Hoisting mechanism of double-layer quadrangular pyramid system bolt ball steel net rack
By designing a combined structure of upper and lower hoisting components, the synchronous hoisting of the steel space frame was achieved, solving the stress concentration problem caused by hook fixing and ensuring the safety and reliability of the hoisting process.
Patent Information
- Application Number
- CN202323602064.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-28
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2033-12-28
AI Technical Summary
In existing technologies, when steel space frames are hoisted, the hook is fixed to a certain node, which causes excessive stress on the node, making it prone to deformation and damage.
The system employs a combination of upper and lower hoisting components, using components such as hooks, connecting ropes, and winches to achieve synchronous hoisting of the steel space frame. This increases the contact area between the hoisting blocks and the steel space frame, reducing stress concentration.
This effectively prevents the steel space frame from deforming or being damaged due to stress concentration during hoisting, thus improving the safety and reliability of the hoisting process.
Smart Images

Figure CN221955634U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of hoisting mechanisms, in particular to a hoisting mechanism of a double-layer tetrahedral pyramid system bolt ball steel grid. Background Art
[0002] The double-layer tetrahedral pyramid system bolt ball node steel grid (hereinafter referred to as grid) is a welded tetrahedral pyramid formed by two welded steel plates as the basic unit, and then several basic units are combined together to form a plane shape according to the engineering requirements. The grid is a spatial bar structure whose basic unit is welded by steel plates. It has the advantages of light weight, large span, high rigidity, and good seismic performance. It is widely used in industrial plants, warehouses, exhibition halls and other construction fields. The structural forms of the double-layer tetrahedral pyramid system bolt ball steel grid include triangular pyramid grid, square tetrahedral pyramid grid, rectangular tetrahedral pyramid grid, etc. Its advantages include: flexible and diverse structural forms, which can be combined according to engineering needs to form plane or curved structures of different shapes and sizes; the grid structure has a high bearing capacity and rigidity, which can meet the requirements of large spans and large loads; the grid structure has a light self-weight, which can reduce the bearing pressure of the foundation structure; the nodes of the grid structure are connected by bolt balls, which is convenient and quick to construct and has good seismic performance. The steel grid can be installed and dismantled by hoisting equipment.
[0003] At present, when the steel grid is hoisted, the hook is usually fixed on a certain node of the steel grid, which will cause the node to be subjected to greater stress and easily deformed and damaged. Therefore, we propose a hoisting mechanism of a double-layer tetrahedral pyramid system bolt ball steel grid to solve the above-mentioned problems. Utility Model Content
[0004] The purpose of this section is to summarize some aspects of the embodiments of the utility model and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the specification abstract and application title of the utility model to avoid blurring the purpose of this section, specification abstract and application title, and such simplifications or omissions cannot be used to limit the scope of the utility model.
[0005] Therefore, the utility model aims to provide a lifting mechanism for a double-layer tetrahedral pyramid system bolt ball steel grid, which can solve the problem that the existing lifting nodes are easily deformed and damaged due to stress.
[0006] The utility model provides a lifting mechanism for a double-layer tetrahedral system bolt ball steel grid, which adopts the following technical solutions:
[0007] The lifting mechanism of the double-layer tetrahedral pyramid system bolt ball steel grid comprises an upper lifting assembly, which comprises an upper installation frame, and a lifting piece penetrating the bottom wall of the upper installation frame is installed at the bottom of the inner cavity of the upper installation frame;
[0008] A lower lifting component includes a connecting piece, which is sleeved on the bottom of the lifting piece, a lifting block is fixed to the bottom wall of the connecting piece, lower mounting frames are arranged at the top positions of the outer walls around the lifting block, multiple groups of top walls of the lower mounting frames are provided with strip holes, multiple groups of translation pieces are installed in the inner cavities of the lower mounting frames, and multiple groups of translation pieces are installed with inner rods that pass through the strip holes.
