Grouting structure for controlling building settlement caused by surrounding environment change
By setting up an isolated grouting body between the foundation pit enclosure structure and the edge building and setting up a tracking grouting body at the bottom of the concrete strip foundation of the building, the modified polyester grouting material improves the resistance of the building's deformation, and solves the traditional foundation The pit reinforcement technology has the limitations and disturbances of construction space in urban historically protected buildings, achieving rapid and environmentally friendly reinforcement effects.
Patent Information
- Application Number
- CN202323651559.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-30
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2033-12-30
AI Technical Summary
Traditional foundation pit reinforcement technology has problems such as limitations in urban historically protected buildings, large disturbances and great impact, resulting in problems such as building offset and inclination, which makes it difficult to meet construction conditions and affect house users.
Using a combined structure of an isolated grouting body and a tracking grouting body, the isolation grouting body is located between the foundation pit enclosure structure and the edge building, and the tracking grouting body is located at the bottom of the concrete strip foundation of the building, and is injected by modified polyester. The formation of slurry materials improves the building's resistance to deformation and reduces construction disturbances and environmental impacts.
It has achieved safety protection for buildings, shortened construction time, reduced construction period impact, reduced construction impact on operations, and did not pollute the environment, and has great construction advantages.
Smart Images

Figure CN221956691U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building settlement, in particular to a grouting structure for controlling building settlement caused by changes in surrounding environment. Background Art
[0002] With the advancement of urban construction and reconstruction, the construction land in urban areas is gradually decreasing. While the construction of new buildings is developing in a higher direction, the foundation pit engineering is also developing in a deeper direction, resulting in the increasing impact of the construction pit on the surrounding environment, especially the adjacent existing buildings. Historical protected buildings in urban areas are usually very old, with aging building materials, low overall strength and deformation resistance, and are more sensitive to changes in the surrounding environment. For foundation pit engineering with complex surrounding environment and high requirements for environmental impact control, the design is mainly based on deformation control.
[0003] At present, in addition to the enclosure method, support system and passive zone reinforcement design in the pit, the effect of strengthening the active zone soil under the existing protective buildings outside the foundation pit has been proven by relevant research and engineering practice. Traditional reinforcement technologies such as anchor static pressure piles, high-pressure rotary jet piles, and flower pipe grouting are increasingly being studied and applied in the reinforcement of soft foundations and settlement control projects of existing buildings. Due to the limitations of the construction space, these conventional construction processes are difficult to meet the construction conditions indoors, or due to the large disturbance, reinforcement in the already used houses often requires the removal of indoor equipment and facilities, which has a great impact on the users of the houses. In addition, during the reinforcement construction process, the traditional technology causes the building to shift and tilt due to the large construction surface and soil disturbance, which runs counter to the original intention of strengthening the building foundation. Summary of the invention
[0004] The purpose of the utility model is to provide a grouting structure for controlling the settlement of buildings and structures caused by changes in the surrounding environment in accordance with the above-mentioned deficiencies of the prior art. In addition to foundation pits, the buildings and structures may also be pipelines, houses, roads, high-speed railways, etc. By arranging an isolation grouting body between the retaining structure of the foundation pit and the buildings and structures at the edge of the foundation pit, and arranging a tracking grouting body at the bottom of the concrete strip foundation of the buildings and structures, the deformation resistance of the buildings and structures can be improved to achieve safety protection of the buildings and structures.
