam side when in use, and the cooling water is used for maintenance after being sprayed out; the open end of the pressure regulating pipe (3) is inserted into the lead-out port on the board surface when in use, and the DN40 sleeve is movable up and down to adjust the water flow rate.

2. The large cross-section beam maintenance and cooling integrated pipe according to claim 1 is characterized by: The cooling pipe (1) is made of a DN32 cold-dip galvanized steel pipe; the water spray pipe (2) is formed by bending a DN32 cold-dip galvanized steel pipe, and the pipe wall is punched with 5 to 6 holes with a diameter of 1 mm in double rows, with a hole spacing of 30 mm, and the punched ends are blocked; the pressure regulating pipe (3) is composed of nested DN32 and DN40 cold-dip galvanized steel pipes, and the pipe wall of the DN32 steel pipe to which the pressure regulating pipe (3) belongs is punched with 5 to 6 holes with a diameter of 3 mm in four rows, with a hole spacing of 30 mm, and one end is blocked.

3. The large cross-section beam maintenance and cooling integrated pipe according to claim 1 is characterized by: Suitable for large-section rectangular cast-in-place concrete beams with a minimum cross-sectional size greater than 1m.