[0009] By adopting the above technical scheme, the lifting block and the lower installation frame are attached to the steel grid, and multiple groups of inner rods and connecting parts are passed through the mesh of the steel grid. Then, the lifting parts and the connecting parts are connected to each other, and the lifting parts are started to drive the lifting block, the lower installation frame and the steel grid to move up and down synchronously to achieve lifting. Under the action of multiple groups of lower installation frames, the contact area between the lifting block and the steel grid can be increased, the stress on the steel grid is reduced, and deformation and damage due to force are avoided as much as possible.
[0010] Optionally, the lifting device includes a winch body, which is fixed on the bottom wall of the upper mounting frame, and a winch rope passing through the bottom wall of the upper mounting frame is installed at the output end of the winch body, and a hook which is mutually socketed with the connecting member is installed at the bottom end of the winch rope.
[0011] Optionally, the connecting member includes a connecting rope loop, which is sleeved on the outside of the hook, and the bottom end of the connecting rope loop is sleeved with a connecting rod fixed to the top wall of the lifting block.
[0012] By adopting the above technical solution, the hook and the connecting rope loop are connected to each other, and the winch body is started to drive the winch rope to contract and extend, and then the lifting block, the lower installation frame and the steel grid can be driven to move up and down synchronously through the hook, the connecting rod and the connecting rope loop to realize lifting.
[0013] Optionally, the translation member includes a screw body, which is rotatably connected in the inner cavity of the lower mounting frame via a bearing, a screw nut fixed to the bottom wall of the inner rod is installed on the outside of the screw body, and a turning plate is fixed to the end of the screw body.
[0014] By adopting the above technical solution, the handle at the corresponding position is turned to drive the inner rod to move horizontally, ensuring that the inner rod can pass through the mesh inside the steel grid, thereby avoiding separation between the steel grid and its lifting mechanism.
[0015] Optionally, lower mounting frames are installed at the bottom positions of the outer walls around the hanging block, and multiple groups of the lower mounting frames are installed with fasteners that are detachably connected to the lower mounting frame.
[0016] Optionally, the fastener includes a fastening bolt, and the fastening bolts are arranged in multiple groups. The multiple groups of fastening bolts are passed through the top wall of the lower mounting frame and extend into the inner cavity of the lower mounting frame. The bottom wall of the lower mounting frame is fixed with multiple groups of fastening nuts matching the threads of the fastening bolts.
[0017] By adopting the above technical solution, the fastening bolts are screwed forward and backward to make them threadedly connected with the fastening nuts at the corresponding positions or separated from each other, so that the lower mounting frame can be disassembled and fixed.
[0018] Optionally, the outer wall threads of multiple groups of the locking inner rods are sleeved with locking outer tubes.
[0019] By adopting the above technical solution, the outer tube is screwed forward and backward to be threadedly connected with the inner rod or separated from each other, so that the internal mesh of the steel grid can be engaged with the inner rod or the outer tube as much as possible.
[0020] Optionally, upper mounting racks are installed at the top positions of the outer walls around the upper mounting frame, and multiple groups of mounting holes are provided on the top walls of the multiple groups of upper mounting racks.
[0021] By adopting the above technical solution, the lifting mechanism of the steel grid can be fixed at the corresponding position using multiple sets of upper mounting frames.
[0022] In summary, the present invention has at least one of the following beneficial effects:
[0023] Fit the lifting block and the lower installation frame onto the steel grid and make multiple sets of inner rods and connecting rods pass through the mesh of the steel grid. Then connect the hook and the connecting rope loop to each other, start the hoisting machine body to drive the lifting block, the lower installation frame and the steel grid to move up and down synchronously to realize lifting. Under the action of multiple sets of lower installation frames, the contact surface between the lifting block and the steel grid can be increased, the stress on the steel grid can be reduced, and deformation and damage due to stress can be avoided as much as possible;
[0024] Twisting the hand plate at the corresponding position drives the screw body to rotate, thereby driving the screw nut to move horizontally. Under the action of the screw nut, the inner rod can be driven to move synchronously in the strip hole, and then the position of the inner rod can be flexibly adjusted according to the position of the mesh inside the steel grid, ensuring that the inner rod can pass through the mesh inside the steel grid, and trying to avoid separation between the steel grid and the lifting mechanism of the steel grid. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for describing the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0026] Figure 1 This is a schematic diagram of the front cross-sectional structure of the utility model;
[0027] Figure 2 This is a front view and cross-sectional structural diagram of the upper hoisting assembly of the utility model;
[0028] Figure 3 It is a front view and cross-sectional structural schematic diagram of the lower hanging assembly of the utility model.