[0005] The purpose of this utility model is achieved by the following technical solutions:
[0006] A grouting structure for controlling the settlement of a building caused by changes in the surrounding environment, characterized in that it comprises an isolation grouting body and a tracking grouting body, the isolation grouting body is arranged between the retaining structure of a foundation pit and the building at the edge of the foundation pit, the tracking grouting body is arranged at the bottom of the concrete strip foundation of the building, the tracking grouting body is composed of a first tracking grouting body, a second tracking grouting body and a third tracking grouting body, the first tracking grouting body, the second tracking grouting body and the third tracking grouting body are respectively arranged at the bottom of the concrete strip foundation of the building away from the foundation pit, the bottom of the concrete strip foundation on the middle side of the building and the bottom of the concrete strip foundation of the building close to the foundation pit, the bottom surface of the isolation grouting body is located below the bottom surface of the third tracking grouting body, the bottom surface of the third tracking grouting body is located below the bottom surface of the second tracking grouting body, and the bottom surface of the second tracking grouting body is located below the bottom surface of the first tracking grouting body.
[0007] The thickness of the isolation grouting body is 3 to 5 meters from the ground to the bottom of the concrete strip foundation.
[0008] The bottom surface of the first tracking grouting body is located 0-1 m below the bottom of the corresponding concrete strip foundation.
[0009] The bottom surface of the second tracking grouting body is located 1 to 2 meters below the bottom of the corresponding concrete strip foundation.
[0010] The bottom surface of the third tracking grouting body is located 2 to 3 meters below the bottom of the corresponding concrete strip foundation.
[0011] The tracking grouting body is connected with the anchor static pressure pile of the building structure.
[0012] The advantages of the utility model are:
[0013] (1) Both the isolation grouting body and the tracking grouting body are formed by modified polyester grouting, which is environmentally friendly and not susceptible to mold and fungus erosion. The reinforced site is an operating club with lush greenery and beautiful landscape, and the construction will not affect or pollute the site.
[0014] (2) The grouting process is fast, which greatly shortens the construction time; the strength is quickly formed after grouting, which will not affect the construction period of the foundation pit;
[0015] (3) The maximum grouting hole is about 16 mm, which basically does not damage the existing method; the construction adopts 12-16 mm grouting pipes inserted into the ground, which has little disturbance to the underground and does not require large-scale excavation of the foundation. Compared with traditional processes, it has great advantages and has little impact on the operation of the club during construction;
[0016] (4) The construction equipment occupies a small area, and there is no need to mix mud on site or pile up materials. The equipment is small and flexible, and only the grouting pipe needs to be pulled to the grouting hole. There is no need to close the clubhouse, which will not affect the operation. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a cross-sectional view of the grouting structure of the utility model;
[0018] Figure 2 It is a flowchart of the grouting structure construction method of the utility model;
[0019] Figure 3 It is a construction schematic diagram of the isolation grouting body of the utility model;
[0020] Figure 4 It is a construction schematic diagram of the tracking grouting body of the utility model;
[0021] Figure 5 It is a schematic diagram of the arrangement of the grouting pipe of the utility model. DETAILED DESCRIPTION
[0022] The following is a further detailed description of the features of the present invention and other related features through embodiments in conjunction with the accompanying drawings to facilitate understanding by technicians in the same industry:
[0023] like Figures 1 to 5 As shown, the marks in the figure represent respectively:
[0024] Enclosure structure 1, building 2, concrete strip foundation 3, isolation grouting body 4, first tracking grouting body 5, second tracking grouting body 6, third tracking grouting body 7, anchor static pressure piles 8, modified polyester slurry 9, grouting pipe 10.
[0025] Example: Figures 1 to 5As shown, this embodiment relates to a grouting structure for controlling the settlement of a building caused by changes in the surrounding environment. In addition to the foundation pit, the building may also be a pipeline, a house, a road, a high-speed railway, etc. The grouting structure mainly includes an isolation grouting body 4 and a tracking grouting body. The isolation grouting body 4 is arranged between the retaining structure 1 of the foundation pit and the building 2 (existing building) at the edge of the foundation pit. The tracking grouting body is arranged at the bottom of the concrete strip foundation 3 of the building 2. The arrangement of the isolation grouting body 4 and the tracking grouting body can improve the deformation resistance of the building 2 to achieve safety protection of the building 2. The tracking grouting body is composed of a first tracking grouting body 5, a second tracking grouting body 6 and a third tracking grouting body 7, which are respectively arranged at the bottom of the concrete strip foundation 3 on the side of the structure 2 away from the foundation pit, the bottom of the concrete strip foundation 3 on the middle side of the structure 2 and the bottom of the concrete strip foundation 3 on the side of the structure 2 close to the foundation pit, and the tracking grouting body is connected to the anchor static pressure pile 8 of the structure 2, so that the tracking grouting body and the structure 2 form a whole, further improving the deformation resistance of the structure 2.
[0026] like Figure 1 As shown, since the influence of foundation pit excavation on the building 2 gradually decreases as the distance between the two increases, the bottom surface of the isolation grouting body 4 is located below the bottom surface of the third tracking grouting body 7, the bottom surface of the third tracking grouting body 7 is located below the bottom surface of the second tracking grouting body 6, and the bottom surface of the second tracking grouting body 6 is located below the bottom surface of the first tracking grouting body 5. Among them, the thickness of the isolation grouting body 4 is 3~5m from the ground to the bottom of the concrete strip foundation 3, the bottom surface of the third tracking grouting body 7 is located 2~3m below the bottom of the corresponding concrete strip foundation 3, the bottom surface of the second tracking grouting body 6 is located 1~2m below the bottom of the corresponding concrete strip foundation 3, and the bottom surface of the first tracking grouting body 5 is located 0~1m below the bottom of the corresponding concrete strip foundation 3.
[0027] like Figures 3-5 As shown, the isolation grouting body 4 and the tracking grouting body are formed by injecting modified polyester slurry 9 into the ground through the grouting pipe 10. Among them, the spacing between the grouting pipes 10 used in the first tracking grouting body 5 is within 2m, and the spacing between the grouting pipes 10 used in the second tracking grouting body 6 / the third tracking grouting body 7 / the isolation grouting body 4 is within 3m.
[0028] like Figures 1 to 5As shown, this embodiment has the following construction method, which is divided into two parts: isolation grouting and tracking grouting. Isolation grouting is constructed before the construction of the enclosure structure, which is used to isolate the impact of foundation pit related construction on the building and to reinforce the original foundation of the building to a certain extent; tracking grouting is a method activated under specific conditions, which is used to further reinforce and lift the foundation of the building itself when the building settlement exceeds the limit, so as to achieve the purpose of controlling the building settlement. The specific steps of the construction method are as follows:
[0029] (S1) Determine the scope of construction control based on the design of the foundation pit support and the foundation type of the adjacent buildings.
[0030] (S2) Divide the construction sections and arrange the construction sites according to the determined construction scope.
[0031] The method of dividing the construction sections is as follows:
[0032] (S21) Determine the diffusion radius of the modified polyester slurry in soil at different depths through field tests;
[0033] (S22) The spacing between distribution points is determined according to the diffusion radius. Usually, the material diffusion radius is in the range of 0.5 to 2 m. Under the condition that the materials overlap each other after diffusion, the spacing between distribution points is usually set to 1 to 3 m.
[0034] (S3) Positioning drilling is performed according to the layout.
[0035] Among them, portable water drill is usually used for positioning drilling. When site conditions are not suitable, other types of drilling equipment can be considered.
[0036] (S4) Insert the grouting pipe and seal it.
[0037] Each hole usually contains 2 to 4 grouting pipes of different depths. The grouting flower pipe with a diameter of 16 mm is made of aluminum pipe. The buried depth is determined according to the depth of the foundation pit and the depth of the building foundation, usually in the range of 2 to 10 meters. The grouting pipe is divided into shallow and deep layers. The shallow grouting pipe is used for isolation grouting, and the deep grouting pipe is used for tracking grouting. The length of the grouting pipe is distributed in an arithmetic progression, and the end is sealed with a plastic cap to avoid soil plugging.