[0029] Explanation of the reference numerals: 100, upper hoisting assembly; 101, upper mounting frame; 1011, mounting hole; 102, upper mounting frame; 103, lifting piece; 1031, winch body; 1032, winch rope; 1033, hook; 200, lower hoisting assembly; 201, lower mounting frame; 2011, strip hole; 202, fastener; 2021, fastening nut; 2022, fastening bolt; 203, hoisting block; 204, lower mounting frame; 205, translation piece; 2051, screw body; 2052, screw nut; 2053, turntable; 206, inner rod in position; 207, connecting piece; 2071, connecting rod; 2072, connecting rope loop; 208, outer tube in position. DETAILED DESCRIPTION
[0030] The following is combined with Figure 1-3 The utility model is described in further detail.
[0031] Example 1, please refer to the attached figure in the specification Figure 1 and 2 The hoisting mechanism of the double-layer tetrahedral pyramid system bolt ball steel grid comprises an upper hoisting assembly 100, which comprises an upper mounting frame 102, a hoisting member 103 is installed at the bottom of the inner cavity of the upper mounting frame 102, the hoisting member 103 comprises a hoisting machine body 1031, the hoisting machine body 1031 is fixed at the middle position of the bottom wall of the upper mounting frame 102, a hoisting rope 1032 penetrating the bottom wall of the upper mounting frame 102 is installed at the output end of the hoisting machine body 1031, and a hook 1033 is installed at the bottom end of the hoisting rope 1032;
[0032] Please refer to the attached figure in the instruction manual Figure 1 and 3, a lower hanging assembly 200 includes a connecting piece 207, the connecting piece 207 includes a connecting rope loop 2072, the connecting rope loop 2072 is sleeved on the outside of the hook 1033, the bottom end of the connecting rope loop 2072 is sleeved with a connecting rod 2071, the bottom wall of the connecting rod 2071 is fixed with a hanging block 203, and the top position of the outer wall around the hanging block 203 is provided with a lower mounting frame 201. The top wall of the lower mounting frame 201 and the top wall position of the hanging block 203 are on the same horizontal plane, and the top walls of multiple groups of lower mounting frames 201 are provided with strip holes 2011, and the inner cavities of multiple groups of lower mounting frames 201 are installed with translation members 205, and the multiple groups of translation members 205 are installed with a locking inner rod 206 that passes through the strip holes 2011.
[0033] The specific working principle is: fit the lifting block 203 and the lower installation frame 201 on the steel grid and make multiple groups of inner rods 206 and connecting rods 2071 pass through the mesh of the steel grid, then connect the hook 1033 and the connecting rope loop 2072 to each other, start the winch body 1031 to drive the winch rope 1032 to contract and stretch, and then the lifting block 203, the lower installation frame 201 and the steel grid can be driven by the hook 1033, the connecting rod 2071 and the connecting rope loop 2072 to move up and down synchronously to achieve lifting. Under the action of multiple groups of lower installation frames 201, the contact area between the lifting block 203 and the steel grid can be increased, the stress on the steel grid can be reduced, and deformation and damage due to force can be avoided as much as possible.