[0038] (S5) Isolation grouting is performed on shallow holes.
[0039] Among them, the grouting volume and grouting pressure need to be determined in advance during the grouting process:
[0040] (S51) The grouting amount is determined in the field test mentioned in step S21, and the calculation formula is grouting reinforcement depth × reinforcement area × grouting amount empirical coefficient, where the grouting amount empirical coefficient is obtained from many years of grouting construction experience, usually 5 to 8 kg / m³, and the specific parameters are determined according to the expected reinforcement effect;
[0041] (S52) The grouting pressure is determined according to the soil layer conditions and the actual construction situation. During the grouting process, the grouting pressure needs to be kept constant and continuous. The grouting pressure used is 1 to 3 MPa;
[0042] (S53) Grouting stop control: During on-site grouting construction, if the change of the current grouting monitoring point is greater than 2mm, the cumulative change of the monitoring points in the non-grouting affected area exceeds 10mm, and the grouting pressure of the equipment needs to be increased to maintain a constant grouting rate or the grouting volume reaches the designed value, when any of the above conditions is met, the grouting of the current hole can be stopped and grouting of the other hole can be changed.
[0043] Grouting material is a special two-component modified polyester grouting material for foundation reinforcement, which belongs to a kind of modified polyester foam material. According to the amount of raw materials used in the formula, it can be divided into two categories: main agent and auxiliary agent. According to the chemical properties of various main agents and auxiliary agents and the principle of mutual non-reaction, the raw materials are divided into two components: polyol system A material, including polyether polyol, chain extender, catalyst and foaming agent, and isocyanate prepolymer B material. When using, the raw materials of the two components are mixed in a certain proportion, and the material can react to form an elastic foam.
[0044] (S6) Based on the monitoring data during the foundation pit construction process, when the monitoring data reaches a critical value, the tracking grouting is started.
[0045] Among them, the activation conditions for tracking grouting are as follows:
[0046] (S61) When the cumulative settlement of a building exceeds 60% of the warning value, initial tracking grouting should be carried out on the area with excessive settlement, with the reinforcement depth being 0 to 1 m below the building foundation, i.e., deep grouting pipes should be used;
[0047] (S62) When the cumulative settlement of a building exceeds 80% of the warning value, a second tracking grouting should be carried out on the area with excessive settlement. The grouting location is between the first grouting holes, and the reinforcement depth is 1 to 2 meters below the first grouting. The second tracking grouting reinforces 20 to 30% of the area of the area each time;
[0048] (S63) When the cumulative settlement of a building exceeds 100% of the warning value, a final follow-up grouting should be carried out on the area with excessive settlement. The grouting location is between the first and second grouting holes, and the reinforcement depth is 1 to 2m below the second grouting. This follow-up grouting will reinforce 30 to 50% of the area each time.
[0049] (S7) Track grouting of deep holes and control of final settlement of existing buildings.
[0050] In addition, this embodiment also has the following three construction methods:
[0051] The first construction method is:
[0052] Step 1: Before construction, determine whether grouting reinforcement is required between the foundation pit and the existing building.
[0053] Step 2: Drill 8m deep reinforcement holes between the foundation pit enclosure and the foundation using a fully hydraulic lightweight drilling rig. The drill holes have a diameter of 38mm and are arranged on the outside of the wall. The center of the hole is about 2.44m away from the center line of the wall, and the hole spacing is 3m. There are 4 grouting holes at each grouting point, with hole depths of 1m, 3m, 5m, and 7m respectively.
[0054] Step 3: Grouting construction is carried out 2 to 3 days after the trench wall reinforcement is completed. High-pressure foaming grouting equipment is used to construct shallow grouting holes. The pressure must be kept constant and continuous during the grouting process. The grouting pressure should be able to ensure that the polymer grouting material fully reacts, the pressure at the slurry point is controlled at 1 to 3Mpa, and the grouting flow rate is 1.0 to 5.0L / min.
[0055] Step 4: Continuous real-time monitoring should be carried out on the protected buildings within the grouting influence range. During the grouting construction process, if one of the following situations occurs: a) the cumulative change exceeds 2mm; b) the grouting pressure of the equipment needs to be increased to maintain a constant slurry discharge rate; c) the grouting volume reaches the design value, and the estimated grouting volume is 7kg per cubic meter of soil, the current hole grouting can be stopped and grouting can be changed to another hole.
[0056] Step 5: The settlement of the existing building did not reach 60% of the warning value and no follow-up grouting was carried out.
[0057] The second construction method is:
[0058] Step 1: Before construction, check the monitoring data, determine the construction scope, and start construction in areas with severe foundation settlement and deformation.
[0059] Step 2: The diameter of the drill hole is Φ12~16mm, and the hole is drilled using a handheld drill. The drilling depth is 0~4.5m below the natural ground. The grouting holes are arranged on one side of the outer wall of the house, with a hole spacing of 3m and a hole center 0.5m away from the wall boundary line. There are 3 grouting holes at each grouting point, and the hole depths are 1.5m, 3m, and 4.5m respectively.
[0060] Step 3: Grout the shallow grouting holes. The pressure needs to be kept constant and continuous during the grouting process. The grouting pressure is 1 to 3 MPa and the grouting flow rate is 1.0 to 5.0 L / min.
[0061] Step 4: Continuous real-time monitoring should be carried out on the protected buildings within the grouting influence range. During the grouting construction process, if one of the following situations occurs: a) the cumulative change exceeds 2mm; b) the grouting pressure of the equipment needs to be increased to maintain a constant slurry discharge rate; c) the grouting volume reaches the design value, and the estimated grouting volume is 5kg per cubic meter of soil, the current hole grouting can be stopped and grouting can be changed to another hole.
[0062] Step 5: The settlement of the existing building did not reach 60% of the warning value and no follow-up grouting was carried out.
[0063] The third construction method is:
[0064] Step 1: Before construction, check monitoring data, determine the scope of construction, and reinforce the foundation of the existing building as a whole. The total reinforcement area of the building's exterior wall foundation is 318m 2 .
[0065] Step 2: The deep grouting reinforcement depth is 0-6m below the foundation, and the hole spacing is 1.5m. Due to the deep depth, a total of 3 adjacent holes are arranged at a single location: (1) 1 grouting hole is set at a depth of 0-1m, the inserted grouting pipe is 1.2m long, and the hole center is 0.5m away from the wall boundary line; (2) 1 grouting hole is set at a depth of 1-3m, the inserted grouting pipes are 2m and 3m long respectively, and the hole center is 0.5m away from the wall boundary line; (3) 1 grouting hole is set at a depth of 3-6m, the inserted grouting pipes are 4m, 5m, and 6m long respectively, and the hole center is 0.3m away from the wall boundary line. Each grouting hole can be staggered by about 5cm in the vertical direction of the wall. The shallow grouting holes are arranged between the deep grouting holes at intervals, with a reinforcement depth of 0-3m below the foundation and a hole spacing of 1.5m. Two adjacent holes are arranged at a single location: (1) a grouting hole is set at a depth of 0 to 1 m, the length of the inserted grouting pipe is 1.2 m, and the distance between the hole center and the wall boundary line is 0.5 m; (2) a grouting hole is set at a depth of 1 to 3 m, the length of the inserted grouting pipe is 2 m and 3 m respectively, and the distance between the hole center and the wall boundary line is 0.5 m. The grouting holes can be staggered by about 5 cm in the vertical direction of the wall.
[0066] Step 3: Grout the shallow grouting holes. The pressure needs to be kept constant and continuous during the grouting process. The grouting pressure is 1 to 3 MPa and the grouting flow rate is 1.0 to 5.0 L / min.