[0034] Example 2, please refer to the attached figure in the specification Figure 3 The lifting mechanism of the double-layer tetrahedral pyramid system bolt ball steel grid includes: the translation member 205 includes a screw body 2051, the screw body 2051 is rotatably connected in the inner cavity of the lower mounting frame 201 through a bearing, a screw nut 2052 fixed to the bottom wall of the inner rod 206 is installed on the outside of the screw body 2051, and a turntable 2053 is fixed to the end of the screw body 2051.
[0035] The specific working principle is: screwing the turntable 2053 at the corresponding position drives the screw body 2051 to rotate, thereby driving the screw nut 2052 to move horizontally, and under the action of the screw nut 2052, the positioning inner rod 206 can be driven to move synchronously in the strip hole 2011, and then the position of the positioning inner rod 206 can be flexibly adjusted according to the position of the mesh inside the steel grid, ensuring that the positioning inner rod 206 can pass through the mesh inside the steel grid, and trying to avoid separation between the steel grid and the lifting mechanism of the steel grid.
[0036] Example 3, please refer to the attached figure in the specification Figure 3The hoisting mechanism of the double-layer tetrahedral system bolt ball steel grid also includes that the bottom positions of the outer walls around the hoisting block 203 are all installed with lower mounting frames 204, and multiple groups of lower mounting frames 204 are installed with fasteners 202. The fasteners 202 include fastening bolts 2022, and multiple groups of fastening bolts 2022 are provided. The multiple groups of fastening bolts 2022 are penetrated through the top wall of the lower mounting frame 204 and extend into the inner cavity of the lower mounting frame 201. The bottom wall of the lower mounting frame 201 is fixed with multiple groups of fastening nuts 2021 that match the threads of the fastening bolts 2022.
[0037] The specific working principle is: screwing the fastening bolt 2022 forward and reverse makes it threadedly connected with the fastening nut 2021 at the corresponding position or separated from each other, so that the lower installation frame 201 can be disassembled and fixed, so that the lower installation frame 201 can be connected and fixed with the lower mounting frame 204 and the lifting block 203 or separated from each other, which is convenient for partial replacement of the lower installation frame 201 when it is damaged, reducing maintenance costs.
[0038] Example 4, please refer to the attached figure in the specification Figure 3 The lifting mechanism of the double-layer tetrahedral system bolt ball steel grid also includes a plurality of groups of positioning inner rods 206 whose outer wall threads are sleeved with positioning outer tubes 208.
[0039] The specific working principle is: twisting the locking outer tube 208 forwards and backwards to make it threadedly connected with the locking inner rod 206 or separated from each other, so as to facilitate adjustment according to the size of the internal mesh of the steel grid, and try to make the internal mesh of the steel grid able to engage with the locking inner rod 206 or the locking outer tube 208, so that relative horizontal sliding is not likely to occur between the steel grid and the lifting block 203 and the lower installation frame 201.
[0040] Example 5, please refer to the attached figure in the specification Figure 2 The lifting mechanism of the double-layer tetrahedral pyramid system bolt ball steel grid also includes upper mounting frames 101 installed on the top positions of the outer walls around the upper mounting frame 102, the top walls of the upper mounting frames 101 and the top walls of the upper mounting frames 102 are on the same horizontal plane, and the top walls of the multiple groups of upper mounting frames 101 are provided with multiple groups of mounting holes 1011.
[0041] The specific working principle is: use multiple sets of upper mounting frames 101 to fit the steel grid frame's hanging mechanism at the appropriate position, and then use external screws to penetrate the mounting holes 1011 at the corresponding positions to fix the steel grid frame's hanging mechanism at the corresponding positions.
[0042] The standard parts used in the present utility model document can all be purchased from the market. The various components in the present utility model document can be customized according to the description in the specification and the drawings. The specific connection methods of each part adopt conventional means such as mature bolts, rivets, welding, etc. in the prior art. The machinery, parts and equipment all adopt conventional models in the prior art, and the circuit connection adopts the conventional connection method in the prior art, which will not be described in detail here.