[0067] Step 4: Continuous real-time monitoring should be carried out on the protected buildings within the grouting influence range. During the grouting construction process, if one of the following situations occurs: a) the cumulative change exceeds 2mm; b) the grouting pressure of the equipment needs to be increased to maintain a constant slurry discharge rate; c) the grouting volume reaches the design value, and the estimated grouting volume is 7kg per cubic meter of soil, the current hole grouting can be stopped and grouting can be changed to another hole.
[0068] Step 5: The settlement of the existing building did not reach 60% of the warning value and no follow-up grouting was carried out.
[0069] The advantages of this embodiment are:
[0070] (1) Both the isolation grouting body and the tracking grouting body are formed by modified polyester grouting, which is environmentally friendly and not susceptible to mold and fungus erosion. The reinforced site is an operating club with lush greenery and beautiful landscape, and the construction will not affect or pollute the site.
[0071] (2) The grouting process is fast, which greatly shortens the construction time; the strength is quickly formed after grouting, which will not affect the construction period of the foundation pit;
[0072] (3) The maximum grouting hole is about 16 mm, which basically does not damage the existing method; the construction adopts 12-16 mm grouting pipes inserted into the ground, which has little disturbance to the underground and does not require large-scale excavation of the foundation. Compared with traditional processes, it has great advantages and has little impact on the operation of the club during construction;
[0073] (4) The construction equipment occupies a small area, and there is no need to mix mud on site or pile up materials. The equipment is small and flexible, and only the grouting pipe needs to be pulled to the grouting hole. There is no need to close the clubhouse, which will not affect the operation.
[0074] Although the above embodiments have described the concepts and embodiments of the purpose of the utility model in detail with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and modifications can still be made to the utility model without departing from the scope of the claims, so they are not described one by one here.
Claims
1. A grouting structure for controlling the settlement of buildings caused by changes in the surrounding environment. Features: It includes an isolation grouting body and a tracking grouting body, wherein the isolation grouting body is arranged between the retaining structure of the foundation pit and the building at the edge of the foundation pit, the tracking grouting body is arranged at the bottom of the concrete strip foundation of the building, and the tracking grouting body consists of a first tracking grouting body, a second tracking grouting body and a third tracking grouting body, wherein the first tracking grouting body, the second tracking grouting body and the third tracking grouting body are respectively arranged at the bottom of the concrete strip foundation of the building away from the foundation pit, the bottom of the concrete strip foundation on the middle side of the building, and the bottom of the concrete strip foundation of the building close to the foundation pit, the bottom surface of the isolation grouting body is located below the bottom surface of the third tracking grouting body, the bottom surface of the third tracking grouting body is located below the bottom surface of the second tracking grouting body, and the bottom surface of the second tracking grouting body is located below the bottom surface of the first tracking grouting body.
2. A grouting structure for controlling the settlement of a building caused by changes in the surrounding environment as claimed in claim 1, Features: The thickness of the isolation grouting body is 3 to 5 meters from the ground to the bottom of the concrete strip foundation.
3. A grouting structure for controlling the settlement of a building caused by changes in the surrounding environment as claimed in claim 1, Features: The bottom surface of the first tracking grouting body is located 0-1 m below the bottom of the corresponding concrete strip foundation.
4. A grouting structure for controlling the settlement of a building caused by changes in the surrounding environment as claimed in claim 1, Features: The bottom surface of the second tracking grouting body is located 1 to 2 meters below the bottom of the corresponding concrete strip foundation.
5. A grouting structure for controlling the settlement of a building caused by changes in the surrounding environment as claimed in claim 1, Features: The bottom surface of the third tracking grouting body is located 2 to 3 meters below the bottom of the corresponding concrete strip foundation.
6. A grouting structure for controlling the settlement of a building caused by changes in the surrounding environment as claimed in claim 1, Features: The tracking grouting body is connected with the anchor static pressure pile of the building structure.