[0043] The above are all preferred embodiments of the present utility model, and are not intended to limit the protection scope of the present utility model. Therefore, any equivalent changes made based on the structure, shape, and principle of the present utility model should be included in the protection scope of the present utility model.
Claims
1. The lifting mechanism of the double-layer tetrahedral system bolt ball steel grid is characterized by: include, An upper hanging assembly (100) comprises an upper installation frame (102), wherein a hanging piece (103) penetrating a bottom wall of the upper installation frame (102) is installed at the bottom of the inner cavity of the upper installation frame (102); A lower hanging assembly (200) comprises a connecting piece (207), wherein the connecting piece (207) is sleeved on the bottom of the hanging piece (103), a hanging block (203) is fixed to the bottom wall of the connecting piece (207), lower mounting frames (201) are arranged at the top positions of the outer walls around the hanging block (203), multiple groups of the top walls of the lower mounting frames (201) are provided with strip holes (2011), multiple groups of the inner cavities of the lower mounting frames (201) are provided with translation pieces (205), and multiple groups of the translation pieces (205) are provided with inner locking rods (206) that pass through the strip holes (2011).
2. The hoisting mechanism of the double-layer tetrahedral pyramid bolt ball steel grid according to claim 1 is characterized by: The lifting member (103) comprises a hoisting machine body (1031), the hoisting machine body (1031) being fixed on the bottom wall of the upper mounting frame (102), a hoisting rope (1032) penetrating the bottom wall of the upper mounting frame (102) being installed at the output end of the hoisting machine body (1031), and a hook (1033) being sleeved with the connecting member (207) being installed at the bottom end of the hoisting rope (1032).
3. The hoisting mechanism of the double-layer tetrahedral pyramid bolt ball steel grid according to claim 2 is characterized by: The connecting member (207) comprises a connecting rope loop (2072), wherein the connecting rope loop (2072) is sleeved on the outside of the lifting hook (1033), and a connecting rod (2071) fixed to the top wall of the lifting block (203) is sleeved on the bottom end of the connecting rope loop (2072).
4. The hoisting mechanism of the double-layer tetrahedral pyramid bolt ball steel grid according to claim 1 is characterized by: The translation member (205) comprises a lead screw body (2051), the lead screw body (2051) being rotatably connected in the inner cavity of the lower mounting frame (201) via a bearing, a lead screw nut (2052) being fixed to the bottom wall of the locking inner rod (206) being mounted on the outside of the lead screw body (2051), and a hand plate (2053) being fixed to the end of the lead screw body (2051).
5. The hoisting mechanism of the double-layer tetrahedral pyramid bolt ball steel grid according to claim 1 is characterized by: Lower mounting frames (204) are installed at the bottom positions of the outer walls around the hanging block (203), and multiple groups of lower mounting frames (204) are installed with fasteners (202) that are detachably connected to the lower mounting frame (201).
6. The hoisting mechanism of the double-layer tetrahedral pyramid bolt ball steel grid according to claim 5 is characterized by: The fastener (202) comprises a fastening bolt (2022), wherein a plurality of groups of the fastening bolts (2022) are provided, wherein the plurality of groups of the fastening bolts (2022) are passed through the top wall of the lower mounting frame (204) and extend into the inner cavity of the lower mounting frame (201), and the bottom wall of the lower mounting frame (201) is fixed with a plurality of groups of fastening nuts (221) whose threads match those of the fastening bolts (2022).
7. The hoisting mechanism of the double-layer tetrahedral pyramid bolt ball steel grid according to claim 1 is characterized by: The outer walls of the plurality of groups of the locking inner rods (206) are threadedly sleeved with locking outer tubes (208).
8. The hoisting mechanism of the double-layer tetrahedral pyramid bolt ball steel grid according to claim 1 is characterized by: Upper mounting frames (101) are installed at the top positions of the outer walls around the upper mounting frame (102), and multiple groups of mounting holes (1011) are provided on the top walls of the multiple groups of upper mounting frames (101).